CN107658906A - A kind of system and method for intelligent control transformer - Google Patents

A kind of system and method for intelligent control transformer Download PDF

Info

Publication number
CN107658906A
CN107658906A CN201710790988.XA CN201710790988A CN107658906A CN 107658906 A CN107658906 A CN 107658906A CN 201710790988 A CN201710790988 A CN 201710790988A CN 107658906 A CN107658906 A CN 107658906A
Authority
CN
China
Prior art keywords
transformer
load
data
module
control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710790988.XA
Other languages
Chinese (zh)
Inventor
陈建民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Yineng Technology Co Ltd
Original Assignee
Zhuhai Yineng Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Yineng Technology Co Ltd filed Critical Zhuhai Yineng Technology Co Ltd
Priority to CN201710790988.XA priority Critical patent/CN107658906A/en
Publication of CN107658906A publication Critical patent/CN107658906A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Abstract

Technical scheme includes a kind of system and method for intelligent control transformer, for realizing:Obtain the necessary data of transformer automatically when system starts;Transformer necessary data is received and carries out classification storage;Necessary data when obtaining the transformer station high-voltage side bus of classification storage carries out data analysis, obtains analysis result and is transmitted;Receive analysis result and obtain default operating parameter and then perform to automatically control accordingly, and using warning device carry out corresponding to alarm.Beneficial effects of the present invention are:The system data are more accurate more timely than artificial regulatory, and data storage database forever retains;Regulation and control ratio is artificial more precisely, convenient, and supports automatic mode and the manually more convenient artificial regulatory of pattern;The data analysis for providing different interval make it that analyze data is more flexible.

