CN107653783B - Double width bridge tail portion feeding beam hanging method - Google Patents

Double width bridge tail portion feeding beam hanging method Download PDF

Info

Publication number
CN107653783B
CN107653783B CN201710910642.9A CN201710910642A CN107653783B CN 107653783 B CN107653783 B CN 107653783B CN 201710910642 A CN201710910642 A CN 201710910642A CN 107653783 B CN107653783 B CN 107653783B
Authority
CN
China
Prior art keywords
group
suspension centre
hanging
suspension
segment block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710910642.9A
Other languages
Chinese (zh)
Other versions
CN107653783A (en
Inventor
崔洪谱
罗领
聂凯
谢小琴
陈若强
胡守增
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201710910642.9A priority Critical patent/CN107653783B/en
Publication of CN107653783A publication Critical patent/CN107653783A/en
Application granted granted Critical
Publication of CN107653783B publication Critical patent/CN107653783B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

The present invention provides a kind of double width bridge tail portion feeding beam hanging methods, include: S1, hoisting overhead travelling crane is installed on Bridge Erector, hoisting overhead travelling crane includes: crossbeam, suspender positioned at crossbeam lower end surface, it is set to two overarm arms of crossbeam lower end surface, overarm arm lower end surface is all provided with there are four hanging beam trolley, and each hanging beam trolley is slidably;S2, it is equipped with first group of suspension centre, second group of suspension centre, third group suspension centre, the 4th group of suspension centre, the 5th group of suspension centre, the 6th group of suspension centre in hanging beam upper end, opposite hanging crossbeam length direction can two width bridge of left and right progress feeding beam lifting to double width bridge between second group of suspension centre and third group suspension centre, between third group suspension centre and the 4th group of suspension centre;Double width bridge section block tail portion feeding beam hanging method of the invention, double width bridge synchronous construction is realized, reduces conventional construction method and traversing Bridge Erector is needed back and forth twice, to reduce longitudinal via hole number of Bridge Erector half, the operational risk for thus greatly reducing equipment, shortens the construction period.

