CN107612137A - A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system - Google Patents
A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system Download PDFInfo
- Publication number
- CN107612137A CN107612137A CN201711075627.3A CN201711075627A CN107612137A CN 107612137 A CN107612137 A CN 107612137A CN 201711075627 A CN201711075627 A CN 201711075627A CN 107612137 A CN107612137 A CN 107612137A
- Authority
- CN
- China
- Prior art keywords
- station
- service
- power
- transformer
- factory
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The present invention relates to a kind of high reliability pressurized-water reactor nuclear power plant station service electric power system.Including main power source, off-site auxiliary power source, on-site power outside 500kV power networks, factory;The 500kV power networks are powered by 500kV step-up transformers to station-service electric load;Main power source includes generator, station-service Working transformer outside the factory, and the generator is powered by station-service Working transformer to station-service electric load;The off-site auxiliary power source includes station-service auxiliary transformer, and the off-site auxiliary power source is powered from 220kV power networks by station-service auxiliary transformer to station-service electric load;The on-site power includes transformer in diesel-driven generator, factory, and the diesel-driven generator is powered by transformer in factory to station-service electric load.The present invention disclosure satisfy that superfine important power consumers possess three-way power condition of power supply.
Description
Technical field
The present invention relates to a kind of high reliability pressurized-water reactor nuclear power plant station service electric power system.
Background technology
Traditional People's Republic of China's core professional standard《Pressurized-water reactor nuclear power plant station service electrical system design criteria》NB/
T20051-2011 proposes specific design criterion to the AC power supply system of pressurized-water reactor nuclear power plant station service:
(1)Compressed water reactor nuclear power station power use system should include the physically independent off-site power being connected with high-voltage fence of two-way(One
Road is main power source outside factory, and another way is off-site auxiliary power source);Each power supply should be able to make all station-service equipments by its power supply
It can be further accelerated or start simultaneously when being switched to another power supply from a power supply.
(2)The on-site power being made up of two diesel generating sets of two-way independence is set for each monoblock.
Main power source outside factory:There is provided by transmission line of electricity outside factory, station-service equipment is by being connected to generator end breaker and main transformer
Between the power supply of station-service Working transformer, main power source can still be powered to station-service equipment outside factory during monoblock is stopped transport.
Off-site auxiliary power source:For Shuan Dui power plant, including circuit and by the line outside factory unrelated with transmission line of electricity all the way
Two auxiliary transformers of road parallel operation.Off-site auxiliary power source is that a pair of units share.
On-site power:Each monoblock is provided with the diesel generating set of two independent energy automatic starts.
Nuclear power plant's exchange house-service equipment is divided by its function as four classes:First, unit station-service equipment;Second, standing station-service is set
It is standby;Third, emergent station-service equipment, fourth, two monoblocks are public and plant area's electrical equipment.Wherein to reliability requirement highest
It is emergent station-service equipment, including safe level(1E)Electrical equipment and the station-service equipment for ensureing main equipment safety, wherein safe level
(1E)Electrical equipment is used for preventing, limiting, reducing the leakage of radioactive substance and alleviates damage sequence.Emergent station-service equipment is general
Powered by main power source outside factory, when main power source powers off outside factory, it is necessary to which off-site auxiliary power source is powered, when off-site power loses,
Need to be by the diesel-electric set electric supply of corresponding safe level station-service equipment series;
Electricity prison [2008] No. 43 texts of safety《On strengthening important power consumers power supply and the emergency power sources of self-preparing monitor configured pipe
The opinion of reason》It is required that:Superfine important power consumers possess three-way power condition of power supply, and two-way power supply therein should come from two
Different transformer stations, when any two-way power failure, three-way power can guarantee that independent normal power supply.
The reliable power supply of Nuclear Power Plant electricity consumption is one of factor that nuclear power station is capable of safe and stable operation most critical.2011
After Fukushima, Japan nuclear power plant accident, countries in the world are all improved to nuclear plant safety, especially emergent station-service equipment security
Requirement.Power monitoring department of China, which has been distinctly claimed nuclear power station service power, should meet that the power supply of superfine important power consumers will
Ask(Such as《On assigning notice-Fujian electricity prison safety (2011) 94 of CNNC Fujian Nuclear Power Co., Ltd.'s electric power safety supervise and examine opinion
Number》It is required that Fuqing nuclear power station service power should meet the power reguirements of superfine important power consumers).Superfine important power consumers tool
Standby three-way power condition of power supply, safety standard are higher than《Pressurized-water reactor nuclear power plant station service electrical system design criteria》NB/T20051-2011
It is required that(The physically independent off-site power being connected with high-voltage fence of Nuclear Power Plant electricity consumption at least two-way, all the way to be main outside factory
Power supply, another way are off-site auxiliary power source).
The large nuclear power station that China has gone into operation at present generally by the electric power that unit is sent by transformer boost to 500 kilovolts
After access power transmission network, by design standard, generally require more than 500 KVs 2 return, typically access two different 500 kilovolt
Transformer station.In addition, also configure 220 kilovolts of auxiliary substations, 220 KVs 1 are set to return or 2 times, access power network 220 kilovolts
Transformer station.
To make Nuclear Power Plant electricity system possess three-way power condition of power supply, the common practice of China's nuclear power station is auxiliary outside factory
Help power supply to be designed by 2 road independent loops, make the station-service electric forming three-way power of each nuclear power generating sets(All the way to be defeated outside factory
Electric line is powered through unit boosting main transformer, then through station-service Working transformer;Another two-way is the two-way unrelated with transmission line of electricity
Circuit and two auxiliary transformers by the line powering outside factory).This method exists《Pressurized-water reactor nuclear power plant station service electrical system is set
Count criterion》On the basis of to add be all the way off-site auxiliary power source, it is two-way to make off-site auxiliary power source increase, although meeting superfine
The power reguirements of important power consumers, but shortcoming is to need increase by one to return, from circuit outside different factories of transformer station, to add and build
If difficulty and construction investment.
China's major part nuclear power is respectively positioned on coastal area, and wherein most is located remotely from the remote edge of populated area again
Sea region, build the difficulty in terms of new transmission line of electricity has line corridor.With Fujian Province's large nuclear power station(Abbreviation Y nuclear powers
Stand)Exemplified by, the nuclear power is building 4 million kilowatt nuclear power units, has gone into operation 2, has built 500 KV transmission lines 4 and has returned,
Pass through two passways for transmitting electricity(Each passage 2 returns 500 KVs)Two 500 different kv substations are accessed, have built 220
Kilovolt auxiliary substation one, plans twice 220 kilovolts of off-site auxiliary power sources, two different 220 kilovolt power transformations outside factory
Stand, but because line construction is obstructed, only build up at present 1 time, cause the station service only 2 road power supplys of each nuclear power generating sets, nothing
Method meets the power reguirements of superfine important power consumers.
The content of the invention
It is an object of the invention to provide a kind of high reliability pressurized-water reactor nuclear power plant station service electric power system, spy disclosure satisfy that
Level important power consumers possess three-way power condition of power supply.
To achieve the above object, the technical scheme is that:A kind of high reliability pressurized-water reactor nuclear power plant station service power supply
Main power source, off-site auxiliary power source, on-site power outside system, including 500kV power networks, factory;The 500kV power networks pass through 500kV liters
Pressure transformer is powered to station-service electric load;Main power source includes generator, station-service Working transformer outside the factory, and the generator leads to
Station-service Working transformer is crossed to power to station-service electric load;The off-site auxiliary power source includes station-service auxiliary transformer, outside the factory
Accessory power supply is powered from 220kV power networks by station-service auxiliary transformer to station-service electric load;The on-site power is sent out including diesel oil
Transformer in motor, factory, the diesel-driven generator are powered by transformer in factory to station-service electric load.
In an embodiment of the present invention, main power source also includes being used to realize generator and station-service Working transformer outside the factory
The generator outlet lead wire of connection, for realizing that station-service Working transformer is the station-service Working transformer that station-service electric load is powered
Export lead wire.
In an embodiment of the present invention, main power source also includes 500kV buses and 500kV outlets, station-service work outside the factory
Transformer outlet lead wire is connected to station-service electric load by 500kV buses, 500kV outlets.
In an embodiment of the present invention, the generator is two, and the generator outlet lead wire is two, the factory
It it is 4 with Working transformer, station-service Working transformer outlet lead wire is 8, and the 500kV buses are two, described
500kV outlets are 8.
In an embodiment of the present invention, the off-site auxiliary power source includes station-service auxiliary transformer outlet lead wire, 220kV
Bus and 220kV outlets, house transformer export lead wire and powered by 220kV buses and 220kV outlets for station-service electric load.
In an embodiment of the present invention, the station-service auxiliary transformer is two, and the station-service auxiliary transformer outlet is drawn
Wiring is two, and the 220kV buses are one, and the 220kV outlets are one.
Compared to prior art, the invention has the advantages that:The present invention is applied to transmit electricity outside PWR nuclear power plant
Circuit accesses the occasion of two 500 different kv substations, and after the system, 220 kilovolts of off-site auxiliary power source circuits are only
Need to build one time, it is not necessary to " superfine important power consumers possess three-way power condition of power supply " can be met two times, avoid building
If second time 220 kilovolts of off-site auxiliary power source circuit, reduce line construction investment, suitable for remoteness, build auxiliary outside factory
Help the big occasion of power circuit difficulty.
Brief description of the drawings
Fig. 1 is high reliability pressurized-water reactor nuclear power plant station service electric power system schematic diagram of the present invention.
Embodiment
Below in conjunction with the accompanying drawings, technical scheme is specifically described.
As shown in figure 1, a kind of high reliability pressurized-water reactor nuclear power plant station service electric power system of the present invention, including 500kV power networks,
Main power source, off-site auxiliary power source, on-site power outside factory;The 500kV power networks are by 500kV step-up transformers to station-service electric load
Power supply;Main power source includes generator, station-service Working transformer outside the factory, and the generator is by station-service Working transformer to factory
Power load is powered;The off-site auxiliary power source includes station-service auxiliary transformer, and the off-site auxiliary power source is led to by 220kV power networks
Station-service auxiliary transformer is crossed to power to station-service electric load;The on-site power includes transformer in diesel-driven generator, factory, the bavin
Fry dried food ingredients motor is powered by transformer in factory to station-service electric load.
Main power source also includes being used to realize that generator draws with the generator outlet that station-service Working transformer is connected outside the factory
Wiring, for realizing that station-service Working transformer exports lead wire for the station-service Working transformer of station-service electric load power supply.The factory
Outer main power source also includes 500kV buses and 500kV outlets, station-service Working transformer export lead wire by 500kV buses,
500kV outlets are connected to station-service electric load.The generator is two, and the generator outlet lead wire is two, the factory
It it is 4 with Working transformer, station-service Working transformer outlet lead wire is 8, and the 500kV buses are two, described
500kV outlets are 8.
The off-site auxiliary power source includes station-service auxiliary transformer outlet lead wire, 220kV buses and 220kV outlets, factory
With transformer outlet lead wire by 220kV buses and 220kV outlets be station-service electric load power.The station-service auxiliary transformer
For two, station-service auxiliary transformer outlet lead wire is two, and the 220kV buses are one, and the 220kV outlets are
One.
The system is applied to the occasion that the outer transmission line of electricity of PWR nuclear power plant accesses two 500 different kv substations,
After the system, 220 kilovolts of off-site auxiliary power source circuits only need to build one time, it is not necessary to can meet " superfine weight for two times
Power consumer is wanted to possess three-way power condition of power supply ", avoid building second time 220 kilovolts of off-site auxiliary power source circuit, reduce
Line construction is invested, and suitable for remoteness, builds the big occasion of off-site auxiliary power source circuit difficulty.
Above is presently preferred embodiments of the present invention, all changes made according to technical solution of the present invention, caused function are made
During with scope without departing from technical solution of the present invention, protection scope of the present invention is belonged to.
Claims (6)
- A kind of 1. high reliability pressurized-water reactor nuclear power plant station service electric power system, it is characterised in that:Including main outside 500kV power networks, factory Power supply, off-site auxiliary power source, on-site power;The 500kV power networks are powered by 500kV step-up transformers to station-service electric load; Main power source includes generator, station-service Working transformer outside the factory, and the generator is by station-service Working transformer to station service Load is powered;The off-site auxiliary power source includes station-service auxiliary transformer, and the off-site auxiliary power source passes through factory by 220kV power networks Powered with auxiliary transformer to station-service electric load;The on-site power includes transformer in diesel-driven generator, factory, the diesel oil hair Motor is powered by transformer in factory to station-service electric load.
- A kind of 2. high reliability pressurized-water reactor nuclear power plant station service electric power system according to claim 1, it is characterised in that:Institute Stating main power source outside factory also includes being used to realize the generator outlet lead wire that generator is connected with station-service Working transformer, for reality Existing station-service Working transformer is that the station-service Working transformer of station-service electric load power supply exports lead wire.
- A kind of 3. high reliability pressurized-water reactor nuclear power plant station service electric power system according to claim 2, it is characterised in that:Institute Stating main power source outside factory also includes 500kV buses and 500kV outlets, station-service Working transformer export lead wire by 500kV buses, 500kV outlets are connected to station-service electric load.
- A kind of 4. high reliability pressurized-water reactor nuclear power plant station service electric power system according to claim 3, it is characterised in that:Institute Generator is stated as two, the generator outlet lead wire is two, and the station-service Working transformer is 4, the station-service work Make transformer outlet lead wire as 8, the 500kV buses are two, and the 500kV outlets are 8.
- A kind of 5. high reliability pressurized-water reactor nuclear power plant station service electric power system according to claim 1, it is characterised in that:Institute Off-site auxiliary power source is stated including station-service auxiliary transformer outlet lead wire, 220kV buses and 220kV outlets, house transformer to go out Mouth lead wire is that station-service electric load is powered by 220kV buses and 220kV outlets.
- A kind of 6. high reliability pressurized-water reactor nuclear power plant station service electric power system according to claim 5, it is characterised in that:Institute Station-service auxiliary transformer is stated as two, station-service auxiliary transformer outlet lead wire is two, and the 220kV buses are one Bar, the 220kV outlets are one.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711075627.3A CN107612137A (en) | 2017-11-06 | 2017-11-06 | A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711075627.3A CN107612137A (en) | 2017-11-06 | 2017-11-06 | A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107612137A true CN107612137A (en) | 2018-01-19 |
Family
ID=61084907
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711075627.3A Pending CN107612137A (en) | 2017-11-06 | 2017-11-06 | A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107612137A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114172261A (en) * | 2021-11-02 | 2022-03-11 | 苏州热工研究院有限公司 | Nuclear power plant emergency power supply system and control method |
CN114336617A (en) * | 2022-01-12 | 2022-04-12 | 中国核电工程有限公司 | Power supply system of nuclear energy heat supply plant |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU736272B2 (en) * | 1997-09-30 | 2001-07-26 | Abb Ab | An electric power plant |
CN203352172U (en) * | 2013-07-25 | 2013-12-18 | 湖南省电力勘测设计院 | Auxiliary power wiring structure for large thermal power plant |
CN203911578U (en) * | 2014-06-19 | 2014-10-29 | 中国电力工程顾问集团西北电力设计院 | Station service power wiring system applied to two-drive-one gas-turbine electric power plant |
CN205753638U (en) * | 2016-07-13 | 2016-11-30 | 贵州北源电力股份有限公司正安牛都电站 | A kind of diesel-driven generator automatic start-stop electric power system |
CN106786545A (en) * | 2017-01-11 | 2017-05-31 | 中国核电工程有限公司 | A kind of public bus bar wiring structure |
-
2017
- 2017-11-06 CN CN201711075627.3A patent/CN107612137A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU736272B2 (en) * | 1997-09-30 | 2001-07-26 | Abb Ab | An electric power plant |
CN203352172U (en) * | 2013-07-25 | 2013-12-18 | 湖南省电力勘测设计院 | Auxiliary power wiring structure for large thermal power plant |
CN203911578U (en) * | 2014-06-19 | 2014-10-29 | 中国电力工程顾问集团西北电力设计院 | Station service power wiring system applied to two-drive-one gas-turbine electric power plant |
CN205753638U (en) * | 2016-07-13 | 2016-11-30 | 贵州北源电力股份有限公司正安牛都电站 | A kind of diesel-driven generator automatic start-stop electric power system |
CN106786545A (en) * | 2017-01-11 | 2017-05-31 | 中国核电工程有限公司 | A kind of public bus bar wiring structure |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114172261A (en) * | 2021-11-02 | 2022-03-11 | 苏州热工研究院有限公司 | Nuclear power plant emergency power supply system and control method |
CN114172261B (en) * | 2021-11-02 | 2023-12-12 | 广东核电合营有限公司 | Nuclear power plant emergency power supply system and control method |
CN114336617A (en) * | 2022-01-12 | 2022-04-12 | 中国核电工程有限公司 | Power supply system of nuclear energy heat supply plant |
CN114336617B (en) * | 2022-01-12 | 2024-02-02 | 中国核电工程有限公司 | Power supply system of nuclear energy heat supply plant |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110277828B (en) | Alternating-current bus rapid backup automatic switching control method based on flexible direct-current distribution network technology | |
CN102447298B (en) | Mobile intelligent direct current power supply device | |
CN110912109A (en) | Low-voltage direct-current power supply and distribution equipment and method | |
CN108173267A (en) | Marine wind electric field and island microgrid joint-monitoring system | |
CN107612137A (en) | A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system | |
CN108792859A (en) | The method and device and system of elevator device power supply are realized based on elevator power supply device | |
CN203554074U (en) | Distributed power generation grid-connected dual-power supply interface apparatus | |
CN208062887U (en) | A kind of control device for the big islet operation of offshore wind generating | |
CN101127453A (en) | A D-UPS power supply system for IDC computer room | |
CN209658908U (en) | A kind of power plant neighbour machine HV auxiliary power s ystem is mutually for system | |
CN209709691U (en) | The alternating current-direct current mixing microgrid framework integrated with distribution transformer rectifier | |
CN208561318U (en) | The device and system of elevator device power supply are realized based on elevator power supply device | |
CN206759143U (en) | Plant standby power supply system | |
CN206481060U (en) | A kind of inverter and box type transformer integration apparatus | |
CN214255721U (en) | System based on diesel generator is high-voltage station-use stand-by power supply | |
CN206237192U (en) | A kind of power communication power-supply system | |
CN214313029U (en) | Wiring structure of gas relay for converter transformer | |
CN102108527B (en) | Method and system for supplying power to large aluminum electrolytic plant | |
CN108462085A (en) | The photovoltaic box-type substation of intelligent interconnection can be achieved | |
CN204905673U (en) | A station service wiring system for thermal power factory | |
CN209389768U (en) | Simple type emergency power supply Quick access device | |
CN208316308U (en) | The grid-connected booster stations system of integrated photovoltaic | |
CN208767849U (en) | The offshore boosting station field electricity system of ring connection | |
CN207149982U (en) | The safety interlock system of photovoltaic DC field | |
CN112967904A (en) | Wiring structure of gas relay for converter transformer and signal output method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180119 |