CN107762075A - 一种提高施工效率的挤塑板保温屋面的施工方法 - Google Patents

一种提高施工效率的挤塑板保温屋面的施工方法 Download PDF

Info

Publication number
CN107762075A
CN107762075A CN201610678945.8A CN201610678945A CN107762075A CN 107762075 A CN107762075 A CN 107762075A CN 201610678945 A CN201610678945 A CN 201610678945A CN 107762075 A CN107762075 A CN 107762075A
Authority
CN
China
Prior art keywords
construction
layer
encapsulant
paving
coiled material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201610678945.8A
Other languages
English (en)
Inventor
彭建明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610678945.8A priority Critical patent/CN107762075A/zh
Publication of CN107762075A publication Critical patent/CN107762075A/zh
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D11/00Roof covering, as far as not restricted to features covered by only one of groups E04D1/00 - E04D9/00; Roof covering in ways not provided for by groups E04D1/00 - E04D9/00, e.g. built-up roofs, elevated load-supporting roof coverings
    • E04D11/02Build-up roofs, i.e. consisting of two or more layers bonded together in situ, at least one of the layers being of watertight composition

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Press-Shaping Or Shaping Using Conveyers (AREA)

Abstract

本发明公开了一种提高施工效率的挤塑板保温屋面的施工方法,包括找坡层施工、保温层施工、水泥砂浆找平层施工、防水层施工这些步骤,檐口将铺贴到檐口端头的卷材裁齐后压入凹槽内,然后将凹槽用密封材料嵌填密实,用压条或用带垫片钉子固定时,钉子应敲入凹槽内,钉帽及卷材端头用密封材料封严;每个部位经防水试验24小时后,无渗漏、阴湿,应马上进行保护层施工,保护层的施工做法应符合设计要求。该方法步骤严谨,对于挤塑板保温屋面所有位置都能够进行施工,施工的效率高,而且缩短了工期,解决了现有对挤塑板保温屋面施工时,其步骤设计不严谨,使得容易出现漏掉的施工位置,需要重新进行施工,施工效率低,工期长的问题。