Description

Double width bridge tail portion feeding beam hanging method
Technical field
The present invention relates to technical field of bridge construction, and in particular to a kind of double width bridge tail portion feeding beam hanging method.
Background technique
For two-way road precast segment bridge, domestic Segmental assembling bridge-erecting machine is commonly traditional single width bridge and applies at present Work, that is, by traversing jib lubbing mechanism by traversing to another width bridge construction of complete machine after a width bridge of having constructed.And such construction method It needs to move back and forth Bridge Erector twice, that is, moves Bridge Erector and constructed after a secondary bridge, again by traversing jib lubbing mechanism by complete machine Traversing to another width bridge construction extends the construction period to considerably increase the operational risk of equipment.And in practice of construction The depth of water is not able to satisfy pontoon fortune beam requirement when building bridge in the process, can not achieve feeding beam under bridge, need to carry out bridge drive end unit feeding beam.
Summary of the invention
It is an object of the invention to solve the above problems, and provide the advantages of at least will be described later.
It is a still further object of the present invention to provide a kind of double width bridge tail portion feeding beam hanging methods, by hoisting overhead travelling crane Two overarm arms in setting left and right on crossbeam, and be arranged on hanging crossbeam six groups of suspension centres can two width bridge of left and right to double width bridge into The lifting of row feeding beam is to complete the construction of double width bridge.
In order to realize these purposes and other advantages according to the present invention, a kind of double width bridge tail portion feeding beam lifting side is provided Method, comprising the following steps:
S1, hoisting overhead travelling crane is installed on Bridge Erector, hoisting overhead travelling crane can be moved along crane's major girder length direction, wherein institute Stating hoisting overhead travelling crane includes: horizontally disposed crossbeam, and the suspender positioned at crossbeam lower end surface is set under crossbeam along crossbeam length direction Two overarm arms of end face, each overarm arm lower end surface are provided along its length two groups of hanging beam trolleies, and every group of hanging beam trolley is equal Including two with the symmetrically arranged two hanging beam trolleies of overarm arm length direction, each hanging beam trolley can be along overarm arm lengths side To sliding;
S2, in hanging beam upper end first group of suspension centre, second group of suspension centre, third group are set gradually along its length hang Point, the 4th group of suspension centre, the 5th group of suspension centre, the 6th group of suspension centre, first group of suspension centre include two and are symmetrical arranged with hanging crossbeam length The first suspension centre, second group of suspension centre include two to hang symmetrically arranged second suspension centre of crossbeam length, third group suspension centre includes Two are symmetrical arranged with hanging the symmetrically arranged third suspension centre of crossbeam length, the 4th group of suspension centre including two with hanging crossbeam length Four-point lifting, the 5th group of suspension centre include two to hang symmetrically arranged 5th suspension centre of crossbeam length, the 6th group of suspension centre includes Two to hang symmetrically arranged 6th suspension centre of crossbeam length, wherein hangs the length of the crossbeam width between crane's major girder 1.26~1.28 times, first group of suspension centre and second group of suspension centre spacing are 0.336~0.353 times for hanging crossbeam length, second Group suspension centre and third group suspension centre distance are 0.179~0.197 times of hanging crossbeam length, between third group suspension centre and the 4th group of suspension centre Away from 0.0053~0.0795 times for hanging crossbeam length, the 4th group of suspension centre and the 5th group of suspension centre spacing are hanging crossbeam length 0.289~0.307 times, the 5th group of suspension centre and the 6th group of suspension centre spacing are 0.043~0.0606 times for hanging crossbeam length, first The spacing of the end of the hanging crossbeam of group suspension centre and close first group of suspension centre is 0.0103~0.0274 times for hanging crossbeam length, Between second group of suspension centre and third group suspension centre, crossbeam length-wise axis pair is hung between third group suspension centre and the 4th group of suspension centre relatively Title is all provided with there are two sling point;
S3, from both ends to centre multiple groups segment block is lifted between the bridge pier of tail portion two, the lifting of every group of segment block includes The lifting of left side segment block and the lifting of right side segment block, wherein the lifting of left side segment block, comprising the following steps:
Hanging crossbeam is mounted on the block of left side segment along its length, and utilizes the suspender at hoisting overhead travelling crane center by step 1 Left side segment block is hung between crane's major girder with width direction, with being located at the suspender at hoisting overhead travelling crane center for left side segment block It slings, and girder or less will be placed under the block of left side segment;
Step 2, suspender drive left side segment block to be moved to the left, after be rotated by 90 ° so that left side segment block length direction and frame Bridge main beam width direction is consistent;
Step 3, the mobile hanging beam trolley being located in overarm arm at left and right sides of suspender, and make close in the overarm arm of left side The suspension hook of one group of hanging beam trolley of suspender catches on two the second suspension centres of second group of suspension centre, close suspender in the overarm arm of right side respectively The suspension hook of one group of hanging beam trolley catch on two the 5th suspension centres of the 5th group of suspension centre respectively, unclamp suspender afterwards, suspender moves right To original position;
Step 4, hanging beam trolley drive left side segment block to be moved to the left, so that one group in the overarm arm of left side far from suspender is hung The suspension hook of beam trolley catches on two the first suspension centres of first group of suspension centre respectively, and one group of hanging beam of close suspender is small in the overarm arm of left side The suspension hook pine hook of vehicle, and move right to two third suspension centres surfaces of third group suspension centre so that its suspension hook catches on third respectively Suspension centre close to the suspension hook pine hook of one group of hanging beam trolley of suspender in the overarm arm of right side, and moves right to the two of the 6th group of suspension centre So that its suspension hook catches on the 6th suspension centre respectively right above a 6th suspension centre, one group of hanging beam trolley of close suspender in the overarm arm of left side Suspension hook pine hook;
Step 5 is moved to the left left side segment block, and makes in the overarm arm of left side close to the suspension hook of one group of hanging beam trolley of suspender Two four-point liftings of the 4th group of suspension centre are caught on respectively, then unclamp one group of hanging beam trolley in the overarm arm of right side close to suspender;
Step 6 is moved to the left left side segment block, under so that left side segment block is located at crane's major girder left side hanging reinforcing bar just Side, and hanging reinforcing bar is made to catch on sling point, it unclamps hanging beam trolley lifting hook and completes left side segment block lifting;
The hanging of right side segment block, comprising the following steps:
Step a, hoisting overhead travelling crane is moved along bridge formation direction, repeats step 1;
Step b, suspender drives right side segment block to move right, and is rotated by 90 °, so that left in right side segment block and step 2 Side segment block is in mirror symmetry;
Step c, mobile one group of hanging beam trolley being located in overarm arm at left and right sides of suspender, and make in the overarm arm of left side Two the 5th suspension centres of the 5th group of suspension centre are caught on respectively close to the suspension hook of one group of hanging beam trolley of suspender, it is close in the overarm arm of right side The suspension hook of one group of hanging beam trolley of suspender catches on two the second suspension centres of second group of suspension centre respectively, and unclamps suspender, and suspender is to the right It is moved to original position;
Step d, hanging beam trolley drives right side segment block to move right, so that one group in the overarm arm of right side far from suspender is hung The suspension hook of beam trolley catches on two the first suspension centres of first group of suspension centre and unclamps one group of hanging beam in the overarm arm of right side close to suspender Trolley;
Step e, it moves one group of hanging beam trolley of close suspender in the overarm arm of right side and its suspension hook is made to catch on third group respectively Then two third suspension centres of suspension centre move one group of hanging beam trolley of close suspender in the overarm arm of left side and hook its suspension hook respectively Then firmly two the 6th suspension centres of the 6th group of suspension centre unclamp the hanging beam trolley of two third suspension centres of third group suspension centre;
Step f, hanging beam trolley drives right side segment block to move right, and makes to hang in the overarm arm of right side close to one group of suspender The suspension hook of beam trolley catches on two third suspension centres of third group suspension centre, then unclamps hanging for two the 6th suspension centres of the 6th group of suspension centre Beam trolley lifting hook;
Step g, hanging beam trolley drives right side segment block to move right, and moves hoisting overhead travelling crane along bridge formation opposite direction, makes Right side segment block and the left side segment block lifted are located in a straight line and are located at right side segment block on the right side of crane's major girder It hangs immediately below reinforcing bar, and hanging reinforcing bar is made to catch on sling point, unclamp hanging beam trolley lifting hook and complete right side segment block lifting.
Preferably, the double width bridge tail portion feeding beam hanging method, in S3 when hanging two groups of segment blocks of arbitrary neighborhood, Wherein one group of left side segment block, right side segment block will place girder or less 1.4 using suspender under left side segment block, right side segment block ~1.5m, another set left side segment block, right side segment block will place girder under left side segment block, right side segment block using suspender 5.2~5.3m below.
Preferably, the double width bridge tail portion feeding beam hanging method, the length that crossbeam is hung in S2 is crane's major girder Between 1.27 times of width, first group of suspension centre and second group of suspension centre spacing are 0.344 times for hanging crossbeam length, second group of suspension centre It is 0.196 times of hanging crossbeam length with third group suspension centre distance, third group suspension centre and the 4th group of suspension centre spacing are hanging crossbeam 0.07094 times of length, the 4th group of suspension centre and the 5th group of suspension centre spacing are 0.298 times for hanging crossbeam length, the 5th group of suspension centre It is 0.0521 times for hanging crossbeam length, first group of suspension centre and the hanging crossbeam close to first group of suspension centre with the 6th group of suspension centre spacing The spacing of end be to hang 0.0188 times of crossbeam length.
Preferably, the double width bridge tail portion feeding beam hanging method hangs any phase when lifting the segment block at both ends It in step 2 further include that mobile hoisting overhead travelling crane makes next group of left side section when hanging next group of left side segment block when adjacent two groups of segment blocks The sling point and previous group that have lifted the left side segment block of completion on section hanging crossbeam close to previous group have lifted the left side of completion Segment block end face horizontal distance is 200mm.
Preferably, the double width bridge tail portion feeding beam hanging method, two between second group of suspension centre and third group suspension centre The axis of sling point between any one in sling point and corresponding third group suspension centre and the 4th group of suspension centre along segment block width direction Line is symmetrical arranged.
Preferably, the double width bridge tail portion feeding beam hanging method, the first suspension centre, the second suspension centre, third suspension centre, the 4th Suspension centre, the 5th suspension centre, the 6th suspension centre circle center line connecting are overlapped with hanging crossbeam length-wise axis.
Preferably, the double width bridge tail portion feeding beam hanging method, hanging crossbeam length be segment block length 1~ 1.01 times, when hanging crossbeam is mounted on along its length on the block of segment, hang the axis and segment block length of crossbeam length direction The axis in direction is overlapped.
The present invention is include at least the following beneficial effects:
1, double width bridge tail portion feeding beam hanging method of the invention at left and right sides of the crossbeam lower end surface of hoisting overhead travelling crane by setting The cantilever beam set, each cantilever beam are equipped with two groups of slidable hanging beam trolleies, and six groups of suspension centres are arranged on hanging crossbeam, due to Width between crane's major girder is small, and the length of segment block is greater than the width between girder, and segment block cannot be with (width) direction Into between girder, it is necessary to be entered between girder after being rotated by 90 ° with length direction, then be transferred to girder hereinafter, being rotated by 90 ° again Back.Simultaneously when hanging segment block, segment block can only move between girder, by the hanging beam trolley of left and right settings and multiple The adjustable left and right segment block position of suspension centre can make left side segment block or the adjustment of right side segment block with respect to the position of girder in this way Double width has been achieved to complete the lifting to left side segment block or right side segment block to the underface of girder hanging reinforcing bar Bridge synchronous construction reduces conventional construction method and needs to move back and forth Bridge Erector twice, reduces longitudinal via hole of bridge machine half Number thus greatly reduces the operational risk of equipment, shortens the construction period.
Further advantage, target and feature of the invention will be partially reflected by the following instructions, and part will also be by this The research and practice of invention and be understood by the person skilled in the art.
Figure of description
Fig. 1 is the structural schematic diagram of segment block;
Fig. 2 is the schematic cross-section of crane's major girder;
Fig. 3 is that hanging crossbeam is mounted on schematic diagram on the block of segment;
Fig. 4 is hoisting overhead travelling crane and hanging beam engagement schematic diagram;
Fig. 5 is Bridge Erector and hoisting overhead travelling crane schematic diagram;
Fig. 6~Figure 11 is the hanging method schematic diagram of left side segment block lifting;
Figure 12 is schematic diagram after the completion of left side segment block and the lifting of right side segment block
Figure 13 is schematic diagram after the lifting of multiple groups segment block.
Specific embodiment
The present invention will be further described in detail below with reference to the embodiments, to enable those skilled in the art referring to specification Text can be implemented accordingly.
It should be noted that experimental method described in following embodiments is unless otherwise specified conventional method, institute Reagent and material are stated, unless otherwise specified, is commercially obtained.
A kind of double width bridge tail portion feeding beam hanging method, comprising the following steps:
S1, hoisting overhead travelling crane 2 is installed on Bridge Erector, hoisting overhead travelling crane 2 can be moved along 1 length direction of crane's major girder, wherein The hoisting overhead travelling crane 2 includes: horizontally disposed crossbeam 21, and crossbeam 21 is located between two supporting legs 22, and supporting leg 22 is splayed branch Leg, supporting leg 22 can be moved along 1 length direction of crane's major girder, the suspender 23 positioned at 21 lower end surface of crossbeam, along 21 length side of crossbeam To two overarm arms 24 for being set to 21 lower end surface of crossbeam, two overarm arms 24 are symmetrically distributed in 23 left and right sides of suspender, each Overarm arm 24 is respectively positioned on 24 outside of crossbeam far from the end of suspender 23, i.e., the two of overarm arm 24 end is located at the two of supporting leg 22 Side, each 24 lower end surface of overarm arm are provided along its length two groups of hanging beam trolleies, and every group of hanging beam trolley includes two with outstanding The symmetrically arranged two hanging beam trolleies 25 of beam arm length direction, two hanging beam trolleies 25, each hanging beam trolley 25 can be along overarm The sliding of 24 length direction of arm;
S2, it is disposed with first group of suspension centre, second group of suspension centre, third along its length in hanging 3 upper surface of crossbeam Group suspension centre, the 4th group of suspension centre, the 5th group of suspension centre, the 6th group of suspension centre, first group of suspension centre include two symmetrical to hang 3 length of crossbeam 31, the second groups of suspension centres of the first suspension centre being arranged include two to hang symmetrically arranged second suspension centre 32 of 3 length of crossbeam, third group Suspension centre includes two to hang the symmetrically arranged third suspension centre 33 of 3 length of crossbeam, the 4th group of suspension centre including two to hang crossbeam 3 The symmetrically arranged four-point lifting 34 of length, the 5th group of suspension centre include two to hang symmetrically arranged 5th suspension centre of 3 length of crossbeam 35, the 6th group of suspension centre includes two to hang symmetrically arranged 6th suspension centre 36 of 3 length of crossbeam, wherein the length of hanging crossbeam 3 1.26~1.28 times of width between crane's major girder 1, first group of suspension centre and second group of suspension centre spacing are hanging 3 length of crossbeam 0.336~0.353 times, second group of suspension centre and third group suspension centre distance are 0.179~0.197 times of hanging 3 length of crossbeam, the Three groups of suspension centres and the 4th group of suspension centre spacing are to hang 0.0053~0.0795 times of 3 length of crossbeam, the 4th group of suspension centre and the 5th group Suspension centre spacing is 0.289~0.307 times for hanging 3 length of crossbeam, and the 5th group of suspension centre and the 6th group of suspension centre spacing are hanging crossbeam 3 The end spacing of 0.043~0.0606 times of length, first group of suspension centre and the hanging crossbeam 3 close to first group of suspension centre is that hanging is horizontal 0.0103~0.0274 times of 3 length of beam, between second group of suspension centre and third group suspension centre, between third group suspension centre and the 4th group of suspension centre Opposite hanging 3 length-wise axis of crossbeam is symmetrically all provided with that there are two sling points 37;
Here it is 31 axis of the first suspension centre and corresponding second suspension centre that the spacing of first group of suspension centre and second group of suspension centre is practical 32 axial line distances, second group of suspension centre and third group suspension centre distance reality are 32 axis of the second suspension centre and corresponding 33 axis of third suspension centre Linear distance, third group suspension centre is practical with the 4th group of suspension centre spacing be 33 axis of third suspension centre and corresponding 34 axis of four-point lifting away from Practical from, the 4th group of suspension centre and the 5th group of suspension centre spacing is 34 axis of four-point lifting and corresponding 5th suspension centre, 35 axial line distance, 5th group of suspension centre and the 6th group of suspension centre spacing it is practical be 35 axis of the 5th suspension centre and corresponding 6th suspension centre, 36 axial line distance, first The end spacing of suspension centre group and the hanging crossbeam 3 close to first group of suspension centre is practical, and to be 31 axis of the first suspension centre hang with close first The end spacing of the hanging crossbeam 3 of point 31;The width of crane's major girder 1 is 9.2m in this programme, then hangs the length of crossbeam 3 For 11.592~11.776m, first group of suspension centre and second group of suspension centre spacing are 3.894~4.156m, second group of suspension centre and third Group suspension centre distance is 2.174~2.319m, and third group suspension centre and the 4th group of suspension centre spacing are 0.0614~0.9361m, the 4th group Suspension centre and the 5th group of suspension centre spacing are 3.35~3.615m, and the 5th group of suspension centre and the 6th group of suspension centre spacing are 0.498~0.713m, The end spacing of first group of suspension centre and the hanging crossbeam 3 close to first group of suspension centre is 0.119~0.322m;
S3, from both ends to centre multiple groups segment block is lifted between the bridge pier of tail portion two, the lifting of every group of segment block includes The lifting of left side segment block and the lifting of right side segment block, wherein the lifting of left side segment block, comprising the following steps:
Hanging crossbeam 3 is mounted on the block of left side segment by step 1 along its length, and hanging using hoisting overhead travelling crane center Left side segment block is hung between crane's major girder by tool with width direction, with being located at the suspender at hoisting overhead travelling crane center for left side segment Block is sling, and girder or less will be placed under the block of left side segment;
Step 2, suspender 23 drive left side segment block to be moved to the left, after be rotated by 90 ° so that left side segment block length direction with 1 width direction of crane's major girder is consistent;
Step 3, the mobile hanging beam trolley 25 being located in 23 left and right sides overarm arm of suspender, and make in the overarm arm of left side It catches on two the second suspension centres 32 of second group of suspension centre respectively close to the suspension hook of one group of hanging beam trolley of suspender, is leaned in the overarm arm of right side The suspension hook of one group of hanging beam trolley of nearly suspender catches on two the 5th suspension centres 35 of the 5th group of suspension centre respectively, rear to unclamp suspender 23, hangs Tool 23 moves right to original position;
Step 4, hanging beam trolley 25 drive left side segment block to be moved to the left, so that one group in the overarm arm of left side far from suspender The suspension hook of hanging beam trolley catches on two the first suspension centres 31 of first group of suspension centre respectively, and one group of close suspender is hung in the overarm arm of left side The suspension hook pine hook of beam trolley, and move right to right above two third suspension centres 33 of third group suspension centre so that its suspension hook catches on the Three suspension centres 33 close to the suspension hook pine hook of one group of hanging beam trolley of suspender in the overarm arm of right side, and move right to the 6th group of suspension centre Two the 6th suspension centres 36 right above so that its suspension hook catches on the 6th suspension centre 36 respectively, close to the one of suspender 23 in the overarm arm of left side The suspension hook pine hook of group hanging beam trolley;
Step 5 is moved to the left left side segment block, and makes in the overarm arm of left side close to the suspension hook of one group of hanging beam trolley of suspender Two four-point liftings 34 of the 4th group of suspension centre are caught on, one group of hanging beam trolley in the overarm arm of right side close to suspender 23 is then unclamped;
Step 6 is moved to the left left side segment block, under so that left side segment block is located at crane's major girder left side hanging reinforcing bar just Side, and hanging reinforcing bar is made to catch on sling point 37, it unclamps hanging beam trolley lifting hook and completes left side segment block lifting;
The hanging of right side segment block, comprising the following steps:
Step a, hoisting overhead travelling crane is moved along bridge formation direction, repeats step 1;
Step b, suspender drives right side segment block to move right, and is rotated by 90 °, so that right side segment block is with respect in step 2 Left side segment block is with crane's major girder length direction mirror symmetry;
Step c, mobile one group of hanging beam trolley 25 being located in overarm arm at left and right sides of suspender, and make left side overarm arm The suspension hook of upper one group of hanging beam trolley close to suspender catches on two the 5th suspension centres 35 of the 5th group of suspension centre respectively, in the overarm arm of right side Suspension hook close to one group of hanging beam trolley of suspender catches on two the second suspension centres 32 of second group of suspension centre respectively, and unclamps suspender, hangs Tool moves right to original position;
Step d, hanging beam trolley drives right side segment block to move right, so that one group in the overarm arm of right side far from suspender is hung The suspension hook of beam trolley catches on two the first suspension centres 31 of first group of suspension centre and unclamps and hangs in the overarm arm of right side close to one group of suspender Beam trolley;
Step e, it moves one group of hanging beam trolley of close suspender in the overarm arm of right side and its suspension hook is made to catch on third group respectively Then two third suspension centres 33 of suspension centre move one group of hanging beam trolley of close suspender in the overarm arm of left side and distinguish its suspension hook Two the 6th suspension centres 36 of the 6th group of suspension centre are caught on, the hanging beam trolley 25 of third suspension centre 33 is then unclamped;
Step f, hanging beam trolley drives right side segment block to move right, and makes to hang in the overarm arm of right side close to one group of suspender The suspension hook of beam trolley catches on two third suspension centres 33 of third group suspension centre, then unclamps two the 6th suspension centres 36 of the 6th group of suspension centre Hanging beam trolley lifting hook;
Step g, hanging beam trolley drives right side segment block to move right, and moves hoisting overhead travelling crane along bridge formation opposite direction, makes Right side segment block and the left side segment block lifted are located in a straight line and are located at right side segment block on the right side of crane's major girder It hangs immediately below reinforcing bar, and hanging reinforcing bar is made to catch on sling point, unclamp hanging beam trolley lifting hook and complete right side segment block lifting.
Fig. 6~Figure 11 is the method and step of left side segment block lifting, and wherein the length of segment block 4 is 11.55m, Bridge Erector Minimum widith between girder inside is 9.2m, and left side segment block is hung to girder or less 1.5m using suspender in Fig. 6, will be left Side segment block traversing 0.7m to the left, is then rotated by 90 °, left side segment block length direction is consistent with crane's major girder width direction; Mobile one group of hanging beam trolley 25 being located in 23 left and right sides overarm arm of suspender in Fig. 7, and make close in the overarm arm of left side The suspension hook of the hanging beam trolley of suspender catches on two the second suspension centres 32 of second group of suspension centre, the hanging beam of close suspender in the overarm arm of right side The suspension hook of trolley catches on two the 5th suspension centres 35 of the 5th group of suspension centre, rear to unclamp suspender 23, and suspender 23 moves right 0.7m to original Position;Hanging beam trolley 25 drives left side segment block to be moved to the left 2.3m in Fig. 8, Fig. 9, so that hanging far from suspender in the overarm arm of left side The suspension hook of beam trolley catches on two the first suspension centres 31 of first group of suspension centre, and the hanging beam trolley of close suspender hangs in the overarm arm of left side Hook pine hook, and to two third suspension centres of third group suspension centre, 33 surface so that its suspension hook catches on third group after the 2.3m that moves right Two third suspension centres 33 of suspension centre, close to the suspension hook pine hook of the hanging beam trolley of suspender in the overarm arm of right side, and the 0.61m that moves right So that its suspension hook catches on two the 6th suspension centres 36 of the 6th group of suspension centre right above to the 6th suspension centre 36, close to hanging in the overarm arm of left side The suspension hook pine hook of the hanging beam trolley of tool 23;After being moved to the left left side segment block 0.75m in Figure 10, and make close in the overarm arm of left side The suspension hook of the hanging beam trolley of suspender catches on two four-point liftings 34 of the 4th group of suspension centre, then unclamps close in the overarm arm of right side hang The hanging beam trolley of tool 23;After being moved to the left left side segment block 2.735m in Figure 11, left side segment block is made to be located at a crane's major girder left side Side is hung immediately below reinforcing bar, and hanging reinforcing bar is made to catch on sling point 37, is unclamped hanging beam trolley lifting hook and is completed left side segment block lifting; Since the supporting leg 22 of Bridge Erector stops so that the suspension hook of hanging beam trolley can only be in overarm arm 24 during catching on hanging crossbeam 3 It is mobile positioned at the side of supporting leg 22, that is, the suspension hook of the hanging beam trolley of 22 two sides of supporting leg is distributed in during catching on hanging crossbeam 3 Mobile no more than supporting leg, and movement is only defined within crane's major girder, therefore is hung using the multiple suspension centres of setting and setting Beam trolley adjusts segment block position, to complete the lifting of left side segment block and right side segment block.
The method that the suspending method of right side segment block is lifted with left side segment block, right side segment block hangs in hoisting process The axial direction for filling the opposite crane's major girder length direction of the lifting with left side segment block is in mirror symmetry, and Figure 12 is section on the left of being finally The schematic diagram that section block and the lifting of right side segment block are completed;
In another technical solution, the double width bridge tail portion feeding beam hanging method, in hanging arbitrary neighborhood two in S3 When group segment block, wherein one group of left side segment block, right side segment block will be placed using suspender under left side segment block, right side segment block 1.4~1.5m below girder, another set left side segment block, right side segment block use suspender by left side segment block, right side segment 5.2~5.3m of girder or less is placed under block.It is in be staggered in lifting such as Figure 13 two adjacent groups segment block.
In another technical solution, the double width bridge tail portion feeding beam hanging method, the length that crossbeam 3 is hung in S2 is 1.27 times of width between crane's major girder 1, first group of suspension centre and second group of suspension centre spacing are hang 3 length of crossbeam 0.344 Times, second group of suspension centre and third group suspension centre distance are 0.196 times for hanging 3 length of crossbeam, third group suspension centre and the 4th group of suspension centre Spacing is 0.07094 times for hanging 3 length of crossbeam, and the 4th group of suspension centre and the 5th group of suspension centre spacing are hanging 3 length of crossbeam 0.298 times, the 5th group of suspension centre and the 6th group of suspension centre spacing are 0.0521 times for hanging 3 length of crossbeam, first group of suspension centre with it is close The end spacing of the hanging crossbeam of first group of suspension centre is 0.0188 times for hanging crossbeam length.I.e. hang crossbeam 3 length be 11.68m, first group of suspension centre and second group of suspension centre spacing are 4.01m, second group of suspension centre and third group suspension centre distance are 2.28m, Three groups of suspension centres and the 4th group of suspension centre spacing be 0.828m, the 4th group of suspension centre and the 5th group of suspension centre spacing are 3.48m, the 5th group of suspension centre It is 0.608m with the 6th group of suspension centre spacing, the end spacing of first group of suspension centre and the hanging crossbeam close to first group of suspension centre is 0.219m。
In another technical solution, the double width bridge tail portion feeding beam hanging method, when lifting the segment block at both ends, Hang two groups of segment blocks of arbitrary neighborhood when, hang next group left side segment block when step 2 in further include under mobile hoisting overhead travelling crane makes The sling point for the left side segment block for having lifted completion close to previous group on one group of left side segment hanging crossbeam has been lifted with previous group The left side segment block end face horizontal distance of completion is 200mm.Technical solution of the present invention lifts segment using by both ends to centre Block, when positioned at the multiple groups segment block lifting of last group of two sides, the two adjacent groups segment block of any side saves on the left of next group When section block lifting, mobile hoisting overhead travelling crane makes the left side section for having lifted completion on next group of left side segment hanging crossbeam close to previous group The left side segment block end face horizontal distance that the sling point and previous group of section block have lifted completion is 200mm, last in lifting in this way Left side segment block or right side segment block in one group will not encounter the adjacent segment block for having lifted completion in rotary course.
In another technical solution, the double width bridge tail portion feeding beam hanging method, second group of suspension centre is hung with third group Sling point of any one in two sling points between corresponding third group suspension centre and the 4th group of suspension centre is wide along segment block between point Spend the axisymmetrical setting in direction.Four sling points being arranged on hanging crossbeam 3, the axial direction in the rectangle length direction formed with The axis of width direction is overlapped with the length-wise axis of hanging crossbeam 3 and width axis respectively.
In another technical solution, the double width bridge tail portion feeding beam hanging method, the first suspension centre 31, the second suspension centre 32, third suspension centre 33, four-point lifting 34, the 5th suspension centre 35,36 circle center line connecting of the 6th suspension centre and hanging 3 length-wise axis of crossbeam It is overlapped.I.e. the setting of suspension centre is located in hanging 3 length-wise axis of crossbeam.
In another technical solution, the double width bridge tail portion feeding beam hanging method, hanging 3 length of crossbeam is segment block 1~1.01 times of length, hanging crossbeam 3 is when being mounted on the block of segment along its length, hang the axis of 3 length direction of crossbeam with The axis in segment block length direction is overlapped.The length for hanging crossbeam 3 is slightly larger than segment block length, and hanging crossbeam 3 is mounted on section Section block center lifts more stable when the block of segment when such.
Although the embodiments of the present invention have been disclosed as above, but its is not only in the description and the implementation listed With it can be fully applied to various fields suitable for the present invention, for those skilled in the art, can be easily Realize other modification, therefore without departing from the general concept defined in the claims and the equivalent scope, the present invention is simultaneously unlimited In specific details and embodiment shown and described herein.

Claims (7)

1. a kind of double width bridge tail portion feeding beam hanging method, which comprises the following steps:
S1, hoisting overhead travelling crane is installed on Bridge Erector, hoisting overhead travelling crane can be moved along crane's major girder length direction, wherein described Weight overhead traveling crane includes: horizontally disposed crossbeam, and the suspender positioned at crossbeam lower end surface is set to crossbeam lower end surface along crossbeam length direction Two overarm arms, each overarm arm lower end surface is provided along its length two groups of hanging beam trolleies, and every group of hanging beam trolley includes Two can be slided with the symmetrically arranged two hanging beam trolleies of overarm arm length direction, each hanging beam trolley along overarm arm length direction It is dynamic;
S2, it is disposed with first group of suspension centre, second group of suspension centre, third group along its length hangs in hanging beam upper end Point, the 4th group of suspension centre, the 5th group of suspension centre, the 6th group of suspension centre, first group of suspension centre include two and are symmetrical arranged with hanging crossbeam length The first suspension centre, second group of suspension centre include two to hang symmetrically arranged second suspension centre of crossbeam length, third group suspension centre includes Two are symmetrical arranged with hanging the symmetrically arranged third suspension centre of crossbeam length, the 4th group of suspension centre including two with hanging crossbeam length Four-point lifting, the 5th group of suspension centre include two to hang symmetrically arranged 5th suspension centre of crossbeam length, the 6th group of suspension centre includes Two to hang symmetrically arranged 6th suspension centre of crossbeam length, wherein hangs the length of the crossbeam width between crane's major girder 1.26~1.28 times, first group of suspension centre and second group of suspension centre spacing are 0.336~0.353 times for hanging crossbeam length, second Group suspension centre and third group suspension centre distance are 0.179~0.197 times of hanging crossbeam length, between third group suspension centre and the 4th group of suspension centre Away from 0.0053~0.0795 times for hanging crossbeam length, the 4th group of suspension centre and the 5th group of suspension centre spacing are hanging crossbeam length 0.289~0.307 times, the 5th group of suspension centre and the 6th group of suspension centre spacing are 0.043~0.0606 times for hanging crossbeam length, first The spacing of the end of the hanging crossbeam of group suspension centre and close first group of suspension centre is 0.0103~0.0274 times for hanging crossbeam length, Between second group of suspension centre and third group suspension centre, crossbeam length-wise axis pair is hung between third group suspension centre and the 4th group of suspension centre relatively Title is all provided with there are two sling point;
S3, between the bridge pier of tail portion two from both ends to centre lift multiple groups segment block, the lifting of every group of segment block includes left side The lifting of segment block and the lifting of right side segment block, wherein the lifting of left side segment block, comprising the following steps:
Hanging crossbeam is mounted on the block of left side segment by step 1 along its length, and will be left using the suspender at hoisting overhead travelling crane center Side segment block is hung between crane's major girder with width direction, is hung left side segment block with the suspender for being located at hoisting overhead travelling crane center It rises, and left side segment block is transferred to girder;
Step 2, suspender drive left side segment block to be moved to the left, after be rotated by 90 ° so that left side segment block length direction and Bridge Erector Width of main beam direction is consistent;
Step 3, the mobile hanging beam trolley being located in overarm arm at left and right sides of suspender, and make in the overarm arm of left side close to suspender The suspension hook of one group of hanging beam trolley catch on two the second suspension centres of second group of suspension centre respectively, close to the one of suspender in the overarm arm of right side The suspension hook of group hanging beam trolley catches on two the 5th suspension centres of the 5th group of suspension centre respectively, unclamps suspender afterwards, suspender moves right to original Position;
Step 4, hanging beam trolley drive left side segment block to be moved to the left, so that one group of hanging beam in the overarm arm of left side far from suspender is small The suspension hook of vehicle catches on two the first suspension centres of first group of suspension centre respectively, one group of hanging beam trolley of close suspender in the overarm arm of left side Suspension hook pine hook, and move right to two third suspension centres surfaces of third group suspension centre so that its suspension hook catches on third respectively and hangs Point close to the suspension hook pine hook of one group of hanging beam trolley of suspender in the overarm arm of right side, and moves right to two of the 6th group of suspension centre So that its suspension hook catches on the 6th suspension centre respectively right above 6th suspension centre, one group of hanging beam trolley of close suspender in the overarm arm of left side Suspension hook pine hook;
Step 5 is moved to the left left side segment block, and makes the suspension hook difference in the overarm arm of left side close to one group of hanging beam trolley of suspender Two four-point liftings of the 4th group of suspension centre are caught on, one group of hanging beam trolley in the overarm arm of right side close to suspender is then unclamped;
Step 6 is moved to the left left side segment block, is located at left side segment block on the left of crane's major girder immediately below hanging reinforcing bar, and So that hanging reinforcing bar is caught on sling point, unclamps hanging beam trolley lifting hook and complete left side segment block lifting;
The hanging of right side segment block, comprising the following steps:
Step a, hoisting overhead travelling crane is moved along bridge formation direction, repeats step 1;
Step b, suspender drives right side segment block to move right, and is rotated by 90 °, so that left side is saved in right side segment block and step 2 Section block is in mirror symmetry;
Step c, mobile one group of hanging beam trolley being located in overarm arm at left and right sides of suspender, and make close in the overarm arm of left side The suspension hook of one group of hanging beam trolley of suspender catches on two the 5th suspension centres of the 5th group of suspension centre, close suspender in the overarm arm of right side respectively The suspension hook of one group of hanging beam trolley catch on two the second suspension centres of second group of suspension centre respectively, and unclamp suspender, suspender moves right To original position;
Step d, hanging beam trolley drives right side segment block to move right, so that one group of hanging beam in the overarm arm of right side far from suspender is small The suspension hook of vehicle catches on two the first suspension centres of first group of suspension centre and unclamps one group of hanging beam trolley in the overarm arm of right side close to suspender;
Step e, it moves one group of hanging beam trolley of close suspender in the overarm arm of right side and its suspension hook is made to catch on third group suspension centre respectively Two third suspension centres, then move in the overarm arm of left side close to one group of hanging beam trolley of suspender and its suspension hook made to catch on the respectively Then two the 6th suspension centres of six groups of suspension centres unclamp the hanging beam trolley of two third suspension centres of third group suspension centre;
Step f, hanging beam trolley drives right side segment block to move right, and makes small close to one group of hanging beam of suspender in the overarm arm of right side The suspension hook of vehicle catches on two third suspension centres of third group suspension centre, and the hanging beam for then unclamping two the 6th suspension centres of the 6th group of suspension centre is small Vehicle suspension hook;
Step g, hanging beam trolley drives right side segment block to move right, and moves hoisting overhead travelling crane along bridge formation opposite direction, makes right side Segment block and the left side segment block lifted are located in a straight line and are located at right side segment block on the right side of crane's major girder and hang Immediately below reinforcing bar, and hanging reinforcing bar is made to catch on sling point, unclamps hanging beam trolley lifting hook and complete right side segment block lifting.
2. double width bridge as described in claim 1 tail portion feeding beam hanging method, which is characterized in that in hanging arbitrary neighborhood two in S3 When group segment block, wherein one group of left side segment block, right side segment block using suspender by left side segment block, right side segment block transfer to Below girder at 1.4~1.5m, segment block, right side segment block are saved left side segment block, right side using suspender on the left of another set Section block is transferred to 5.2~5.3m below girder.
3. double width bridge as described in claim 1 tail portion feeding beam hanging method, which is characterized in that the length of hanging crossbeam is in S2 1.27 times of width between crane's major girder, first group of suspension centre and second group of suspension centre spacing are 0.344 times for hanging crossbeam length, Second group of suspension centre and third group suspension centre distance are 0.196 times of hanging crossbeam length, third group suspension centre and the 4th group of suspension centre spacing For 0.07094 times for hanging crossbeam length, the 4th group of suspension centre and the 5th group of suspension centre spacing are 0.298 times for hanging crossbeam length, 5th group of suspension centre and the 6th group of suspension centre spacing are 0.0521 times for hanging crossbeam length, first group of suspension centre and close first group of suspension centre The spacing of end of hanging crossbeam be to hang 0.0188 times of crossbeam length.
4. double width bridge as claimed in claim 2 tail portion feeding beam hanging method, which is characterized in that the segment block at lifting both ends When, hang two groups of segment blocks of arbitrary neighborhood when, hang next group left side segment block when step 2 in further include that mobile hoisting overhead travelling crane makes The sling point for the left side segment block for having lifted completion close to previous group on next group of left side segment hanging crossbeam has been hung with previous group The left side segment block end face horizontal distance installed is 200mm.
5. double width bridge as described in claim 1 tail portion feeding beam hanging method, which is characterized in that second group of suspension centre is hung with third group Sling point of any one in two sling points between corresponding third group suspension centre and the 4th group of suspension centre is wide along segment block between point Spend the axisymmetrical setting in direction.
6. double width bridge as described in claim 1 tail portion feeding beam hanging method, which is characterized in that the first suspension centre, the second suspension centre, Three suspension centres, four-point lifting, the 5th suspension centre, the 6th suspension centre circle center line connecting are overlapped with hanging crossbeam length-wise axis.
7. double width bridge as described in claim 1 tail portion feeding beam hanging method, which is characterized in that hanging crossbeam length is segment block 1~1.01 times of length hangs the axis and section of crossbeam length direction when hanging crossbeam is mounted on along its length on the block of segment The axis in section block length direction is overlapped.
CN201710910642.9A 2017-09-29 2017-09-29 Double width bridge tail portion feeding beam hanging method Active CN107653783B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710910642.9A CN107653783B (en) 2017-09-29 2017-09-29 Double width bridge tail portion feeding beam hanging method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710910642.9A CN107653783B (en) 2017-09-29 2017-09-29 Double width bridge tail portion feeding beam hanging method

Publications (2)

Publication Number Publication Date
CN107653783A CN107653783A (en) 2018-02-02
CN107653783B true CN107653783B (en) 2018-12-11

Family

ID=61117344

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710910642.9A Active CN107653783B (en) 2017-09-29 2017-09-29 Double width bridge tail portion feeding beam hanging method

Country Status (1)

Country Link
CN (1) CN107653783B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797352B (en) * 2018-06-08 2020-02-18 王勇 Bridge building laying device
CN108797379B (en) * 2018-07-03 2023-05-26 中交第二航务工程局有限公司 Synchronous construction method for variable-spacing double-frame bridge by adopting segment assembly bridge girder erection machine

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101260650B (en) * 2008-04-21 2010-09-15 中铁二局股份有限公司 50m/1430t double width integral box girder construction process
JP5477898B2 (en) * 2009-10-28 2014-04-23 戸田建設株式会社 Construction equipment and construction method for foundation work of directly elevated viaduct
US8671490B1 (en) * 2013-03-06 2014-03-18 Mark Carney Bridge span replacement system
CN105862598A (en) * 2016-04-14 2016-08-17 中铁八局集团第二工程有限公司 Guide beam non-moving lifting type construction method for tunnel-through operation of 24-meter first span of bridge erecting machine
CN107140543A (en) * 2017-06-12 2017-09-08 无锡石油化工起重机有限公司 The comprehensive plating gantry of electroplating assembly line special mobile formula

Also Published As

Publication number Publication date
CN107653783A (en) 2018-02-02

Similar Documents

Publication Publication Date Title
CN107445065B (en) Hanging device
JP6701362B2 (en) STS Multi Trolley Portal Gantry Container Crane
CN110540134B (en) Grabbing hand, multi-pipe-piece crane comprising grabbing hand and pipe piece dispatching method
CN107653783B (en) Double width bridge tail portion feeding beam hanging method
CN107687132B (en) The method that equidistant double width bridge uses Segmental assembling bridge-erecting machine synchronous construction
CN110258352A (en) The steel reinforced concrete combined bridge construction method that two bridgings are done
CN101967823A (en) Tubular pile upper mould and hoisting system thereof
CN209455933U (en) A kind of superimposed sheet lifting appliance for hoisting
CN102852095A (en) Prefabricated bridge abutment multifunctional lifting system and construction procedure thereof
JPH1181244A (en) Bridge erecting device
CN108408667A (en) Broken line type girder truss rod piece Quick overturning device and its method for turning
CN209353734U (en) For installing the double-track device of curtain wall
CN105502145A (en) Lifting appliance and lifting frame of PK prestressed concrete composite slab
JP2017078311A (en) Heavy load installation device
CN207484304U (en) Can double width synchronous construction Segmental assembling bridge-erecting machine
CN205555856U (en) PK prestressed concrete superimposed sheet hoist and hoist and mount frame
CN207078901U (en) Gravity motion hanging beam
CN107140528B (en) Boom hoisting
CN203159036U (en) Line-shaped lifting appliance
CN207030751U (en) Boom hoisting
CN206513058U (en) Both a kind of dismounting device of wired hangar tunnel construction suspention bow member girder steel
CN206538694U (en) A kind of band carries the quick deck unit erection gantry walked with lifting
CN110329902A (en) A kind of with uniformly distributed function grab sleeper suspender more
CN217921004U (en) Quick hoist and mount system of superimposed sheet
CN211283414U (en) Combined hanger for steel rail

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant