CN107612137A - A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system - Google Patents

A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system Download PDF

Info

Publication number
CN107612137A
CN107612137A CN201711075627.3A CN201711075627A CN107612137A CN 107612137 A CN107612137 A CN 107612137A CN 201711075627 A CN201711075627 A CN 201711075627A CN 107612137 A CN107612137 A CN 107612137A
Authority
CN
China
Prior art keywords
station
service
power
transformer
factory
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711075627.3A
Other languages
Chinese (zh)
Inventor
杜翼
杨晓东
林章岁
林红阳
蒋朋博
吴威
胡臻达
林毅
柯圣舟
黎萌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Economic and Technological Research Institute of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201711075627.3A priority Critical patent/CN107612137A/en
Publication of CN107612137A publication Critical patent/CN107612137A/en
Pending legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to a kind of high reliability pressurized-water reactor nuclear power plant station service electric power system.Including main power source, off-site auxiliary power source, on-site power outside 500kV power networks, factory;The 500kV power networks are powered by 500kV step-up transformers to station-service electric load;Main power source includes generator, station-service Working transformer outside the factory, and the generator is powered by station-service Working transformer to station-service electric load;The off-site auxiliary power source includes station-service auxiliary transformer, and the off-site auxiliary power source is powered from 220kV power networks by station-service auxiliary transformer to station-service electric load;The on-site power includes transformer in diesel-driven generator, factory, and the diesel-driven generator is powered by transformer in factory to station-service electric load.The present invention disclosure satisfy that superfine important power consumers possess three-way power condition of power supply.

Description

A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system
Technical field
The present invention relates to a kind of high reliability pressurized-water reactor nuclear power plant station service electric power system.
Background technology
Traditional People's Republic of China's core professional standard《Pressurized-water reactor nuclear power plant station service electrical system design criteria》NB/ T20051-2011 proposes specific design criterion to the AC power supply system of pressurized-water reactor nuclear power plant station service:
(1)Compressed water reactor nuclear power station power use system should include the physically independent off-site power being connected with high-voltage fence of two-way(One Road is main power source outside factory, and another way is off-site auxiliary power source);Each power supply should be able to make all station-service equipments by its power supply It can be further accelerated or start simultaneously when being switched to another power supply from a power supply.
(2)The on-site power being made up of two diesel generating sets of two-way independence is set for each monoblock.
Main power source outside factory:There is provided by transmission line of electricity outside factory, station-service equipment is by being connected to generator end breaker and main transformer Between the power supply of station-service Working transformer, main power source can still be powered to station-service equipment outside factory during monoblock is stopped transport.
Off-site auxiliary power source:For Shuan Dui power plant, including circuit and by the line outside factory unrelated with transmission line of electricity all the way Two auxiliary transformers of road parallel operation.Off-site auxiliary power source is that a pair of units share.
On-site power:Each monoblock is provided with the diesel generating set of two independent energy automatic starts.
Nuclear power plant's exchange house-service equipment is divided by its function as four classes:First, unit station-service equipment;Second, standing station-service is set It is standby;Third, emergent station-service equipment, fourth, two monoblocks are public and plant area's electrical equipment.Wherein to reliability requirement highest It is emergent station-service equipment, including safe level(1E)Electrical equipment and the station-service equipment for ensureing main equipment safety, wherein safe level (1E)Electrical equipment is used for preventing, limiting, reducing the leakage of radioactive substance and alleviates damage sequence.Emergent station-service equipment is general Powered by main power source outside factory, when main power source powers off outside factory, it is necessary to which off-site auxiliary power source is powered, when off-site power loses, Need to be by the diesel-electric set electric supply of corresponding safe level station-service equipment series;
Electricity prison [2008] No. 43 texts of safety《On strengthening important power consumers power supply and the emergency power sources of self-preparing monitor configured pipe The opinion of reason》It is required that:Superfine important power consumers possess three-way power condition of power supply, and two-way power supply therein should come from two Different transformer stations, when any two-way power failure, three-way power can guarantee that independent normal power supply.
The reliable power supply of Nuclear Power Plant electricity consumption is one of factor that nuclear power station is capable of safe and stable operation most critical.2011 After Fukushima, Japan nuclear power plant accident, countries in the world are all improved to nuclear plant safety, especially emergent station-service equipment security Requirement.Power monitoring department of China, which has been distinctly claimed nuclear power station service power, should meet that the power supply of superfine important power consumers will Ask(Such as《On assigning notice-Fujian electricity prison safety (2011) 94 of CNNC Fujian Nuclear Power Co., Ltd.'s electric power safety supervise and examine opinion Number》It is required that Fuqing nuclear power station service power should meet the power reguirements of superfine important power consumers).Superfine important power consumers tool Standby three-way power condition of power supply, safety standard are higher than《Pressurized-water reactor nuclear power plant station service electrical system design criteria》NB/T20051-2011 It is required that(The physically independent off-site power being connected with high-voltage fence of Nuclear Power Plant electricity consumption at least two-way, all the way to be main outside factory Power supply, another way are off-site auxiliary power source).
The large nuclear power station that China has gone into operation at present generally by the electric power that unit is sent by transformer boost to 500 kilovolts After access power transmission network, by design standard, generally require more than 500 KVs 2 return, typically access two different 500 kilovolt Transformer station.In addition, also configure 220 kilovolts of auxiliary substations, 220 KVs 1 are set to return or 2 times, access power network 220 kilovolts Transformer station.
To make Nuclear Power Plant electricity system possess three-way power condition of power supply, the common practice of China's nuclear power station is auxiliary outside factory Help power supply to be designed by 2 road independent loops, make the station-service electric forming three-way power of each nuclear power generating sets(All the way to be defeated outside factory Electric line is powered through unit boosting main transformer, then through station-service Working transformer;Another two-way is the two-way unrelated with transmission line of electricity Circuit and two auxiliary transformers by the line powering outside factory).This method exists《Pressurized-water reactor nuclear power plant station service electrical system is set Count criterion》On the basis of to add be all the way off-site auxiliary power source, it is two-way to make off-site auxiliary power source increase, although meeting superfine The power reguirements of important power consumers, but shortcoming is to need increase by one to return, from circuit outside different factories of transformer station, to add and build If difficulty and construction investment.
China's major part nuclear power is respectively positioned on coastal area, and wherein most is located remotely from the remote edge of populated area again Sea region, build the difficulty in terms of new transmission line of electricity has line corridor.With Fujian Province's large nuclear power station(Abbreviation Y nuclear powers Stand)Exemplified by, the nuclear power is building 4 million kilowatt nuclear power units, has gone into operation 2, has built 500 KV transmission lines 4 and has returned, Pass through two passways for transmitting electricity(Each passage 2 returns 500 KVs)Two 500 different kv substations are accessed, have built 220 Kilovolt auxiliary substation one, plans twice 220 kilovolts of off-site auxiliary power sources, two different 220 kilovolt power transformations outside factory Stand, but because line construction is obstructed, only build up at present 1 time, cause the station service only 2 road power supplys of each nuclear power generating sets, nothing Method meets the power reguirements of superfine important power consumers.
The content of the invention
It is an object of the invention to provide a kind of high reliability pressurized-water reactor nuclear power plant station service electric power system, spy disclosure satisfy that Level important power consumers possess three-way power condition of power supply.
To achieve the above object, the technical scheme is that:A kind of high reliability pressurized-water reactor nuclear power plant station service power supply Main power source, off-site auxiliary power source, on-site power outside system, including 500kV power networks, factory;The 500kV power networks pass through 500kV liters Pressure transformer is powered to station-service electric load;Main power source includes generator, station-service Working transformer outside the factory, and the generator leads to Station-service Working transformer is crossed to power to station-service electric load;The off-site auxiliary power source includes station-service auxiliary transformer, outside the factory Accessory power supply is powered from 220kV power networks by station-service auxiliary transformer to station-service electric load;The on-site power is sent out including diesel oil Transformer in motor, factory, the diesel-driven generator are powered by transformer in factory to station-service electric load.
In an embodiment of the present invention, main power source also includes being used to realize generator and station-service Working transformer outside the factory The generator outlet lead wire of connection, for realizing that station-service Working transformer is the station-service Working transformer that station-service electric load is powered Export lead wire.
In an embodiment of the present invention, main power source also includes 500kV buses and 500kV outlets, station-service work outside the factory Transformer outlet lead wire is connected to station-service electric load by 500kV buses, 500kV outlets.
In an embodiment of the present invention, the generator is two, and the generator outlet lead wire is two, the factory It it is 4 with Working transformer, station-service Working transformer outlet lead wire is 8, and the 500kV buses are two, described 500kV outlets are 8.
In an embodiment of the present invention, the off-site auxiliary power source includes station-service auxiliary transformer outlet lead wire, 220kV Bus and 220kV outlets, house transformer export lead wire and powered by 220kV buses and 220kV outlets for station-service electric load.
In an embodiment of the present invention, the station-service auxiliary transformer is two, and the station-service auxiliary transformer outlet is drawn Wiring is two, and the 220kV buses are one, and the 220kV outlets are one.
Compared to prior art, the invention has the advantages that:The present invention is applied to transmit electricity outside PWR nuclear power plant Circuit accesses the occasion of two 500 different kv substations, and after the system, 220 kilovolts of off-site auxiliary power source circuits are only Need to build one time, it is not necessary to " superfine important power consumers possess three-way power condition of power supply " can be met two times, avoid building If second time 220 kilovolts of off-site auxiliary power source circuit, reduce line construction investment, suitable for remoteness, build auxiliary outside factory Help the big occasion of power circuit difficulty.
Brief description of the drawings
Fig. 1 is high reliability pressurized-water reactor nuclear power plant station service electric power system schematic diagram of the present invention.
Embodiment
Below in conjunction with the accompanying drawings, technical scheme is specifically described.
As shown in figure 1, a kind of high reliability pressurized-water reactor nuclear power plant station service electric power system of the present invention, including 500kV power networks, Main power source, off-site auxiliary power source, on-site power outside factory;The 500kV power networks are by 500kV step-up transformers to station-service electric load Power supply;Main power source includes generator, station-service Working transformer outside the factory, and the generator is by station-service Working transformer to factory Power load is powered;The off-site auxiliary power source includes station-service auxiliary transformer, and the off-site auxiliary power source is led to by 220kV power networks Station-service auxiliary transformer is crossed to power to station-service electric load;The on-site power includes transformer in diesel-driven generator, factory, the bavin Fry dried food ingredients motor is powered by transformer in factory to station-service electric load.
Main power source also includes being used to realize that generator draws with the generator outlet that station-service Working transformer is connected outside the factory Wiring, for realizing that station-service Working transformer exports lead wire for the station-service Working transformer of station-service electric load power supply.The factory Outer main power source also includes 500kV buses and 500kV outlets, station-service Working transformer export lead wire by 500kV buses, 500kV outlets are connected to station-service electric load.The generator is two, and the generator outlet lead wire is two, the factory It it is 4 with Working transformer, station-service Working transformer outlet lead wire is 8, and the 500kV buses are two, described 500kV outlets are 8.
The off-site auxiliary power source includes station-service auxiliary transformer outlet lead wire, 220kV buses and 220kV outlets, factory With transformer outlet lead wire by 220kV buses and 220kV outlets be station-service electric load power.The station-service auxiliary transformer For two, station-service auxiliary transformer outlet lead wire is two, and the 220kV buses are one, and the 220kV outlets are One.
The system is applied to the occasion that the outer transmission line of electricity of PWR nuclear power plant accesses two 500 different kv substations, After the system, 220 kilovolts of off-site auxiliary power source circuits only need to build one time, it is not necessary to can meet " superfine weight for two times Power consumer is wanted to possess three-way power condition of power supply ", avoid building second time 220 kilovolts of off-site auxiliary power source circuit, reduce Line construction is invested, and suitable for remoteness, builds the big occasion of off-site auxiliary power source circuit difficulty.
Above is presently preferred embodiments of the present invention, all changes made according to technical solution of the present invention, caused function are made During with scope without departing from technical solution of the present invention, protection scope of the present invention is belonged to.

Claims (6)

  1. A kind of 1. high reliability pressurized-water reactor nuclear power plant station service electric power system, it is characterised in that:Including main outside 500kV power networks, factory Power supply, off-site auxiliary power source, on-site power;The 500kV power networks are powered by 500kV step-up transformers to station-service electric load; Main power source includes generator, station-service Working transformer outside the factory, and the generator is by station-service Working transformer to station service Load is powered;The off-site auxiliary power source includes station-service auxiliary transformer, and the off-site auxiliary power source passes through factory by 220kV power networks Powered with auxiliary transformer to station-service electric load;The on-site power includes transformer in diesel-driven generator, factory, the diesel oil hair Motor is powered by transformer in factory to station-service electric load.
  2. A kind of 2. high reliability pressurized-water reactor nuclear power plant station service electric power system according to claim 1, it is characterised in that:Institute Stating main power source outside factory also includes being used to realize the generator outlet lead wire that generator is connected with station-service Working transformer, for reality Existing station-service Working transformer is that the station-service Working transformer of station-service electric load power supply exports lead wire.
  3. A kind of 3. high reliability pressurized-water reactor nuclear power plant station service electric power system according to claim 2, it is characterised in that:Institute Stating main power source outside factory also includes 500kV buses and 500kV outlets, station-service Working transformer export lead wire by 500kV buses, 500kV outlets are connected to station-service electric load.
  4. A kind of 4. high reliability pressurized-water reactor nuclear power plant station service electric power system according to claim 3, it is characterised in that:Institute Generator is stated as two, the generator outlet lead wire is two, and the station-service Working transformer is 4, the station-service work Make transformer outlet lead wire as 8, the 500kV buses are two, and the 500kV outlets are 8.
  5. A kind of 5. high reliability pressurized-water reactor nuclear power plant station service electric power system according to claim 1, it is characterised in that:Institute Off-site auxiliary power source is stated including station-service auxiliary transformer outlet lead wire, 220kV buses and 220kV outlets, house transformer to go out Mouth lead wire is that station-service electric load is powered by 220kV buses and 220kV outlets.
  6. A kind of 6. high reliability pressurized-water reactor nuclear power plant station service electric power system according to claim 5, it is characterised in that:Institute Station-service auxiliary transformer is stated as two, station-service auxiliary transformer outlet lead wire is two, and the 220kV buses are one Bar, the 220kV outlets are one.
CN201711075627.3A 2017-11-06 2017-11-06 A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system Pending CN107612137A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711075627.3A CN107612137A (en) 2017-11-06 2017-11-06 A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711075627.3A CN107612137A (en) 2017-11-06 2017-11-06 A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system

Publications (1)

Publication Number Publication Date
CN107612137A true CN107612137A (en) 2018-01-19

Family

ID=61084907

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711075627.3A Pending CN107612137A (en) 2017-11-06 2017-11-06 A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system

Country Status (1)

Country Link
CN (1) CN107612137A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114172261A (en) * 2021-11-02 2022-03-11 苏州热工研究院有限公司 Nuclear power plant emergency power supply system and control method
CN114336617A (en) * 2022-01-12 2022-04-12 中国核电工程有限公司 Power supply system of nuclear energy heat supply plant

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU736272B2 (en) * 1997-09-30 2001-07-26 Abb Ab An electric power plant
CN203352172U (en) * 2013-07-25 2013-12-18 湖南省电力勘测设计院 Auxiliary power wiring structure for large thermal power plant
CN203911578U (en) * 2014-06-19 2014-10-29 中国电力工程顾问集团西北电力设计院 Station service power wiring system applied to two-drive-one gas-turbine electric power plant
CN205753638U (en) * 2016-07-13 2016-11-30 贵州北源电力股份有限公司正安牛都电站 A kind of diesel-driven generator automatic start-stop electric power system
CN106786545A (en) * 2017-01-11 2017-05-31 中国核电工程有限公司 A kind of public bus bar wiring structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU736272B2 (en) * 1997-09-30 2001-07-26 Abb Ab An electric power plant
CN203352172U (en) * 2013-07-25 2013-12-18 湖南省电力勘测设计院 Auxiliary power wiring structure for large thermal power plant
CN203911578U (en) * 2014-06-19 2014-10-29 中国电力工程顾问集团西北电力设计院 Station service power wiring system applied to two-drive-one gas-turbine electric power plant
CN205753638U (en) * 2016-07-13 2016-11-30 贵州北源电力股份有限公司正安牛都电站 A kind of diesel-driven generator automatic start-stop electric power system
CN106786545A (en) * 2017-01-11 2017-05-31 中国核电工程有限公司 A kind of public bus bar wiring structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114172261A (en) * 2021-11-02 2022-03-11 苏州热工研究院有限公司 Nuclear power plant emergency power supply system and control method
CN114172261B (en) * 2021-11-02 2023-12-12 广东核电合营有限公司 Nuclear power plant emergency power supply system and control method
CN114336617A (en) * 2022-01-12 2022-04-12 中国核电工程有限公司 Power supply system of nuclear energy heat supply plant
CN114336617B (en) * 2022-01-12 2024-02-02 中国核电工程有限公司 Power supply system of nuclear energy heat supply plant

Similar Documents

Publication Publication Date Title
CN110277828B (en) Alternating-current bus rapid backup automatic switching control method based on flexible direct-current distribution network technology
CN102447298B (en) Mobile intelligent direct current power supply device
CN110912109A (en) Low-voltage direct-current power supply and distribution equipment and method
CN108173267A (en) Marine wind electric field and island microgrid joint-monitoring system
CN107612137A (en) A kind of high reliability pressurized-water reactor nuclear power plant station service electric power system
CN108792859A (en) The method and device and system of elevator device power supply are realized based on elevator power supply device
CN203554074U (en) Distributed power generation grid-connected dual-power supply interface apparatus
CN208062887U (en) A kind of control device for the big islet operation of offshore wind generating
CN101127453A (en) A D-UPS power supply system for IDC computer room
CN209658908U (en) A kind of power plant neighbour machine HV auxiliary power s ystem is mutually for system
CN209709691U (en) The alternating current-direct current mixing microgrid framework integrated with distribution transformer rectifier
CN208561318U (en) The device and system of elevator device power supply are realized based on elevator power supply device
CN206759143U (en) Plant standby power supply system
CN206481060U (en) A kind of inverter and box type transformer integration apparatus
CN214255721U (en) System based on diesel generator is high-voltage station-use stand-by power supply
CN206237192U (en) A kind of power communication power-supply system
CN214313029U (en) Wiring structure of gas relay for converter transformer
CN102108527B (en) Method and system for supplying power to large aluminum electrolytic plant
CN108462085A (en) The photovoltaic box-type substation of intelligent interconnection can be achieved
CN204905673U (en) A station service wiring system for thermal power factory
CN209389768U (en) Simple type emergency power supply Quick access device
CN208316308U (en) The grid-connected booster stations system of integrated photovoltaic
CN208767849U (en) The offshore boosting station field electricity system of ring connection
CN207149982U (en) The safety interlock system of photovoltaic DC field
CN112967904A (en) Wiring structure of gas relay for converter transformer and signal output method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180119