CN107762501A CN201610677532.8A CN201610677532A CN107762501A CN 107762501 A CN107762501 A CN 107762501A CN 201610677532 A CN201610677532 A CN 201610677532A CN 107762501 A CN107762501 A CN 107762501A
Authority
CN
China
Prior art keywords
frame
rock body
helldriver
group
splits
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610677532.8A
Other languages
Chinese (zh)
Inventor
陈林
初文
宋祖鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610677532.8A priority Critical patent/CN107762501A/en
Publication of CN107762501A publication Critical patent/CN107762501A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C25/00Cutting machines, i.e. for making slits approximately parallel or perpendicular to the seam
    • E21C25/66Machines for making slits with additional arrangements for drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C25/00Cutting machines, i.e. for making slits approximately parallel or perpendicular to the seam
    • E21C25/68Machines for making slits combined with equipment for removing, e.g. by loading, material won by other means

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Earth Drilling (AREA)

Abstract

Bored the invention discloses one kind and split helldriver, including car body mechanism, the rock body being connected in car body mechanism, cleaving mechanism, slag removal mechanism and supporting mechanism, wherein, rock body and cleaving mechanism are respectively multiple, and the rock body group and a cleaving mechanism group of an arrangement architecture are made up of a housing assembly respectively, rock body group and cleaving mechanism group are connected in car body mechanism by a working arm respectively.The present invention splits rock, slag removal mechanism continuous crushing and deslagging using the drilling of rock body cluster, cleaving mechanism cluster and supporting mechanism carries out supporting, and applied widely, operating efficiency is high.

Description

One kind, which is bored, splits helldriver
Technical field
The present invention relates to a kind of development machine, specifically, be related to one kind be mainly used in Urban Underground rock tunnel dig, The driving of rock tunnel, even ground work in the engineering construction such as mine rock tunnelling and water conservancy, railway, highway, national defence The brill of the rock developing of journey splits helldriver.
Background technology
The piercing technique method of rock tunnel has two kinds in the world at present, first, drilling and blasting method, technological process are:Bore blast hole → explosive blasting → ventilation depositing dust → is slagged tap;Second, shield method, technological process are:Engineering preparation (vertical shaft or inclined shaft, for transferring TBM shield machine systems) → shield machine system installation → continuous driving → continuously slags tap.
Drilling and blasting method technique tradition, belongs to discontinuous process, and each procedure is both needed to the long period, particularly divulges information depositing dust and to go out Most times that the consumption of slag process is entirely tunneled, operating efficiency is low, 40m2The daily drilling depth of rock tunnel of left and right section Less than 10 meters, security is low, big to workmen and equipment menace.In addition, drill bursting construction is of poor quality, country rock is shaken by explosion Dynamic to cause to loosen and unstable, supporting requires high, bores quick-fried technique in Urban Underground or the environment for being not allow for this vibrations damage and is Do not allow what is used, it is often more important that it is seriously controlled that the explosive needed for explosion is in security purpose.Therefore, quick-fried technique is bored in tunnel More fall behind in excavation work.
Shield method technique is advanced, and equipment is high-end, and good engineering quality, efficiency is higher, this be also use at present it is more and more Rock tunnel piercing technique and equipment.But shield method engineering preparation workload is big, investment is high, equipment set-up time length, dress Machine capacity is big, and electric energy and cutter consumption are big, and overall operation cost is high, and maximum limitation is the adaptability of formation hardness, rock Stone hardness is less than 90MP/cm2When do not apply to, and the bigger driving speed of hardness is slower, and cutter loss is more serious, and cost is higher, surpasses Cross 180MP/cm2Shi Jiben can not work.
Publication No. is that CN102261250A Chinese invention patent application discloses a kind of hydraulic crushing-type excavator for hard rock, Whole machine installation rock drilling arm and broken rock arm, the tunneling method of broken rock after first drilling is taken, collect drilling, broken rock, rewinding, transport in one Body, have the functions such as walking and dedusting concurrently, it is possible to achieve the driving in superhard total rock tunnel, but its drilling machine and broken rock machine structure list One, operating efficiency is limited.
The content of the invention
Bored it is an object of the invention to provide one kind and split helldriver, using the drilling of rock body cluster, cleaving mechanism collection Group splits rock, slag removal mechanism continuous crushing and deslagging and supporting mechanism carries out supporting, and applied widely, operating efficiency is high.
To achieve these goals, brill of the invention splits helldriver, including car body mechanism, is connected to the car Rock body, cleaving mechanism, slag removal mechanism and supporting mechanism on body mechanism, wherein, the rock body and cleaving mechanism It is respectively multiple, and rock body group and the cleaving mechanism group of an arrangement architecture are made up of a housing assembly respectively Group, the rock body group and cleaving mechanism group are connected in the car body mechanism by a working arm respectively.
Above-mentioned brill is split in an embodiment of helldriver, and each housing assembly includes a cluster frame and company At least one be connected in the cluster frame is disbursed from the cost and expenses frame, described to be disbursed from the cost and expenses frame to set the rock body/cleaving mechanism.
Above-mentioned brill is split in an embodiment of helldriver, and the frame of being disbursed from the cost and expenses has row's structure stacked up and down, and Each row's structure of the frame of being disbursed from the cost and expenses is used to set a rock body/cleaving mechanism.
Above-mentioned brill is split in an embodiment of helldriver, and the bottom of the frame of being disbursed from the cost and expenses is provided with lowering or hoisting gear, institute The relatively described cluster frame of frame of being disbursed from the cost and expenses described in lowering or hoisting gear drive is stated to move up and down.
Above-mentioned brill is split in an embodiment of helldriver, and the housing assembly also includes multiple pedestals, multiple cunnings Road and multiple slideway bases, each rock body are slidably connected on the slideway by the pedestal respectively, the cunning Road is connected on the slideway base, and the slideway base is fixed on described be disbursed from the cost and expenses in corresponding row's structure of frame.
