CN107781505A - The integrated installation method of aerial pipeline - Google Patents

The integrated installation method of aerial pipeline Download PDF

Info

Publication number
CN107781505A
CN107781505A CN201610733563.0A CN201610733563A CN107781505A CN 107781505 A CN107781505 A CN 107781505A CN 201610733563 A CN201610733563 A CN 201610733563A CN 107781505 A CN107781505 A CN 107781505A
Authority
CN
China
Prior art keywords
module units
pipeline
suspension bracket
aerial
top support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610733563.0A
Other languages
Chinese (zh)
Inventor
孙剑
魏尚起
蔡联河
付佳军
徐冰
宁健
谭芳娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201610733563.0A priority Critical patent/CN107781505A/en
Publication of CN107781505A publication Critical patent/CN107781505A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water

Abstract

The present invention relates to the transport of building element or assembling field, the integrated installation method of specially a kind of aerial pipeline.A kind of integrated installation method of aerial pipeline, to implement in installation, aerial pipe network (1) to be installed includes pipeline (11) and suspension bracket (12), and top support platform (2) is provided with installation, it is characterized in that:Implement successively as follows:A. plan;B. set;C. lift;D. it is assembled.The present invention is easy to operate, reduces operation intensity, reduces cost, operating efficiency is high, securely and reliably.

Description

The integrated installation method of aerial pipeline
Technical field
The present invention relates to the transport of building element or assembling field, the integrated installation side of specially a kind of aerial pipeline Method.
Background technology
With metallurgical, chemical industry development, production capacity is gone to come into effect successively, with washing in a pan for largely backward production line Eliminate, the production line of many new optimizations starts to land successively, started.Aerial pipeline is known as in new production technology and production line The title of " main artery " of production line, aerial pipeline installment work are always the most important thing.Existing aerial pipeline is installed Carry out the installation of various pipelines after overcast installation one by one again.This clock installation method is uneconomical, installation workload Big and danger coefficient is high, greatly adds operating cost and the labor intensity of worker, is also unfavorable for duration progress monitoring.
The content of the invention
The defects of in order to overcome prior art, there is provided a kind of easy to operate, reduction operation intensity, reduce cost, work effect High, the safe and reliable pipeline method for dismounting of rate, the invention discloses a kind of integrated installation method of aerial pipeline.
The present invention reaches goal of the invention by following technical solution:
A kind of integrated installation method of aerial pipeline, to implement in installation, aerial pipe network to be installed includes pipeline and suspension bracket, It is laid in suspension bracket to each bar pipe level, top support platform is provided with installation, the top of suspension bracket is fixed on the top on installation ground In support platform, top support platform selects the ceiling of factory building, or in ground vertical columns, it is flatly solid on each root post Determine crossbeam, using crossbeam as top support platform, it is characterized in that:Implement successively as follows:
A is planned:Module units is determined according to aerial pipe network, module units includes piping unit and suspension bracket unit, piping unit are solid It is scheduled in suspension bracket unit, two end faces of each module units are mating surface, i.e., include one between adjacent two mating surfaces Module units;
B is set:Suspension centre is fixed on top support platform, a module units, each suspension centre are included between adjacent two suspension centres On a boom hoisting is all set, each boom hoisting is all hitched module units;
C is lifted:Each module units is promoted to setting height(from bottom) with boom hoisting, makes adjacent module units mutual with mating surface Fit;
D is assembled:Adjacent module units is sequentially connected, each module units is pieced together completely aerial pipe network, during split Piping unit pieces together pipeline successively, and suspension bracket unit pieces together suspension bracket successively, and the top of each suspension bracket is all fixed on into top support Platform.
The integrated installation method of described aerial pipeline, it is characterized in that:
When step b is set, boom hoisting is from differential chain block or lifting steel wire rope, the lifting force sum of two neighboring boom hoisting Not less than 1.2 times of module units weight;
During step d assembly, unit is assembled from gas welding.
The present invention makees integrated segmentation by carrying out pipeline and its support, and rationally sets mating surface, by substantial amounts of high-altitude Assembly working is reduced to two sex works, by pipeline and its support integral installation, greatly reduces the danger of work high above the ground Property and operation intensity, improve construction speed and reduce construction cost.Present invention can be suitably applied in factory building and outside factory building it is large-scale Comprehensive pipe network removes work.
The beneficial effects of the invention are as follows:It is easy to operate, operation intensity is reduced, reduces cost, operating efficiency is high, safely may be used Lean on.
Brief description of the drawings
Fig. 1 is the schematic diagram for the module units that split is treated in the present invention;
Fig. 2 is the diagrammatic cross-section of the aerial pipe network after the completion of the present invention;
Fig. 3 is the schematic diagram of the aerial pipe network after the completion of the present invention.
Embodiment
The present invention is further illustrated below by way of specific embodiment.
Embodiment 1
A kind of integrated installation method of aerial pipeline, implement in installation, aerial pipe network 1 to be installed includes pipeline 11 and hung Frame 12, each bar pipeline 11 are flatly laid in suspension bracket 12, are provided with top support platform 2 in installation, the top of suspension bracket 12 is fixed On the top support platform 2 on installation ground, top support platform 2 selects the ceiling of factory building, or as shown in Figure 3:Fixed on ground Column 21, flatly fixed cross beam 22 on each root post 21, using crossbeam 22 as top support platform 2, as follows successively Implement:
A is planned:It is as shown in Figure 1 according to aerial pipe network 1 determination module units 13, module units 13:Including the He of piping unit 131 Suspension bracket unit 132, piping unit 131 are fixed in suspension bracket unit 132, and two end faces of each module units 13 are mating surface 3, A module units 13 is included between two i.e. adjacent mating surfaces 3;
B is set:Suspension centre 4 is fixed on top support platform 2, includes a module units 13 between adjacent two suspension centres 4, often One boom hoisting 5 is all set on individual suspension centre 4, each boom hoisting 5 is all hitched module units 13;Boom hoisting 5 is from poor Movable pulley or lifting steel wire rope, the lifting force sum of two neighboring boom hoisting 5 are not less than 1.2 times of the weight of module units 13;
C is lifted:Each module units 13 is promoted to setting height(from bottom) with boom hoisting 5, makes adjacent module units 13 with split Face 3 mutually fits;
D is assembled:Adjacent module units 13 is sequentially connected with gas welding, pieces together each module units 13 complete aerial Pipe network 1, piping unit 131 pieces together pipeline 11 successively during split, and suspension bracket unit 132 pieces together suspension bracket 12 successively, is hung each The top of frame 12 is all fixed on top support platform 2, after the completion of aerial pipe network 1 as shown in Figures 2 and 3.

Claims (2)

1. a kind of integrated installation method of aerial pipeline, implement in installation, aerial pipe network (1) to be installed includes pipeline (11) flatly it is laid in suspension bracket (12) with suspension bracket (12), each bar pipeline (11), top support platform (2) is provided with installation, The top of suspension bracket (12) is fixed on the top support platform (2) on installation ground, and top support platform (2) selects the ceiling of factory building, or Person flatly fixed cross beam (22) on each root post (21), top support is used as using crossbeam (22) in ground vertical columns (21) Platform (2), it is characterized in that:Implement successively as follows:
A is planned:Module units (13) is determined according to aerial pipe network (1), module units (13) includes piping unit (131) and hung Frame unit (132), piping unit (131) are fixed in suspension bracket unit (132), and two end faces of each module units (13) are spelling Conjunction face (3), i.e., a module units (13) is included between adjacent two mating surfaces (3);
B is set:Suspension centre (4) is fixed on top support platform (2), a module units is included between adjacent two suspension centres (4) (13) boom hoisting (5), is set on each suspension centre (4), each boom hoisting (5) is all hitched module units (13);
C is lifted:Each module units (13) is promoted to setting height(from bottom) with boom hoisting (5), makes adjacent module units (13) Mutually fitted with mating surface (3);
D is assembled:Adjacent module units (13) is sequentially connected, each module units (13) is pieced together complete cross-over pipe Net (1), piping unit (131) pieces together pipeline (11) successively during split, and suspension bracket unit (132) pieces together suspension bracket (12) successively, The top of each suspension bracket (12) is all fixed on top support platform (2).
2. the integrated installation method of aerial pipeline as claimed in claim 1, it is characterized in that:
When step b is set, boom hoisting (5) is from differential chain block or lifting steel wire rope, the lifting of two neighboring boom hoisting (5) Power sum is not less than 1.2 times of module units (13) weight;
During step d assembly, unit (13) is assembled from gas welding.
CN201610733563.0A 2016-08-27 2016-08-27 The integrated installation method of aerial pipeline Pending CN107781505A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610733563.0A CN107781505A (en) 2016-08-27 2016-08-27 The integrated installation method of aerial pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610733563.0A CN107781505A (en) 2016-08-27 2016-08-27 The integrated installation method of aerial pipeline

Publications (1)

Publication Number Publication Date
CN107781505A true CN107781505A (en) 2018-03-09

Family

ID=61439927

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610733563.0A Pending CN107781505A (en) 2016-08-27 2016-08-27 The integrated installation method of aerial pipeline

Country Status (1)

Country Link
CN (1) CN107781505A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109160416A (en) * 2018-10-30 2019-01-08 北京机械设备研究所 A kind of method and device of hydraulic pipe network integral hoisting

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0726726A (en) * 1993-05-14 1995-01-27 Mitsubishi Heavy Ind Ltd Zone module construction method for constructing steel structure
CN101451397A (en) * 2007-12-05 2009-06-10 中冶天工建设有限公司 Steel structure modularization construction process
CN103615601A (en) * 2013-11-11 2014-03-05 中国北车集团大连机车车辆有限公司 Locomotive pipeline and cable composite assembling method
CN203770835U (en) * 2013-10-30 2014-08-13 森松(江苏)海油工程装备有限公司 Spliced structure of modularized pipe gallery transportation unit
CN104806822A (en) * 2015-04-16 2015-07-29 上海市安装工程集团有限公司 Combined type stand pipe and modularized installation method thereof
CN105421792A (en) * 2015-12-15 2016-03-23 安徽伟宏钢结构集团股份有限公司 Lifting construction process of modular steel structural components

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0726726A (en) * 1993-05-14 1995-01-27 Mitsubishi Heavy Ind Ltd Zone module construction method for constructing steel structure
CN101451397A (en) * 2007-12-05 2009-06-10 中冶天工建设有限公司 Steel structure modularization construction process
CN203770835U (en) * 2013-10-30 2014-08-13 森松(江苏)海油工程装备有限公司 Spliced structure of modularized pipe gallery transportation unit
CN103615601A (en) * 2013-11-11 2014-03-05 中国北车集团大连机车车辆有限公司 Locomotive pipeline and cable composite assembling method
CN104806822A (en) * 2015-04-16 2015-07-29 上海市安装工程集团有限公司 Combined type stand pipe and modularized installation method thereof
CN105421792A (en) * 2015-12-15 2016-03-23 安徽伟宏钢结构集团股份有限公司 Lifting construction process of modular steel structural components

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109160416A (en) * 2018-10-30 2019-01-08 北京机械设备研究所 A kind of method and device of hydraulic pipe network integral hoisting

Similar Documents

Publication Publication Date Title
CN105908761B (en) A kind of high slope hanging basket mobile platform construction technology
CN107191676A (en) Buried pipeline construction method
CN204199721U (en) A kind of erecting device for factory building construction high and medium structure
CN105781590B (en) TBM bears ring with reception hole and removes technique
CN203654702U (en) Operating platform for construction of reinforced concrete chimney
CN204753397U (en) Gallows is installed to steel case bridge temporarily
CN208151865U (en) A kind of introversion formula steel case arch bridge integrally promotes simulation Lift-on/Lift-off System
CN107781505A (en) The integrated installation method of aerial pipeline
CN203867198U (en) Slip equipment for high-rise steel structure transfer layer truss
CN106016233A (en) Boiler roof with long span and fewer welding spots and hoisting method for boiler roof
CN204474106U (en) Deep shaft manned lift device
CN106044580A (en) Whole lifting method of wet electrostatic dust removing device body equipment
CN203486787U (en) Integral lifting device for cabinet top of Wiggins coal gas cabinet
CN205575534U (en) Lattice formula groined type support body lifting means
CN105060124B (en) Intra-frame portal crane system and hoisting use method thereof
CN106121254A (en) Heavy component transportation system and construction method after a kind of contrary sequence method dismounting
CN107781504A (en) The integrated method for dismounting of aerial pipeline
CN211009152U (en) Underwater fire pump
CN205077876U (en) Machine and stressing jack linkage are worn to restraint by prestress wire
CN206328067U (en) Movable draining platform
CN207226943U (en) A kind of double crossbeam synchronous hoisting devices
CN206014340U (en) A kind of cooperation fork truck can 360 degree of pipe risers for rotating
CN206328690U (en) A kind of big discrepancy in elevation, large span stiff skeleton external wrapping concrete template construction equipment
CN201099690Y (en) Steel-smelting converter repairing equipment
CN207073290U (en) Supporting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180309

RJ01 Rejection of invention patent application after publication