CN107687132A - The method that equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction - Google Patents

The method that equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction Download PDF

Info

Publication number
CN107687132A
CN107687132A CN201710910609.6A CN201710910609A CN107687132A CN 107687132 A CN107687132 A CN 107687132A CN 201710910609 A CN201710910609 A CN 201710910609A CN 107687132 A CN107687132 A CN 107687132A
Authority
CN
China
Prior art keywords
group
suspension centre
hanging
suspension
afterbody
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710910609.6A
Other languages
Chinese (zh)
Other versions
CN107687132B (en
Inventor
崔洪谱
罗领
聂凯
胡守增
谢小琴
陈若强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201710910609.6A priority Critical patent/CN107687132B/en
Publication of CN107687132A publication Critical patent/CN107687132A/en
Application granted granted Critical
Publication of CN107687132B publication Critical patent/CN107687132B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a kind of method that equidistantly double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, comprise the following steps:S1, hoisting overhead travelling crane is installed on Bridge Erector, it includes:Crossbeam, two overarm arms being arranged under crossbeam, overarm arm lower surface is equipped with two groups of hanging beam dollies;S2, at the both ends of hanging crossbeam first group of suspension centre, the 6th group of suspension centre are provided with, it is relative between first group of suspension centre, the 6th group of suspension centre to be provided with two groups of sling points;Include successively lifting multigroup section block when S3, bridge formation, the lifting of every group of section block includes the lifting of left side section block and the lifting of right side section block, and regulation two adjacent groups section block spacing completes construction.The method that the equidistant double width bridge of the present invention uses Segmental assembling bridge-erecting machine synchronous construction, by setting the overarm arm of left and right two on the crossbeam of hoisting overhead travelling crane, and to set multigroup suspension centre to enter every trade to the width bridge of left and right two of double width bridge traversing on hanging crossbeam, afterbody feeding beam is realized, so as to complete the construction of double width bridge.

