CN107665368A - A kind of grid equipment stoppage in transit lean managing and control system - Google Patents
A kind of grid equipment stoppage in transit lean managing and control system Download PDFInfo
- Publication number
- CN107665368A CN107665368A CN201710739937.4A CN201710739937A CN107665368A CN 107665368 A CN107665368 A CN 107665368A CN 201710739937 A CN201710739937 A CN 201710739937A CN 107665368 A CN107665368 A CN 107665368A
- Authority
- CN
- China
- Prior art keywords
- data
- transit
- lean
- managing
- control system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000013500 data storage Methods 0.000 claims abstract description 26
- 238000007726 management method Methods 0.000 claims abstract description 23
- 238000012423 maintenance Methods 0.000 claims abstract description 8
- 238000009826 distribution Methods 0.000 claims abstract description 5
- 238000005516 engineering process Methods 0.000 claims description 24
- 238000000034 method Methods 0.000 claims description 11
- 238000013506 data mapping Methods 0.000 claims description 5
- 239000000463 material Substances 0.000 claims description 5
- 238000002360 preparation method Methods 0.000 claims description 5
- 238000003860 storage Methods 0.000 claims description 4
- 238000004458 analytical method Methods 0.000 claims description 3
- 230000005540 biological transmission Effects 0.000 claims description 3
- 230000005611 electricity Effects 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 claims description 3
- 238000012545 processing Methods 0.000 claims description 3
- 238000012546 transfer Methods 0.000 claims description 2
- 238000013480 data collection Methods 0.000 claims 1
- 238000011156 evaluation Methods 0.000 claims 1
- 230000015556 catabolic process Effects 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000013499 data model Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 238000005201 scrubbing Methods 0.000 description 1
- 238000007619 statistical method Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Economics (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The present invention relates to a kind of grid equipment stoppage in transit lean managing and control system, including data collecting system, data-storage system, Data application system, it is characterised in that:The system obtains initial data by metadata acquisition tool from information system for power enterprise, and it is stored in data-storage system, Data application system reads the data in data-storage system, passes through polynary (containing scheduled overhaul, breakdown repair, temporary interruption, fault outage etc.) Row control, equipment stoppage in transit Whole Course Management and performance appraisal that to be stopped transport because of the accurate distribution apparatus interruption maintenance plan of index storehouse, equipment of Data application system.
Description
Technical field
The invention belongs to power network management and control technical field, and in particular to a kind of grid equipment stoppage in transit lean managing and control system.
Background technology
Maintenance lean management is holding for each material time node of equipment interruption maintenance with outage information issue index
The performance assessment criteria that market condition and outage information are issued situation and formulated, its objective is to strive carrying out each material time section of interruption maintenance
Point zero time difference, and ensure outage information issue it is smooth with process of feedback, reduce customer complaint, lifting generation lean management and
Good service of marketing is horizontal.Managing and control system existence information isolated island of the prior art, the inadequate specification of Row control, service work essence
The shortcomings of benefitization is insufficient, a kind of efficient grid equipment stoppage in transit lean managing and control system is developed, to solve the above problems.
The content of the invention
The invention aims to overcome the existing operating deficiency of grid equipment stoppage in transit managing and control system, there is provided a kind of
The management and control means of equipment stoppage in transit lean can be improved.
The technical scheme is that:
A kind of grid equipment stoppage in transit lean managing and control system, including data collecting system, data-storage system, data application system
System, it is characterised in that:The system obtains initial data by metadata acquisition tool from information system for power enterprise, and is stored in
Data-storage system, Data application system read the data in data-storage system, and polynary by Data application system will be because
Index storehouse accurately regulates and controls power failure plan issue, stoppage in transit plan management and control, the management and control of stoppage in transit overall process and performance appraisal.
Above-described data-storage system can preserve the applied analysis result of Data application system, and can transfer makes at any time
With.
Above-described managing and control system also includes data-reduction system, and data-reduction system can read data-storage system
In initial data and carry out arrangement processing, reduced data is stored by data-storage system again.
Above-described data-reduction system, provide standard for grid equipment stoppage in transit lean managing and control system and accurately may be used
With data, data preparation includes improving critical data, data two submodules of check.
Above-described data collecting system includes at least data acquisition of dispatching management information system, electric power management system
Data acquisition, the data acquisition of Electric Power Marketing System, the data acquisition of EMS, production link system, electricity consumption
At least one function in acquisition system and electric energy metering system.
Above-described data collecting system is using " DOM+Windows API " technologies, realize part of data acquisition
Institute is functional, realizes identification and acquisition based on IE browser target web critical data using DOM technologies, uses simultaneously
Windows API technologies, analog manual operation is carried out, realize the shutoff operation of Windows pop-up windows, it is final to realize based on clear
Look at the automation collection of device web data.
Above-described data-storage system uses " ETL+database " technology, realizes that the institute of data storage section is active
Can, wherein, the data cleansing to initial data is realized using ETL technologies, data mapping relations is established, finally gives and meet the requirements
Normal data.Maintenance data storehouse technology simultaneously, realizes and unified storage management is carried out to normal data.
Above-described Data application system is after the initial data collected is arranged into standardization, to be predefined according to user
Rule, miscellaneous service application is carried out by automatic or manual mode, so as to complete the work that user specifies, obtained corresponding
Achievement.
The institute of above-described Data application system is functional to be sent out around the management of overhaul of the equipments lean and outage information
Cloth index is deployed, mainly for " have a power failure in week plan accuracy ", " outage information issues promptness and accuracy ", " distribution and visitor
Family equipment account integrality and correctness ", " stopping power transmission promptness and accuracy in scene " and " material time node accuracy " five
Individual aspect Develop Data application, its specific application mode include:Data query, statistical forms, historical trend displaying and
Data compare.
Above-described Data application system uses " data modeling technology+benchmark method ", realizes data application
Partial institute is functional, wherein, realize the abstractdesription to target service using data modeling technology.Use benchmark simultaneously
Method realizes lean Standardization Construction, realizes key index storehouse.
The beneficial effect of the grid equipment stoppage in transit lean managing and control system of the present invention is to break information island, is realized different
The data acquisition of system;Specification stoppage in transit Row control, establishes unified enterprise data model;Lean management is overhauled, according to true
Real data carries out statistical analysis, completes management and control and assessment mode.
Brief description of the drawings
Fig. 1 is that present system respectively sets up cooperation relation;
Fig. 2 is each component cooperation relation of present system;
Fig. 3 is data acquisition principle parameters information of the present invention;
Fig. 4 is data storage principle parameters information of the present invention;
Fig. 5 is data application principle parameters information of the present invention;
Fig. 6 is data acquisition function structure chart of the present invention;
Fig. 7 is data preparation functional structure chart of the present invention;
Fig. 8 is data application functional structure chart of the present invention.
Embodiment
As shown in figure 1, a kind of grid equipment stoppage in transit lean managing and control system, including data collecting system, data storage system
System, Data application system, the system obtains initial data by metadata acquisition tool from information system for power enterprise, and stores
In data-storage system, Data application system reads the data in data-storage system, and polynary by Data application system will
Because index storehouse accurately regulates and controls power failure plan issue, stoppage in transit plan management and control, the management and control of stoppage in transit overall process and performance appraisal.
As shown in Fig. 2 above-described data-storage system can preserve the applied analysis result of Data application system, at any time
Use can be transferred.
As shown in figure 1, above-described managing and control system also includes data-reduction system, data-reduction system can read number
According to the initial data in storage system and arrangement processing is carried out, reduced data is stored by data-storage system again.
As shown in fig. 7, above-described data-reduction system, mark is provided for grid equipment stoppage in transit lean managing and control system
Accurate accurate data available, data preparation include improving critical data, data two submodules of check.
As shown in fig. 6, above-described data collecting system includes at least data acquisition of OMS, PMS systems
Data acquisition, SG186 data acquisition, the data acquisition of Open3000 systems, production link system, electricity consumption acquisition system
With function at least one in TMR systems.
Data collecting system, which uses, " DOM+Windows API " technologies, to be realized that the institute of part of data acquisition is functional, makes
Identification and acquisition based on IE browser target web critical data are realized with DOM technologies, while uses Windows API skills
Art, analog manual operation is carried out, realize the shutoff operation of Windows pop-up windows, final realize is based on browsing device net page data
Automation collection.
Data-storage system uses " ETL+database " technology, realizes that the institute of data storage section is functional, wherein, make
The data cleansing to initial data is realized with ETL technologies, data mapping relations is established, finally gives satisfactory criterion numeral
According to.Maintenance data storehouse technology simultaneously, realizes and unified storage management is carried out to normal data.
Data application system is after the initial data collected is arranged into standardization, according to the predefined rule of user, is led to
Cross automatic or manual mode and carry out miscellaneous service application, so as to complete the work that user specifies, obtain corresponding achievement.
As shown in figure 8, above-described Data application system institute it is functional around the management of overhaul of the equipments lean with
Outage information issue index expansion, mainly for " week have a power failure plan accuracy ", " outage information issues promptness and accuracy ",
" distribution and customer equipment account integrality and correctness ", " stopping power transmission promptness and accuracy in scene " and " material time node
Five aspect Develop Data applications of accuracy ", its specific application mode include:Data query, statistical forms, history become
Gesture is shown and data compare.
Above-described Data application system uses " data modeling technology+benchmark method ", realizes data application
Partial institute is functional, wherein, realize the abstractdesription to target service using data modeling technology.Use benchmark simultaneously
Method realizes lean Standardization Construction, realizes key index storehouse.
As shown in figure 3, data acquisition principle parameters information Step includes:
(1)The target web specified by browser access, concrete operations are input target web addresses;
(2)The critical data web page element of target web is identified according to the characteristic value of key index storehouse;Concrete operations are input mesh
Web user interface and target to be collected are marked, exports the index value set of target to be collected;
(3)Web page access flow according to having predefined jumps to next target web;Concrete operations are input access orders
And rule, output target web user section;
As shown in figure 4, data storage principle parameters information Step includes:
(4)Initial data stores, and concrete operations are the data acquisition systems that input collects, and output database initial data stores;
(5)By data scrubbing rule, data format is realized, concrete operations are 2 forms of 1 original data set of input and input
Change regular, the data acquisition system after output format;
(6)Each system data mapping ruler is compareed, screens invalid data, realizes that data map, concrete operations are that input 1 formats
2 data mapping rulers of data acquisition system and input afterwards, outputting standard data acquisition system;
(7)Normal data stores, and concrete operations are input standardized data set, and output database normal data stores.
As shown in figure 5, data application principle parameters information Step includes:
(1)Application target is determined, studies various knowledge models, concrete operations are 1 each traffic criteria workflow of input and input 2
Each process step key index, export 1 stoppage in transit planning model, 3 stoppage in transit overall process pipes of 2 outage information Issuance models of output and output
Control model;
(2)For knowledge model, various exclusive algorithms are designed, concrete operations export 1 power failure range to input various knowledge models
Analytical algorithm, output 2 repeat stoppage in transit warning algorithm, export 3 performance appraisal algorithms;
(3)Explore mark post and build key index storehouse, concrete operations are 1 various knowledge models of input, input the exclusive algorithm of 2 brothers, defeated
Go out it is polynary will be because of key index storehouse;Carry out various data applications, concrete operations are 1 key index storehouse of input, and 2 each functions of input should
With output lean management and control form.
Claims (10)
1. a kind of grid equipment stoppage in transit lean managing and control system, including data collecting system, data-storage system, data application system
System, it is characterised in that:The system obtains initial data by metadata acquisition tool from information system for power enterprise, and is stored in
Data-storage system, Data application system read the data in data-storage system, and polynary by Data application system will be because
Index storehouse accurately regulates and controls the plan of distribution apparatus interruption maintenance, equipment stoppage in transit Row control, equipment stoppage in transit Whole Course Management and performance
Evaluation.
2. grid equipment stoppage in transit lean managing and control system as claimed in claim 1, it is characterised in that:Described data storage system
System can preserve the applied analysis result of Data application system, can transfer use at any time.
3. grid equipment stoppage in transit lean managing and control system as claimed in claim 1, it is characterised in that:Described managing and control system is also
Including data-reduction system, data-reduction system can read the initial data in data-storage system and carry out arrangement processing,
Reduced data is stored by data-storage system again.
4. grid equipment stoppage in transit lean managing and control system as claimed in claim 1, it is characterised in that:Described data preparation system
System, the accurate data available of standard is provided for grid equipment stoppage in transit lean managing and control system, data preparation includes improving key
Data, data check two submodules.
5. the grid equipment stoppage in transit lean managing and control system as described in foregoing any one claim, it is characterised in that:It is described
Data collecting system in data source includes at least data acquisition of dispatching management information system, the data of electric power management system are adopted
Collection, the data acquisition of electric power SG186 marketing systems, the data acquisition of EMS, production link system, electricity consumption are adopted
At least one function in collecting system, electric energy metering system and other application system.
6. the grid equipment stoppage in transit lean managing and control system as described in foregoing any one claim, it is characterised in that:It is described
Data collecting system using " DOM+Windows API " technologies, realize part of data acquisition institute it is functional, use DOM
Technology realizes identification and acquisition based on IE browser target web critical data, while uses Windows API technologies, carries out
Analog manual operation, the shutoff operation of Windows pop-up windows is realized, it is final to realize the automation based on browsing device net page data
Collection.
7. the grid equipment stoppage in transit lean managing and control system as described in foregoing any one claim, it is characterised in that:It is described
Data-storage system use " ETL+database " technology, realize data storage section institute it is functional, wherein, use ETL
Technology realizes the data cleansing to initial data, establishes data mapping relations, finally gives satisfactory normal data, simultaneously
Maintenance data storehouse technology, realizes and unified storage management is carried out to normal data.
8. the grid equipment stoppage in transit lean managing and control system as described in foregoing any one claim, it is characterised in that:It is described
Data application system be by the initial data collected arrange standardization after, according to the predefined rule of user, by automatic
Or artificial mode carries out miscellaneous service application, so as to complete the work that user specifies, corresponding achievement is obtained.
9. the grid equipment stoppage in transit lean managing and control system as described in foregoing any one claim, it is characterised in that:It is described
Data application system institute it is functional around the issue index expansion of the management of overhaul of the equipments lean and outage information, main pin
To " week have a power failure plan accuracy ", " outage information issues promptness and accuracy ", " distribution and customer equipment account integrality and
Correctness ", " stopping power transmission promptness and accuracy in scene " and " material time node accuracy " five aspect Develop Data applications,
Its specific application mode includes:Data query, statistical forms, historical trend displaying and data compare.