Description

一种提高施工效率的挤塑板保温屋面的施工方法
技术领域
本发明涉及一种方法,尤其是涉及一种提高施工效率的挤塑板保温屋面的施工方法。
背景技术
从广义上来说,建筑学是研究建筑及其环境的学科。建筑学是一门横跨工程技术和人文艺术的学科。建筑学所涉及的建筑艺术和建筑技术、以及作为实用艺术的建筑艺术所包括的美学的一面和实用的一面,它们虽有明确的不同但又密切联系,并且其分量随具体情况和建筑物的不同而大不相同。中国古代建筑具有朴素淡雅的风格,主要以茅草、木材为建筑材料,以木架构为结构方式(柱、梁、枋、檩、椽等构件),按照结构需要的实际大小、形状和间距组合在一起。这种建筑结构方式反映了古代宗法社会结构的清晰、有序和稳定。由于木质材质制作的梁柱不易形成巨大的内部空间,古代建筑便巧妙地利用外埠自然空间,组成庭院。庭院是建筑的基本单位,它既是封闭的,又是开放的;既是人工的,又是自然的,可以俯植花草树木,仰观风云日月,成为古人“天人合一”观念的又一表现,也体现了中国人既含蓄内向,又开拓进取的民族性格。古代稍大一些的建筑都是由若干个庭院组成的建筑群,单个建筑物和庭院沿一定走向布置,有主有次,有高潮有过渡,成为有层次、有深度的空间,呈现出一种中国人所追求的整体美和深邃美。其中宫殿、寺庙一类比较庄严的建筑,往往沿着中轴线一个接一个地纵向布置主要建筑物,两侧对称的布置次要建筑物,布局平衡舒展,引人入胜。
现有在对挤塑板保温屋面施工时,其步骤设计不严谨,使得容易出现漏掉的施工位置,需要重新进行施工,施工效率低,工期长。
发明内容
本发明的目的在于克服上述现有对挤塑板保温屋面施工时,其步骤设计不严谨,使得容易出现漏掉的施工位置,需要重新进行施工,施工效率低,工期长的问题,设计了一种提高施工效率的挤塑板保温屋面的施工方法,该方法步骤严谨,对于挤塑板保温屋面所有位置都能够进行施工,施工的效率高,而且缩短了工期,解决了现有对挤塑板保温屋面施工时,其步骤设计不严谨,使得容易出现漏掉的施工位置,需要重新进行施工,施工效率低,工期长的问题。
本发明的目的通过下述技术方案实现:一种提高施工效率的挤塑板保温屋面的施工方法,包括以下步骤:
(1)找坡层施工:先按设计坡度及流水方向,用砂浆打点定位,确保坡度、厚度正确,铺设水泥炉渣找坡,用平板振动器压实适当,表面平整,找坡正确,找坡层完工后,应用彩条布覆盖,以防浸水和破坏,铺设找坡层时,应按设计规定埋设好排气槽、管;
(2)保温层施工:基层应平整、干净、干燥;挤塑板的铺贴方式采用干铺;挤塑板不应破碎、缺棱角,铺设时遇有缺棱掉角、破碎不齐的,应锯平拼接使用,板与板间之间要错缝、挤紧,不得有缝隙,若因挤塑板裁剪不方正或裁剪不直而形成缝隙,应用挤塑板条塞入并打磨平;
(3)水泥砂浆找平层施工:使用清净中砂并过5mm孔筛,含泥量不大于3%,做好防水基层的处理,墙上四周弹出水平标高控制线,孔洞、管线应事前预埋、预留,严禁事后打洞,施工前应在底层先刷一道素水泥奖,找平层应粘结牢固,表面平整度≤5mm,找平层应设臵30宽分隔缝,间距不大于6m×6m,在女儿墙、管道出屋面处均做成半径不小于10~15cm的圆角,防水层施工前,将一块薄膜覆盖在找平层上,经过一夜后第2天早上掀起薄膜处没有明显的潮湿痕迹,则可进行防水层施工;
(4)防水层施工:基层处理剂的涂刷要薄而均匀;涂刷时间宜在铺贴油毡前1-2h进行,使油层干燥而不粘灰尘;基层处理剂涂刷后宜在当天铺完防水层,一次涂的面积,根据基层处理剂干燥时间的长短和施工进度快慢确定,卷材应平行于屋脊铺贴;防水层施工时,应先做好节点、附加层和屋面排水比较集中部位的处理,然后由屋面最低标高处向上施工;
(5)檐口将铺贴到檐口端头的卷材裁齐后压入凹槽内,然后将凹槽用密封材料嵌填密实,用压条或用带垫片钉子固定时,钉子应敲入凹槽内,钉帽及卷材端头用密封材料封严;
(6)天沟、檐沟、水落口及檐沟卷材铺设前,应先对水落口进行密封处理,在水落口杯埋设时,水落口杯与竖管承插口的连接处用密封材料嵌填密实,水落口周围直径500mm范围内用防水涂料或密封材料涂封作为附加增强层,厚度不少于2mm,涂刷时应根据防水材料的种类采用不同的涂刷遍数来满足涂层的厚度要求,水落口杯与基层接触应留宽10mm、深10mm的凹槽,嵌填密封材料,在天沟转角处应先用密封材料涂封,每边宽度不少于30mm,干燥后再增铺一层卷材或涂刷防水涂料作为附加增强层,天沟或檐沟铺贴卷材应从沟底开始,顺天沟从水落口向分水岭铺贴,边铺边用刮板从沟低中心向两侧刮压,赶出气泡使卷材铺贴平整,粘贴密实,如沟底过宽时,会有纵向搭接缝,搭接缝处必须用密封材料封口,铺至水落口的各层卷材和附加增强层,均应粘贴在杯口上,用雨水罩的底盘将其压紧,底盘与卷材间应满涂胶结材料以粘接,底盘周围用密封材料填封;
(7)要在屋面的转角与立墙部位加铺一层卷材或涂刷涂料作为附加增强层,泛水部位卷材铺贴前,应先进行试铺,将立面卷材长度留足,先铺贴平面卷材至转角处,然后从下向上铺贴立面卷材,卷材铺贴完成后,将端头塞齐,若采用预留凹槽收头,将端头全部压入凹槽内,用压条钉压平,再用密封材料密封,最后用水泥砂浆抹封凹槽,如无法预留凹槽,应先用带垫片钉子或金属压条将卷材端头固定在墙面上,用密封材料封严,再将金属或合成高分子卷材条用压条钉压作盖板,盖板与立体墙间用密封材料封固或采用聚合物水泥砂浆将整个端头部位埋压;
(8)伸出屋面管道排气孔与屋面交角处卷材的铺贴方法和立墙与屋面转角处相似,所不同的是流水方向不应有逆槎,排气孔阴角处卷材应作附加增强层,上部剪口交叉贴实或者涂刷防水涂料增强,伸出屋面管道卷材铺贴与排气孔相似,但应加铺两层附加层,防水层铺贴后,上端用细铁丝扎紧,最后用密封材料封密;
(9)将预留洞口湿润并清除洞口内残留杂物,充分浇水湿润,在补洞前洞壁四周先刷界面剂一道,厚2~3mm,再用1∶2防水砂浆填嵌入洞,补灰面应比墙面凹进10mm,此处周围堵嵌油膏,每个部位经防水试验24小时后,无渗漏、阴湿,应马上进行保护层施工,保护层的施工做法应符合设计要求。
综上所述,本发明的有益效果是:该方法步骤严谨,对于挤塑板保温屋面所有位置都能够进行施工,施工的效率高,而且缩短了工期,解决了现有对挤塑板保温屋面施工时,其步骤设计不严谨,使得容易出现漏掉的施工位置,需要重新进行施工,施工效率低,工期长的问题。
具体实施方式
下面结合实施例,对本发明作进一步的详细说明,但本发明的实施方式不仅限于此。
实施例:
一种提高施工效率的挤塑板保温屋面的施工方法,包括以下步骤:
(1)找坡层施工:先按设计坡度及流水方向,用砂浆打点定位,确保坡度、厚度正确,铺设水泥炉渣找坡,用平板振动器压实适当,表面平整,找坡正确,找坡层完工后,应用彩条布覆盖,以防浸水和破坏,铺设找坡层时,应按设计规定埋设好排气槽、管;
(2)保温层施工:基层应平整、干净、干燥;挤塑板的铺贴方式采用干铺;挤塑板不应破碎、缺棱角,铺设时遇有缺棱掉角、破碎不齐的,应锯平拼接使用,板与板间之间要错缝、挤紧,不得有缝隙,若因挤塑板裁剪不方正或裁剪不直而形成缝隙,应用挤塑板条塞入并打磨平;
(3)水泥砂浆找平层施工:使用清净中砂并过5mm孔筛,含泥量不大于3%,做好防水基层的处理,墙上四周弹出水平标高控制线,孔洞、管线应事前预埋、预留,严禁事后打洞,施工前应在底层先刷一道素水泥奖,找平层应粘结牢固,表面平整度≤5mm,找平层应设臵30宽分隔缝,间距不大于6m×6m,在女儿墙、管道出屋面处均做成半径不小于10~15cm的圆角,防水层施工前,将一块薄膜覆盖在找平层上,经过一夜后第2天早上掀起薄膜处没有明显的潮湿痕迹,则可进行防水层施工;
(4)防水层施工:基层处理剂的涂刷要薄而均匀;涂刷时间宜在铺贴油毡前1-2h进行,使油层干燥而不粘灰尘;基层处理剂涂刷后宜在当天铺完防水层,一次涂的面积,根据基层处理剂干燥时间的长短和施工进度快慢确定,卷材应平行于屋脊铺贴;防水层施工时,应先做好节点、附加层和屋面排水比较集中部位的处理,然后由屋面最低标高处向上施工;
(5)檐口将铺贴到檐口端头的卷材裁齐后压入凹槽内,然后将凹槽用密封材料嵌填密实,用压条或用带垫片钉子固定时,钉子应敲入凹槽内,钉帽及卷材端头用密封材料封严;
(6)天沟、檐沟、水落口及檐沟卷材铺设前,应先对水落口进行密封处理,在水落口杯埋设时,水落口杯与竖管承插口的连接处用密封材料嵌填密实,水落口周围直径500mm范围内用防水涂料或密封材料涂封作为附加增强层,厚度不少于2mm,涂刷时应根据防水材料的种类采用不同的涂刷遍数来满足涂层的厚度要求,水落口杯与基层接触应留宽10mm、深10mm的凹槽,嵌填密封材料,在天沟转角处应先用密封材料涂封,每边宽度不少于30mm,干燥后再增铺一层卷材或涂刷防水涂料作为附加增强层,天沟或檐沟铺贴卷材应从沟底开始,顺天沟从水落口向分水岭铺贴,边铺边用刮板从沟低中心向两侧刮压,赶出气泡使卷材铺贴平整,粘贴密实,如沟底过宽时,会有纵向搭接缝,搭接缝处必须用密封材料封口,铺至水落口的各层卷材和附加增强层,均应粘贴在杯口上,用雨水罩的底盘将其压紧,底盘与卷材间应满涂胶结材料以粘接,底盘周围用密封材料填封;
(7)要在屋面的转角与立墙部位加铺一层卷材或涂刷涂料作为附加增强层,泛水部位卷材铺贴前,应先进行试铺,将立面卷材长度留足,先铺贴平面卷材至转角处,然后从下向上铺贴立面卷材,卷材铺贴完成后,将端头塞齐,若采用预留凹槽收头,将端头全部压入凹槽内,用压条钉压平,再用密封材料密封,最后用水泥砂浆抹封凹槽,如无法预留凹槽,应先用带垫片钉子或金属压条将卷材端头固定在墙面上,用密封材料封严,再将金属或合成高分子卷材条用压条钉压作盖板,盖板与立体墙间用密封材料封固或采用聚合物水泥砂浆将整个端头部位埋压;
(8)伸出屋面管道排气孔与屋面交角处卷材的铺贴方法和立墙与屋面转角处相似,所不同的是流水方向不应有逆槎,排气孔阴角处卷材应作附加增强层,上部剪口交叉贴实或者涂刷防水涂料增强,伸出屋面管道卷材铺贴与排气孔相似,但应加铺两层附加层,防水层铺贴后,上端用细铁丝扎紧,最后用密封材料封密;
(9)将预留洞口湿润并清除洞口内残留杂物,充分浇水湿润,在补洞前洞壁四周先刷界面剂一道,厚2~3mm,再用1∶2防水砂浆填嵌入洞,补灰面应比墙面凹进10mm,此处周围堵嵌油膏,每个部位经防水试验24小时后,无渗漏、阴湿,应马上进行保护层施工,保护层的施工做法应符合设计要求。
该方法步骤严谨,对于挤塑板保温屋面所有位置都能够进行施工,施工的效率高,而且缩短了工期,解决了现有对挤塑板保温屋面施工时,其步骤设计不严谨,使得容易出现漏掉的施工位置,需要重新进行施工,施工效率低,工期长的问题。
以上所述,仅是本发明的较佳实施例,并非对本发明做任何形式上的限制,凡是依据本发明的技术、方法实质上对以上实施例所作的任何简单修改、等同变化,均落入本发明的保护范围之内。

Claims (1)

1.一种提高施工效率的挤塑板保温屋面的施工方法,其特征在于,包括以下步骤:
(1)找坡层施工:先按设计坡度及流水方向,用砂浆打点定位,确保坡度、厚度正确,铺设水泥炉渣找坡,用平板振动器压实适当,表面平整,找坡正确,找坡层完工后,应用彩条布覆盖,以防浸水和破坏,铺设找坡层时,应按设计规定埋设好排气槽、管;
(2)保温层施工:基层应平整、干净、干燥;挤塑板的铺贴方式采用干铺;挤塑板不应破碎、缺棱角,铺设时遇有缺棱掉角、破碎不齐的,应锯平拼接使用,板与板间之间要错缝、挤紧,不得有缝隙,若因挤塑板裁剪不方正或裁剪不直而形成缝隙,应用挤塑板条塞入并打磨平;
(3)水泥砂浆找平层施工:使用清净中砂并过5mm孔筛,含泥量不大于3%,做好防水基层的处理,墙上四周弹出水平标高控制线,孔洞、管线应事前预埋、预留,严禁事后打洞,施工前应在底层先刷一道素水泥奖,找平层应粘结牢固,表面平整度≤5mm,找平层应设臵30宽分隔缝,间距不大于6m×6m,在女儿墙、管道出屋面处均做成半径不小于10~15cm的圆角,防水层施工前,将一块薄膜覆盖在找平层上,经过一夜后第2天早上掀起薄膜处没有明显的潮湿痕迹,则可进行防水层施工;
(4)防水层施工:基层处理剂的涂刷要薄而均匀;涂刷时间宜在铺贴油毡前1-2h进行,使油层干燥而不粘灰尘;基层处理剂涂刷后宜在当天铺完防水层,一次涂的面积,根据基层处理剂干燥时间的长短和施工进度快慢确定,卷材应平行于屋脊铺贴;防水层施工时,应先做好节点、附加层和屋面排水比较集中部位的处理,然后由屋面最低标高处向上施工;
(5)檐口将铺贴到檐口端头的卷材裁齐后压入凹槽内,然后将凹槽用密封材料嵌填密实,用压条或用带垫片钉子固定时,钉子应敲入凹槽内,钉帽及卷材端头用密封材料封严;
(6)天沟、檐沟、水落口及檐沟卷材铺设前,应先对水落口进行密封处理,在水落口杯埋设时,水落口杯与竖管承插口的连接处用密封材料嵌填密实,水落口周围直径500mm范围内用防水涂料或密封材料涂封作为附加增强层,厚度不少于2mm,涂刷时应根据防水材料的种类采用不同的涂刷遍数来满足涂层的厚度要求,水落口杯与基层接触应留宽10mm、深10mm的凹槽,嵌填密封材料,在天沟转角处应先用密封材料涂封,每边宽度不少于30mm,干燥后再增铺一层卷材或涂刷防水涂料作为附加增强层,天沟或檐沟铺贴卷材应从沟底开始,顺天沟从水落口向分水岭铺贴,边铺边用刮板从沟低中心向两侧刮压,赶出气泡使卷材铺贴平整,粘贴密实,如沟底过宽时,会有纵向搭接缝,搭接缝处必须用密封材料封口,铺至水落口的各层卷材和附加增强层,均应粘贴在杯口上,用雨水罩的底盘将其压紧,底盘与卷材间应满涂胶结材料以粘接,底盘周围用密封材料填封;
(7)要在屋面的转角与立墙部位加铺一层卷材或涂刷涂料作为附加增强层,泛水部位卷材铺贴前,应先进行试铺,将立面卷材长度留足,先铺贴平面卷材至转角处,然后从下向上铺贴立面卷材,卷材铺贴完成后,将端头塞齐,若采用预留凹槽收头,将端头全部压入凹槽内,用压条钉压平,再用密封材料密封,最后用水泥砂浆抹封凹槽,如无法预留凹槽,应先用带垫片钉子或金属压条将卷材端头固定在墙面上,用密封材料封严,再将金属或合成高分子卷材条用压条钉压作盖板,盖板与立体墙间用密封材料封固或采用聚合物水泥砂浆将整个端头部位埋压;
(8)伸出屋面管道排气孔与屋面交角处卷材的铺贴方法和立墙与屋面转角处相似,所不同的是流水方向不应有逆槎,排气孔阴角处卷材应作附加增强层,上部剪口交叉贴实或者涂刷防水涂料增强,伸出屋面管道卷材铺贴与排气孔相似,但应加铺两层附加层,防水层铺贴后,上端用细铁丝扎紧,最后用密封材料封密;
(9)将预留洞口湿润并清除洞口内残留杂物,充分浇水湿润,在补洞前洞壁四周先刷界面剂一道,厚2~3mm,再用1∶2防水砂浆填嵌入洞,补灰面应比墙面凹进10mm,此处周围堵嵌油膏,每个部位经防水试验24小时后,无渗漏、阴湿,应马上进行保护层施工,保护层的施工做法应符合设计要求。
CN201610678945.8A 2016-08-17 2016-08-17 一种提高施工效率的挤塑板保温屋面的施工方法 Withdrawn CN107762075A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610678945.8A CN107762075A (zh) 2016-08-17 2016-08-17 一种提高施工效率的挤塑板保温屋面的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610678945.8A CN107762075A (zh) 2016-08-17 2016-08-17 一种提高施工效率的挤塑板保温屋面的施工方法

Publications (1)

Publication Number Publication Date
CN107762075A true CN107762075A (zh) 2018-03-06

Family

ID=61260181

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610678945.8A Withdrawn CN107762075A (zh) 2016-08-17 2016-08-17 一种提高施工效率的挤塑板保温屋面的施工方法

Country Status (1)

Country Link
CN (1) CN107762075A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109057189A (zh) * 2018-07-26 2018-12-21 浙江广辉建设有限公司 一种泛水施工方法及搬运装置
CN111456485A (zh) * 2020-04-22 2020-07-28 深圳市科顺一零五六技术有限公司 一种具有大面积钢架结构屋顶的防水修缮方法
CN111456484A (zh) * 2020-04-22 2020-07-28 深圳市科顺一零五六技术有限公司 一种大型年代建筑物的屋面防水修缮方法
CN111962775A (zh) * 2020-08-04 2020-11-20 安增麦 一种楼顶屋面保温斜坡一体化无渗漏施工方案

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109057189A (zh) * 2018-07-26 2018-12-21 浙江广辉建设有限公司 一种泛水施工方法及搬运装置
CN109057189B (zh) * 2018-07-26 2021-04-23 浙江广辉建设有限公司 一种泛水施工方法及搬运装置
CN111456485A (zh) * 2020-04-22 2020-07-28 深圳市科顺一零五六技术有限公司 一种具有大面积钢架结构屋顶的防水修缮方法
CN111456484A (zh) * 2020-04-22 2020-07-28 深圳市科顺一零五六技术有限公司 一种大型年代建筑物的屋面防水修缮方法
CN111962775A (zh) * 2020-08-04 2020-11-20 安增麦 一种楼顶屋面保温斜坡一体化无渗漏施工方案

Similar Documents

Publication Publication Date Title
CN107762075A (zh) 一种提高施工效率的挤塑板保温屋面的施工方法
CN104773023B (zh) 挡墙附着式钢架密网现塑grc假山及其施工方法
CN207597740U (zh) 一种平屋面女儿墙内天沟的防水构造
CN106120873A (zh) 一种桩筏基础预铺反粘复合高分子防水卷材的施工方法
CN101333858A (zh) 聚苯板外墙外保温工艺方法
CN209145172U (zh) 金属屋面保温防火防水装饰一体化系统
CN107338967A (zh) 一种旧楼外墙瓷砖饰面翻新改造的新工艺及新材料
KR20080109584A (ko) 식물재배구조, 방근구조 및 이것들에 사용하는 방근시트
CN102912945B (zh) 一种屋面复式防渗排汽孔细部处理工艺
CN204774343U (zh) 挡墙附着式钢架密网现塑grc假山
US2271143A (en) Composite covering and flashing for roofs and the like
AU2005247966B2 (en) Method and system for constructing a concrete waterstop joint and use of a cementitious and reactive waterproofing grout strip
CN205975795U (zh) 绿化屋顶结构
CN105756293B (zh) 一种绿色屋顶结构及其施工方法
CN210857769U (zh) 一种带花池的女儿墙防水结构
CN212001969U (zh) 屋面落水口防水构造
CN201087509Y (zh) 屋面的防水收头
CN104264911B (zh) 一种沥青瓦的铺设方法
CN207376387U (zh) 一种具有高耐久性能的轻质混凝土结构
CN205314394U (zh) 一种抗倾覆挑檐构造
CN204081297U (zh) 一种斜屋面高层建筑沥青瓦屋面防水体系
CN108643476A (zh) 一种波形沥青瓦屋面的避雷带施工方法
CN212248924U (zh) 一种用于种植屋面端部檐沟处连接节点结构
KR101032821B1 (ko) 건물옥상의 방근방수 시공방법
CN208702026U (zh) 一种带外檐沟的屋面防水隔热结构

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180306