Above-mentioned brill is split in an embodiment of helldriver, and the rock body group also includes multiple slideway hydraulic pressure Cylinder, the slideway hydraulic cylinder are connected to the rear portion of the slideway.
Above-mentioned brill is split in an embodiment of helldriver, and the rock body group also includes multiple working hydraulic pressures Cylinder, the hydraulic cylinder for working are connected between the rock body and the slideway base.
Above-mentioned brill is split in an embodiment of helldriver, has limit between the cluster frame and the frame of being disbursed from the cost and expenses Position slideway mechanism.
Above-mentioned brill is split in an embodiment of helldriver, and the rock body group is one, the splitting machine Structure group is two, and two cleaving mechanism groups are respectively arranged at the both sides of the rock body group.
Above-mentioned brill is split in an embodiment of helldriver, and the rock body group is two, the splitting machine Structure group is two, and two cleaving mechanism groups may be contained between two cleaving mechanism groups.
The beneficial functional of the present invention is, splits helldriver using the brill of the present invention, brill splits same machine, joint driving, pole Improve operating efficiency greatly.
Below in conjunction with the drawings and specific embodiments, the present invention will be described in detail, but not as a limitation of the invention.
Brief description of the drawings
The brill that Fig. 1 is the present invention splits helldriver in the structural representation of an operating mechanism position;
The brill that Fig. 2 is the present invention splits helldriver in the structural representation of another operating mechanism position;
Fig. 3 is front view (the removal cluster frame side that the brill of the present invention splits the rock body group of helldriver Wall);
Fig. 4 is Fig. 3 right view;
Fig. 5 is Fig. 3 top view;
Fig. 6 is the structural representation for another embodiment that the brill of the present invention splits the rock body group of helldriver;
Fig. 7 is that the brill of the present invention splits the structural representation for sliding hydraulic cylinder action and promoting slideway motion of helldriver;
Fig. 8 is the structural representation that the brill of the present invention splits the lowering or hoisting gear action drive row support motion of helldriver;
Fig. 9 is the front view for the embodiment that the brill of the present invention splits the cleaving mechanism group of helldriver;
Figure 10 is Fig. 9 top view.
Wherein, reference
100 car body mechanisms
200 rock body groups
210 rock bodies
220 slideway hydraulic cylinders
230 hydraulic cylinder for working
300 cleaving mechanism groups
310 cleaving mechanism
400 slag removal mechanisms
500 supporting mechanisms
600 working arms
700th, 700a housing assemblies
710th, 700a clusters frame
720th, 700a is disbursed from the cost and expenses frame
721st, 721a arranges structure
730 pedestals
740 slideways
750 slideway bases
760th, 700a lowering or hoisting gears
770 spacing slideway mechanisms
Embodiment
Technical solution of the present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings, to be further understood that The purpose of the present invention, scheme and effect, but it is not intended as the limitation of scope of the appended claims of the present invention.
The brill of the present invention splits the helldriver course of work and comprised the following steps:Dig the scope of freedom, drilling, deslagging and branch Shield.
As depicted in figs. 1 and 2, brill of the invention, which splits helldriver, includes car body mechanism 100, operating mechanism, slag remover Structure 400, supporting mechanism 500 and working arm 600, slag removal mechanism 400, supporting mechanism 500 and working arm 600 are connected to car On body mechanism 100.Operating mechanism includes rock body group 200 and cleaving mechanism group 300.Rock body group 200 includes Multiple rock bodies 210, multiple rock bodies 210 are made up of the rock body group of arrangement architecture a housing assembly 700 200.Likewise, cleaving mechanism group 300 includes multiple cleaving mechanism 310, multiple cleaving mechanism 310 pass through a housing assembly 700a forms the cleaving mechanism group 300 of arrangement architecture.Rock body group 200 and cleaving mechanism group 300 pass through one respectively Working arm 600 is connected in car body mechanism 100.
Wherein, car body mechanism 100 includes walking mechanism, driver's cabin, operating desk, control system, dynamical system, hydraulic system Deng.Require that it is more that the walking mechanism of car body mechanism 100 may be designed as crawler type, wheeled, rail mounted etc. according to the difference of tunnel system Kind mode;Main control system, dynamical system and hydraulic system can according to demand be arranged on car body or hang shape after being designed to Formula.
Slag removal mechanism 200 includes backhoe type slagging-off bucket, boulder cracker, drag conveyor, outer conveying belt type conveyer etc.. Wherein, backhoe type slagging-off bucket work, the rubble of working face is collected into collection slag scraper bowl;Drag conveyor in scraper bowl is by rubble It is transported to the boulder cracker at rear;Boulder cracker crushes bulk rubble, discharge termination outward transport ribbon conveyer, is responsible for slag Tunnel is transported outside stone.
According to the geological conditions characteristic in tunnel, supporting mechanism 500 can take some support mode such as shotcrete, section of jurisdiction.
Working arm 600 is furnished with multiple piston-type hydraulic cylinders and rotary oil cylinder.Before tunnel piercing operation is carried out, multiple work Arm 600 is under the cooperation effect of each hydraulic system, by operating mechanism (rock body group 200 and cleaving mechanism group 300) it is fixed on setting position (referring to Fig. 1 and Fig. 2, operating mechanism has different positions).By adjusting each hydraulic cylinder Running, the working range of working arm 600 can cover whole tunnel front, and can make the regulation of operating mechanism's progress all angles And rotation.Different according to tunnel width, the design can design multiple working arms 600 while manipulate multiple rock body groups 200 Excavation operation is carried out with cleaving mechanism group 300, improves efficiency.
The rock body group of operating mechanism 200 and cleaving mechanism group 300 of the present invention are specifically described below.
As shown in Figures 3 to 5, rock body group 200 is installed on the front end of working arm 600, the multiple rock drilling of cluster arrangement Mechanism 210, arrangement straight line (referring to Fig. 6) or multiple row, single row or multiple rows arrangement.Spacing between rock body 210 (row and row, between row and row distance) can be adjusted according to splitting pitch-row requirement.Often cover each column in rock body group 200 With the quantity of every row's rock body 210 30 sets are set to according to tunnel cross-section and size and driving schedule requirement arrangement, total amount not from 2 Deng.
Specifically, housing assembly 700 includes cluster frame 710 and at least one and is disbursed from the cost and expenses frame 720, and frame 720 of being disbursed from the cost and expenses is connected to collection In group's frame 710, frame 720 is disbursed from the cost and expenses to set rock body 210.
Frame 720 of being disbursed from the cost and expenses has row's structure 721 stacked up and down, and each row's structure 721 for frame 720 of being disbursed from the cost and expenses is used to set one Individual rock body 210.
Housing assembly 700 also includes multiple pedestals 730, multiple slideways 740 and multiple slideway bases 750.Every hydraulic pressure chisel Rock mechanism 210 is fixed on pedestal 730, and pedestal 730 is fixed on slideway 740, and slideway 740 is fixed on slideway base 750, i.e., every One rock body 210 is slidably connected on slideway 740 by pedestal 730 respectively, and slideway 740 is fixed on by slideway base 750 It is disbursed from the cost and expenses on frame 720 accordingly in row's structure 721.According to being actually needed, frame 720 of being each disbursed from the cost and expenses can install 2 to 10 chisels not waited Rock mechanism 210, cluster frame 710 can arrange 1 to 10 frame 720 of being disbursed from the cost and expenses, i.e. a housing assembly 700 can install 2~100 chisels Rock mechanism 210.
For the frame 720 of being disbursed from the cost and expenses of housing assembly 700 shown in Fig. 4 with three, frame 720 of being each disbursed from the cost and expenses has four row's structures 721, each structure 721 of arranging is respectively provided with a rock body 210, that is, 12 clusters of rock body 210 form the row's of three row four Rock body group 200.
Each bottom for being disbursed from the cost and expenses frame 720 is respectively provided with lowering or hoisting gear 760, and lowering or hoisting gear 760 can drive frame 720 of being disbursed from the cost and expenses relative Cluster frame 710 moves up and down, so that the position of each independent adjustment short transverse of rock body 210 being disbursed from the cost and expenses on frame 720, such as Shown in Fig. 8.By setting lowering or hoisting gear 760, position can adjust up and down between the column and the column, to adapt to circular or arched tunnel The drilling of section.Lowering or hoisting gear 760 is, for example, rackwork, screw mechanism, hydraulic cylinder mechanism etc..
As shown in figure 5, there is spacing slideway mechanism 770 between cluster frame 710 and frame 720 of being disbursed from the cost and expenses, it is spacing to slide into mechanism 770 adjustment and installation that can be easy to be disbursed from the cost and expenses frame 720.
The front end of slideway 740 is provided with triangle mechanism, for being brought into close contact with palisades to be tunneled, to provide stable branch Support.
Rock body group 200 also includes multiple slideway hydraulic cylinders 220, and slideway hydraulic cylinder 220 is connected to setting rock drill The rear portion of each slideway 740 of structure 210.Slideway hydraulic cylinder 220 is set to be used for before starting to headwork to promoting slideway 740 Initial position is adjusted, and to ensure in all hydraulic rock body 210 before drilling, slideway 740 is steadily contacted with palisades, such as Shown in Fig. 7.
Rock body group 200 also includes multiple hydraulic cylinder for working 230, is hollow mechanism in slideway 740, hydraulic cylinder for working 230 loaded in slideway 740, and the cylinder bucket of hydraulic cylinder for working 230 is fixed on slideway base 750, and piston rod front end is by being fixed on It is responsible for promoting rock body 210 to move forward and backward to connect rock body 210 on pedestal 730, during work.
Cleaving mechanism group 300 is installed on the front end of working arm 600, the multiple cleaving mechanism 310 of cluster arrangement, arrangement Straight line or multiple row, single row or multiple rows arrangement.Between rock cleavage mechanism 310 spacing (row with row, between row and row away from From) can be adjusted according to splitting pitch-row requirement.Often cover each column in cleaving mechanism group 300 and often arrange cleaving mechanism 310 Quantity is set to 20 sets according to tunnel cross-section and size and driving schedule requirement arrangement, total amount from 2.
As shown in Figure 9 and Figure 10, multiple cleaving mechanism 310 pass through housing assembly 700a cluster arrangements.Housing assembly 700a Including cluster frame 710a, at least one frame 720a and lowering or hoisting gear 760a that is disbursed from the cost and expenses.The frame 720a that is disbursed from the cost and expenses has row stacked up and down Structure 721a, cleaving mechanism 310 are arranged in plurality of rows of form and are disbursed from the cost and expenses on frame 720a;The frame 720a that is disbursed from the cost and expenses is fixed on cluster frame On 710a, multiple frame 720a that are disbursed from the cost and expenses can be arranged as required to.
According to tunnel piercing technique and hydraulic rock system, different rows and columns can be set by housing assembly 700a Cleaving mechanism 310, this point is similar to the cluster arrangement mode of rock body 210.
Each bottom for being disbursed from the cost and expenses frame 720a is respectively provided with lowering or hoisting gear 760a, and lowering or hoisting gear 760a can drive the frame 720a that is disbursed from the cost and expenses Moved up and down with respect to cluster frame 710a, so that each independent adjustment short transverse of cleaving mechanism 310 being disbursed from the cost and expenses on frame 720a Position.
When carrying out tunnel piercing operation, working arm 600 first adjusts driving angle and the position of rock body group 200 (as depicted in figs. 1 and 2).Further according to bore position demand, the frame of being disbursed from the cost and expenses adjusted by the lowering or hoisting gear 760 of housing assembly 700 720 upper-lower position (as shown in Figure 8);Subsequent start-up slideway hydraulic cylinder 220, slideway 740 is promoted, make its front end triangle stable Mechanism is in close contact (as shown in Figure 7) with palisades;After the front end rock-steady structure of slideway 740 is with palisades fixation, start work Make hydraulic cylinder 230 and start rock body 210, promote rock body 210 to advance to palisades direction and start excavation operation.
The course of work of rock body 210 is:The position of cleaving mechanism group 300 is adjusted by working arm 600 first, and is led to Lowering or hoisting gear 760a adjustment housing assemblies 700a each frame 720a positions of being disbursed from the cost and expenses are crossed, cleaving mechanism 310 is aligned rock body 210 petrosal foramens dug out, then promote cleaving mechanism 310 to advance and go deep into petrosal foramen.
Deslagging and supporting step are carried out simultaneously, until completing tunnel piercing.
It is with crawler belt that the car body mechanism 100 of the present invention, which can use caterpillar track travelling or the major class of railing two, crawler type, Walking mechanism is platform, installs other all functional modules.Creeper undercarriage can be electronic or hydraulic-driven.Track Formula lays track when being and digging tunnel, and development machine overall structure forms platform by support of track, is installed on platform other all Functional module.The propulsion of rail mounted development machine is realized by oil cylinder step type.
Each major class is divided into three series according to the difference of operating mechanism's quantity, is divided into:
It is single to bore simple check:Rock body group 200 is one, and cleaving mechanism group 300 is one.Brill splits helldriver Two sets of working arms are installed in front end, and a rock body group 200, the front end installation of a set of working arm are installed in the front end of a set of working arm One cleaving mechanism group 300.
It is single to bore double split:Rock body group 200 is one, and cleaving mechanism group 300 is two.Brill splits helldriver A working arm is arranged in front end left, center, right, and middle working arm is used to install rock body group 200, and left and right working arm is respectively installed a set of Cleaving mechanism group 300.
It is double to bore double split:Rock body group 200 is two, and cleaving mechanism group 300 is two.Before brill splits helldriver End four sets of hydraulic arms of arrangement, middle two working arms are used to install Liang Tao rock bodies group 200, the respectively installation one of left and right working arm Cover cleaving mechanism group 300.
Certainly, the present invention can also have other various embodiments, ripe in the case of without departing substantially from spirit of the invention and its essence Know those skilled in the art when can be made according to the present invention it is various it is corresponding change and deformation, but these corresponding change and become Shape should all belong to the protection domain of appended claims of the invention.

Claims (10)

1. one kind, which is bored, splits helldriver, including car body mechanism, the rock body being connected in the car body mechanism, splitting Mechanism, slag removal mechanism and supporting mechanism, it is characterised in that the rock body and cleaving mechanism are respectively multiple, and respectively The rock body group and a cleaving mechanism group of an arrangement architecture, the rock body group are made up of a housing assembly It is connected to respectively by a working arm in the car body mechanism with cleaving mechanism group.
2. brill according to claim 1 splits helldriver, it is characterised in that each housing assembly includes a cluster Frame and what is be connected in the cluster frame at least one be disbursed from the cost and expenses frame, it is described to be disbursed from the cost and expenses frame to set the rock body/splitting Mechanism.
3. brill according to claim 2 splits helldriver, it is characterised in that the frame of being disbursed from the cost and expenses has row stacked up and down Structure, and each row's structure of the frame of being disbursed from the cost and expenses is used to set a rock body/cleaving mechanism.
4. brill according to claim 2 splits helldriver, it is characterised in that the bottom of the frame of being disbursed from the cost and expenses is provided with lifting Device, the lowering or hoisting gear drive described in the relatively described cluster frame of frame of being disbursed from the cost and expenses move up and down.
5. brill according to claim 3 splits helldriver, it is characterised in that the housing assembly also includes multiple bases Seat, multiple slideways and multiple slideway bases, each rock body are slidably connected at the slideway by the pedestal respectively On, the slideway is connected on the slideway base, and the slideway base is fixed on described be disbursed from the cost and expenses in corresponding row's structure of frame.
6. brill according to claim 5 splits helldriver, it is characterised in that the rock body group also includes multiple Slideway hydraulic cylinder, the slideway hydraulic cylinder are connected to the rear portion of the slideway.
7. brill according to claim 5 splits helldriver, it is characterised in that the rock body group also includes multiple Hydraulic cylinder for working, the hydraulic cylinder for working are connected between the rock body and the slideway base.
8. brill according to claim 2 splits helldriver, it is characterised in that the cluster frame and it is described be disbursed from the cost and expenses frame it Between there is spacing slideway mechanism.
9. brill according to claim 1 splits helldriver, it is characterised in that the rock body group is one, institute Cleaving mechanism group is stated as two, two cleaving mechanism groups are respectively arranged at the both sides of the rock body group.
10. brill according to claim 1 splits helldriver, it is characterised in that the rock body group is two, institute Cleaving mechanism group is stated as two, two cleaving mechanism groups may be contained between two cleaving mechanism groups.
CN201610677532.8A 2016-08-16 2016-08-16 One kind, which is bored, splits helldriver Pending CN107762501A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610677532.8A CN107762501A (en) 2016-08-16 2016-08-16 One kind, which is bored, splits helldriver

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610677532.8A CN107762501A (en) 2016-08-16 2016-08-16 One kind, which is bored, splits helldriver

Publications (1)

Publication Number Publication Date
CN107762501A true CN107762501A (en) 2018-03-06

Family

ID=61260167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610677532.8A Pending CN107762501A (en) 2016-08-16 2016-08-16 One kind, which is bored, splits helldriver

Country Status (1)

Country Link
CN (1) CN107762501A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109882191A (en) * 2019-04-02 2019-06-14 许和翔 A kind of all-hydraulic cleave-cracking bench vehicle
CN110219662A (en) * 2019-06-20 2019-09-10 中铁隧道局集团有限公司 A kind of device and method using boulder in front of high -pressure water cutting tunnel
CN112695724A (en) * 2020-12-14 2021-04-23 国网福建省电力有限公司 Hydraulic bracing mechanism of ship lift
CN113446015A (en) * 2021-08-03 2021-09-28 哈尔滨工业大学 Soil pressure adjustable-mining method dual-mode shield tunneling machine and construction method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109882191A (en) * 2019-04-02 2019-06-14 许和翔 A kind of all-hydraulic cleave-cracking bench vehicle
CN109882191B (en) * 2019-04-02 2024-04-12 许和翔 Full-hydraulic splitting trolley
CN110219662A (en) * 2019-06-20 2019-09-10 中铁隧道局集团有限公司 A kind of device and method using boulder in front of high -pressure water cutting tunnel
CN110219662B (en) * 2019-06-20 2020-10-02 中铁隧道局集团有限公司 Device and method for cutting boulder in front of tunnel by using high-pressure water
CN112695724A (en) * 2020-12-14 2021-04-23 国网福建省电力有限公司 Hydraulic bracing mechanism of ship lift
CN112695724B (en) * 2020-12-14 2022-06-10 国网福建省电力有限公司 Hydraulic supporting mechanism of ship lift
CN113446015A (en) * 2021-08-03 2021-09-28 哈尔滨工业大学 Soil pressure adjustable-mining method dual-mode shield tunneling machine and construction method thereof
CN113446015B (en) * 2021-08-03 2022-08-02 哈尔滨工业大学 Soil pressure adjustable-mining method dual-mode shield tunneling machine and construction method thereof

Similar Documents

Publication Publication Date Title
CN205936603U (en) Brill splits combined tunnel boring machine
CN202510121U (en) Hard rock boring machine
CN101349533B (en) Dip laneway digging hole layout mode
CN101737050B (en) Deep hole arranging method in mining
CN201236704Y (en) Coal drift drill shipping and anchoring integrated machine
CN101105129B (en) Mining environment reconstructed continuous mining afterwards filling mining method
CN103291308B (en) For boom-type roadheader and the method for tunnel construction of constructing tunnel
CN103527196B (en) Method for recovery of room-type coal pillar through loess filling
CN105952450B (en) A kind of new method of the double stope collaboration exploitations in underground mine underground
CN107762501A (en) One kind, which is bored, splits helldriver
CN107816353B (en) A kind of excessive drop tomography new method of fully-mechanized mining working
CN110242300B (en) Splitting mechanism and tunneling equipment
CN107829741B (en) Mining method of gently inclined thin ore body
Liu et al. Key technologies of drilling process with raise boring method
CN102787847A (en) Roadway tunneling machine
CN103850685A (en) Heading machine applicable to drill vertical well through pioneer well
CN103790584A (en) Impact-assisted heading machine for hard rock ore exploitation
CN104564089A (en) Rock roadway quick tunneling process of impact crushing rock roadway tunneling machine
CN108150177B (en) Multi-functional hard-rock tunnel fast digging technique and equipment
CN107191191A (en) A kind of rock gangway fast digging technique of the breaking rock gangway anchor driving machine of three hammering blows
CN111140246A (en) Full-section multifunctional non-explosive excavating equipment
CN101302932A (en) Method for underground chamber digging and laneway opening digging
CN201650332U (en) Hydraulic supporting device for fully-mechanized coal winning working face
CN202810858U (en) Roadway heading machine
CN113356847A (en) Rock swelling and breaking equipment and rock swelling and breaking construction method for tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180306

WD01 Invention patent application deemed withdrawn after publication