10. as described in foregoing any one claim such as grid equipment stoppage in transit lean managing and control system, it is characterised in that:Institute
The Data application system stated uses " data modeling technology+benchmark method ", realizes that the institute of data application part is functional,
Wherein, the abstractdesription to target service is realized using data modeling technology, while lean mark is realized with benchmark method
Standardization is built, and realizes key index storehouse.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710739937.4A CN107665368A (en) | 2017-09-29 | 2017-09-29 | A kind of grid equipment stoppage in transit lean managing and control system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710739937.4A CN107665368A (en) | 2017-09-29 | 2017-09-29 | A kind of grid equipment stoppage in transit lean managing and control system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107665368A true CN107665368A (en) | 2018-02-06 |
Family
ID=61097336
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710739937.4A Pending CN107665368A (en) | 2017-09-29 | 2017-09-29 | A kind of grid equipment stoppage in transit lean managing and control system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107665368A (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102999815A (en) * | 2012-12-04 | 2013-03-27 | 北京中恒博瑞数字电力科技有限公司 | Multi-dimensional risk assessment and control method for power system safety and model |
CN103646329A (en) * | 2013-11-04 | 2014-03-19 | 国家电网公司 | Interregional and interprovincial electricity trading operational control method |
CN105116291A (en) * | 2015-09-07 | 2015-12-02 | 国电南瑞科技股份有限公司 | Power grid operating steady state monitoring information-based fault diagnosis system and method |
US9258131B2 (en) * | 2010-01-25 | 2016-02-09 | Samsung Electronics Co., Ltd. | Method and apparatus for controlling operations of devices based on information regarding power consumption of the devices |
-
2017
- 2017-09-29 CN CN201710739937.4A patent/CN107665368A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9258131B2 (en) * | 2010-01-25 | 2016-02-09 | Samsung Electronics Co., Ltd. | Method and apparatus for controlling operations of devices based on information regarding power consumption of the devices |
CN102999815A (en) * | 2012-12-04 | 2013-03-27 | 北京中恒博瑞数字电力科技有限公司 | Multi-dimensional risk assessment and control method for power system safety and model |
CN103646329A (en) * | 2013-11-04 | 2014-03-19 | 国家电网公司 | Interregional and interprovincial electricity trading operational control method |
CN105116291A (en) * | 2015-09-07 | 2015-12-02 | 国电南瑞科技股份有限公司 | Power grid operating steady state monitoring information-based fault diagnosis system and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2023115842A1 (en) | Data-driven offline and online integrated simulation system and method for power distribution network | |
CN111162608B (en) | Distribution transformer area topology identification and verification method based on correlation analysis | |
CN102545213B (en) | System and method for managing line loss of power grid in real time | |
CN102411764B (en) | The data management system of grid equipment and management method | |
CN103578039B (en) | A kind of power networks risk prewarning analysis system | |
CN103489062B (en) | Scheduled outage method and device based on CIM | |
CN102063563B (en) | Network-province-local integrative bus load predicting method | |
CN106570784A (en) | Integrated model for voltage monitoring | |
CN105574593B (en) | Track state static detection and control system and method based on cloud computing and big data | |
CN107402976A (en) | Power grid multi-source data fusion method and system based on multi-element heterogeneous model | |
CN104638764A (en) | Intelligent state diagnosis and overhauling system for power distribution network equipment | |
CN107767067A (en) | Power distribution network management and running evaluation index system construction method based on big data | |
CN103617561A (en) | System and method for evaluating state of secondary equipment of power grid intelligent substation | |
CN107835107A (en) | A kind of metering display systems based on power network metering topological sum WebGis | |
CN112132443A (en) | Reliability distribution network power supply management and control system | |
CN105654393A (en) | Energy efficiency management service system of power distribution network area | |
CN206294207U (en) | Grid power blackout proposed figures for the plan Optimization Platform based on " big operation " multi-constraint condition | |
CN106374458A (en) | Intelligent analysis method for identifying unreasonable power-failure management | |
CN104156787A (en) | Power partition load prediction method based on different load characteristics | |
CN103020870A (en) | State evaluation modeling method and system for SF6 circuit breaker | |
CN104123588A (en) | Comprehensive evaluation system and method of smart distribution grid | |
CN110311369A (en) | A kind of stabilization of power grids section short term curve prediction method and system | |
CN109840646A (en) | Voltage monitoring method based on big data processing | |
CN103647279A (en) | Plant wiring information based anticipatory fault set generation method | |
CN103545805A (en) | Modeling-based railway power supply arm monitoring method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180206 |