CN107630463A - A kind of construction technology of underground pipe gallery construction mobile jumbo device - Google Patents

A kind of construction technology of underground pipe gallery construction mobile jumbo device Download PDF

Info

Publication number
CN107630463A
CN107630463A CN201710845815.3A CN201710845815A CN107630463A CN 107630463 A CN107630463 A CN 107630463A CN 201710845815 A CN201710845815 A CN 201710845815A CN 107630463 A CN107630463 A CN 107630463A
Authority
CN
China
Prior art keywords
template
piping lane
construction
hydraulic cylinder
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710845815.3A
Other languages
Chinese (zh)
Inventor
黄高飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Fly Bridge Machinery Co Ltd
Original Assignee
Luoyang Fly Bridge Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luoyang Fly Bridge Machinery Co Ltd filed Critical Luoyang Fly Bridge Machinery Co Ltd
Priority to CN201710845815.3A priority Critical patent/CN107630463A/en
Publication of CN107630463A publication Critical patent/CN107630463A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

A kind of construction technology of underground pipe gallery construction mobile jumbo device, during piping lane lining construction, the construction section that the lifting running gear of piping lane formwork jumbo is entered in piping lane tunnel by track, piping lane formwork jumbo promotes top template by the cylinder rod of template hydraulic cylinder, by rotating angle mould spin axis, make oblique angle template, right angle form fixed after outwards strutting respectively to upper arm and backform plate level;The traversing casing bit of lifting door frame both sides pushes out side template by hydraulic cylinder respectively, completes the formwork of piping lane template;After the completion of piping lane template formwork, by the working window in template to casting concrete on the outside of template, it is stripped after concrete setting;The piping lane construction walking carriage of the present invention is using lifting walking carriage, template is supported by the flexible of hydraulic-driven, it is stripped after concrete cast, solidification, the piping lane running gear of piping lane construction walking carriage is retreated flexibly, steadily, it is piping lane inner wall smooth, smooth, consistent, it is ensured that the high-quality quality of engineering.

Description

A kind of construction technology of underground pipe gallery construction mobile jumbo device
Technical field
The present invention relates to the piping lane chassis of underground pipeline engineering.Especially a kind of underground pipe gallery construction mobile jumbo device Construction technology.
Background technology
At present, underground pipe network construction is more in work progress, it is necessary to ensure the safety on ground in the infrastructure in China Use and constructed with the formal approach of heavy excavation, because pipeline network construction has construction the dense population areas, it is necessary to ground more Appendicular to carry out removal and construct, appendicular removal causes engineering construction phenomenon hindered and happened occasionally, and And want the input budget of increased capital;During construction, by artificial support's framework, template assembly carries out concrete after the completion of fixing and poured Note forms, and after band concrete setting, form removable difficulty is big, of poor quality;Cause construction speed slow, job site dust is big, ring Comment not up to standard;In view of the foregoing, it is proposed that a kind of construction technology of underground pipe gallery construction mobile jumbo device.
The content of the invention
The invention aims to overcome underground pipe network construction in infrastructure, it is necessary to ensure the safety on ground, apply During work, more use is constructed with the formal approach of heavy excavation, because pipeline network construction has construction the dense population areas more, need The appendicular of ground is carried out by removal can constructed, when appendicular removal causes engineering construction phenomenon hindered There is generation, and want the input budget of increased capital;During construction, by artificial support's framework, it is laggard that template assembly fixes completion The cast of row concrete forms, and after band concrete setting, form removable difficulty is big, of poor quality;Cause construction speed slow, job site Dust is big, environmental impact assessment is not up to standard, by reasonably designing, there is provided a kind of construction technology of underground pipe gallery construction mobile jumbo device, The piping lane construction walking carriage of the present invention does not need artificial support's framework, template assembly using lifting walking carriage, piping lane construction Fixed, template is supported by the flexible of hydraulic-driven, and after concrete cast, solidification, template is taken off by hydraulic retract Mould, the piping lane running gear of piping lane construction walking carriage retreat flexibly, it is steady, it is piping lane inner wall smooth, smooth, consistent, it is ensured that work Cheng Youzhi quality.
The present invention to achieve these goals, adopts the following technical scheme that:A kind of underground pipe gallery construction mobile jumbo device Construction technology, described underground pipe gallery construction mobile jumbo device be by:Lift door frame, lifting running gear, side template, top Template, oblique angle template, right angle form, the support frame that crosses the river, traversing support meanss, traversing supporting sleeve, track, piping lane Schaltisch Car, template hydraulic cylinder, girder, angle mould spin axis are formed;Piping lane is respectively set to single-row or arranged side by side, piping lane formwork jumbo in piping lane, Door frames are lifted at least provided with three in piping lane formwork jumbo, the support frame that crosses the river, overhead door are set between lifting door frame lower cage body Frame both sides support body is respectively arranged below two girders, and the both ends of two girders set lifting running gear, lifting walking respectively The road wheel lower end of system sets track;
Lifting door frame top both sides are symmetrical arranged traversing supporting sleeve, and lifting door frame both sides are symmetrical arranged two traversing supports Device, the traversing casing bit of both sides set two pieces of side templates respectively with traversing supporting sleeve outer end;
Template hydraulic cylinder, the lifting support of template hydraulic cylinder cylinder rod upper end are set respectively in the support body of lifting door frame both sides Bar, the lift supporting rod upper end of template hydraulic cylinder set top template, and top template one end sets oblique angle template, and the top template other end is set Right angle form is put, top template both ends set angle mould spin axis between oblique angle template, right angle form respectively;
Oblique angle template, right angle form lower end are correspondingly arranged with the upper end of side template as piping lane pattern plate respectively, oblique angle template, Right angle form lower end is respectively set to outer oblique angle, and the upper end of side template corresponds to oblique angle template, the outer oblique angle of right angle form respectively Gradient sets inner bevel;
During piping lane lining construction, construction that the lifting running gear of piping lane formwork jumbo is entered in piping lane tunnel by track Section, lifting running gear stop.
After lifting running gear stopping, piping lane formwork jumbo promotes lift supporting rod to make top by the cylinder rod of template hydraulic cylinder Template raises in place, and template hydraulic cylinder stops.
After template hydraulic cylinder stops, top template both ends by rotating angle mould spin axis, make oblique angle template, right angle form point respectively It is fixed after outwards not strutting to upper arm and backform plate level.
After oblique angle template, right angle form outwards strut fixation respectively, the traversing casing bit of lifting door frame both sides leads to respectively Cross hydraulic cylinder and push out side template, make both sides side template upper end inclined-plane respectively with oblique angle template, right angle form inclined-plane pair Stop after connecing;Template outside after side template docks with oblique angle template, right angle form respectively is piping lane type, completes piping lane template Formwork.
After the completion of piping lane template formwork, by the working window in template to casting concrete on the outside of template, casting concrete Completion is after concrete setting, and traversing casing bit pulls side template return by hydraulic cylinder respectively, by rotating angle mould spin axis Oblique angle template, right angle form return are packed up respectively, and top template return is reduced by template hydraulic cylinder cylinder rod, completes the demoulding;Complete After the demoulding, next section of piping lane lining construction is entered by lifting running gear drive piping lane formwork jumbo.
Beneficial effect:The piping lane construction walking carriage of the present invention need not be artificial using lifting walking carriage, piping lane construction Support frame, template assembly are fixed, and template is supported by the flexible of hydraulic-driven, and after concrete cast, solidification, template is led to Hydraulic retract to be crossed to be stripped, the piping lane running gear of piping lane construction walking carriage is retreated flexibly, steadily, piping lane inner wall smooth, It is smooth, consistent, it is ensured that the high-quality quality of engineering.
Brief description of the drawings
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is general assembly structural representation;
Fig. 2 is Fig. 1 receipts mould status architecture schematic diagram;
Fig. 3 is Fig. 1 side structure schematic view;
In Fig. 1,2,3:Lift door frame 1, lifting running gear 2, side template 3, top template 4, oblique angle template 5, right angle form 6th, cross the river support frame 7, traversing support meanss 8, traversing supporting sleeve 9, track 10, piping lane formwork jumbo 11, template hydraulic cylinder 12, Girder 13, angle mould spin axis 14.
Embodiment
The present invention is described in further detail with embodiment with reference to embodiment:
Embodiment 1
Piping lane is respectively set to single-row or arranged side by side, piping lane formwork jumbo 11 in piping lane, is at least set in piping lane formwork jumbo 11 Three lifting door frames 1 are put, the support frame 7 that crosses the river is set between the lifting bottom support body of door frame 1, lifts the lower section of the both sides support body of door frame 1 Two girders 13 are set respectively, and the both ends of two girders 13 set lifting running gear 2, lift the walking of running gear 2 respectively Take turns lower end and track 10 is set;
Lifting door frame 1 top both sides are symmetrical arranged traversing supporting sleeve 9, lifting door frame 1 both sides be symmetrical arranged two it is traversing Support meanss 8, the traversing casing bit 8 of both sides set two pieces of side templates 3 respectively with the traversing outer end of supporting sleeve 9;
Template hydraulic cylinder 12, the lifting of the cylinder rod upper end of template hydraulic cylinder 12 are set respectively in the support body of lifting door frame 1 both sides Support bar, the lift supporting rod upper end of template hydraulic cylinder 12 set top template 4, and the one end of top template 4 sets oblique angle template 5, backform The other end of plate 4 sets right angle form 6, and the both ends of top template 4 set angle mould spin axis between oblique angle template 5, right angle form 6 respectively 14;
Oblique angle template 5, the lower end of right angle form 6 are correspondingly arranged with the upper end of side template 3 as piping lane pattern plate, oblique angle mould respectively Plate 5, the lower end of right angle form 6 are respectively set to outer oblique angle, and the upper end of side template 3 corresponds to oblique angle template 5, right angle form 6 respectively The gradient at outer oblique angle sets inner bevel;
During piping lane lining construction, the lifting running gear 2 of piping lane formwork jumbo 11 is entered in piping lane tunnel by track 10 Construction section, lifting running gear 2 stop.
Embodiment 2
After lifting the stopping of running gear 2, the cylinder rod that piping lane formwork jumbo 11 passes through template hydraulic cylinder 12 promotes lifting support Bar makes top template 4 raise in place, and template hydraulic cylinder 12 stops.
Embodiment 3
After template hydraulic cylinder 12 stops, the both ends of top template 4 by rotating angle mould spin axis 14, make oblique angle template 5, right angle respectively Template 6 is fixed after outwards strutting respectively to upper arm and the level of top template 4.
Embodiment 4
After oblique angle template 5, right angle form 6 outwards strut fixation respectively, the traversing casing bit 8 of lifting door frame 1 both sides divides Side template 3 is not pushed out by hydraulic cylinder, make both sides the upper end of side template 3 inclined-plane respectively with oblique angle template 5, right angle form Stop after the docking of 6 inclined-planes;Template outside after side template 3 docks with oblique angle template 5, right angle form 6 respectively is piping lane type, is completed The formwork of piping lane template.
Embodiment 5
After the completion of piping lane template formwork, by the working window in template to casting concrete on the outside of template, casting concrete After concrete setting, traversing casing bit 8 pulls the return of side template 3 by hydraulic cylinder respectively for completion, is revolved by rotating angle mould Axle 14 packs up oblique angle template 5, the return of right angle form 6 respectively, reduces the return of top template 4 by the cylinder rod of template hydraulic cylinder 12, completes The demoulding;After completing the demoulding, next section of piping lane lining construction is entered by lifting the drive piping lane of running gear 2 formwork jumbo 11.

Claims (5)

1. a kind of construction technology of underground pipe gallery construction mobile jumbo device, described underground pipe gallery construction mobile jumbo device are By:Lift door frame (1), lifting running gear (2), side template (3), top template (4), oblique angle template (5), right angle form (6), mistake River support frame (7), traversing support meanss (8), traversing supporting sleeve (9), track (10), piping lane formwork jumbo (11), template liquid Cylinder pressure (12), girder (13), angle mould spin axis (14) are formed;It is characterized in that:Piping lane be respectively set to it is single-row or arranged side by side, in piping lane Piping lane formwork jumbo (11), at least provided with three lifting door frames (1) in piping lane formwork jumbo (11), lift door frame (1) lower cage The support frame (7) that crosses the river is set between body, and lifting door frame (1) both sides support body is respectively arranged below two girders (13), two masters The both ends of beam (13) set lifting running gear (2) respectively, and the road wheel lower end of lifting running gear (2) sets track (10);
Lifting door frame (1) top both sides are symmetrical arranged traversing supporting sleeve (9), and lifting door frame (1) both sides are symmetrical arranged two horizontal strokes Support meanss (8) are moved, traversing casing bit (8) and traversing supporting sleeve (9) outer end of both sides set two pieces of side templates respectively (3);
Lift in the support body of door frame (1) both sides and template hydraulic cylinder (12), the liter of template hydraulic cylinder (12) cylinder rod upper end are set respectively Descending branch strut, the lift supporting rod upper end of template hydraulic cylinder (12) set top template (4), and top template (4) one end sets oblique angle mould Plate (5), top template (4) other end set right angle form (6), top template (4) both ends respectively with oblique angle template (5), right angle form (6) angle mould spin axis (14) is set between;
Oblique angle template (5), right angle form (6) lower end are correspondingly arranged with the upper end of side template (3) as piping lane pattern plate, oblique angle respectively Template (5), right angle form (6) lower end are respectively set to outer oblique angle, and the upper end of side template (3) corresponds to oblique angle template (5), straight respectively The gradient at the outer oblique angle of Angle formwork (6) sets inner bevel;
During piping lane lining construction, the lifting running gear (2) of piping lane formwork jumbo (11) enters piping lane tunnel by track (10) In construction section, lifting running gear (2) stop.
A kind of 2. construction technology of underground pipe gallery construction mobile jumbo device according to claim 1, it is characterised in that:Rise After dropping running gear (2) stopping, piping lane formwork jumbo (11) promotes lift supporting rod to make by the cylinder rod of template hydraulic cylinder (12) Top template (4) raises in place, and template hydraulic cylinder (12) stops.
A kind of 3. construction technology of underground pipe gallery construction mobile jumbo device according to claim 1, it is characterised in that:Mould After plate hydraulic cylinder (12) stops, top template (4) both ends by rotating angle mould spin axis (14), make oblique angle template (5), right angle mould respectively Plate (6) is fixed after outwards strutting respectively to upper arm and top template (4) level.
A kind of 4. construction technology of underground pipe gallery construction mobile jumbo device according to claim 1, it is characterised in that:Tiltedly After Angle formwork (5), right angle form (6) outwards strut fixation respectively, the traversing casing bit (8) of lifting door frame (1) both sides is respectively Side template (3) is pushed out by hydraulic cylinder, make both sides side template (3) upper end inclined-plane respectively with oblique angle template (5), right angle Stop after the docking of template (6) inclined-plane;Side template (3) docked respectively with oblique angle template (5), right angle form (6) after template outside For piping lane type, the formwork of completion piping lane template.
A kind of 5. construction technology of underground pipe gallery construction mobile jumbo device according to claim 1, it is characterised in that:Pipe After the completion of corridor template formwork, by the working window in template to casting concrete on the outside of template, casting concrete is completed to treat coagulation After soil solidification, traversing casing bit (8) pulls side template (3) return by hydraulic cylinder respectively, by rotating angle mould spin axis (14) Oblique angle template (5), right angle form (6) return are packed up respectively, and top template (4) return is reduced by template hydraulic cylinder (12) cylinder rod, Complete the demoulding;After completing the demoulding, the piping lane for driving piping lane formwork jumbo (11) to enter next section by lifting running gear (2) serves as a contrast Build construction.
CN201710845815.3A 2017-09-19 2017-09-19 A kind of construction technology of underground pipe gallery construction mobile jumbo device Pending CN107630463A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710845815.3A CN107630463A (en) 2017-09-19 2017-09-19 A kind of construction technology of underground pipe gallery construction mobile jumbo device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710845815.3A CN107630463A (en) 2017-09-19 2017-09-19 A kind of construction technology of underground pipe gallery construction mobile jumbo device

Publications (1)

Publication Number Publication Date
CN107630463A true CN107630463A (en) 2018-01-26

Family

ID=61102232

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710845815.3A Pending CN107630463A (en) 2017-09-19 2017-09-19 A kind of construction technology of underground pipe gallery construction mobile jumbo device

Country Status (1)

Country Link
CN (1) CN107630463A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756956A (en) * 2018-07-30 2018-11-06 洛阳高飞桥隧机械有限公司 A kind of anchor bar of waterproof plate in tunnels reinforcement trolley is laid with the application method of positioning device
CN111608199A (en) * 2020-05-25 2020-09-01 中铁隧道集团二处有限公司 Lateral formwork translation driving mechanism for pipe gallery concrete construction
CN112593573A (en) * 2020-11-02 2021-04-02 北京城建设计发展集团股份有限公司 Underground pipe gallery concrete formwork system and using method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758640A (en) * 2012-07-13 2012-10-31 中铁四局集团第四工程有限公司 Metro tunnel lining trolley steel template system
CN104594918A (en) * 2014-12-31 2015-05-06 上海市机械施工集团有限公司 Split integrated underground passage steel mold plate trolley and construction method thereof
CN104632251A (en) * 2014-12-31 2015-05-20 上海市机械施工集团有限公司 Integrally cast type mould plate trolley and construction method of concrete pouring of underground passage
CN104763446A (en) * 2015-03-24 2015-07-08 粤水电轨道交通建设有限公司 Multi-functional trolley for subway station construction
CN204457802U (en) * 2014-12-31 2015-07-08 上海市机械施工集团有限公司 Formed by integrally casting formula formwork jumbo
CN205618174U (en) * 2016-04-14 2016-10-05 中铁八局集团第二工程有限公司 Box culvert platform truck
CN106759487A (en) * 2017-02-14 2017-05-31 中国冶集团有限公司 Underground pipe gallery inner formwork system continuous-flow type construction method
CN106996296A (en) * 2017-06-02 2017-08-01 中铁四局集团第四工程有限公司 A kind of integral inside molding chassis for Urban Underground pipe gallery main structure construction

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758640A (en) * 2012-07-13 2012-10-31 中铁四局集团第四工程有限公司 Metro tunnel lining trolley steel template system
CN104594918A (en) * 2014-12-31 2015-05-06 上海市机械施工集团有限公司 Split integrated underground passage steel mold plate trolley and construction method thereof
CN104632251A (en) * 2014-12-31 2015-05-20 上海市机械施工集团有限公司 Integrally cast type mould plate trolley and construction method of concrete pouring of underground passage
CN204457802U (en) * 2014-12-31 2015-07-08 上海市机械施工集团有限公司 Formed by integrally casting formula formwork jumbo
CN104763446A (en) * 2015-03-24 2015-07-08 粤水电轨道交通建设有限公司 Multi-functional trolley for subway station construction
CN205618174U (en) * 2016-04-14 2016-10-05 中铁八局集团第二工程有限公司 Box culvert platform truck
CN106759487A (en) * 2017-02-14 2017-05-31 中国冶集团有限公司 Underground pipe gallery inner formwork system continuous-flow type construction method
CN106996296A (en) * 2017-06-02 2017-08-01 中铁四局集团第四工程有限公司 A kind of integral inside molding chassis for Urban Underground pipe gallery main structure construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756956A (en) * 2018-07-30 2018-11-06 洛阳高飞桥隧机械有限公司 A kind of anchor bar of waterproof plate in tunnels reinforcement trolley is laid with the application method of positioning device
CN111608199A (en) * 2020-05-25 2020-09-01 中铁隧道集团二处有限公司 Lateral formwork translation driving mechanism for pipe gallery concrete construction
CN112593573A (en) * 2020-11-02 2021-04-02 北京城建设计发展集团股份有限公司 Underground pipe gallery concrete formwork system and using method thereof

Similar Documents

Publication Publication Date Title
CN105649654B (en) Automatic hydraulic inverted arch trestle chassis and its construction method
CN207109856U (en) Piping lane, culvert construction hydraulic steel formwork jumbo
CN103967050B (en) Construction system of subway station
CN205778910U (en) A kind of outer mould trolley of cut-and-cover tunnel lining cutting
CN105952482A (en) Self-propelled tunnel invert lining trolley
CN102635369B (en) Construction method for integrally pouring inverted arch concrete by matching trestle with top formwork
CN107630463A (en) A kind of construction technology of underground pipe gallery construction mobile jumbo device
CN204343173U (en) A kind of Segmental assembling bridge-erecting machine
CN104533460B (en) Support replacement formula formwork jumbo and the construction method of underpass concreting
CN103195450A (en) Hydraulic tunnel inverted arch operation trolley and inverted arch construction method
CN103046473A (en) Construction method for constructing double-limb hollow high-pier mould side hydraulic jacking creeping formwork and double-limb hollow high-pier
CN104763446A (en) Multi-functional trolley for subway station construction
CN205618174U (en) Box culvert platform truck
CN104005775B (en) Tunnel invert backfill construction integrated template and construction technology thereof
CN106593469A (en) Trolley for construction of inverted arch
CN111809660A (en) Comprehensive pipe gallery rectangular trolley and construction method
CN205936645U (en) A full liquid die plate system for culvert is pour
CN205259074U (en) Basket traveling system is hung to triangle
CN110173281A (en) A kind of sliding mode system for circular tunnel concreting
CN102425140A (en) Special mobile support frame for high-altitude arch closing and construction method thereof
CN207453986U (en) A kind of mobile jumbo device of underground pipe gallery construction
CN203603928U (en) Rubber-tyred walking full-hydraulic lining trolley
CN106401606B (en) Template trestle trolley
CN104894943B (en) Road and bridge gutter construction concrete cast integral mold plate
CN107191205B (en) Self-moving full-arc template for loop casting of tunnel side wall inverted arch concrete

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180126

WD01 Invention patent application deemed withdrawn after publication