Description

The method that equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction
Technical field
The present invention relates to technical field of bridge construction, and in particular to a kind of equidistantly double width bridge uses Segmental assembling bridge-erecting machine The method of synchronous construction.
Background technology
For two-way road precast segment bridge, current domestic Segmental assembling bridge-erecting machine is commonly traditional single width bridge and applied Work, that is, by traversing jib lubbing mechanism by traversing to another width bridge construction of complete machine after a width bridge of having constructed.So construction method needs Transverse shifting Bridge Erector twice, that is, moves Bridge Erector and constructed after a secondary bridge back and forth, again by traversing jib lubbing mechanism by complete machine Traversing to another width bridge construction, and the Bridge Erector via number of single width construction doubles, so as to considerably increase the operation of equipment Risk, extend the construction period.And the depth of water can not meet that pontoon transports beam requirement when being built bridge during practice of construction, it is impossible to real Feeding beam under existing bridge, need to carry out bridge drive end unit feeding beam.
The content of the invention
It is an object of the invention to solve the above problems, and provide the advantages of at least will be described later.
It is a still further object of the present invention to provide a kind of equidistantly double width bridge using Segmental assembling bridge-erecting machine synchronous construction Method, it sets multigroup suspension centre can by setting the overarm arm of left and right two on the crossbeam of hoisting overhead travelling crane on hanging crossbeam Luggage is entered so as to complete the construction of double width bridge with the width bridge of left and right two to double width bridge.
In order to realize according to object of the present invention and further advantage, there is provided a kind of equidistantly double width bridge uses section The method of assembled Bridge Erector synchronous construction, comprises the following steps:
S1, hoisting overhead travelling crane is installed on Bridge Erector, hoisting overhead travelling crane can move along crane's major girder length direction, wherein, institute Stating hoisting overhead travelling crane includes:Horizontally disposed crossbeam, the suspender positioned at crossbeam lower surface, it is arranged at along crossbeam length direction under crossbeam Two overarm arms of end face, two overarm arms are symmetrically distributed at left and right sides of suspender, and each end of the arm away from suspender of hanging oneself from a beam is equal Positioned at cross rail outer, each arm lower surface of hanging oneself from a beam is provided with two groups of hanging beam dollies along its length, and every group of hanging beam dolly includes Two can be slided with the symmetrically arranged two hanging beam dollies in arm lengths direction of hanging oneself from a beam, each hanging beam dolly along overarm arm lengths direction It is dynamic;
S2, the both ends on hanging crossbeam along its length are provided with first group of suspension centre, the 6th group of suspension centre, first group of suspension centre Including two to hang symmetrically arranged first suspension centre of crossbeam length-wise axis, the 6th group of suspension centre include two to hang crossbeam Symmetrically arranged 6th suspension centre of length-wise axis, it is relative between first group of suspension centre, the 6th group of suspension centre to be provided with two groups of sling points, often Group sling point includes two along the hanging symmetrical sling point of crossbeam length direction, the relative hanging beam width direction of two groups of sling points Symmetrically;
Include successively lifting multigroup section block when S3, bridge formation, the lifting of every group of section block includes left side section block and lifted Being lifted with right side section block, regulation two adjacent groups section block spacing completes construction, wherein, block lifting in left side section includes:
Left side section block is transported to below crane's major girder using fortune beam pontoon, and hanging crossbeam is pacified along its length On the block of left side section, and the suspension hook on left side overarm arm close to the hanging beam dolly of suspender is set to catch on the 6th group of suspension centre respectively Two the 6th suspension centres, the suspension hook of the hanging beam dolly away from suspender catches on two first of first group of suspension centre respectively on left side overarm arm Suspension centre, it is lifted up on the left of left side section block to crane's major girder immediately below hanging reinforcing bar, and hanging reinforcing bar is caught on sling point, Unclamp hanging beam trolley lifting hook and complete the block lifting of left side section;
The block lifting of right side section includes:
Right side section block is transported to below crane's major girder using fortune beam pontoon, and hanging crossbeam is pacified along its length On the block of right side section, and the suspension hook on right side overarm arm close to the hanging beam dolly of suspender is set to catch on the 6th group of suspension centre respectively Two the 6th suspension centres, the suspension hook of the hanging beam dolly away from suspender catches on two first of first group of suspension centre respectively on right side overarm arm Suspension centre, it is lifted up on the right side of right side section block to crane's major girder immediately below hanging reinforcing bar, and hanging reinforcing bar is caught on sling point, Unclamp hanging beam trolley lifting hook and complete the block lifting of right side section.
Preferably, the method that described equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, hang in s1 Be additionally provided with along its length and between first group of suspension centre, the 6th group of suspension centre on crossbeam second group of suspension centre, the 3rd group hang Point, the 4th group of suspension centre, the 5th group of suspension centre, second group of suspension centre include two to hang crossbeam length-wise axis symmetrically arranged the Two suspension centres, the 3rd group of suspension centre include two to hang symmetrically arranged 3rd suspension centre of crossbeam length-wise axis, the 4th group of suspension centre Including two to hang the symmetrically arranged four-point lifting of crossbeam length-wise axis, the 5th group of suspension centre include two to hang crossbeam Symmetrically arranged 5th suspension centre of length-wise axis;Wherein, hang the length of crossbeam between crane's major girder width 1.26 ~1.28 times, first group of suspension centre and second group of suspension centre spacing are 0.336~0.353 times of hanging crossbeam length, second group of suspension centre 0.179~0.197 times with the 3rd group of suspension centre distance for hanging crossbeam length, the 3rd group of suspension centre is to hang with the 4th group of suspension centre spacing Hang crossbeam length 0.0053~0.0795 times, the 4th group of suspension centre and the 5th group of suspension centre spacing are the 0.289 of hanging crossbeam length ~0.307 times, the 5th group of suspension centre and the 6th group of suspension centre spacing are 0.043~0.0606 times of hanging crossbeam length, and first group is hung The spacing of point and the end of the hanging crossbeam close to first group of suspension centre is hangs 0.0103~0.0274 times of crossbeam length, and second Relative hanging crossbeam length-wise axis is symmetrically equal between group suspension centre and the 3rd group of suspension centre, between the 3rd group of suspension centre and the 4th group of suspension centre Provided with two sling points;
S4, along between two bridge piers of afterbody multigroup section block is lifted from both ends to centre, the lifting of every group of section block includes The lifting of section block and the block lifting of afterbody right side section on the left of afterbody, wherein, the lifting of section block, comprises the following steps on the left of afterbody:
Step 1, crossbeam will be hung along its length on the block of afterbody left side section, and utilize hoisting overhead travelling crane center Between left side section block is hung to crane's major girder with width by suspender, left side is saved with the suspender positioned at hoisting overhead travelling crane center Section block is sling, and will be placed under the block of left side section below girder;
Step 2, suspender drive section block on the left of afterbody to be moved to the left, after be rotated by 90 ° so that section block length on the left of afterbody Direction is consistent with crane's major girder width;
Step 3, the mobile hanging beam dolly being located at left and right sides of suspender on overarm arm, and make close on left side overarm arm The suspension hook of one group of hanging beam dolly of suspender catches on two the second suspension centres of second group of suspension centre respectively, close to suspender on right side overarm arm The suspension hook of one group of hanging beam dolly catch on two the 5th suspension centres of the 5th group of suspension centre respectively, unclamp suspender afterwards, suspender moves right To original position;
Step 4, hanging beam dolly drive section block on the left of afterbody to be moved to the left, so that hanging away from suspender on left side overarm arm The suspension hook of beam dolly catches on two the first suspension centres of first group of suspension centre respectively, and one group of hanging beam on left side overarm arm close to suspender is small The suspension hook pine hook of car, and move right to two the 3rd suspension centres surface of the 3rd group of suspension centre so that its suspension hook catches on the 3rd respectively Suspension centre, on right side overarm arm close to suspender one group of hanging beam dolly suspension hook pine hook, and move right to the two of the 6th group of suspension centre Directly over individual 6th suspension centre so that its suspension hook catches on the 6th suspension centre respectively, the hanging beam dolly on left side overarm arm close to suspender is hung Hook pine hook;
Step 5, section block on the left of afterbody is moved to the left, and makes one group of hanging beam dolly of close suspender on left side overarm arm Suspension hook catches on two four-point liftings of the 4th group of suspension centre respectively, and the one group of hanging beam then unclamped on right side overarm arm close to suspender is small Car;
Step 6, section block on the left of afterbody is moved to the left, section block on the left of afterbody is located at hanging steel on the left of crane's major girder Immediately below muscle, and hanging reinforcing bar is caught on sling point, unclamp hanging beam trolley lifting hook and complete block lifting in section on the left of afterbody;
The hanging of section block, comprises the following steps on the right side of afterbody:
Step a, hoisting overhead travelling crane, repeat step 1 are moved along bridge formation direction;
Step b, suspender drives section block on the right side of afterbody to move right, and is rotated by 90 °, so that section block and step on the right side of afterbody Section block is in specular on the left of afterbody in rapid 2;
Step c, mobile one group of hanging beam dolly being located at left and right sides of suspender on overarm arm, and make on left side overarm arm Two the 5th suspension centres of the 5th group of suspension centre are caught on respectively close to the suspension hook of one group of hanging beam dolly of suspender, it is close on right side overarm arm The suspension hook of one group of hanging beam dolly of suspender catches on two the second suspension centres of second group of suspension centre respectively, and unclamps suspender, and suspender is to the right It is moved to original position;
Step d, hanging beam dolly drives section block on the right side of afterbody to move right so that on right side overarm arm away from suspender one The suspension hook of group hanging beam dolly catches on two the first suspension centres of first group of suspension centre and unclamped on right side overarm arm close to one group of suspender Hanging beam dolly;
Step e, move one group of hanging beam dolly of close suspender on right side overarm arm and its suspension hook is caught on the 3rd group respectively Two the 3rd suspension centres of suspension centre, then move on left side overarm arm close to suspender one group of hanging beam dolly and its suspension hook is caught on the Six suspension centres, then unclamp the hanging beam dolly of two the 3rd suspension centres of the 3rd group of suspension centre;
Step f, hanging beam dolly drives section block on the right side of afterbody to move right, and makes on right side overarm arm close to the one of suspender The suspension hook of group hanging beam dolly catches on two the 3rd suspension centres of the 3rd group of suspension centre respectively, then unclamp the 6th group of suspension centre two the 6th The hanging beam trolley lifting hook of suspension centre;
Step g, hanging beam dolly drives section block on the right side of afterbody to move right, and moves lifting day along bridge formation opposite direction Car, the afterbody left side section block for making section block on the right side of afterbody and having lifted are located on straight line and make section block position on the right side of afterbody The hanging reinforcing bar underface on the right side of crane's major girder, and hanging reinforcing bar is caught on sling point, unclamp hanging beam trolley lifting hook and complete tail Block lifting in section on the right side of portion.
Preferably, the method that described equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, appoint in hanging During meaning two adjacent groups section block, section block, afterbody right side section block use suspender by section on the left of afterbody on the left of one of which afterbody 1.4~1.5m below girder is placed on the right side of section block, afterbody under the block of section, is saved on the right side of another set afterbody left side section block, afterbody Section block will place 5.2~5.3m below girder on the left of afterbody using suspender under section block, afterbody right side section block.
Preferably, the method that described equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, crossbeam is hung Length 1.27 times of width between crane's major girder, first group of suspension centre and second group of suspension centre spacing are hanging crossbeam length
0.344 times, second group of suspension centre and the 3rd group of suspension centre distance are 0.196 times of hanging crossbeam length, the 3rd group of suspension centre 0.07094 times with the 4th group of suspension centre spacing for hanging crossbeam length, the 4th group of suspension centre and the 5th group of suspension centre spacing are horizontal for hanging 0.298 times of beam length, the 5th group of suspension centre and the 6th group of suspension centre spacing are 0.0521 times of hanging crossbeam length, first group of suspension centre Spacing with the end of the hanging crossbeam close to first group of suspension centre is 0.0188 times of hanging crossbeam length.
Preferably, the method that described equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, in lifting tail During the section block at portion both ends, when hanging two groups of section blocks of arbitrary neighborhood, when hanging section block on the left of next group of afterbody in step 2 also Make to have lifted close to previous group on section hanging crossbeam on the left of next group of afterbody on the left of the afterbody of completion including mobile hoisting overhead travelling crane It is 200mm that the sling point of section block, which has lifted section block end face horizontal range on the left of the afterbody of completion with previous group,.
Preferably, the method that described equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, second group is hung Point and the hanging between any one in two sling points between the 3rd group of suspension centre and corresponding 3rd group of suspension centre and the 4th group of suspension centre Axisymmetrical of the point along section block width is set.
Preferably, the method that described equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, the first suspension centre, Second suspension centre, the 3rd suspension centre, four-point lifting, the 5th suspension centre, the 6th suspension centre circle center line connecting and hanging crossbeam length-wise axis weight Close.
Preferably, the method that described equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, crossbeam is hung Length is 1~1.01 times of section block length, when hanging crossbeam is arranged on the block of section along its length, hangs crossbeam length side To axis overlapped with the axis in section block length direction.
The present invention comprises at least following beneficial effect:
1st, the method that equidistant double width bridge of the invention spells bridge machine synchronous construction using section, passes through the crossbeam in hoisting overhead travelling crane The cantilever beam set at left and right sides of lower surface, each cantilever beam are provided with two groups of slidable hanging beam dollies, on hanging crossbeam Two groups of suspension centres are set, left and right sides section block is hung respectively using the hanging beam dolly on the cantilever beam of left and right, can be achieved to realize double Width bridge synchronous construction, reducing conventional construction method needs, transverse shifting Bridge Erector twice, reduces Bridge Erector half back and forth Via number, so as to greatly reduce the operational risk of equipment, shorten the construction period.
2nd, the method that equidistant double width bridge of the invention spells bridge machine synchronous construction using section, it is further horizontal in original hanging Four groups of suspension centres are set between two groups of suspension centres on beam, during afterbody feeding beam, because the width between crane's major girder is small, section The length of section block is more than the width between girder, and section block can not be entered between girder with length direction, it is necessary to width Into between girder, then below lower section to girder, while when hanging section block, section block can only move between girder, The hanging beam dolly and multigroup suspension centre set by left and right can adjust position of the left and right section block position with respect to girder, so can be with Left side section block or right side section block is set to adjust to the underface of girder hanging reinforcing bar, so as to complete to left side section block or right side The lifting of section block, the afterbody feeding beam of double width bridge synchronous construction method is achieved in that, so as to realize double width bridge synchronous construction.
Further advantage, target and the feature of the present invention embodies part by following explanation, and part will also be by this The research and practice of invention and be understood by the person skilled in the art.
Figure of description
Fig. 1 is the structural representation of section block;
Fig. 2 is the schematic cross-section of crane's major girder;
Fig. 3 is arranged on schematic diagram on the block of section for hanging crossbeam;
Fig. 4 is hoisting overhead travelling crane and hanging beam engagement schematic diagram;
Fig. 5 is Bridge Erector and hoisting overhead travelling crane schematic diagram;
Fig. 6~Figure 11 is the hanging method schematic diagram of block lifting in section on the left of afterbody;
Figure 12 is schematic diagram after the completion of afterbody left side section block and the block lifting of afterbody right side section;
Figure 13 is schematic diagram after the multigroup section block lifting of afterbody.
Embodiment
With reference to embodiment, the present invention is described in further detail, to make those skilled in the art with reference to specification Word can be implemented according to this.
It should be noted that experimental method described in following embodiments, is conventional method unless otherwise specified, institute Reagent and material are stated, unless otherwise specified, is commercially obtained.
A kind of method that equidistantly double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, comprises the following steps:
S1, hoisting overhead travelling crane 2 is installed on Bridge Erector, hoisting overhead travelling crane 2 can move along the length direction of crane's major girder 1, wherein, The hoisting overhead travelling crane 2 includes:Horizontally disposed crossbeam 21, for crossbeam 21 between two supporting legs 22, supporting leg 22 is splayed branch Leg, supporting leg 22 can move along the length direction of crane's major girder 1, the suspender 23 positioned at the lower surface of crossbeam 21, along the length side of crossbeam 21 To two overarm arms 24 for being arranged at the lower surface of crossbeam 21, two overarm arms 24 are symmetrically distributed in the left and right sides of suspender 23, each End of the overarm arm 24 away from suspender 23 is respectively positioned on the outside of crossbeam 24, that is, two ends of arm 24 of hanging oneself from a beam are located at the two of supporting leg 22 Side, each lower surface of arm 24 of hanging oneself from a beam are equipped with two groups of hanging beam dollies, and every group of hanging beam dolly includes two with the length of arm 24 of hanging oneself from a beam The symmetrically arranged two hanging beam dollies 25 in direction, each hanging beam dolly can slide along overarm arm lengths direction;
S2, the both ends on hanging crossbeam 3 along its length are provided with first group of suspension centre, the 6th group of suspension centre, and first group is hung Point includes two to hang symmetrically arranged first suspension centre 31 of the length-wise axis of crossbeam 3, the 6th group of suspension centre including two to hang Symmetrically arranged 6th suspension centre 36 of the length-wise axis of crossbeam 3 is hung, it is relative between first group of suspension centre, the 6th group of suspension centre to be provided with two groups Sling point, every group of sling point include two along the symmetrical sling point 37 of crossbeam length direction is hung, and two groups of sling points are relative to be hung The width of crossbeam 3 is symmetrical;
Include successively lifting multigroup section block when S3, bridge formation, the lifting of every group of section block includes left side section block and lifted Being lifted with right side section block, regulation two adjacent groups section block spacing completes construction, wherein, block lifting in left side section includes:
Left side section block is transported to crane's major girder below 1 using fortune beam pontoon, and crossbeam 3 will be hung along its length On the block of left side section, and the suspension hook of one group of hanging beam dolly 25 of close suspender on left side overarm arm is caught on the 6th group and hang Two the 6th suspension centres 36 of point, the suspension hook of one group of hanging beam dolly 25 away from suspender catches on first group of suspension centre on left side overarm arm Two the first suspension centres 31, it is lifted up immediately below left side section block to the left side of crane's major girder 1 hanging reinforcing bar, and makes hanging reinforcing bar Sling point 37 is caught on, the suspension hook of hanging beam dolly 25 is unclamped and completes the block lifting of left side section;
The block lifting of right side section includes:
Right side section block is transported to below crane's major girder using fortune beam pontoon, and crossbeam 3 will be hung along its length On the block of right side section, and the suspension hook of one group of hanging beam dolly 25 of close suspender on right side overarm arm is caught on the 6th group and hang Two the 6th suspension centres 36 of point, the suspension hook of one group of hanging beam dolly away from suspender catches on the two of first group of suspension centre on right side overarm arm Individual first suspension centre 31, it is lifted up on the right side of right side section block to crane's major girder immediately below hanging reinforcing bar, and hooks hanging reinforcing bar Firmly sling point, unclamp the suspension hook of hanging beam dolly 25 and complete the block lifting of right side section.
The method that the equidistant double width bridge of the present invention uses Segmental assembling bridge-erecting machine synchronous construction, suitable for feeding beam under bridge, Directly section block is transported to below crane's major girder by transporting beam pontoon, reuses the hanging of hanging beam dolly;With left side section Exemplified by block lifting:
Left side section block is transported to immediately below the left side of crane's major girder 1 hanging reinforcing bar using fortune beam pontoon, and will hanging Crossbeam 3 is arranged on the block of left side section along its length, on mobile left side overarm arm close to suspender one group of hanging beam dolly 25 simultaneously Its suspension hook is set to catch on two the 6th suspension centres 36 of the 6th group of suspension centre respectively, one group of hanging beam away from suspender on arm of being hung oneself from a beam on the left of movement Dolly 25 makes its suspension hook catch on two the first suspension centres 31 of first group of suspension centre respectively, is lifted up left side section block to the owner that builds bridge Immediately below the left side of beam 1 hanging reinforcing bar, and hanging reinforcing bar is caught on sling point 37, unclamp the suspension hook of hanging beam dolly 25 and complete left side section Block lifts;Right side section block hanging method is the same as left side section block hanging method.
In another technical solution, described equidistant double width bridge uses the side of Segmental assembling bridge-erecting machine synchronous construction Method, in addition to afterbody to section block lifting on the right side of block lifting in section on the left of afterbody and afterbody;Hung in s1 on crossbeam 3 along its length Degree direction and be additionally provided between first group of suspension centre, the 6th group of suspension centre second group of suspension centre, the 3rd group of suspension centre, the 4th group hang Point, the 5th group of suspension centre, wherein, second group of suspension centre is hung including two with hanging the length-wise axis of crossbeam 3 symmetrically arranged second 32, the 3rd groups of suspension centres of point include two to hang symmetrically arranged 3rd suspension centre 33 of the length-wise axis of crossbeam 3, the 4th group of suspension centre Including two to hang the symmetrically arranged four-point lifting 34 of the length-wise axis of crossbeam 3, the 5th group of suspension centre include two with hanging Symmetrically arranged 5th suspension centre 35 of the length-wise axis of crossbeam 3, wherein, the length for hanging crossbeam 3 is wide between crane's major girder 1 1.26~1.28 times of degree, first group of suspension centre and second group of suspension centre spacing are hang the length of crossbeam 1 0.336~0.353 times, the Two groups of suspension centres and the 3rd group of suspension centre distance are 0.179~0.197 times of the hanging length of crossbeam 3, and the 3rd group of suspension centre is hung with the 4th group Point spacing is 0.0053~0.0795 times of the hanging length of crossbeam 3, and the 4th group of suspension centre and the 5th group of suspension centre spacing are hanging crossbeam 3 0.289~0.307 times of length, the 5th group of suspension centre and the 6th group of suspension centre spacing are the 0.043~0.0606 of the hanging length of crossbeam 3 Times, the spacing of first group of suspension centre and the end of the hanging crossbeam 3 close to first group of suspension centre for the hanging length of crossbeam 3 0.0103~ 0.0274 times, two groups of sling point one of which are between second group of suspension centre and the 3rd group of suspension centre, and another set is positioned at the Between three groups of suspension centres and the 4th group of suspension centre;
Here it is the axis of the first suspension centre 31 and corresponding second suspension centre that first group of suspension centre is actual with the spacing of second group of suspension centre 32 axial line distances, it is the axis of the second suspension centre 32 and the corresponding axle of 3rd suspension centre 33 that second group of suspension centre is actual with the 3rd group of suspension centre distance Linear distance, the 3rd group of suspension centre and the 4th group of suspension centre spacing it is actual for the axis of the 3rd suspension centre 33 and the corresponding axis of four-point lifting 34 away from Actual with the 5th group of suspension centre spacing from, the 4th group of suspension centre is the axis of four-point lifting 34 and the corresponding axial line distance of 5th suspension centre 35, It is the axis of the 5th suspension centre 35 and the corresponding axial line distance of 6th suspension centre 36 that 5th group of suspension centre be actual with the 6th group of suspension centre spacing, first It is the axis of the first suspension centre 31 with being hung with close first that the end spacing of suspension centre group and the hanging crossbeam 3 close to first group of suspension centre is actual The end spacing of the hanging crossbeam 3 of point 31;The width of crane's major girder 1 is 9.2m in this programme, then hangs the length of crossbeam 3 For 11.592~11.776m, first group of suspension centre and second group of suspension centre spacing are 3.894~4.156m, second group of suspension centre and the 3rd Group suspension centre distance be 2.174~2.319m, the 3rd group of suspension centre and the 4th group of suspension centre spacing be 0.0614~0.9361m, the 4th group Suspension centre and the 5th group of suspension centre spacing are 3.35~3.615m, and the 5th group of suspension centre and the 6th group of suspension centre spacing are 0.498~0.713m, The end spacing of first group of suspension centre and the hanging crossbeam 3 close to first group of suspension centre is 0.119~0.322m;
S4, along between two bridge piers of afterbody multigroup section block is lifted from both ends to centre, the lifting of every group of section block includes The lifting of section block and the block lifting of afterbody right side section on the left of afterbody, wherein, the lifting of section block, comprises the following steps on the left of afterbody:
Step 1, crossbeam will be hung along its length on the block of afterbody left side section, and utilize hoisting overhead travelling crane center Between left side section block is hung to crane's major girder with width by suspender, left side is saved with the suspender positioned at hoisting overhead travelling crane center Section block is sling, and will be placed under the block of left side section below girder;
Step 2, suspender drive section block on the left of afterbody to be moved to the left, after be rotated by 90 ° so that section block length on the left of afterbody Direction is consistent with crane's major girder width;
Step 3, the mobile hanging beam dolly being located at left and right sides of suspender on overarm arm, and make close on left side overarm arm The suspension hook of one group of hanging beam dolly of suspender catches on two the second suspension centres of second group of suspension centre respectively, close to suspender on right side overarm arm The suspension hook of one group of hanging beam dolly catch on two the 5th suspension centres of the 5th group of suspension centre respectively, unclamp suspender afterwards, suspender moves right To original position;
Step 4, hanging beam dolly drive section block on the left of afterbody to be moved to the left, so that hanging away from suspender on left side overarm arm The suspension hook of beam dolly catches on two the first suspension centres of first group of suspension centre respectively, and one group of hanging beam on left side overarm arm close to suspender is small The suspension hook pine hook of car, and move right to two the 3rd suspension centres surface of the 3rd group of suspension centre so that its suspension hook catches on the 3rd respectively Suspension centre, on right side overarm arm close to suspender one group of hanging beam dolly suspension hook pine hook, and move right to the two of the 6th group of suspension centre Directly over individual 6th suspension centre so that its suspension hook catches on the 6th suspension centre respectively, the hanging beam dolly on left side overarm arm close to suspender is hung Hook pine hook;
Step 5, section block on the left of afterbody is moved to the left, and makes one group of hanging beam dolly of close suspender on left side overarm arm Suspension hook catches on two four-point liftings of the 4th group of suspension centre respectively, and the one group of hanging beam then unclamped on right side overarm arm close to suspender is small Car;
Step 6, section block on the left of afterbody is moved to the left, section block on the left of afterbody is located at hanging steel on the left of crane's major girder Immediately below muscle, and hanging reinforcing bar is caught on sling point, unclamp hanging beam trolley lifting hook and complete block lifting in section on the left of afterbody;
The hanging of section block, comprises the following steps on the right side of afterbody:
Step a, hoisting overhead travelling crane, repeat step 1 are moved along bridge formation direction;
Step b, suspender drives section block on the right side of afterbody to move right, and is rotated by 90 °, so that section block and step on the right side of afterbody Section block is in specular on the left of afterbody in rapid 2;
Step c, mobile one group of hanging beam dolly being located at left and right sides of suspender on overarm arm, and make on left side overarm arm Two the 5th suspension centres of the 5th group of suspension centre are caught on respectively close to the suspension hook of one group of hanging beam dolly of suspender, it is close on right side overarm arm The suspension hook of one group of hanging beam dolly of suspender catches on two the second suspension centres of second group of suspension centre respectively, and unclamps suspender, and suspender is to the right It is moved to original position;
Step d, hanging beam dolly drives section block on the right side of afterbody to move right so that on right side overarm arm away from suspender one The suspension hook of group hanging beam dolly catches on two the first suspension centres of first group of suspension centre and unclamped on right side overarm arm close to one group of suspender Hanging beam dolly;
Step e, move one group of hanging beam dolly of close suspender on right side overarm arm and its suspension hook is caught on the 3rd group respectively Two the 3rd suspension centres of suspension centre, then move on left side overarm arm close to suspender one group of hanging beam dolly and its suspension hook is caught on the Six suspension centres, then unclamp the hanging beam dolly of two the 3rd suspension centres of the 3rd group of suspension centre;
Step f, hanging beam dolly drives section block on the right side of afterbody to move right, and makes on right side overarm arm close to the one of suspender The suspension hook of group hanging beam dolly catches on two the 3rd suspension centres of the 3rd group of suspension centre respectively, then unclamp the 6th group of suspension centre two the 6th The hanging beam trolley lifting hook of suspension centre;
Step g, hanging beam dolly drives section block on the right side of afterbody to move right, and moves lifting day along bridge formation opposite direction Car, the afterbody left side section block for making section block on the right side of afterbody and having lifted are located on straight line and make section block position on the right side of afterbody The hanging reinforcing bar underface on the right side of crane's major girder, and hanging reinforcing bar is caught on sling point, unclamp hanging beam trolley lifting hook and complete tail Block lifting in section on the right side of portion.
In the technical program in work progress due to build bridge when the afterbody bridge depth of water it is inadequate, it is impossible to carry out under bridge feed Beam, therefore afterbody feeding beam can only be carried out, but because the width between crane's major girder is less than section block, stage blocks can not be with length Direction enters between crane's major girder, therefore sets multiple suspension centres to come the position of adjusting stage block, realizes afterbody feeding beam.Fig. 6~ Figure 11 is the method and step of left side section block lifting, and the wherein length of section block 4 is 11.55m, between crane's major girder inside Minimum widith is 9.2m, section block on the left of afterbody is hung into 1.5m below girder using suspender in figure 6, by section on the left of afterbody Block traversing 0.7m to the left, is then rotated by 90 °, and section block length direction is consistent with crane's major girder width on the left of afterbody;Fig. 7 Middle movement is located at one group of hanging beam dolly 25 on the left and right sides of suspender 23 overarm arm, and makes on left side overarm arm close to suspender The suspension hook of hanging beam dolly catch on two the second suspension centres 32 of second group of suspension centre, close to the hanging beam dolly of suspender on right side overarm arm Suspension hook catch on two the 5th suspension centres 35 of the 5th group of suspension centre, rear to unclamp suspender 23, suspender 23 moves right 0.7m to original position;Figure 8th, hanging beam dolly 25 drives section block on the left of afterbody to be moved to the left 2.3m in Fig. 9, so that hanging away from suspender on left side overarm arm The suspension hook of beam dolly catches on two the first suspension centres 31 of first group of suspension centre, and the hanging beam dolly on left side overarm arm close to suspender is hung Hook pine hook, and to the surface of two the 3rd suspension centres 33 of the 3rd group of suspension centre so that its suspension hook catches on the 3rd group after the 2.3m that moves right Two the 3rd suspension centres 33 of suspension centre, on right side overarm arm close to suspender hanging beam dolly suspension hook pine hook, and the 0.61m that moves right So that its suspension hook catches on two the 6th suspension centres 36 of the 6th group of suspension centre directly over to the 6th group of suspension centre, close to hanging on left side overarm arm The suspension hook pine hook of the hanging beam dolly of tool 23;It is moved to the left on the left of afterbody after the block 0.75m of section, and makes on left side overarm arm in Figure 10 Two four-point liftings 34 of the 4th group of suspension centre are caught on close to the suspension hook of the hanging beam dolly of suspender, then unclamps and is leaned on right side overarm arm The hanging beam dolly of nearly suspender 23;It is moved to the left in Figure 11 on the left of afterbody after the block 2.735m of section, is located at section block on the left of afterbody On the left of crane's major girder immediately below hanging reinforcing bar, and hanging reinforcing bar is caught on sling point 37, unclamp hanging beam trolley lifting hook and complete tail Block lifting in section on the left of portion;Because the supporting leg 22 of Bridge Erector stops that the suspension hook for causing hanging beam dolly is catching on the mistake of hanging crossbeam 3 The side movement of supporting leg 22 can only be located in journey in overarm arm 24, that is, the suspension hook for being distributed in the hanging beam dolly of the both sides of supporting leg 22 is hooking Movement is no more than supporting leg during firmly hanging crossbeam 3, and movement is only defined within crane's major girder, therefore uses and set Multiple suspension centres adjust section block position with setting hanging beam dolly, to complete the lifting of left side section block and right side section block.
The suspending method of section block is with the method for block lifting in section on the left of afterbody on the right side of afterbody, and afterbody is right in hoisting process The axial direction of relative crane's major girder length direction is in specular with the lifting of section block on the left of afterbody for the lifting of side section block, figure 12 be the schematic diagram for being finally afterbody left side section block and the block lifting completion of afterbody right side section.
In another technical solution, described equidistant double width bridge uses the side of Segmental assembling bridge-erecting machine synchronous construction Method, when hanging two groups of section blocks of arbitrary neighborhood, section block, afterbody right side section block will using suspender on the left of one of which afterbody 1.4~1.5m below placement girder under section block, afterbody right side section block on the left of afterbody, another set afterbody left side section block, Section block will place 5.2~5.3m below girder on the left of afterbody using suspender under section block, afterbody right side section block on the right side of afterbody. I.e. if Figure 13 afterbody two adjacent groups section block is in be staggered in lifting.
In another technical solution, described equidistant double width bridge uses the side of Segmental assembling bridge-erecting machine synchronous construction Method, the length of crossbeam 3 is hung 1.27 times of width between crane's major girder 1, first group of suspension centre is with second group of suspension centre spacing Hang the length of crossbeam 3 0.344 times, second group of suspension centre and the 3rd group of suspension centre distance are hang the length of crossbeam 3 0.196 times, the Three groups of suspension centres and the 4th group of suspension centre spacing are hang the length of crossbeam 3 0.07094 times, the 4th group of suspension centre and the 5th group of suspension centre spacing To hang 0.298 times of the length of crossbeam 3, the 5th group of suspension centre and the 6th group of suspension centre spacing are hang the length of crossbeam 3 0.0521 times, The end spacing of first group of suspension centre and the hanging crossbeam close to first group of suspension centre is 0.0188 times of hanging crossbeam length.Hang The length of crossbeam 3 is 11.68m, first group of suspension centre and second group of suspension centre spacing are 4.01m, second group of suspension centre and the 3rd group of suspension centre Distance is 2.28m, the 3rd group of suspension centre and the 4th group of suspension centre spacing are 0.828m, the 4th group of suspension centre is with the 5th group of suspension centre spacing 3.48m, the 5th group of suspension centre and the 6th group of suspension centre spacing are 0.608m, the hanging crossbeam of first group of suspension centre and close first group of suspension centre End spacing be 0.219m.
In another technical solution, described equidistant double width bridge uses the side of Segmental assembling bridge-erecting machine synchronous construction Method, when lifting the section block at afterbody both ends, when hanging two groups of section blocks of arbitrary neighborhood, hang section block on the left of next group of afterbody When step 2 in also include mobile hoisting overhead travelling crane and make to have lifted completion close to previous group on section hanging crossbeam on the left of next group of afterbody Afterbody on the left of the sling point of section block the afterbody left side section block end face horizontal range of completion lifted with previous group be 200mm.Technical scheme, afterbody uses lifts section block by both ends to centre, positioned at the multigroup of last group of both sides During the block lifting of section, the two adjacent groups section block of any side, when section block lifts on the left of next group of afterbody, mobile lifting day Car makes the sling point for having lifted section block on the left of the afterbody of completion on the left of next group of afterbody on section hanging crossbeam close to previous group The left side section block end face horizontal range that completion has been lifted with previous group is 200mm, so the afterbody in last group is lifted Section block will not encounter the adjacent section block for having lifted completion in rotary course on the right side of left side section block or afterbody.
In another technical solution, method that described equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, Any one in two sling points and corresponding 3rd group of suspension centre and the 4th group of suspension centre between second group of suspension centre and the 3rd group of suspension centre Between axisymmetrical of the sling point along section block width set.Four sling points set on hanging crossbeam 3, what it was formed The axial direction in rectangle length direction and the axis of width are respectively with hanging the length-wise axis and width axis of crossbeam 3 Overlap.
In another technical solution, method that described equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, First suspension centre 31, the second suspension centre 32, the 3rd suspension centre 33, four-point lifting 34, the 5th suspension centre 35, the circle center line connecting of the 6th suspension centre 36 are with hanging The length-wise axis of crossbeam 3 is hung to overlap.I.e. the setting of suspension centre is in the hanging length-wise axis of crossbeam 3.
In another technical solution, method that described equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, 1~1.01 times that the length of crossbeam 3 is section block length is hung, when hanging crossbeam 3 is arranged on the block of section along its length, hanging The axis of the length direction of crossbeam 3 overlaps with the axis in section block length direction.The length for hanging crossbeam 3 is slightly larger than section block length Degree, hanging crossbeam 3 are arranged on section block center, are lifted when so more stable during the block of section.
Although embodiment of the present invention is disclosed as above, it is not restricted in specification and embodiment listed With it can be applied to various suitable the field of the invention completely, can be easily for those skilled in the art Other modification is realized, therefore under the universal limited without departing substantially from claim and equivalency range, it is of the invention and unlimited In specific details and shown here as the embodiment with description.

Claims (8)

  1. A kind of 1. method that equidistantly double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, it is characterised in that including following step Suddenly:
    S1, hoisting overhead travelling crane is installed on Bridge Erector, hoisting overhead travelling crane can move along crane's major girder length direction, wherein, described Weight overhead traveling crane includes:Horizontally disposed crossbeam, the suspender positioned at crossbeam lower surface, crossbeam lower surface is arranged at along crossbeam length direction Two overarm arms, two overarm arms are symmetrically distributed at left and right sides of suspender, and each end of the arm away from suspender of hanging oneself from a beam is respectively positioned on Cross rail outer, each arm lower surface of hanging oneself from a beam are provided with two groups of hanging beam dollies along its length, and every group of hanging beam dolly includes two With the symmetrically arranged two hanging beam dollies in arm lengths direction of hanging oneself from a beam, each hanging beam dolly can slide along overarm arm lengths direction;
    S2, the both ends on hanging crossbeam along its length are provided with first group of suspension centre, the 6th group of suspension centre, and first group of suspension centre includes Two to hang symmetrically arranged first suspension centre of crossbeam length-wise axis, the 6th group of suspension centre include two to hang crossbeam length Symmetrically arranged 6th suspension centre of azimuth axis, relative between first group of suspension centre, the 6th group of suspension centre to be provided with two groups of sling points, every group is hung Hanging point includes two along the symmetrical sling point of crossbeam length direction is hung, and two groups of sling points are relative to hang beam width direction pair Claim;
    Include successively lifting multigroup section block when S3, bridge formation, the lifting of every group of section block includes the lifting of left side section block and the right side The block lifting of side section, regulation two adjacent groups section block spacing complete construction, wherein, block lifting in left side section includes:
    Left side section block is transported to below crane's major girder using fortune beam pontoon, and hanging crossbeam is arranged on along its length On the block of left side section, and the suspension hook on left side overarm arm close to the hanging beam dolly of suspender is set to catch on two of the 6th group of suspension centre respectively 6th suspension centre, the suspension hook of the hanging beam dolly away from suspender catches on two first of first group of suspension centre and hung respectively on left side overarm arm Point, it is lifted up on the left of left side section block to crane's major girder immediately below hanging reinforcing bar, and hanging reinforcing bar is caught on sling point, pine Beam trolley lifting hook of holding funeral rites completes the block lifting of left side section;
    The block lifting of right side section includes:
    Right side section block is transported to below crane's major girder using fortune beam pontoon, and hanging crossbeam is arranged on along its length On the block of right side section, and the suspension hook on right side overarm arm close to the hanging beam dolly of suspender is set to catch on two of the 6th group of suspension centre respectively 6th suspension centre, the suspension hook of the hanging beam dolly away from suspender catches on two first of first group of suspension centre and hung respectively on right side overarm arm Point, it is lifted up on the right side of right side section block to crane's major girder immediately below hanging reinforcing bar, and hanging reinforcing bar is caught on sling point, pine Beam trolley lifting hook of holding funeral rites completes the block lifting of right side section.
  2. 2. the method as claimed in claim 1 that equidistantly double width bridge uses Segmental assembling bridge-erecting machine synchronous construction, its feature exist In being hung in s1 on crossbeam along its length and be additionally provided with second group between first group of suspension centre, the 6th group of suspension centre and hang Point, the 3rd group of suspension centre, the 4th group of suspension centre, the 5th group of suspension centre, second group of suspension centre include two to hang crossbeam length-wise axis Symmetrically arranged second suspension centre, the 3rd group of suspension centre are hung including two with hanging crossbeam length-wise axis the symmetrically arranged 3rd Point, the 4th group of suspension centre include two to hang the symmetrically arranged four-point lifting of crossbeam length-wise axis, the 5th group of suspension centre includes Two to hang symmetrically arranged 5th suspension centre of crossbeam length-wise axis;Wherein, the length for hanging crossbeam is crane's major girder Between 1.26~1.28 times of width, first group of suspension centre and second group of suspension centre spacing are the 0.336~0.353 of hanging crossbeam length Times, second group of suspension centre and the 3rd group of suspension centre distance are 0.179~0.197 times of hanging crossbeam length, the 3rd group of suspension centre and the 4th Group suspension centre spacing is 0.0053~0.0795 times of hanging crossbeam length, and the 4th group of suspension centre and the 5th group of suspension centre spacing are horizontal for hanging 0.289~0.307 times of beam length, the 5th group of suspension centre and the 6th group of suspension centre spacing for hanging crossbeam length 0.043~ 0.0606 times, first group of suspension centre and the spacing of the end of the hanging crossbeam close to first group of suspension centre are to hang crossbeam length 0.0103~0.0274 times, hung relatively between second group of suspension centre and the 3rd group of suspension centre, between the 3rd group of suspension centre and the 4th group of suspension centre Crossbeam length-wise axis is symmetrically equipped with two sling points;
    S4, along between two bridge piers of afterbody multigroup section block is lifted from both ends to centre, the lifting of every group of section block includes afterbody Section block lifting on the right side of the block lifting of left side section and afterbody, wherein, the lifting of section block, comprises the following steps on the left of afterbody:
    Step 1, crossbeam will be hung along its length on the block of afterbody left side section, and utilize the suspender at hoisting overhead travelling crane center Between left side section block is hung into crane's major girder with width, with the suspender positioned at hoisting overhead travelling crane center by left side section block Sling, and will be placed under the block of left side section below girder;
    Step 2, suspender drive section block on the left of afterbody to be moved to the left, after be rotated by 90 ° so that section block length direction on the left of afterbody It is consistent with crane's major girder width;
    Step 3, the mobile hanging beam dolly being located at left and right sides of suspender on overarm arm, and make on left side overarm arm close to suspender The suspension hook of one group of hanging beam dolly catch on two the second suspension centres of second group of suspension centre respectively, close to the one of suspender on right side overarm arm The suspension hook of group hanging beam dolly catches on two the 5th suspension centres of the 5th group of suspension centre respectively, unclamps suspender afterwards, suspender moves right to original Position;
    Step 4, hanging beam dolly drive section block on the left of afterbody to be moved to the left, so that the hanging beam away from suspender is small on left side overarm arm The suspension hook of car catches on two the first suspension centres of first group of suspension centre respectively, close to one group of hanging beam dolly of suspender on left side overarm arm Suspension hook pine hook, and move right to directly over two the 3rd suspension centres of the 3rd group of suspension centre so that its suspension hook catches on the 3rd respectively hangs Point, on right side overarm arm close to suspender one group of hanging beam dolly suspension hook pine hook, and move right to two of the 6th group of suspension centre So that its suspension hook catches on the 6th suspension centre respectively directly over 6th suspension centre, on left side overarm arm close to suspender hanging beam dolly suspension hook Loose hook;
    Step 5, section block on the left of afterbody is moved to the left, and makes the suspension hook of one group of hanging beam dolly of close suspender on left side overarm arm Two four-point liftings of the 4th group of suspension centre are caught on respectively, are then unclamped on right side overarm arm close to one group of hanging beam dolly of suspender;
    Step 6, section block on the left of afterbody is moved to the left, section block on the left of afterbody is being located at crane's major girder left side hanging reinforcing bar just Lower section, and hanging reinforcing bar is caught on sling point, unclamp hanging beam trolley lifting hook and complete block lifting in section on the left of afterbody;
    The hanging of section block, comprises the following steps on the right side of afterbody:
    Step a, hoisting overhead travelling crane, repeat step 1 are moved along bridge formation direction;
    Step b, suspender drives section block on the right side of afterbody to move right, and is rotated by 90 °, so that section block and step 2 on the right side of afterbody Section block is in specular on the left of middle afterbody;
    Step c, mobile one group of hanging beam dolly being located at left and right sides of suspender on overarm arm, and make close on left side overarm arm The suspension hook of one group of hanging beam dolly of suspender catches on two the 5th suspension centres of the 5th group of suspension centre respectively, close to suspender on right side overarm arm The suspension hook of one group of hanging beam dolly catch on two the second suspension centres of second group of suspension centre respectively, and unclamp suspender, suspender moves right To original position;
    Step d, hanging beam dolly drives section block on the right side of afterbody to move right, so that one group on right side overarm arm away from suspender is hung The suspension hook of beam dolly catches on two the first suspension centres of first group of suspension centre and unclamped on right side overarm arm close to one group of hanging beam of suspender Dolly;
    Step e, move one group of hanging beam dolly of close suspender on right side overarm arm and its suspension hook is caught on the 3rd group of suspension centre respectively Two the 3rd suspension centres, then move on left side overarm arm close to suspender one group of hanging beam dolly and make its suspension hook catch on the 6th to hang Point, then unclamp the hanging beam dolly of two the 3rd suspension centres of the 3rd group of suspension centre;
    Step f, hanging beam dolly drives section block on the right side of afterbody to move right, and makes to hang close to one group of suspender on right side overarm arm The suspension hook of beam dolly catches on two the 3rd suspension centres of the 3rd group of suspension centre respectively, then unclamps two the 6th suspension centres of the 6th group of suspension centre Hanging beam trolley lifting hook;
    Step g, hanging beam dolly drives section block on the right side of afterbody to move right, and moves hoisting overhead travelling crane along bridge formation opposite direction, makes Section block and the afterbody left side section block lifted are located on straight line and section block on the right side of afterbody is located at frame on the right side of afterbody On the right side of bridge main beam immediately below hanging reinforcing bar, and hanging reinforcing bar is caught on sling point, it is right to unclamp hanging beam trolley lifting hook completion afterbody The block lifting of side section.
  3. 3. the method as claimed in claim 2 that equidistantly double width bridge spells bridge machine synchronous construction using section, it is characterised in that hanging When hanging two groups of section blocks of arbitrary neighborhood, section block, afterbody right side section block are left by afterbody using suspender on the left of one of which afterbody 1.4~1.5m below girder is placed on the right side of side section block, afterbody under the block of section, another set afterbody left side section block, afterbody are right Side section block will place 5.2~5.3m below girder on the left of afterbody using suspender under section block, afterbody right side section block.
  4. 4. the method as claimed in claim 2 that equidistantly double width bridge spells bridge machine synchronous construction using section, it is characterised in that hanging For the length of crossbeam 1.27 times of width between crane's major girder, first group of suspension centre and second group of suspension centre spacing are hanging crossbeam length 0.344 times of degree, second group of suspension centre and the 3rd group of suspension centre distance is hang 0.196 times of crossbeam length, the 3rd group of suspension centre and the Four groups of suspension centre spacing are 0.07094 times of hanging crossbeam length, and the 4th group of suspension centre and the 5th group of suspension centre spacing are hanging crossbeam length 0.298 times of degree, the 5th group of suspension centre and the 6th group of suspension centre spacing are 0.0521 times of hanging crossbeam length, and first group of suspension centre is with leaning on The spacing of the end of the hanging crossbeam of nearly first group of suspension centre is 0.0188 times of hanging crossbeam length.
  5. 5. the method as claimed in claim 2 that equidistantly double width bridge spells bridge machine synchronous construction using section, it is characterised in that hanging When filling the section block at afterbody both ends, when hanging two groups of section blocks of arbitrary neighborhood, step 2 when hanging section block on the left of next group of afterbody In also include the afterbody that mobile hoisting overhead travelling crane makes to have lifted completion on the left of next group of afterbody on section hanging crossbeam close to previous group It is 200mm that the sling point of left side section block, which has lifted section block end face horizontal range on the left of the afterbody of completion with previous group,.
  6. 6. the method as claimed in claim 2 that equidistantly double width bridge spells bridge machine synchronous construction using section, it is characterised in that second Any one in two sling points is between corresponding 3rd group of suspension centre and the 4th group of suspension centre between group suspension centre and the 3rd group of suspension centre Axisymmetrical of the sling point along section block width is set.
  7. 7. the method as claimed in claim 2 that equidistantly double width bridge spells bridge machine synchronous construction using section, it is characterised in that first Suspension centre, the second suspension centre, the 3rd suspension centre, four-point lifting, the 5th suspension centre, the 6th suspension centre circle center line connecting and hanging crossbeam longitudinal axis Line overlaps.
  8. 8. the method as claimed in claim 2 that equidistantly double width bridge spells bridge machine synchronous construction using section, it is characterised in that hanging Crossbeam length is 1~1.01 times of section block length, when hanging crossbeam is arranged on the block of section along its length, hanging crossbeam length The axis in degree direction overlaps with the axis in section block length direction.
CN201710910609.6A 2017-09-29 2017-09-29 The method that equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction Active CN107687132B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710910609.6A CN107687132B (en) 2017-09-29 2017-09-29 The method that equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710910609.6A CN107687132B (en) 2017-09-29 2017-09-29 The method that equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction

Publications (2)

Publication Number Publication Date
CN107687132A true CN107687132A (en) 2018-02-13
CN107687132B CN107687132B (en) 2019-03-08

Family

ID=61153824

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710910609.6A Active CN107687132B (en) 2017-09-29 2017-09-29 The method that equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction

Country Status (1)

Country Link
CN (1) CN107687132B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797379A (en) * 2018-07-03 2018-11-13 中交第二航务工程局有限公司 Become the method that spacing double width bridge uses Segmental assembling bridge-erecting machine synchronous construction
CN109629422A (en) * 2018-11-28 2019-04-16 中交第二航务工程局有限公司 A kind of new Bridge Erector traverses over width method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1244230A1 (en) * 1984-12-26 1986-07-15 Государственный Ордена Трудового Красного Знамени Проектно-Изыскательский Институт По Проектированию И Изысканиям Больших Мостов "Гипротрансмост" Crane for balanced mounting of bridge span structure assembled of prefabricated span and above-pier blocks
KR20030093680A (en) * 2002-06-05 2003-12-11 브이에스엘코리아 주식회사 The construction method of double-t girder bridge by underslung movable scaffolding system
CN104631335A (en) * 2015-02-05 2015-05-20 郑州新大方重工科技有限公司 Novel large-tonnage bridge girder erection machine and construction method thereof
CN205474869U (en) * 2016-03-23 2016-08-17 中铁一局集团有限公司 Festival section is assembled case roof beam structure and is established construction equipment
CN206256380U (en) * 2016-11-10 2017-06-16 秦皇岛天业通联重工科技有限公司 One kind combination beam car
CN107165055A (en) * 2017-07-07 2017-09-15 中铁二局集团有限公司 Beam and full span erection construction method are transported on a kind of large-tonnage, asymmetric, framing prefabricated case beam beam

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1244230A1 (en) * 1984-12-26 1986-07-15 Государственный Ордена Трудового Красного Знамени Проектно-Изыскательский Институт По Проектированию И Изысканиям Больших Мостов "Гипротрансмост" Crane for balanced mounting of bridge span structure assembled of prefabricated span and above-pier blocks
KR20030093680A (en) * 2002-06-05 2003-12-11 브이에스엘코리아 주식회사 The construction method of double-t girder bridge by underslung movable scaffolding system
CN104631335A (en) * 2015-02-05 2015-05-20 郑州新大方重工科技有限公司 Novel large-tonnage bridge girder erection machine and construction method thereof
CN205474869U (en) * 2016-03-23 2016-08-17 中铁一局集团有限公司 Festival section is assembled case roof beam structure and is established construction equipment
CN206256380U (en) * 2016-11-10 2017-06-16 秦皇岛天业通联重工科技有限公司 One kind combination beam car
CN107165055A (en) * 2017-07-07 2017-09-15 中铁二局集团有限公司 Beam and full span erection construction method are transported on a kind of large-tonnage, asymmetric, framing prefabricated case beam beam

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄耀抑,余春红: "略论我国大吨位架桥机从创始到世界领先之路(下)", 《铁道建筑技术》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797379A (en) * 2018-07-03 2018-11-13 中交第二航务工程局有限公司 Become the method that spacing double width bridge uses Segmental assembling bridge-erecting machine synchronous construction
CN108797379B (en) * 2018-07-03 2023-05-26 中交第二航务工程局有限公司 Synchronous construction method for variable-spacing double-frame bridge by adopting segment assembly bridge girder erection machine
CN109629422A (en) * 2018-11-28 2019-04-16 中交第二航务工程局有限公司 A kind of new Bridge Erector traverses over width method

Also Published As

Publication number Publication date
CN107687132B (en) 2019-03-08

Similar Documents

Publication Publication Date Title
CN105649654B (en) Automatic hydraulic inverted arch trestle chassis and its construction method
CN105421249B (en) Dragging- hoisting combined type hanging basket structure and construction method
CN100549348C (en) Construction method for hanging wide span arcuated open-web beam
CN206796168U (en) The complete erecting device of prefabricated case beam reinforcing bar is used in construction
CN101736703B (en) 3000t special bridge girder erection machine for integrally erecting 120m-span double-layer four-line steel beam bridge for highway and railway
CN105155417B (en) A kind of climb type fortune girder span car and the tunnel face bridge fortune frame method based on it
CN109653105A (en) Box girder bridge cantilever construction main truss cradle system and its application method
CN107687132A (en) The method that equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction
CN107265296A (en) Guy device
CN107653783B (en) Double width bridge tail portion feeding beam hanging method
CN108408667A (en) Broken line type girder truss rod piece Quick overturning device and its method for turning
CN102926330B (en) Installation method of hanging basket suitable for bridge construction
JPH08165613A (en) Erection method of bridge beam
CN202465099U (en) Single-girder partial hanging gantry crane
CN207973408U (en) Simple lifting appliance in a kind of tunnel
CN109607384A (en) The turn-over method of super-large-diameter shield machine knife disk
CN207484304U (en) Can double width synchronous construction Segmental assembling bridge-erecting machine
CN110510500A (en) A kind of carbon bar shifting basket special hanger
CN204569150U (en) A kind of tyre crane driver's cab hoisting fixture
CN207078901U (en) Gravity motion hanging beam
JP2018084101A (en) Stacking device and stacking method
CN103523678B (en) Crane
CN103496630B (en) A kind of suspender and use the weight-lifting equipment of this suspender
CN205855847U (en) A kind of telescopic arm bridge crane
CN208201527U (en) A kind of integrated sleeper bed accurate adjustment vehicle

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant