CN107621171B - Large-scale normalizing furnace winter brickwork method - Google Patents

Large-scale normalizing furnace winter brickwork method Download PDF

Info

Publication number
CN107621171B
CN107621171B CN201610553172.0A CN201610553172A CN107621171B CN 107621171 B CN107621171 B CN 107621171B CN 201610553172 A CN201610553172 A CN 201610553172A CN 107621171 B CN107621171 B CN 107621171B
Authority
CN
China
Prior art keywords
furnace
steel
brickwork
heating installation
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610553172.0A
Other languages
Chinese (zh)
Other versions
CN107621171A (en
Inventor
刘小勇
周继军
韩超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201610553172.0A priority Critical patent/CN107621171B/en
Publication of CN107621171A publication Critical patent/CN107621171A/en
Application granted granted Critical
Publication of CN107621171B publication Critical patent/CN107621171B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of large size normalizing furnace winter brickwork method, it is characterised in that the following steps are included: a, setting wall-hanging heating installation, b, block the heat preservation of furnace shell hole.Large-scale normalizing furnace winter brickwork method of the invention has wall-hanging heating installation frame structure simple; it makes, is easy to use; brickwork construction quality is safe and reliable; overcome the shortcomings that traditional winter severe cold environment building method is unable to satisfy brickwork temperature requirement; the protection of heater cable closure formula; the advantages of ensure that brickwork safety, guaranteeing the duration and reduce engineering cost.

Description

Large-scale normalizing furnace winter brickwork method
Technical field
The present invention relates to a kind of normalizing furnace brickwork methods, specifically, being a kind of large-scale normalizing furnace winter brickwork method.
Background technique
Normalizing furnace is the equipment for steel plate heat treatment.Large-scale normalizing furnace furnace construction engineering, requiring height to temperature, (temperature is not low In 5 DEG C), when encountering winter construction, often influences the duration because temperature is low or construction quality, security problems occur.
Summary of the invention
The purpose of the present invention is to propose a kind of safe and reliable large-scale normalizing furnace winter brickwork method.
To achieve the above object, the technical solution of the invention is as follows:
A kind of large size normalizing furnace winter brickwork method, normalizing furnace overall length are 250m, on the sustained height of furnace shell two sides between 2m Away from the φ 190mm round kiln roller aperture being dispersed with for installing furnace roller, furnace shell is welded by steel plate, and inside can not hang heating Device belongs to confined space in furnace, does not allow cabling, it is characterised in that the following steps are included:
A, wall-hanging heating installation is set, comprising the following steps:
(1) wall-hanging heating installation frame is made comprising the steps of:
It is used to place the wall built-up of heating installation according to normalizing furnace length, furnace roller pore size distribution and the big little makings several groups of heater Formula heating installation frame, heating installation frame include the fixing seat of furnace roller hole collar extension and the heating installation bracket of furnace roller hole mouth,
Wherein: fixing seat includes square or the 1st steel plate of rectangle and the 2nd steel plate, and it is logical that four bolts are arranged in the 1st steel plate surrounding The 1st steel pipe is welded at hole, the 1st steel plate center admittedly;The shape of 2nd steel plate, size, bolt hole are arranged with the 1st steel plate, the 2nd steel plate A through-hole is arranged in center, makes to be inserted into the 1st steel pipe in the 2nd steel plate by the through-hole, and made in four bolt holes with bolt Together, fixing seat is retained in fixing seat with the 1st steel pipe one end out of furnace roller hole when use for 1st steel plate and the 2nd Interal fixation Furnace roller hole collar extension;
Heating installation bracket includes diameter 2nd steel pipe 3-5mm bigger than the 1st steel pipe, and the 2nd steel pipe one end can fitting insertion the In 1 steel pipe, the 1st round steel one end of the 2nd steel pipe other port is welded and fixed, and keeps the 1st round steel vertical with the 2nd steel pipe, the 1st round steel The center tack welding of the other end and the 3rd round steel keeps the 1st round steel vertical with the 3rd round steel, the both ends of the 3rd round steel respectively with the 2nd round steel one End is welded and fixed, and keeps the 3rd round steel vertical with the 2nd steel pipe, and the other end of two the 2nd round steel is respectively welded and fixed with bar one end, makes Bar is parallel with the 1st round steel;
(2) heating installation is placed on wall-hanging heating installation frame
Heating installation is heater, heater diameter 300mm, 400mm long, and heater is shelved on two the 2nd round steel, keeps off Bar prevents heater from skidding off heating installation bracket in the 2nd round steel end;
B, the heat preservation of furnace shell hole is blocked
There are furnace roller hole, burner hole, radiation pore and manhole in furnace shell outer wall two sides, right to keep construction environment temperature in furnace Hole carries out temporary plugging comprising the steps of:
(1) furnace shell side wall has band steel reinforcement, and furnace shell side wall is divided into many grid, is cut into using yellow plate paper appropriately sized Block furnace roller hole, the burner hole, radiation pore within the scope of grid;
(2) for the manhole of furnace shell side in addition to leaving necessary construction personnel's inlet and outlet, remaining piles up envelope using manhole brick It is stifled;
(3) stove both ends inlet seal room, exit seal room furnace are blocked using cloth door curtain, are facilitated construction personnel and are built object Money disengaging;
(4) a thermometer is hung every 20m long in furnace, observes in-furnace temperature at any time;
(5) sequence of construction is adjusted, furnace inside holding is reinforced
Brickwork design sequence: 1. surveying setting-out, 2. side wall lay bricks, 3. make furnace roof module or set up arch mould, 4. build furnace roof 5. brick spreads bottom brick, 6. demoulding cleaning brickwork joint gap;Bottom brick will be 5. spread in practice of construction to shift to an earlier date, and first be laid with furnace bottom fibre module And 2 layers of bottom brick, stay last surface layer brick that wouldn't be laid with, and be laid with yellow plate paper protection, furnace of then constructing again on bottom brick Dome brick, can more preferably keep in-furnace temperature;
(6) brickwork is built using segmentation, and every 50m is one section, and primary reformer rearwards promotes after building, and will heating Device with moving backward, before built part and retain a heater and keep furnace temperature.
Large-scale normalizing furnace winter brickwork method of the invention can also be further achieved by the following technical measures.
Method above-mentioned, wherein the thickness of the 1st steel plate and the 2nd steel plate >=6mm.
Method above-mentioned, wherein the bolt specification is >=M12 bolt.
Method above-mentioned, wherein round steel diameter >=10mm.
Method above-mentioned, wherein the heater is in every 50m long normalizing furnace apart from eight heaters of interior installation.
Method above-mentioned, wherein the yellow plate paper is refractory material outer packing.
After adopting the above technical scheme, large-scale normalizing furnace winter brickwork method of the invention has the advantage that
1, wall-hanging heating installation frame structure is simple, makes, is easy to use;
2, brickwork construction quality is safe and reliable, overcomes traditional winter severe cold environment building method and is unable to satisfy brickwork temperature It is required that the shortcomings that;
3, heater cable closure formula is protected, and ensure that brickwork safety;
4, guarantee the duration, reduce engineering cost.
Detailed description of the invention
Fig. 1 is the normalizing furnace boiler face structural schematic diagram of the embodiment of the present invention;
Fig. 2 is the wall-hanging heating installation structural schematic diagram of the embodiment of the present invention;
Fig. 3 is the 1st steel plate main view of the embodiment of the present invention;
Fig. 4 is the side view of Fig. 3;
Fig. 5 is the 2nd steel plate main view of the embodiment of the present invention;
Fig. 6 is the wall-hanging heating installation frame structural schematic diagram of the embodiment of the present invention;
Fig. 7 is the side view of Fig. 6;
Fig. 8 is that the wall-hanging heating installation of the embodiment of the present invention combines scheme of installation with heater;
Fig. 9 is the wall-hanging heating installation use state diagram of the embodiment of the present invention.
In figure: 1 the 1st steel pipe, 2 bolts, 3 the 1st steel plates, 4 the 2nd steel plates, 5 the 2nd steel pipes, 6 the 1st round steel, 7 the 2nd round steel, 8 gears Bar, 9 heaters, 10 normalizing furnace center lines, 11 cable interfaces, 12 the 3rd round steel, 13 furnace roller holes, 14 wall-hanging heating installation framves.
Specific embodiment
With reference to embodiments and its attached drawing further explains the present invention.
Embodiment 1
It is the normalizing furnace boiler face structural schematic diagram of the embodiment of the present invention referring now to Fig. 1, Fig. 1.
Large-scale normalizing furnace winter brickwork method of the invention, normalizing furnace are always about 250m, on the sustained height of furnace shell two sides with 2m spacing is dispersed with the φ 190mm round kiln roller aperture for installing furnace roller, and furnace shell is welded by steel plate, and inside can not hang and take Warmer belongs to confined space in furnace, does not allow cabling.Normalizing furnace winter brickwork method the following steps are included:
A, wall-hanging heating installation is set, comprising the following steps:
(1) wall-hanging heating installation frame is made comprising the steps of:
It is used to place the wall built-up of heating installation according to normalizing furnace length, furnace roller pore size distribution and the big little makings several groups of heater Formula heating installation frame, heating installation frame include the fixing seat of furnace roller hole collar extension and the heating installation bracket of furnace roller hole mouth.
It is the normalizing furnace boiler face structural schematic diagram of the embodiment of the present invention referring now to Fig. 3 and Fig. 4, Fig. 1.Fig. 3 is the present invention 1st steel plate main view of embodiment, Fig. 4 are the side view of Fig. 3.
Fixing seat includes square 1st steel plate 3 and the 2nd steel plate 4, and four bolt holes, the 1st steel is arranged in the 1st steel plate surrounding Admittedly the 1st steel pipe 1 of DN25 of long 300mm is welded in plate center;1st steel plate, 3 side length 300mm.The shape of 2nd steel plate 4, size, bolt are logical Hole is arranged with the 1st steel plate 3, and a M12 bolt hole is arranged in the center of the 2nd steel plate 4, and through-hole spacing 140mm is made by the through-hole It is inserted into the 1st steel pipe 1 in 2nd steel plate 4, and is fixed on the 1st steel plate 3 and the 2nd steel plate 4 with M12 bolt 2 in four bolt holes Together, fixing seat is entered in normalizing furnace with 1 one end of the 1st steel pipe from furnace roller hole 13 when use, is retained in fixing seat outside furnace roller hole Mouthful.The thickness of 1st steel plate 3 and the 2nd steel plate 4 is 6mm.
Fig. 6 is the wall-hanging heating installation frame structural schematic diagram of the embodiment of the present invention, and Fig. 7 is the side view of Fig. 6.
Heating installation bracket includes 2nd steel pipe 5 of the diameter than the big 3mm of the 1st steel pipe 1, and the 2nd steel pipe 5 is the DN32 of long 250mm Steel pipe, steel pipe one end energy fitting are inserted into the 1st steel pipe 1, and 6 one end of the 1st round steel of the 2nd steel pipe other port and long 260mm are welded Fixation is connect, keeps the 1st round steel 6 vertical with the 2nd steel pipe 5, the central point of the 3rd round steel 12 of the other end and long 200mm of the 1st round steel 6 Gu weldering, keeps the 1st round steel vertical with the 3rd round steel, the both ends of the 3rd round steel 12 are respectively welded and fixed with long 7 one end of the 2nd round steel of 410mm, make 3rd round steel 12 is vertical with the 2nd steel pipe 5, and the other end of two the 2nd round steel 7 is respectively welded and fixed with 8 one end of bar of long 50mm, makes Bar is parallel with the 1st round steel 6;
(2) heating installation is placed on wall-hanging heating installation frame
Fig. 2 is the wall-hanging heating installation structural schematic diagram of the embodiment of the present invention.Heating installation is heater, and heater is straight Diameter 300mm, 400mm long, heater are shelved on two the 2nd round steel 7, and bar 8 prevents heater from skidding off in 7 end of the 2nd round steel Heating installation bracket;Round steel diameter >=the 10mm.
B, the heat preservation of furnace shell hole is blocked
There are furnace roller hole, burner hole, radiation pore and manhole in furnace shell outer wall two sides, right to keep construction environment temperature in furnace Hole carries out temporary plugging comprising the steps of:
(1) furnace shell side wall has band steel reinforcement, and furnace shell side wall is divided into many grid, is cut into using yellow plate paper appropriately sized Block furnace roller hole, the burner hole, radiation pore within the scope of grid;
(2) for the manhole of furnace shell side in addition to leaving necessary construction personnel's inlet and outlet, remaining piles up envelope using manhole brick It is stifled;
(3) belong to entrance in confined space in furnace, outlet is blocked using cloth door curtain, facilitate construction personnel to pass in and out;
(4) a thermometer is hung every 20m long in furnace, observes in-furnace temperature at any time;
(5) sequence of construction is adjusted, furnace inside holding is reinforced
Brickwork design sequence: 1. surveying setting-out, 2. side wall lay bricks, 3. make furnace roof module or set up arch mould, 4. build furnace roof 5. brick spreads bottom brick, 6. demoulding cleaning brickwork joint gap;Bottom brick will be 5. spread in practice of construction to shift to an earlier date, and first be laid with furnace bottom fibre module And 2 layers of bottom brick, stay last surface layer that wouldn't be laid with, and be laid with yellow plate paper protection, furnace roof of then constructing again on bottom brick Brick, can more preferably keep in-furnace temperature.Fig. 8 is that the wall-hanging heating installation of the embodiment of the present invention combines installation signal with heater Figure, Fig. 9 are the wall-hanging heating installation use state diagram of the embodiment of the present invention.
(6) brickwork is built using segmentation, and every 50m is one section, and primary reformer rearwards promotes after building, and will heating Device with moving backward, before built part and retain a heater and keep furnace temperature.The heater is in every section of 50m length Normalizing furnace apart from eight heaters of interior installation.The yellow plate paper is refractory material outer packing.Power supply line overhauls from each suspension column Power supply box takes, and power supply line uses ZR-YJV-0.6/1KV 3*4 power cable, and 8 heaters need to use 300m cable altogether.Cable from DN25 steel pipe is pierced into outside, then pierces into DN32 steel pipe, with connection jaws wiring at the top of heater, and is wrapped up with insulating tape, so DN32 pipeline is packed into DN25 pipeline afterwards, and tenses cable in outside, is totally placed in cable in steel pipe.It is suitable in view of constructing Sequence, 8 heaters can be installed concentratedly first in 5~6 section furnace shells of construction (50m or so), concentrate and build this several sections, with subsequent It builds, the effect of tapetum fibrosum and refractory brick, furnace inside holding effect can gradually increase, then heater is moved back.
The present invention have substantive distinguishing features and significant technological progress, large-scale normalizing furnace winter brickwork method of the invention, Its key technology main points: heating and heat preservation.It is wherein heated using heater, it is important to guarantee that heater can move at any time, together When guarantee heater cable using safe.Heat preservation is mainly to the furnace roller hole of furnace shell two sides, manhole, radiation pore, burner hole Carry out a temporary plugging.When winter severe cold environment, the shortcomings that traditional building method is unable to satisfy brickwork temperature requirement is overcome, It can preferably guarantee the duration, save cost;Wall-hanging heating installation of the invention is used simultaneously, and the cable of heater is accomplished to seal The protection of enclosed ensure that the safety built the road.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent Technical solution also should belong to scope of the invention, should be limited by each claim.

Claims (6)

1. a kind of large size normalizing furnace winter brickwork method, normalizing furnace overall length is 250m, with 2m spacing on the sustained height of furnace shell two sides It is dispersed with the φ 190mm round kiln roller aperture for installing furnace roller, furnace shell is welded by steel plate, and inside can not hang heater, Belong to confined space in furnace, does not allow cabling, it is characterised in that the following steps are included:
A, wall-hanging heating installation is set, comprising the following steps:
(1) wall-hanging heating installation frame is made comprising the steps of:
It is taken according to the wall-hanging that normalizing furnace length, furnace roller pore size distribution and the big little makings several groups of heater are used to place heating installation Heater device frame, heating installation frame include the fixing seat of furnace roller hole collar extension and the heating installation bracket of furnace roller hole mouth,
Wherein: fixing seat includes square 1st steel plate (3) and the 2nd steel plate (4), and four bolt holes are arranged in the 1st steel plate surrounding, Admittedly the 1st steel pipe (1) is welded in 1st steel plate center;The shape of 2nd steel plate (4), size, same 1st steel plate (3) of bolt hole setting, the 2nd A through-hole is arranged in the center of steel plate (4), makes to be inserted into the 1st steel pipe (1) in the 2nd steel plate (4) by the through-hole, and in four bolts The 1st steel plate (3) and the 2nd steel plate (4) is set to be fixed together with bolt (2) in through-hole, fixing seat is with the 1st steel pipe (1) one when use End enters in normalizing furnace from furnace roller hole (13), and fixing seat is made to be retained in furnace roller hole collar extension;Heating installation bracket includes diameter than the 1st The 2nd steel pipe (5) of the big 3-5mm of steel pipe (1), the 2nd steel pipe (5) one end energy fitting are inserted into the 1st steel pipe (1), the 2nd steel pipe other end It is welded and fixed at mouthful with the 1st round steel (6) one end, keeps the 1st round steel (6) vertical with the 2nd steel pipe (5), the other end of the 1st round steel (6) With the center tack welding of the 3rd round steel (12), keep the 1st round steel vertical with the 3rd round steel, the both ends of the 3rd round steel (12) respectively with the 2nd round steel (7) one end is welded and fixed, and keeps the 3rd round steel (12) vertical with the 2nd steel pipe (5), and the other end of two the 2nd round steel (7) is respectively and bar (8) one end is welded and fixed, and keeps bar parallel with the 1st round steel (6);
(2) heating installation is placed on wall-hanging heating installation frame
Heating installation is heater, heater diameter 300mm, 400mm long, and heater is shelved on two the 2nd round steel (7), keeps off Bar (8) prevents heater from skidding off heating installation bracket in the 2nd round steel (7) end;
B, the heat preservation of furnace shell hole is blocked
There are furnace roller hole, burner hole, radiation pore and manhole in furnace shell outer wall two sides, to keep construction environment temperature in furnace, to hole Carry out temporary plugging comprising the steps of:
(1) furnace shell side wall has band steel reinforcement, and furnace shell side wall is divided into many grid, is cut into appropriately sized closure using yellow plate paper Furnace roller hole, burner hole, radiation pore within the scope of grid;
(2) for the manhole of furnace shell side in addition to leaving necessary construction personnel's inlet and outlet, remaining piles up closure using manhole brick;
(3) stove both ends inlet seal room, exit seal room furnace using cloth door curtain block, facilitate construction personnel and build goods and materials into Out;
(4) a thermometer is hung every 20m long in furnace, observes in-furnace temperature at any time;
(5) sequence of construction is adjusted, furnace inside holding is reinforced
Brickwork design sequence: 1. surveying setting-out, 2. side wall is laid bricks, 3. makes furnace roof module or is set up arch mould, 4. builds furnace roof brick, 5. Spread bottom brick, 6. demoulding cleaning brickwork joint gap;Bottom brick will be 5. spread in practice of construction to shift to an earlier date, and first be laid with furnace bottom fibre module and 2 layers Bottom brick stays last surface layer that wouldn't be laid with, and yellow plate paper protection is laid on bottom brick, furnace roof brick of then constructing again, with In-furnace temperature can more preferably be kept;
(6) brickwork using segmentation build, every 50m be one section, primary reformer build after rearwards promote, and by heater with Move backward, before built part and retain heater and keep furnace temperature.
2. large size normalizing furnace winter brickwork method as described in claim 1, which is characterized in that the 1st steel plate (3) and the 2nd The thickness of steel plate (4) >=6mm.
3. large size normalizing furnace winter brickwork method as described in claim 1, which is characterized in that bolt (2) specification is >= M12 bolt.
4. large size normalizing furnace winter brickwork method as described in claim 1, which is characterized in that the round steel diameter >=10mm.
5. large size normalizing furnace winter brickwork method as described in claim 1, which is characterized in that the heater is in every 50m long Normalizing furnace is apart from eight heaters of interior installation.
6. large size normalizing furnace winter brickwork method as described in claim 1, which is characterized in that the yellow plate paper is refractory material Outer packing.
CN201610553172.0A 2016-07-14 2016-07-14 Large-scale normalizing furnace winter brickwork method Active CN107621171B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610553172.0A CN107621171B (en) 2016-07-14 2016-07-14 Large-scale normalizing furnace winter brickwork method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610553172.0A CN107621171B (en) 2016-07-14 2016-07-14 Large-scale normalizing furnace winter brickwork method

Publications (2)

Publication Number Publication Date
CN107621171A CN107621171A (en) 2018-01-23
CN107621171B true CN107621171B (en) 2019-04-23

Family

ID=61087174

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610553172.0A Active CN107621171B (en) 2016-07-14 2016-07-14 Large-scale normalizing furnace winter brickwork method

Country Status (1)

Country Link
CN (1) CN107621171B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10232091A (en) * 1997-02-18 1998-09-02 Nkk Corp Board pushing device for flame spray repairing of penetrated damaged part of carbonizing chamber for coke oven
CN102269522A (en) * 2011-06-28 2011-12-07 南京钢铁股份有限公司 Building process of furnace bottom of electric furnace
CN103822466A (en) * 2012-11-19 2014-05-28 丹阳市江南工业炉有限公司 Buried-type large-scale pit furnace insulation device
CN205241751U (en) * 2015-12-28 2016-05-18 南阳汉冶特钢有限公司 Novel normalizing furnace

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10232091A (en) * 1997-02-18 1998-09-02 Nkk Corp Board pushing device for flame spray repairing of penetrated damaged part of carbonizing chamber for coke oven
CN102269522A (en) * 2011-06-28 2011-12-07 南京钢铁股份有限公司 Building process of furnace bottom of electric furnace
CN103822466A (en) * 2012-11-19 2014-05-28 丹阳市江南工业炉有限公司 Buried-type large-scale pit furnace insulation device
CN205241751U (en) * 2015-12-28 2016-05-18 南阳汉冶特钢有限公司 Novel normalizing furnace

Also Published As

Publication number Publication date
CN107621171A (en) 2018-01-23

Similar Documents

Publication Publication Date Title
CN106246209B (en) A kind of tunnel inner lining concrete insulated curing constructing device and its construction method
CN106592430A (en) Cast-in-place winter construction method for hanging basket cantilever
CN104775833B (en) A kind of tunnel in cold area anti-freezing and heat-insulating system and anti-freezing and heat-insulating construction method
CN104976894B (en) A kind of industrial furnace integral module structure and method of construction
CN206111210U (en) Freeze proof device of long tunnel concrete in winter of cold area heat preservation
CN107621171B (en) Large-scale normalizing furnace winter brickwork method
CN106368722A (en) Freezing prevention, thermal insulation and fire prevention integrated facility for tunnel in cold region
CN203501300U (en) Carbon fiber floor heating device
CN105065916A (en) Heat release structure of high-temperature oil conveying pipeline
CN103727791B (en) A kind of modular construction of industrial furnace radiant section
CN204879457U (en) High temperature oil pipeline's exothermic structure
CN204960967U (en) High height above sea level is ventilation intensification system for severe cold district tunnel construction
CN206220981U (en) A kind of tunnel in cold area anti-freezing and heat-insulating and the integrated facility of fire prevention
CN205917728U (en) Arched cross -section steel buckled plate city utility tunnel
CN109058663A (en) Pattern low energy consumption long heat transport net is slided in a kind of
CN104406007A (en) Vacuum heat-insulating steam-conveying pipeline
CN212358000U (en) Be applied to portable equipment of curing by vaporization of north highway bridge bent cap winter construction
KR20090008991A (en) Device for curing and heating for concrete lining form of tunnel
CN104120217B (en) Assembly type thermal treatment heating furnace and constructing method thereof
CN102383398A (en) Grouting and venting system of roller compacted concrete dam inducing joint seam and construction technology thereof
CN206177007U (en) Cracking furnace tube normal position coating processing heat treatment furnace
CN203309998U (en) Steel external protecting prefabricated insulating double pipeline installation structure
CN106403599B (en) Cracking furnace pipe in-situ TEM processing and heat treatment furnace
CN205917730U (en) Tubular cross section steel buckled plate city utility tunnel
CN204960966U (en) High height above sea level is ventilation heating pipe for severe cold district tunnel construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant