CN107724572A - One kind insulation wall construction method - Google Patents

One kind insulation wall construction method Download PDF

Info

Publication number
CN107724572A
CN107724572A CN201710967346.2A CN201710967346A CN107724572A CN 107724572 A CN107724572 A CN 107724572A CN 201710967346 A CN201710967346 A CN 201710967346A CN 107724572 A CN107724572 A CN 107724572A
Authority
CN
China
Prior art keywords
bar
wire side
mat reinforcement
pushes against
locating rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710967346.2A
Other languages
Chinese (zh)
Other versions
CN107724572B (en
Inventor
李华
祝兰兰
姜伟军
黄洪兰
宋丽加
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
(group) Co Ltd Is Built In Pudong New Area Shanghai
Original Assignee
(group) Co Ltd Is Built In Pudong New Area Shanghai
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (group) Co Ltd Is Built In Pudong New Area Shanghai filed Critical (group) Co Ltd Is Built In Pudong New Area Shanghai
Priority to CN201710967346.2A priority Critical patent/CN107724572B/en
Publication of CN107724572A publication Critical patent/CN107724572A/en
Application granted granted Critical
Publication of CN107724572B publication Critical patent/CN107724572B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/78Heat insulating elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/78Heat insulating elements
    • E04B1/80Heat insulating elements slab-shaped
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/02Reinforcing elements of metal, e.g. with non-structural coatings of low bending resistance
    • E04C5/04Mats
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Acoustics & Sound (AREA)
  • Building Environments (AREA)

Abstract

The invention discloses one kind to be incubated wall construction method, comprises the following steps:S1, muscle is pricked, carry out being bundled into bar-mat reinforcement using reinforcing bar;S2, some hollow pipes are inserted in bar-mat reinforcement;S3, the first protection network, warming plate and the second protection network are sequentially arranged in bar-mat reinforcement side;S4, bar-mat reinforcement side and the side of the second protection network placement template;S5, placing concrete into bar-mat reinforcement and between warming plate and template;After S6, solidification, by form removable, wall is formed;S7, decorated in surface of wall.It is fixed by the way of warming plate be cast in wall, while can providing heat-insulating property so as to warming plate, it is possible to increase the life-span that insulated wall uses, warming plate are influenceed smaller by external environment.Base chamber is inserted into using hollow pipe, allows inside wall and air be present, so allow wall both sides between heat transfer can be obstructed, so as to make the effect of heat insulation of wall more preferable.

Description

One kind insulation wall construction method
Technical field
The present invention relates to a kind of building structure, more specifically, it relates to a kind of insulation wall construction method.
Background technology
Insulated wall be it is for building come isolating chamber in and outdoor temperature influence wall, its can allow interior temperature by External environment influence is weak.
Notification number is that CN2716378Y Chinese patent discloses the insulation that a kind of inside heat insulation wall adds concrete beam column external thermal insulation wall Heat insulation wall, it is set gradually on matrix as boundary layer, heat insulation layer, anti-cracking protective layer and finish coat, by this The setting of Rotating fields, allow wall that there is heat insulation effect, still, during practical function, because heat-insulation layer is by later stage powder Paint, its structural strength between wall is influenceed by mortar bonding force, also, after a long time use, can make Into situation about coming off, therefore, although this insulated wall can play heat insulation effect, its service life is shorter, needs to be changed Enter.
The content of the invention
For existing technical problem, the present invention provides a kind of insulation wall construction method, and it can provide one kind and use the longevity The longer insulated wall of life.
To achieve the above object, the invention provides following technical scheme:
One kind insulation wall construction method, comprises the following steps:S1, muscle is pricked, tied up using reinforcing bar progress is crisscross, form reinforcing bar Net;S2, some hollow pipes are inserted in bar-mat reinforcement, and gap is left between hollow pipe and bar-mat reinforcement, and hollow net and bar-mat reinforcement It is fixed;S3, the first protection network, warming plate and the second protection network are sequentially arranged in bar-mat reinforcement side;S4, bar-mat reinforcement side with And second protection network side placement template;S5, placing concrete into bar-mat reinforcement and between warming plate and template;S6, coagulate After Gu, by form removable, wall is formed;S7, decorated in surface of wall.
Pass through above-mentioned technical proposal, the mode that warming plate be cast in wall is fixed, so as to warming plate energy While enough allowing the whole wall there is the performance of insulation, it is possible to increase in the life-span that insulated wall uses, warming plate is by the external world Environment influences smaller.Base chamber is inserted into using hollow pipe, allows inside wall and air be present, and then allows the both sides of wall Between heat transfer can be obstructed, so as to make the effect of heat insulation of wall more preferable.
The present invention is further arranged to:The bar-mat reinforcement includes the first wire side and the second wire side, and the first wire side and Fixing muscle is provided between two wire sides, the fixing muscle is fixed with the first wire side and the second wire side respectively, and the warming plate leans on Nearly second wire side is set.
Pass through above-mentioned technical proposal, two wire sides form intermediate space, so as to make bar-mat reinforcement branch in wall uniform, from And make the structural strength of wall higher.
The present invention is further arranged to:It is provided with the first abutting component between first wire side and template, described first Pushing against component includes the first abutting screw rod and the first abutting set, and the first abutting nut is arranged with the first abutting screw rod, The first abutting set is set on the first abutting screw rod, and is abutted with the first abutting nut, the first abutting screw rod and the One wire side contradicts, and described first pushes against set contradicts with template.
Pass through above-mentioned technical proposal, first abutting component setting allow between the first wire side and template can be formed it is certain Gap, the first abutting nut is screwed, allow the first abutting screw rod and the first position pushed against between set to be adjusted, and then can adjust Spacing between whole first wire side and template, so as to allow distribution of first wire side in wall than more uniform.
The present invention is further arranged to:U-type groove is provided with the first abutting screw rod, the U-type groove coordinates with reinforcing bar.
Pass through above-mentioned technical proposal, the setting of U-type groove, it can be enclosed on reinforcing bar, so that will not during extruding There is situation about being slid from the first wire side.
The present invention is further arranged to:First abutting, which is put, is welded with transverse slat, and the transverse slat contradicts with template.
Pass through above-mentioned technical proposal, the setting of transverse slat make the conflict of itself and template more stable, allow template by pressure It is small, so as to cause to damage to template.
The present invention is further arranged to:It is provided with the second abutting component between second wire side and template, described second The second abutting that push against that component includes contradicting with template second push against set, is located in the second abutting set and is set in screw rod Second pushes against the second abutting nut on screw rod, and described second pushes against set pushes against nut conflict with second, and described second pushes against spiral shell Bar and the second wire side push against.
Pass through above-mentioned technical proposal, the structure that the second structure for pushing against component pushes against component with first is identical, and it acts on phase Together, by the cooperation of two abutting components, bar-mat reinforcement can be fixed.
The present invention is further arranged to:The second abutting screw rod sequentially passes through the first protection network, warming plate and second Protection network and second pushes against set connection.
Pass through above-mentioned technical proposal, the second abutting screw rod is attached through protection network with warming plate, on the one hand can Warming plate is fixed, equally can also allow bar-mat reinforcement to be fixed more stable.
The present invention is further arranged to:The positioning group of fixation hollow pipe is provided between second wire side and the first wire side Part, the positioning component includes the first locating rod and the second locating rod, and the first locating rod is distinguished with the second locating rod both ends It is sequentially provided with gland and clamping joint, the gland of first locating rod and the gland of the second locating rod are respectively with One wire side and the second wire side, which contradict, to be fixed, and the clamping joint of first locating rod and the clamping joint of the second locating rod respectively will Hollow pipe is held tightly.
Hollow pipe is fixed for Pass through above-mentioned technical proposal, the setting of positioning component, so as to allow hollow pipe and bar-mat reinforcement Between leave gap, the distribution allowed between Concrete Filled and bar-mat reinforcement when pouring is more uniform.
The present invention is further arranged to:First locating rod uses expansion link, and the first positioning with the second locating rod Bar and the second locating rod include positioning screw and positioning sleeve, and location nut is arranged with the positioning screw, described Positioning is set on positioning screw and contradicted with location nut, and the gland is fixedly connected with positioning sleeve, the clamping joint and Positioning screw is fixedly connected.
Pass through above-mentioned technical proposal, by screwing for location nut, make the position between positioning screw and positioning sleeve relative Change, so as to allow locating rod(First locating rod and the second locating rod)Length can convert and then hollow pipe can be consolidated It is fixed.
The present invention is further arranged to:Concrete employed in S5 is self-heat conserving sand aerated concrete.
Pass through above-mentioned technical proposal, poured using self-heat conserving air entrained concrete, it can be allowed to be allowed after pouring Wall is internally formed tiny bubble, so as to make the thermal and insulating performance of wall more preferable.
Brief description of the drawings
Fig. 1 is the overall structure diagram of the present embodiment;
Fig. 2 is the first abutting component installation structure schematic diagram;
Fig. 3 is the second abutting component installation structure schematic diagram;
Fig. 4 is positioning component structure chart.
Reference:1st, bar-mat reinforcement;11st, the first wire side;12nd, the second wire side;2nd, hollow pipe;21st, inner sleeve;22nd, reinforcement; 3rd, first component is pushed against;31st, first screw rod is pushed against;32nd, first set is pushed against;33rd, first nut is pushed against;34th, U-type groove;35th, it is horizontal Plate;4th, second component is pushed against;41st, second screw rod is pushed against;42nd, second set is pushed against;43rd, second nut is pushed against;5th, positioning component; 51st, the first locating rod;52nd, the second locating rod;61st, positioning screw;62nd, positioning sleeve;63rd, location nut;64th, gland;65th, block Joint;71st, the first protection network;72nd, the second protection network;73rd, warming plate;8th, template.
Embodiment
The present invention will be described in detail below in conjunction with the accompanying drawings.
One kind insulation wall construction method, comprises the following steps:
S1, muscle is pricked, tied up using reinforcing bar progress is crisscross, form bar-mat reinforcement 1;
S2, some hollow pipes 2 of insertion in bar-mat reinforcement 1, and gap is left between hollow pipe 2 and bar-mat reinforcement 1, and hollow net and steel Muscle net 1 is fixed;
S3, the first protection network 71, the protection network 72 of warming plate 73 and second are sequentially arranged in the side of bar-mat reinforcement 1;
S4, the side of bar-mat reinforcement 1 and the side of the second protection network 72 placement template 8;
S5, placing concrete into bar-mat reinforcement 1 and between warming plate 73 and template 8, concrete are self-heat conserving sand aerating coagulation Soil;
After S6, solidification, template 8 is removed, forms wall;
S7, decorated in surface of wall.
Wherein, the first wire side 11 and the second wire side 12, the first wire side are included with reference to above-mentioned steps and Fig. 1, bar-mat reinforcement 1 11 and second wire side 12 use the crisscross formation of reinforcing bar, and be provided with fixation between the first wire side 11 and the second wire side 12 Muscle, fixing muscle are fixed with the reinforcing bar on the first wire side 11 and the reinforcing bar on the second wire side 12 respectively, and fixed form can be with Tied up, can also be fixed by the way of welding using thin wire.Warming plate 73 is set close to the second wire side 12, And allow the first protection network 71 to be fixed with the second wire side 12, can carry out tying up fixation by thin wire, or welding is admittedly It is fixed, connecting filament is provided between the first protection network 71 and the second protection network 72, by connecting filament by the first protection network 71 and second Protection network 72 is fixed, and then warming plate 73 stably can be placed in the first protection network 71 and the second protection network 72, Connecting filament directly through warming plate 73, can also be arranged on the link position of warming plate 73 and warming plate 73, and it is carried out Support.Certain elastic force be present to allow between protection network and warming plate 73, warming plate 73 is further protected, will The steel wire for being woven into the first protection network 71 and the second protection network 72 is arranged to helical structure.
As depicted in figs. 1 and 2, be fixed to allow between template 8 and bar-mat reinforcement 1, the first wire side 11 with close to the The first abutting component 3 is provided between the template 8 of the position of one wire side 11, likewise, in the second wire side 12 and close second wire side The second abutting component 4 is provided between the template 8 of 12 positions, is referred to Fig. 3.Wherein, the first abutting component 3 supports including first Tight screw rod 31 and first pushes against set 32, is arranged with the first abutting nut 33 on the first abutting screw rod 31, first pushes against 32 sets of set It is located on the first abutting screw rod 31, and is abutted with the first abutting nut 33, the first abutting screw rod 31 contradicts with the first wire side 11, the One pushes against set 32 contradicts with template 8.U-type groove 34 is provided with first abutting set 32, U-type groove 34 coordinates with reinforcing bar.First pushes against Transverse slat 35 is welded with screw rod 31, transverse slat 35 contradicts with template 8.And second pushes against the structure of component 4 and the first abutting structure of component 3 Identical, what the second abutting component 4 included contradicting with template 8 second pushes against set 42, is located in second supporting in the second abutting set 42 Tight screw rod 41 and the second abutting nut 43 being set on the second abutting screw rod 41, second, which pushes against set 42 and second, pushes against nut 43 contradict, and the second abutting screw rod 41 pushes against with the second wire side 12.Second abutting screw rod 41 is sequentially passed through into the first protection network 71, protected The warm protection network 72 of plate 73 and second pushes against set 42 with second and is connected.Likewise, it is also equipped with horizontal stroke on the second abutting screw rod 41 Plate 35, the second abutting covers is provided with U-type groove 34 on 42.
As shown in Figure 1 and Figure 4, in order to which hollow pipe 2 is fixed, set between the second wire side 12 and the first wire side 11 There is the positioning component 5 of fixation hollow pipe 2.Positioning component 5 includes the first locating rod 51 and the second locating rod 52, solid for convenience It is fixed, allow the first locating rod 51 and the second locating rod 52 to be all provided with being set to expansion link, and the first locating rod 51 and the second locating rod 52 Include positioning screw 61 and positioning sleeve 62, location nut 63 is provided with positioning screw 61, allow location nut 63 with positioning Screw rod 61 is threadedly coupled, and location nut 63 can be moved on positioning screw 61.It is fixed that positioning sleeve 62 is set in On the screw rod 61 of position, and it is allowed to be contradicted with location nut 63, so as to when location nut 63 screws, allow it to positioning Set 62 carries out conflict movement, and then can reach the purpose of the first locating rod 51 of adjustment and the length of the second locating rod 52.First The both ends of 51 and second locating rod of locating rod 52 are sequentially provided with gland 64 and clamping joint 65 respectively, i.e., by gland 64 and positioning Set 62 is fixedly connected, and clamping joint 65 is fixedly connected with positioning screw 61.Gland 64 is arranged to U-shape structure, the first locating rod The gland 64 of 51 locating rod 52 of gland 64 and second respectively with the reinforcing bar of the first wire side 11 and the second wire side 12 Reinforcing bar, which contradicts, to be fixed.Likewise, clamping joint 65 is arranged to arcuate structure, arcuate structure can be carried out with the outer surface of hollow pipe 2 Fitting, and the clamping joint 65 of the locating rod 52 of clamping joint 65 and second of the first locating rod 51 is respectively embraced hollow pipe 2 Tightly.
Reference picture 4, in order to improve the structural strength of whole insulated wall, steel hoop net 1 is provided with hollow pipe 2, and And inner sleeve 21 is internally provided with hollow pipe 2, the placing concrete between inner sleeve 21 and hollow pipe 2, and in inner sleeve 21 and sky Reinforcement 22 is provided between heart pipe 2, concrete herein uses publication No. to be mixed for the high intensity disclosed in CN103570287A Solidifying soil is formed, or the concrete poured using common building is formed.Allow between hollow pipe 2 and inner sleeve 21 and form high intensity pouring Post, it can improve the structural strength of whole wall.
Due to whole wall using self-heat conserving sand aerated concrete form, its overall water resistance is poor, therefore, Wall both sides are coated with one layer of waterproof mortar, so as to allow wall to carry out waterproof.
Described above is only the preferred embodiment of the present invention, and protection scope of the present invention is not limited merely to above-mentioned implementation Example, all technical schemes belonged under thinking of the present invention belong to protection scope of the present invention.It should be pointed out that for the art Those of ordinary skill for, some improvements and modifications without departing from the principles of the present invention, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (10)

1. one kind insulation wall construction method, it is characterised in that comprise the following steps:S1, muscle is pricked, carried out using reinforcing bar crisscross Tie up, form bar-mat reinforcement(1);S2, in bar-mat reinforcement(1)Interior some hollow pipes of insertion(2), and hollow pipe(2)With bar-mat reinforcement(1)It Between leave gap, and hollow net and bar-mat reinforcement(1)It is fixed;S3, in bar-mat reinforcement(1)Side is sequentially arranged the first protection network(71)、 Warming plate(73)And second protection network(72);S4, in bar-mat reinforcement(1)Side and the second protection network(72)Side placement mould Plate(8);S5, to bar-mat reinforcement(1)Interior and warming plate(73)With template(8)Between placing concrete;After S6, solidification, by template (8)Remove, form wall;S7, decorated in surface of wall.
2. insulation wall construction method according to claim 1, it is characterised in that the bar-mat reinforcement(1)Including the first wire side (11)And second wire side(12), and the first wire side(11)With the second wire side(12)Between be provided with fixing muscle, the fixing muscle Respectively with the first wire side(11)And second wire side(12)It is fixed, the warming plate(73)Close to the second wire side(12)Set.
3. insulation wall construction method according to claim 2, it is characterised in that first wire side(11)With template(8) Between be provided with the first abutting component(3), described first pushes against component(3)Screw rod is pushed against including first(31)And first push against Set(32), described first pushes against screw rod(31)On be arranged with the first abutting nut(33), described first pushes against set(32)It is set in First pushes against screw rod(31)On, and push against nut with first(33)Abut, described first pushes against screw rod(31)With the first wire side (11)Contradict, described first pushes against set(32)With template(8)Contradict.
4. insulation wall construction method according to claim 3, it is characterised in that described first pushes against screw rod(31)Upper setting There is U-type groove(34), the U-type groove(34)Coordinate with reinforcing bar.
5. insulation wall construction method according to claim 3, it is characterised in that described first pushes against set(32)On be welded with Transverse slat(35), the transverse slat(35)With template(8)Contradict.
6. insulation wall construction method according to claim 2, it is characterised in that second wire side(12)With template(8) Between be provided with the second abutting component(4), described second pushes against component(4)Including with template(8)Second contradicted pushes against set (42), be located in the second abutting set(42)Interior second pushes against screw rod(41)And it is set in the second abutting screw rod(41)On Two push against nut(43), described second pushes against set(42)Nut is pushed against with second(43)Contradict, described second pushes against screw rod(41) With the second wire side(12)Push against.
7. insulation wall construction method according to claim 6, it is characterised in that described second pushes against screw rod(41)Wear successively Cross the first protection network(71), warming plate(73)And second protection network(72)Push against and cover with second(42)Connection.
8. insulation wall construction method according to claim 2, it is characterised in that second wire side(12)With the first wire side (11)Between be provided with fixation hollow pipe(2)Positioning component(5), the positioning component(5)Including the first locating rod(51)With And second locating rod(52), and the first locating rod(51)With the second locating rod(52)Both ends are sequentially provided with gland respectively(64)With And clamping joint(65), first locating rod(51)Gland(64)And second locating rod(52)Gland(64)Respectively With the first wire side(11)And second wire side(12)Contradict and fix, first locating rod(51)Clamping joint(65)And second Locating rod(52)Clamping joint(65)Respectively by hollow pipe(2)Held tightly.
9. insulation wall construction method according to claim 8, it is characterised in that first locating rod(51)It is fixed with second Position bar(52)Use expansion link, and the first locating rod(51)And second locating rod(52)Include positioning screw(61)And Positioning sleeve(62), the positioning screw(61)On be arranged with location nut(63), the positioning sleeve(62)It is located at positioning screw (61)Upper and and location nut(63)Contradict, the gland(64)With positioning sleeve(62)It is fixedly connected, the clamping joint(65) With positioning screw(61)It is fixedly connected.
10. insulation wall construction method according to claim 1, it is characterised in that the concrete employed in S5 is self-insurance Warm sand aerated concrete.
CN201710967346.2A 2017-10-17 2017-10-17 A kind of heat preservation wall construction method Active CN107724572B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710967346.2A CN107724572B (en) 2017-10-17 2017-10-17 A kind of heat preservation wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710967346.2A CN107724572B (en) 2017-10-17 2017-10-17 A kind of heat preservation wall construction method

Publications (2)

Publication Number Publication Date
CN107724572A true CN107724572A (en) 2018-02-23
CN107724572B CN107724572B (en) 2019-05-28

Family

ID=61211743

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710967346.2A Active CN107724572B (en) 2017-10-17 2017-10-17 A kind of heat preservation wall construction method

Country Status (1)

Country Link
CN (1) CN107724572B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110284634A (en) * 2019-06-03 2019-09-27 上海港城建筑安装工程有限公司 A kind of insulated wall pouring molding construction technology

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1067503A (en) * 1964-04-11 1967-05-03 Baustahlgewebe Gmbh Improvements in or relating to holding devices for steel or other rods of concrete reinforcing grids or the like
JPH11303305A (en) * 1998-04-24 1999-11-02 Sumitomo Metal Mining Co Ltd Large alc panel
CN200964641Y (en) * 2006-10-25 2007-10-24 张晶廷 Combined stress reinforcing steel bar composite shear wall frame
JP2007327269A (en) * 2006-06-08 2007-12-20 Gentaro Yasunaga Heat insulating panel for building
CN102758484A (en) * 2011-04-27 2012-10-31 方强 Self-insulation self-sound-insulation cast-in-place concrete structure
EP2572057A1 (en) * 2010-05-20 2013-03-27 Kalús, Daniel Heat insulating panel with active regulation of heat transition
CN204282581U (en) * 2014-12-09 2015-04-22 张静 A kind of heat insulating and sound insulating combined type shear wall
CN205712570U (en) * 2016-06-06 2016-11-23 常卫星 Heat-preserving wall
CN107246080A (en) * 2017-07-04 2017-10-13 上海悦钦建筑安装工程有限公司 One kind insulation wall construction method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1067503A (en) * 1964-04-11 1967-05-03 Baustahlgewebe Gmbh Improvements in or relating to holding devices for steel or other rods of concrete reinforcing grids or the like
JPH11303305A (en) * 1998-04-24 1999-11-02 Sumitomo Metal Mining Co Ltd Large alc panel
JP2007327269A (en) * 2006-06-08 2007-12-20 Gentaro Yasunaga Heat insulating panel for building
CN200964641Y (en) * 2006-10-25 2007-10-24 张晶廷 Combined stress reinforcing steel bar composite shear wall frame
EP2572057A1 (en) * 2010-05-20 2013-03-27 Kalús, Daniel Heat insulating panel with active regulation of heat transition
CN102758484A (en) * 2011-04-27 2012-10-31 方强 Self-insulation self-sound-insulation cast-in-place concrete structure
CN204282581U (en) * 2014-12-09 2015-04-22 张静 A kind of heat insulating and sound insulating combined type shear wall
CN205712570U (en) * 2016-06-06 2016-11-23 常卫星 Heat-preserving wall
CN107246080A (en) * 2017-07-04 2017-10-13 上海悦钦建筑安装工程有限公司 One kind insulation wall construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110284634A (en) * 2019-06-03 2019-09-27 上海港城建筑安装工程有限公司 A kind of insulated wall pouring molding construction technology
CN110284634B (en) * 2019-06-03 2021-05-07 上海港城建筑安装工程有限公司 Pouring forming construction process for heat-insulating wall

Also Published As

Publication number Publication date
CN107724572B (en) 2019-05-28

Similar Documents

Publication Publication Date Title
CN103437439B (en) A kind of prefabricated steel wire net rack thermal-insulating board and preparation method thereof and construction method
CN108167553B (en) Inner sliding type prefabricated overhead steam heat-insulating pipe and manufacturing method thereof
CN107724572A (en) One kind insulation wall construction method
CN104912195B (en) The preparation method of the ultralight concrete component of shaped steel
CN102061487A (en) External thermal insulation structure of electrolytic cell
JP4953973B2 (en) Embedded heat exchanger and method for manufacturing the same
CN206999268U (en) A kind of PC component conservations fixed die station of heating
CN107060146A (en) One kind polymerization styrofoam composite thermal-insulating wall
CN206829427U (en) A kind of two-chamber square bar restrains heat-preserving wall component
CN113465061B (en) Self-cleaning type cold and warm radiation aluminum plate
JP5814139B2 (en) Method for suppressing thermal stress cracking in wall-shaped reinforced concrete structures and thermal stress crack-inhibiting wall-shaped reinforced concrete structures
CN110375154B (en) Fixed pipe bracket for prefabricated finished heat preservation pipe
CN213926879U (en) Self preservation temperature wall body and frame post connection structure
CN208884742U (en) A kind of wall face insulation board of embedding plastic three-dimensional rack
CN112282165A (en) Multifunctional truss support type floor slab and construction method thereof
CN208219878U (en) A kind of building exterior wall heat preserving node integral structure
CN2573586Y (en) Sandwich insulating brick
CN104912290B (en) Underground heat radiating circuit board and installation method
CN221749095U (en) Ultrathin heat-preservation rammed earth wall and greenhouse
CN213897787U (en) Assembled integration heat preservation wallboard
AU2012203018A1 (en) Wall Construction and Method
CN207279984U (en) A kind of mosaic type solar water system
CN215759778U (en) Energy-saving wall
RU216002U1 (en) HYBRID WALL PANEL
CN211597168U (en) Sound insulation device for hollow wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant