CN107630465A - Assembled circle underground space structure and its construction method - Google Patents
Assembled circle underground space structure and its construction method Download PDFInfo
- Publication number
- CN107630465A CN107630465A CN201711145758.4A CN201711145758A CN107630465A CN 107630465 A CN107630465 A CN 107630465A CN 201711145758 A CN201711145758 A CN 201711145758A CN 107630465 A CN107630465 A CN 107630465A
- Authority
- CN
- China
- Prior art keywords
- component
- concrete
- basil
- precast concrete
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 17
- 239000011178 precast concrete Substances 0.000 claims abstract description 55
- 241001529734 Ocimum Species 0.000 claims abstract description 51
- 235000010676 Ocimum basilicum Nutrition 0.000 claims abstract description 51
- 125000004122 cyclic group Chemical group 0.000 claims abstract description 4
- 239000004567 concrete Substances 0.000 claims description 73
- 239000002689 soil Substances 0.000 claims description 20
- 238000009412 basement excavation Methods 0.000 claims description 6
- 238000009827 uniform distribution Methods 0.000 claims description 6
- 229910000831 Steel Inorganic materials 0.000 claims description 5
- 239000010959 steel Substances 0.000 claims description 5
- 230000003014 reinforcing effect Effects 0.000 claims description 4
- 241000196324 Embryophyta Species 0.000 claims description 3
- 235000008331 Pinus X rigitaeda Nutrition 0.000 claims description 3
- 235000011613 Pinus brutia Nutrition 0.000 claims description 3
- 241000018646 Pinus brutia Species 0.000 claims description 3
- 238000005266 casting Methods 0.000 claims description 3
- 238000006073 displacement reaction Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 3
- 230000015271 coagulation Effects 0.000 claims description 2
- 238000005345 coagulation Methods 0.000 claims description 2
- 238000013019 agitation Methods 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 18
- 238000009435 building construction Methods 0.000 abstract description 2
- 230000008602 contraction Effects 0.000 abstract description 2
- 239000011435 rock Substances 0.000 description 7
- 230000005641 tunneling Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 230000004888 barrier function Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 239000011378 shotcrete Substances 0.000 description 1
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
The present invention relates to a kind of assembled circle underground space structure and its construction method, belong to technical field of building construction.Its prefabricated component is divided into precast concrete basil component and precast concrete retaining wall component;The precast concrete basil component and precast concrete retaining wall component are cyclic structure, the quantity of precast concrete basil component is one and be located at bottom, the quantity of precast concrete retaining wall component be one or more than one and vertically splice in the top of precast concrete basil component;The present invention can improve a rate of advance of the underground space;The process that the present invention removes slope retaining from;The present invention can reduce manual work, reduce Contraction in Site;The invention enables job site noise is small, pollution is small;The present invention realizes factorial praluction, convenient and swift.
Description
Technical field
The present invention relates to a kind of assembled circle underground space structure and its construction method, belongs to building construction technology neck
Domain.
Background technology
At present there is the problems such as to excavate hole speed slow, long in time limit in the common underground engineering of Building Trade in China.
1st, underground engineering construction method has cut and cover method, subsurface excavation method, immersed tunnelling method, push bench process, New Austrian Tunneling Method etc..2nd, tunnel and underground
During building engineering construction, corresponding space must be first excavated out, then builds lining cutting wherein.The selection of construction method, should be with ground
Matter, landform and environmental condition and buried depth are Main Basiss, wherein have decisive influence to construction method is embedding depth
Degree.Embedding shallower engineering, first foundation ditch or trench are dug from ground during construction, build and backfill again after lining cutting, here it is cut and cover method.
3rd, subsurface excavation method, i.e., ground is not excavated, is constructed by the way of digging a hole into the earth.Mining Method and shield method etc. belong to subsurface excavation method.4、
Immersed tunnelling method is the abbreviation of prefabricated tube section sinking method, is a kind of construction method in water-bed building tunnel.Turn into subaqueous tunnel
Main construction method.The tunnel built up in this way is referred to as immersed tube tunnel.5th, push bench process refers to that tunnel or underground piping are worn
More the various barriers such as railway, road, river or building when a kind of tunneling formula construction method for using.6th, New Austrian Tunneling Method is application
Rock mass mechanics is theoretical, using safeguard and using country rock self-bearing ability as basic point, use anchor pole and gunite concrete as main supporting
Means, supporting is timely carried out, control the deformation and relaxation of country rock, country rock is turned into the part of support system, and pass through
The method and principle that constructing tunnel and underground engineering design are constructed are instructed to the measurement of country rock and supporting, monitoring.
The content of the invention
It is an object of the invention to provide a kind of assembled circle underground space structure and its construction method, can effectively improve
A rate of advance, the working procedures such as slope retaining, reinforcing are eliminated, reduce cost, shorten the construction period.
The present invention to achieve these goals, adopts the following technical scheme that:
A kind of assembled circle underground space structure, its prefabricated component is divided into precast concrete basil component to be protected with precast concrete
Wall member;
The precast concrete basil component and precast concrete retaining wall component are cyclic structure, precast concrete basil component
Quantity is one and be located at bottom, the quantity of precast concrete retaining wall component be one or more than one and vertically splice pre-
The top of concrete basil component processed;
The precast concrete basil component passes through concrete rib by lateral arcs surface concrete plate I and inside arc surface concrete plate I
The connection of plate I forms an entirety, and circular hole I, lateral arcs surface concrete plate I and inner side cambered surface are uniform-distribution with concrete floor I
The bottom of concrete slab I is connected as a single entity, and forms sharp concrete basil part, and the bottom of concrete basil part is surrounded by angle steel shield
The top of set, lateral arcs surface concrete plate I and inside arc surface concrete plate I is provided with concave-convex type bayonet socket I, and both ends are again provided with bumps
Type bayonet socket I;
The precast concrete retaining wall component passes through concrete by lateral arcs surface concrete plate II and inside arc surface concrete plate II
The connection of floor II forms an entirety, is uniform-distribution with circular hole II on concrete floor II, lateral arcs surface concrete plate II and interior
The top and bottom of side cambered surface concrete slab II is provided with concave-convex type bayonet socket II, and both ends are again provided with concave-convex type bayonet socket II.
A kind of construction method of assembled circle underground space structure:
A, by soil excavation into a circular groove;
B, precast concrete basil component is lifted in place along circular groove, inserted in the trench, the He of lateral arcs surface concrete plate I
Inside arc surface concrete plate I contacts with soil;
C, precast concrete basil component is installed along circular groove, splicing in place, is assembled into the circle enclosed;
D, intracavitary installs structure reinforcing bars, and casting concrete in prefabricated components, the circular prefabricated components of assembling is unified into one
Individual entirety;
E, loosened the soil plant equipment with rotary digging, foundation soil is stirred along lateral arcs surface concrete plate I and inside arc surface concrete plate I
Dynamic, digging pine, and mud is filled in the gap between cambered surface concrete slab and the soil body, make precast concrete basil component because certainly
Weight, sink naturally;
F, stop loosening the soil to after specifying absolute altitude after the prefabricated basil component entire lowering of annular;
G. hoisting prefabricated concrete guard wall component, installation, splice at the top of precast concrete basil component, notice that the fissure of displacement is spelled
Connect, be assembled into the annular enclosed a prefabricated components;
H. c, d, e, f steps are repeated, until precast concrete basil component sinks down into final designed elevation, cylindrical underground
Space structure is formed.
The angle steel basil sheath, it is in order to encase the concrete basil, to protect concrete basil part will not be by the soil body
Or the rock failure mechanism of rock.
The circular hole being distributed on the concrete floor, it is the connection for transverse steel.
The lateral arcs surface concrete plate, surface should be accomplished enough smoothly to reduce to the frictional force of the soil body, can also be
The attached last layer stalloy in outer surface is rubbed with reducing.
Beneficial effects of the present invention:
1st, the present invention can improve a rate of advance of the underground space;
2nd, the present invention removes the process of slope retaining from;
3rd, the present invention can reduce manual work, reduce Contraction in Site;
4th, the invention enables job site noise is small, pollution is small;
5th, the present invention realizes factorial praluction, convenient and swift.
Brief description of the drawings
Fig. 1 is precast concrete basil component stereogram of the present invention;
Fig. 2 is precast concrete retaining wall component stereogram of the present invention;
Fig. 3 is precast concrete basil component top view of the present invention;
Fig. 4 is precast concrete basil component profile of the present invention;
Fig. 5 is precast concrete basil component spliced map of the present invention;
Fig. 6 is precast concrete retaining wall component top view of the present invention;
Fig. 7 is precast concrete retaining wall component profile of the present invention;
Fig. 8 is precast concrete retaining wall component spliced map of the present invention;
Fig. 9 is precast concrete basil component of the present invention and retaining wall component general assembly drawing.
Embodiment
The present invention will be described in detail below in conjunction with the accompanying drawings:
A kind of assembled circle underground space structure, its prefabricated component is divided into precast concrete basil component to be protected with precast concrete
Wall member;
The precast concrete basil component and precast concrete retaining wall component are cyclic structure, precast concrete basil component
Quantity is one and be located at bottom, the quantity of precast concrete retaining wall component be one or more than one and vertically splice pre-
The top of concrete basil component processed;
The precast concrete basil component passes through concrete by lateral arcs surface concrete plate I 1 and inside arc surface concrete plate I 2
The connection of floor I 3 forms an entirety, is uniform-distribution with circular hole I 4 on concrete floor I 3, lateral arcs surface concrete plate I 1 with it is interior
The bottom of side cambered surface concrete slab I 2 is connected as a single entity, and forms sharp concrete basil part 6, the bottom of concrete basil part 6
It is surrounded by angle steel sheath 7, the top of lateral arcs surface concrete plate I 1 and inside arc surface concrete plate I 2 is provided with concave-convex type bayonet socket I 5, and two
End is again provided with concave-convex type bayonet socket I 5;
The precast concrete retaining wall component is passed through mixed by lateral arcs surface concrete plate II 11 and inside arc surface concrete plate II 12
The solidifying native connection of floor II 13 forms an entirety, and circular hole II 14, outside cambered surface coagulation are uniform-distribution with concrete floor II 13
The top and bottom of native plate II 11 and inside arc surface concrete plate II 12 is provided with concave-convex type bayonet socket II 15, and both ends are again provided with bumps
Type bayonet socket II 15.
A kind of construction method of assembled circle underground space structure:
A, by soil excavation into a circular groove;
B, precast concrete basil component is lifted in place along circular groove, inserted in the trench, lateral arcs surface concrete plate I 1
Contacted with inside arc surface concrete plate I 2 with soil;
C, precast concrete basil component is installed along circular groove, splicing in place, is assembled into the circle enclosed;
D, intracavitary installs structure reinforcing bars, and casting concrete in prefabricated components, the circular prefabricated components of assembling is unified into one
Individual entirety;
E, loosened the soil plant equipment with rotary digging, stirred along I 2 pairs of foundation soils of lateral arcs surface concrete plate I 1 and inside arc surface concrete plate
Dynamic, digging pine, and mud is filled in the gap between cambered surface concrete slab and the soil body, make precast concrete basil component because certainly
Weight, sink naturally;
F, stop loosening the soil to after specifying absolute altitude after the prefabricated basil component entire lowering of annular;
G. hoisting prefabricated concrete guard wall component, installation, splice at the top of precast concrete basil component, notice that the fissure of displacement is spelled
Connect, be assembled into the annular enclosed a prefabricated components;
H. c, d, e, f steps are repeated, until precast concrete basil component sinks down into final designed elevation, cylindrical underground
Space structure is formed.
Claims (2)
- A kind of 1. assembled circle underground space structure, it is characterised in that:Its prefabricated component is divided into precast concrete basil component With precast concrete retaining wall component;The precast concrete basil component and precast concrete retaining wall component are cyclic structure, precast concrete basil component Quantity is one and be located at bottom, the quantity of precast concrete retaining wall component be one or more than one and vertically splice pre- The top of concrete basil component processed;The precast concrete basil component is by lateral arcs surface concrete plate I(1)With inside arc surface concrete plate I(2)By mixed Coagulate native floor I(3)Connection forms an entirety, concrete floor I(3)On be uniform-distribution with circular hole I(4), outside cambered surface coagulation Native plate I(1)With inside arc surface concrete plate I(2)Bottom is connected as a single entity, and forms sharp concrete basil part(6), concrete Basil part(6)Bottom be surrounded by angle steel sheath(7), lateral arcs surface concrete plate I(1)With inside arc surface concrete plate I(2)'s Top is provided with concave-convex type bayonet socket I(5), both ends are again provided with concave-convex type bayonet socket I(5);The precast concrete retaining wall component is by lateral arcs surface concrete plate II(11)With inside arc surface concrete plate II(12)It is logical Cross concrete floor II(13)Connection forms an entirety, concrete floor II(13)On be uniform-distribution with circular hole II(14), outside Side cambered surface concrete slab II(11)With inside arc surface concrete plate II(12)Top and bottom be provided with concave-convex type bayonet socket II(15), Both ends are again provided with concave-convex type bayonet socket II(15).
- A kind of 2. construction method of assembled circle underground space structure as claimed in claim 1:A, by soil excavation into a circular groove;B, precast concrete basil component is lifted in place along circular groove, inserted in the trench, lateral arcs surface concrete plate I (1)With inside arc surface concrete plate I(2)Contacted with soil;C, precast concrete basil component is installed along circular groove, splicing in place, is assembled into the circle enclosed;D, intracavitary installs structure reinforcing bars, and casting concrete in prefabricated components, the circular prefabricated components of assembling is unified into one Individual entirety;E, loosened the soil plant equipment with rotary digging, along lateral arcs surface concrete plate I(1)With inside arc surface concrete plate I(2)To ground Soil agitation, dig pine, and fill mud in the gap between cambered surface concrete slab and the soil body, make precast concrete basil component because For deadweight, sink naturally;F, stop loosening the soil to after specifying absolute altitude after the prefabricated basil component entire lowering of annular;G. hoisting prefabricated concrete guard wall component, installation, splice at the top of precast concrete basil component, notice that the fissure of displacement is spelled Connect, be assembled into the annular enclosed a prefabricated components;H. c, d, e, f steps are repeated, until precast concrete basil component sinks down into final designed elevation, cylindrical underground Space structure is formed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711145758.4A CN107630465A (en) | 2017-11-17 | 2017-11-17 | Assembled circle underground space structure and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711145758.4A CN107630465A (en) | 2017-11-17 | 2017-11-17 | Assembled circle underground space structure and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107630465A true CN107630465A (en) | 2018-01-26 |
Family
ID=61108686
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711145758.4A Pending CN107630465A (en) | 2017-11-17 | 2017-11-17 | Assembled circle underground space structure and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107630465A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108149702A (en) * | 2018-01-24 | 2018-06-12 | 中交二航局第四工程有限公司 | A kind of assembled caisson wall cutting shoe structure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10152853A (en) * | 1996-11-25 | 1998-06-09 | Kato Kensetsu:Kk | Method of building underground structure and structure member used therein |
CN103669400A (en) * | 2013-12-03 | 2014-03-26 | 国家电网公司 | Typical construction method for prefabricated tube bank |
CN205636750U (en) * | 2016-04-20 | 2016-10-12 | 山东大学 | Permanent supporting assembled cellar structure system of intensification |
CN106854873A (en) * | 2017-02-22 | 2017-06-16 | 中铁科建有限公司 | A kind of engineering method and garage parking in precast spliced sinking type garage parking |
CN106869548A (en) * | 2017-04-09 | 2017-06-20 | 北京工业大学 | A kind of newel framework assembled underground parking structural system and construction method |
-
2017
- 2017-11-17 CN CN201711145758.4A patent/CN107630465A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10152853A (en) * | 1996-11-25 | 1998-06-09 | Kato Kensetsu:Kk | Method of building underground structure and structure member used therein |
CN103669400A (en) * | 2013-12-03 | 2014-03-26 | 国家电网公司 | Typical construction method for prefabricated tube bank |
CN205636750U (en) * | 2016-04-20 | 2016-10-12 | 山东大学 | Permanent supporting assembled cellar structure system of intensification |
CN106854873A (en) * | 2017-02-22 | 2017-06-16 | 中铁科建有限公司 | A kind of engineering method and garage parking in precast spliced sinking type garage parking |
CN106869548A (en) * | 2017-04-09 | 2017-06-20 | 北京工业大学 | A kind of newel framework assembled underground parking structural system and construction method |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108149702A (en) * | 2018-01-24 | 2018-06-12 | 中交二航局第四工程有限公司 | A kind of assembled caisson wall cutting shoe structure |
CN108149702B (en) * | 2018-01-24 | 2024-01-26 | 中交二航局第四工程有限公司 | Assembled open caisson wall of a well cutting edge structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109723065B (en) | Reinforcing device and deep foundation pit local freezing reinforcing construction method in water-rich gravel stratum | |
CN105672348A (en) | Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region | |
CN103726495B (en) | Coastal waters deep foundation pit supporting structure and construction method thereof | |
KR20130081971A (en) | Precast concrete wall and method for constructing underground permanent wall using the precast concrete wall | |
CN105239598A (en) | Integral sinking construction method for well-type full-automatic stereo garage | |
JP2017186783A (en) | Construction method of continuous underground wall | |
KR101536209B1 (en) | Steel Pipe Multi Step Grouting device Open and cut and NATM complex excavation tunnel construction method | |
CN104532853A (en) | Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning | |
KR101021915B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
CN110306989A (en) | A kind of non-open cut assembled pipe canal digging support reinforcement method | |
CN112726627B (en) | Bored pile structure in karst region and construction method | |
CN110055973A (en) | Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time | |
CN108755719A (en) | Seabed municipal tunnel over strait cofferdam open cutting construction method | |
CN107630465A (en) | Assembled circle underground space structure and its construction method | |
CN217053672U (en) | Large-diameter inspection well pile drilling method construction system | |
JP3889750B2 (en) | Face stabilization method in underground structure construction method | |
CN110512594A (en) | The simple and easy method of churning driven opportunity cavity pore-forming | |
CN103161469A (en) | Method for excavating vertical shaft to underground repair pipe-jacking tool pipe | |
CN106337418A (en) | Supporting structure and supporting method of deep foundation pit in narrow area | |
CN205296194U (en) | Rich irrigated land layer undercut tunnel interlock pipe curtain | |
CN207469302U (en) | Assembled circle underground space structure | |
CN113322965A (en) | Deep foundation clearing construction method for near-subway deep foundation pit | |
CN114592581A (en) | Large-diameter inspection well pile drilling method construction method | |
JP4074198B2 (en) | How to remove existing piles | |
KR101437882B1 (en) | Tunnel excavating method having various cross sectional shapes |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180126 |