Description

A kind of system and method for intelligent control transformer
Technical field
The present invention relates to a kind of system and method for intelligent control transformer, belong to computer Electric control field.
Background technology
Carry out transformer load control in industry by way of artificial regulatory at present, it is cumbersome and time consuming, it is important to Timing not enough.Currently without special messenger's regulation and control are arranged, some enterprises are afraid of, because producing fine, often to use at the beginning of design for many enterprises Heavy load transformer is powered to skinny device, transformer permanent load is not reached 50%, is caused very big idling and is carried waste. Also some enterprises, because design is improper, many equipment are subsequently added, cause transformer load inadequate, enterprise is born a lot Overburden is imposed a fine.These are all due to the good system of neither one to monitor, caused energy waste.
The content of the invention
In view of the shortcomings of the prior art, technical scheme provides system and the side of a kind of intelligent control transformer Method, for solving the deficiencies in the prior art.
Technical scheme includes a kind of system of intelligent control transformer, it is characterised in that the system includes:Number According to acquisition module, for obtaining the necessary data of transformer automatically when system starts;Data memory module, for the number The transformer necessary data gathered according to acquisition module receives and carries out classification storage;Data analysis module, for obtaining the number According to memory module classification storage transformer station high-voltage side bus when necessary data, and then carry out data analysis, obtain analysis result and go forward side by side Row is sent;Control module, for receiving the analysis result of the data analysis module transmission and obtaining default operating parameter then Execution automatically controls accordingly, and carries out corresponding alarm using warning device.
According to the system of described intelligent control transformer, wherein data acquisition module also includes:For starting in system When obtain transformer configuration data, and obtain transformer station high-voltage side bus when service data, wherein the interval of each gathered data Can be with self-defined setting.
According to the system of described intelligent control transformer, wherein data analysis module also includes:Monitoring in real time is outside to be It is no to have control access manually, send the controlled instruction of pause institute to the control module if access manually is detected.
According to the system of described intelligent control transformer, wherein data analysis module is used to perform following steps:In real time Whether monitoring transformer current loads are above standard load value;If detecting, transformer load is less than mark load, sends normal knot Fruit and normally control to the control module, if detecting, transformer load is more than or equal to gauge load, sends reach immediately The result of standard value continues to judge whether transformer is more than load warning value to control module;If detect transformer load Less than warning load, the result less than early warning value is sent to the control module, if it is negative to detect that transformer load is more than warning Lotus, send and reach the result of warning value to the control module.
According to the system of described intelligent control transformer, wherein control module also includes:Timer is set to receiving The transformer load result for stating data analysis module transmission is recorded;Obtain solving if transformer load is normal outcome if receiving Except the alarm condition of warning device, and remove all transformer load states recorded of timer;If reception obtains transformation Device load then enables warning device more than or equal to the result of gauge load value and alarmed, and records last transformer load State is to meet or exceed standard value;Obtain persistently starting alarm if transformer load is less than the result of warning load value if receiving Device is alarmed, and removes all transformer load states recorded of timer.
According to the system of described intelligent control transformer, wherein control module is used to perform following steps:S61, if on One next state is load N-1 timing, judges whether load N-1 timer periods reach load N-1 delay times, if less than negative Lotus N-1 delay times, then the N timers that are delayed are continued timing, persistently alarmed using warning device, last state is arranged to load N-1 timing;S62, reaches load N-1 delay times, control module cut-out load N-1 corresponding lines, and load N timers start to count When, persistently alarmed using warning device, and it is load N timing to set last state, wherein N>=1.
According to the system of described intelligent control transformer, wherein control module also includes:A transformer is completed every time The corresponding early warning control of result data execution that state is sent according to data analysis module is returned again after setting.
Technical scheme also includes a kind of method of intelligent control transformer, and this method includes:Start in system Shi Zidong obtains the necessary data of transformer;Transformer necessary data is received and carries out classification storage;Obtain classification storage Necessary data during transformer station high-voltage side bus carries out data analysis, obtains analysis result and is transmitted;Receive analysis result and obtain Default operating parameter then performs to be automatically controlled accordingly, and carries out corresponding alarm using warning device.
Beneficial effects of the present invention are:The system data are more accurate more timely than artificial regulatory, and data storage database is permanent Retain;Regulation and control ratio is artificial more precisely, convenient, and supports automatic mode and the manually more convenient artificial regulatory of pattern;There is provided not Data analysis with interval make it that analyze data is more flexible.
Brief description of the drawings
Fig. 1 show the general structure block diagram according to embodiment of the present invention;
Fig. 2 show the flow chart according to embodiment of the present invention.
Embodiment
In order that the object, technical solutions and advantages of the present invention are clearer, below in conjunction with the accompanying drawings with specific embodiment pair The present invention is described in detail.The system and method for the intelligent control transformer of the present invention are applied to power domain, particularly suitable In the control of transformer.
Fig. 1 show the general structure block diagram according to embodiment of the present invention.Data acquisition module, for starting in system Shi Zidong obtains the necessary data of transformer;Data memory module, must for the transformer to the data collecting module collected Want data to receive and carry out classification storage;Data analysis module, for obtaining the transformation of the data memory module classification storage Necessary data when device is run, and then data analysis is carried out, obtain analysis result and be transmitted;Control module, for receiving Analysis result that the data analysis module is sent simultaneously obtains default operating parameter and then performed and automatically control accordingly, and makes The alarm corresponding to warning device is carried out.When system is opened, data acquisition module can be actively to number needed for transformer acquisition system According to the data that data memory module in real time can arrive data collecting module collected carry out classification storage, and data analysis module is to being The data of system storage carry out analysis judgement, and the result after analysis is sent to control module, and control module receives data point The result of judge module is analysed, performs corresponding operate.
Fig. 2 show the flow chart according to embodiment of the present invention.Shown in it is summarized as follows:
System starts, and data acquisition module is started working, and gathers the data of corresponding configuration parameter, collects friendship after data By a data to data analysis module, a data transfer to data memory module to carry out classification storage in addition, for subsequently looking into Ask and use.After data analysis module receives the data of data acquisition module, corresponding analyze is carried out.Step is as follows:
System meeting is it is first determined whether automatically control, if do not automatically controlled, system will not send any result to control Module, corresponding control module are also not carried out any operation;Automatically controlled if provided as system, analysis module can judge to adopt Collect whether transformer current loads are more than setting gauge load value;
If transformer load is less than gauge load, analysis module sends normal outcome control module, control module meeting Sound and light alarm is released, and removes all timers, last state is arranged to normal;If transformer load is more than or equal to mark Quasi- load value, analysis module is sent immediately to be reached standard value result and is given to control module, and control module is immediately performed sound and light alarm, Analysis module continues to judge whether transformer is more than load warning value;
If transformer load value is less than warning value, analysis module transmission is given to control mould less than the result of warning value Block, control module remove all timers, continue sound and light alarm, and last state is arranged to reach standard value.If transformer Load is more than or equal to warning value, and the result that analysis module transmission reaches warning value is given to control module;
Control module judges last state;
If last state is normal or reaches standard value, control module enables the timer of load 1, continues acousto-optic report Alert, last state is arranged to the timing of load 1;F) if, last state be the timing of load 1, control module judges that load 1 is counted When the device time whether reach the delay time of load 1, if less than the delay time of load 1, then 1 timer that is delayed continue timing, hold Continuous sound and light alarm, last state are arranged to the timing of load 1;If reaching the delay time of load 1, control module cut-out load 1 Circuit, the timer of load 2 start timing, continue sound and light alarm, and it is the timing of load 2 to set last state;
If last state is the timing of load 1, control module judges whether the timer periods of load 1 reach load 1 and prolong When the time, if less than the delay time of load 1, then 1 timer that is delayed continues timing, continues sound and light alarm, last state sets It is set to the timing of load 1;If reaching the delay time of load 1, the control module cut-out circuit of load 1, the timer of load 2 starts to count When, continue sound and light alarm, and it is the timing of load 2 to set last state;
If last state is the timing of load 2, control module judges whether the timer periods of load 2 reach load 2 and prolong When the time, if less than the delay time of load 2, then 2 timers that are delayed continue timing, continue sound and light alarm, last state sets It is set to the timing of load 2;If reaching the delay time of load 2, the control module cut-out circuit of load 2, the timer of load 3 starts to count When, continue sound and light alarm, and it is the timing of load 3 to set last state;
If last state is load N-1 timing, control module judges whether load N-1 timer periods reach load N-1 delay times, if less than load N-1 delay times, then the N timers that are delayed continue timing, continue sound and light alarm, last State is arranged to load N-1 timing;If reaching load N-1 delay times, control module cut-out load N-1 circuits, load N meters When device start timing, continue sound and light alarm, and it is load N timing to set last state.
The system needs to reacquire data acquisition module after the step of each execution identifies and sets state terminating Gathered data is simultaneously reanalysed and controlled.
It is described above, simply presently preferred embodiments of the present invention, the invention is not limited in above-mentioned embodiment, as long as It reaches the technique effect of the present invention with identical means, should all belong to protection scope of the present invention.In the protection model of the present invention Its technical scheme and/or embodiment can have a variety of modifications and variations in enclosing.

Claims (8)

1. a kind of system of intelligent control transformer, it is characterised in that the system includes:
Data acquisition module, for obtaining the necessary data of transformer automatically when system starts;
Data memory module, deposited for receiving the transformer necessary data of the data collecting module collected and carrying out classification Storage;
Data analysis module, necessary data during transformer station high-voltage side bus for obtaining the data memory module classification storage, enters And data analysis is carried out, obtain analysis result and be transmitted;
Control module, then performed for receiving the analysis result of the data analysis module transmission and obtaining default operating parameter Automatically control accordingly, and corresponding alarm is carried out using warning device.
2. the system of intelligent control transformer according to claim 1, it is characterised in that described data acquisition module is also Including:
For obtaining the configuration data of transformer, and service data during acquisition transformer station high-voltage side bus when system starts, wherein The interval of each gathered data can be with self-defined setting.
3. the system of intelligent control transformer according to claim 1, it is characterised in that described data analysis module is also Including:
Whether monitoring in real time is outside control access manually, and pause institute is sent to the control module if access manually is detected Controlled instruction.
4. the system of intelligent control transformer according to claim 1, it is characterised in that described data analysis module is used In execution following steps:
Whether monitoring transformer current loads are above standard load value in real time, if detecting, transformer load is less than gauge load Value, send normal outcome and normally control to the control module, if detecting, transformer load is more than or equal to gauge load, The result for reaching standard value is sent immediately to control module, and continues to judge whether transformer is more than load warning value;
If detecting, transformer load is less than warning load, the result less than early warning value is sent to the control module, if detection It is more than warning load to transformer load, sends and reach the result of warning value to the control module.
5. the system of intelligent control transformer according to claim 1, it is characterised in that described control module is also wrapped Include:
Timer is set to be recorded to receiving the transformer load result that the data analysis module is sent;
The alarm condition that warning device is released if transformer load is normal outcome is obtained if receiving, and removes timer and owns The transformer load state recorded;
Warning device is enabled if reception obtains result of the transformer load more than or equal to gauge load value to be alarmed, and is remembered Last transformer load state is carried to meet or exceed standard value;
Transformer load is obtained less than persistently startup warning device is alarmed if the result for guarding against load value if receiving, Yi Jiqing The transformer load state recorded except timer is all.
6. according to the system of any described intelligent control transformer of claim 1,4,5, it is characterised in that described control mould Block is used to perform following steps:
S61, if last state is load N-1 timing, when judging whether load N-1 timer periods reach load N-1 delays Between, if less than load N-1 delay times, then the N timers that are delayed are continued timing, persistently alarmed using warning device, last State is arranged to load N-1 timing;
S62, reaching load N-1 delay times, control module cut-out load N-1 corresponding lines, load N timers start timing, Persistently alarmed using warning device, and it is load N timing to set last state, wherein N>=1.
7. according to the system of any described intelligent control transformer of claim 6, it is characterised in that described control module is also Including:
The result data for completing to be sent according to time data analysis module again after a transformer state is set every time performs correspondence Early warning control.
A kind of 8. method of intelligent control transformer, it is characterised in that this method includes:
Obtain the necessary data of transformer automatically when system starts;
Transformer necessary data is received and carries out classification storage;
Necessary data when obtaining the transformer station high-voltage side bus of classification storage carries out data analysis, obtains analysis result and is transmitted;
Receive analysis result and obtain default operating parameter and then perform to automatically control accordingly, and carried out using warning device Corresponding alarm.
CN201710790988.XA 2017-09-05 2017-09-05 A kind of system and method for intelligent control transformer Pending CN107658906A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710790988.XA CN107658906A (en) 2017-09-05 2017-09-05 A kind of system and method for intelligent control transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710790988.XA CN107658906A (en) 2017-09-05 2017-09-05 A kind of system and method for intelligent control transformer

Publications (1)

Publication Number Publication Date
CN107658906A true CN107658906A (en) 2018-02-02

Family

ID=61129401

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710790988.XA Pending CN107658906A (en) 2017-09-05 2017-09-05 A kind of system and method for intelligent control transformer

Country Status (1)

Country Link
CN (1) CN107658906A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102957208A (en) * 2012-09-19 2013-03-06 北开电气集团有限公司 Intelligent monitoring device of power distribution transformer and control method thereof
CN203135574U (en) * 2012-10-24 2013-08-14 国网电力科学研究院武汉南瑞有限责任公司 Intelligent monitoring terminal of distribution transformer
CN103475090A (en) * 2013-08-20 2013-12-25 上海海能信息科技有限公司 Intelligent short-term transformer load prediction system and method
CN103702367A (en) * 2013-12-26 2014-04-02 大唐移动通信设备有限公司 Cell load balancing method and device
CN106026390A (en) * 2016-05-26 2016-10-12 国网河南省电力公司南阳供电公司 Distribution network transformer load monitoring system and use method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102957208A (en) * 2012-09-19 2013-03-06 北开电气集团有限公司 Intelligent monitoring device of power distribution transformer and control method thereof
CN203135574U (en) * 2012-10-24 2013-08-14 国网电力科学研究院武汉南瑞有限责任公司 Intelligent monitoring terminal of distribution transformer
CN103475090A (en) * 2013-08-20 2013-12-25 上海海能信息科技有限公司 Intelligent short-term transformer load prediction system and method
CN103702367A (en) * 2013-12-26 2014-04-02 大唐移动通信设备有限公司 Cell load balancing method and device
CN106026390A (en) * 2016-05-26 2016-10-12 国网河南省电力公司南阳供电公司 Distribution network transformer load monitoring system and use method thereof

Similar Documents

Publication Publication Date Title
CN102957208B (en) Intelligent monitoring device of power distribution transformer and control method thereof
CN106655522A (en) Master station system suitable for operation and maintenance management of secondary equipment of power grid
CN114819415B (en) Power equipment fault prediction system based on data analysis
CN110988559A (en) Online monitoring method for full life cycle of transformer substation direct current system based on Internet of things
CN104502753A (en) Networked on-line real-time analysis system for electric power fault recording device and application of system
CN108573761A (en) A kind of Nuclear Power Plant Equipment real-time performance monitoring method and system
CN207926521U (en) Diagnosing failure of photovoltaic array apparatus and system
CN117078113B (en) Outdoor battery production quality management system based on data analysis
CN115002166B (en) Intelligent battery monitoring and leasing management system and method based on Internet of things
CN103630799A (en) Fault early warning system and fault early warning method for distribution lines
CN109615817A (en) Monitoring system combines alarm method, device, electronic equipment and storage medium
CN104682565B (en) Automatic acquisition and monitoring system for power grid information
CN107658906A (en) A kind of system and method for intelligent control transformer
CN115128999A (en) Integrated distributed rural sewage treatment station intelligent control system
CN107064743A (en) Power distribution network transient state ripple failure tracking method and device based on cloud analysis with identification
CN110932881B (en) Equipment portrait method based on monitoring alarm signal
CN104730978A (en) Real-time data collection distributed type integration system based on big data
CN107482767A (en) A kind of distributed measure line loss and the apparatus and method for for monitoring power network
CN109470981B (en) Method and system for studying and judging faults of power protection and distribution network
CN109039278A (en) Junction box of photovoltaic module, monitoring method and system
CN213457248U (en) Fault alarm device for intelligent manufacturing
CN203813525U (en) Intelligent distribution network equipment state monitoring system
CN114218861A (en) Novel smart power grids battery is at line nuclear capacity monitoring system
CN116150195A (en) System and method for online monitoring safety low-carbon electricity consumption of users in multiple types of parks
CN206563886U (en) Recognize the system and electric equipment of knob-operated

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180202

RJ01 Rejection of invention patent application after publication