CN107781505A - The integrated installation method of aerial pipeline - Google Patents
The integrated installation method of aerial pipeline Download PDFInfo
- Publication number
- CN107781505A CN107781505A CN201610733563.0A CN201610733563A CN107781505A CN 107781505 A CN107781505 A CN 107781505A CN 201610733563 A CN201610733563 A CN 201610733563A CN 107781505 A CN107781505 A CN 107781505A
- Authority
- CN
- China
- Prior art keywords
- module units
- pipeline
- suspension bracket
- aerial
- top support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
Abstract
The present invention relates to the transport of building element or assembling field, the integrated installation method of specially a kind of aerial pipeline.A kind of integrated installation method of aerial pipeline, to implement in installation, aerial pipe network (1) to be installed includes pipeline (11) and suspension bracket (12), and top support platform (2) is provided with installation, it is characterized in that:Implement successively as follows:A. plan;B. set;C. lift;D. it is assembled.The present invention is easy to operate, reduces operation intensity, reduces cost, operating efficiency is high, securely and reliably.
Description
Technical field
The present invention relates to the transport of building element or assembling field, the integrated installation side of specially a kind of aerial pipeline
Method.
Background technology
With metallurgical, chemical industry development, production capacity is gone to come into effect successively, with washing in a pan for largely backward production line
Eliminate, the production line of many new optimizations starts to land successively, started.Aerial pipeline is known as in new production technology and production line
The title of " main artery " of production line, aerial pipeline installment work are always the most important thing.Existing aerial pipeline is installed
Carry out the installation of various pipelines after overcast installation one by one again.This clock installation method is uneconomical, installation workload
Big and danger coefficient is high, greatly adds operating cost and the labor intensity of worker, is also unfavorable for duration progress monitoring.
The content of the invention
The defects of in order to overcome prior art, there is provided a kind of easy to operate, reduction operation intensity, reduce cost, work effect
High, the safe and reliable pipeline method for dismounting of rate, the invention discloses a kind of integrated installation method of aerial pipeline.
The present invention reaches goal of the invention by following technical solution:
A kind of integrated installation method of aerial pipeline, to implement in installation, aerial pipe network to be installed includes pipeline and suspension bracket,
It is laid in suspension bracket to each bar pipe level, top support platform is provided with installation, the top of suspension bracket is fixed on the top on installation ground
In support platform, top support platform selects the ceiling of factory building, or in ground vertical columns, it is flatly solid on each root post
Determine crossbeam, using crossbeam as top support platform, it is characterized in that:Implement successively as follows:
A is planned:Module units is determined according to aerial pipe network, module units includes piping unit and suspension bracket unit, piping unit are solid
It is scheduled in suspension bracket unit, two end faces of each module units are mating surface, i.e., include one between adjacent two mating surfaces
Module units;
B is set:Suspension centre is fixed on top support platform, a module units, each suspension centre are included between adjacent two suspension centres
On a boom hoisting is all set, each boom hoisting is all hitched module units;
C is lifted:Each module units is promoted to setting height(from bottom) with boom hoisting, makes adjacent module units mutual with mating surface
Fit;
D is assembled:Adjacent module units is sequentially connected, each module units is pieced together completely aerial pipe network, during split
Piping unit pieces together pipeline successively, and suspension bracket unit pieces together suspension bracket successively, and the top of each suspension bracket is all fixed on into top support
Platform.
The integrated installation method of described aerial pipeline, it is characterized in that:
When step b is set, boom hoisting is from differential chain block or lifting steel wire rope, the lifting force sum of two neighboring boom hoisting
Not less than 1.2 times of module units weight;
During step d assembly, unit is assembled from gas welding.
The present invention makees integrated segmentation by carrying out pipeline and its support, and rationally sets mating surface, by substantial amounts of high-altitude
Assembly working is reduced to two sex works, by pipeline and its support integral installation, greatly reduces the danger of work high above the ground
Property and operation intensity, improve construction speed and reduce construction cost.Present invention can be suitably applied in factory building and outside factory building it is large-scale
Comprehensive pipe network removes work.
The beneficial effects of the invention are as follows:It is easy to operate, operation intensity is reduced, reduces cost, operating efficiency is high, safely may be used
Lean on.
Brief description of the drawings
Fig. 1 is the schematic diagram for the module units that split is treated in the present invention;
Fig. 2 is the diagrammatic cross-section of the aerial pipe network after the completion of the present invention;
Fig. 3 is the schematic diagram of the aerial pipe network after the completion of the present invention.
Embodiment
The present invention is further illustrated below by way of specific embodiment.
Embodiment 1
A kind of integrated installation method of aerial pipeline, implement in installation, aerial pipe network 1 to be installed includes pipeline 11 and hung
Frame 12, each bar pipeline 11 are flatly laid in suspension bracket 12, are provided with top support platform 2 in installation, the top of suspension bracket 12 is fixed
On the top support platform 2 on installation ground, top support platform 2 selects the ceiling of factory building, or as shown in Figure 3:Fixed on ground
Column 21, flatly fixed cross beam 22 on each root post 21, using crossbeam 22 as top support platform 2, as follows successively
Implement:
A is planned:It is as shown in Figure 1 according to aerial pipe network 1 determination module units 13, module units 13:Including the He of piping unit 131
Suspension bracket unit 132, piping unit 131 are fixed in suspension bracket unit 132, and two end faces of each module units 13 are mating surface 3,
A module units 13 is included between two i.e. adjacent mating surfaces 3;
B is set:Suspension centre 4 is fixed on top support platform 2, includes a module units 13 between adjacent two suspension centres 4, often
One boom hoisting 5 is all set on individual suspension centre 4, each boom hoisting 5 is all hitched module units 13;Boom hoisting 5 is from poor
Movable pulley or lifting steel wire rope, the lifting force sum of two neighboring boom hoisting 5 are not less than 1.2 times of the weight of module units 13;
C is lifted:Each module units 13 is promoted to setting height(from bottom) with boom hoisting 5, makes adjacent module units 13 with split
Face 3 mutually fits;
D is assembled:Adjacent module units 13 is sequentially connected with gas welding, pieces together each module units 13 complete aerial
Pipe network 1, piping unit 131 pieces together pipeline 11 successively during split, and suspension bracket unit 132 pieces together suspension bracket 12 successively, is hung each
The top of frame 12 is all fixed on top support platform 2, after the completion of aerial pipe network 1 as shown in Figures 2 and 3.
Claims (2)
1. a kind of integrated installation method of aerial pipeline, implement in installation, aerial pipe network (1) to be installed includes pipeline
(11) flatly it is laid in suspension bracket (12) with suspension bracket (12), each bar pipeline (11), top support platform (2) is provided with installation,
The top of suspension bracket (12) is fixed on the top support platform (2) on installation ground, and top support platform (2) selects the ceiling of factory building, or
Person flatly fixed cross beam (22) on each root post (21), top support is used as using crossbeam (22) in ground vertical columns (21)
Platform (2), it is characterized in that:Implement successively as follows:
A is planned:Module units (13) is determined according to aerial pipe network (1), module units (13) includes piping unit (131) and hung
Frame unit (132), piping unit (131) are fixed in suspension bracket unit (132), and two end faces of each module units (13) are spelling
Conjunction face (3), i.e., a module units (13) is included between adjacent two mating surfaces (3);
B is set:Suspension centre (4) is fixed on top support platform (2), a module units is included between adjacent two suspension centres (4)
(13) boom hoisting (5), is set on each suspension centre (4), each boom hoisting (5) is all hitched module units (13);
C is lifted:Each module units (13) is promoted to setting height(from bottom) with boom hoisting (5), makes adjacent module units (13)
Mutually fitted with mating surface (3);
D is assembled:Adjacent module units (13) is sequentially connected, each module units (13) is pieced together complete cross-over pipe
Net (1), piping unit (131) pieces together pipeline (11) successively during split, and suspension bracket unit (132) pieces together suspension bracket (12) successively,
The top of each suspension bracket (12) is all fixed on top support platform (2).
2. the integrated installation method of aerial pipeline as claimed in claim 1, it is characterized in that:
When step b is set, boom hoisting (5) is from differential chain block or lifting steel wire rope, the lifting of two neighboring boom hoisting (5)
Power sum is not less than 1.2 times of module units (13) weight;
During step d assembly, unit (13) is assembled from gas welding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610733563.0A CN107781505A (en) | 2016-08-27 | 2016-08-27 | The integrated installation method of aerial pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610733563.0A CN107781505A (en) | 2016-08-27 | 2016-08-27 | The integrated installation method of aerial pipeline |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107781505A true CN107781505A (en) | 2018-03-09 |
Family
ID=61439927
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610733563.0A Pending CN107781505A (en) | 2016-08-27 | 2016-08-27 | The integrated installation method of aerial pipeline |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107781505A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109160416A (en) * | 2018-10-30 | 2019-01-08 | 北京机械设备研究所 | A kind of method and device of hydraulic pipe network integral hoisting |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0726726A (en) * | 1993-05-14 | 1995-01-27 | Mitsubishi Heavy Ind Ltd | Zone module construction method for constructing steel structure |
CN101451397A (en) * | 2007-12-05 | 2009-06-10 | 中冶天工建设有限公司 | Steel structure modularization construction process |
CN103615601A (en) * | 2013-11-11 | 2014-03-05 | 中国北车集团大连机车车辆有限公司 | Locomotive pipeline and cable composite assembling method |
CN203770835U (en) * | 2013-10-30 | 2014-08-13 | 森松(江苏)海油工程装备有限公司 | Spliced structure of modularized pipe gallery transportation unit |
CN104806822A (en) * | 2015-04-16 | 2015-07-29 | 上海市安装工程集团有限公司 | Combined type stand pipe and modularized installation method thereof |
CN105421792A (en) * | 2015-12-15 | 2016-03-23 | 安徽伟宏钢结构集团股份有限公司 | Lifting construction process of modular steel structural components |
-
2016
- 2016-08-27 CN CN201610733563.0A patent/CN107781505A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0726726A (en) * | 1993-05-14 | 1995-01-27 | Mitsubishi Heavy Ind Ltd | Zone module construction method for constructing steel structure |
CN101451397A (en) * | 2007-12-05 | 2009-06-10 | 中冶天工建设有限公司 | Steel structure modularization construction process |
CN203770835U (en) * | 2013-10-30 | 2014-08-13 | 森松(江苏)海油工程装备有限公司 | Spliced structure of modularized pipe gallery transportation unit |
CN103615601A (en) * | 2013-11-11 | 2014-03-05 | 中国北车集团大连机车车辆有限公司 | Locomotive pipeline and cable composite assembling method |
CN104806822A (en) * | 2015-04-16 | 2015-07-29 | 上海市安装工程集团有限公司 | Combined type stand pipe and modularized installation method thereof |
CN105421792A (en) * | 2015-12-15 | 2016-03-23 | 安徽伟宏钢结构集团股份有限公司 | Lifting construction process of modular steel structural components |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109160416A (en) * | 2018-10-30 | 2019-01-08 | 北京机械设备研究所 | A kind of method and device of hydraulic pipe network integral hoisting |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105908761B (en) | A kind of high slope hanging basket mobile platform construction technology | |
CN107191676A (en) | Buried pipeline construction method | |
CN204199721U (en) | A kind of erecting device for factory building construction high and medium structure | |
CN105781590B (en) | TBM bears ring with reception hole and removes technique | |
CN203654702U (en) | Operating platform for construction of reinforced concrete chimney | |
CN204753397U (en) | Gallows is installed to steel case bridge temporarily | |
CN208151865U (en) | A kind of introversion formula steel case arch bridge integrally promotes simulation Lift-on/Lift-off System | |
CN107781505A (en) | The integrated installation method of aerial pipeline | |
CN203867198U (en) | Slip equipment for high-rise steel structure transfer layer truss | |
CN106016233A (en) | Boiler roof with long span and fewer welding spots and hoisting method for boiler roof | |
CN204474106U (en) | Deep shaft manned lift device | |
CN106044580A (en) | Whole lifting method of wet electrostatic dust removing device body equipment | |
CN203486787U (en) | Integral lifting device for cabinet top of Wiggins coal gas cabinet | |
CN205575534U (en) | Lattice formula groined type support body lifting means | |
CN105060124B (en) | Intra-frame portal crane system and hoisting use method thereof | |
CN106121254A (en) | Heavy component transportation system and construction method after a kind of contrary sequence method dismounting | |
CN107781504A (en) | The integrated method for dismounting of aerial pipeline | |
CN211009152U (en) | Underwater fire pump | |
CN205077876U (en) | Machine and stressing jack linkage are worn to restraint by prestress wire | |
CN206328067U (en) | Movable draining platform | |
CN207226943U (en) | A kind of double crossbeam synchronous hoisting devices | |
CN206014340U (en) | A kind of cooperation fork truck can 360 degree of pipe risers for rotating | |
CN206328690U (en) | A kind of big discrepancy in elevation, large span stiff skeleton external wrapping concrete template construction equipment | |
CN201099690Y (en) | Steel-smelting converter repairing equipment | |
CN207073290U (en) | Supporting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180309 |
|