CN107575338B - The two-way dual disaster tolerance control system of turbine-generator units and its method - Google Patents

The two-way dual disaster tolerance control system of turbine-generator units and its method Download PDF

Info

Publication number
CN107575338B
CN107575338B CN201710771494.7A CN201710771494A CN107575338B CN 107575338 B CN107575338 B CN 107575338B CN 201710771494 A CN201710771494 A CN 201710771494A CN 107575338 B CN107575338 B CN 107575338B
Authority
CN
China
Prior art keywords
unit
hydraulic turbine
adjustment
control unit
field excitation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710771494.7A
Other languages
Chinese (zh)
Other versions
CN107575338A (en
Inventor
陈开宇
汪晓强
郭忠慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN LIDE AUTOMATION EQUIPMENT CO LTD
Original Assignee
FUJIAN LIDE AUTOMATION EQUIPMENT CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN LIDE AUTOMATION EQUIPMENT CO LTD filed Critical FUJIAN LIDE AUTOMATION EQUIPMENT CO LTD
Priority to CN201710771494.7A priority Critical patent/CN107575338B/en
Publication of CN107575338A publication Critical patent/CN107575338A/en
Application granted granted Critical
Publication of CN107575338B publication Critical patent/CN107575338B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Control Of Eletrric Generators (AREA)

Abstract

The present invention discloses the two-way dual disaster tolerance control system of turbine-generator units and its method, the system comprises adjustment of field excitation units, demagnetization control mechanism and hydraulic turbine automatic control unit, adjustment of field excitation unit is connected by its master control circuit and controls demagnetization control mechanism, adjustment of field excitation unit connects by its backup control line road and controls hydraulic turbine control mechanism, hydraulic turbine automatic control unit is connected by its master control circuit and controls hydraulic turbine control mechanism, hydraulic turbine automatic control unit connects by its backup control line road and controls demagnetization control mechanism, mutual high speed communication between adjustment of field excitation unit and hydraulic turbine automatic control unit.Generation control unit of the present invention and excitation con-trol unit close in set of system, both sides are hot standby each other, and when generation control unit failure, excitation con-trol unit is automatically performed system closedown demagnetization process, otherwise when excitation con-trol unit breaks down, generation control unit completes system closedown demagnetization process.

Description

The two-way dual disaster tolerance control system of turbine-generator units and its method
Technical field
The present invention relates to the two-way dual disaster tolerance control system of power generation technical field more particularly to turbine-generator units and Its method.
Background technique
Medium and Small Hydraulic Generator group generallys use two kinds of failure protection techniques in the prior art.One, relay protection is installed Equipment, the voltage and current state of relay protection device real time on-line monitoring electricity generation system, when power-generating control system is out of order generation When the failures such as over-voltage, under-voltage, overcurrent, protection equipment issues separating brake shutdown group command;Two, it using double excitation systems, is set when one For when being out of order, another carries out rapidly excitation con-trol.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide the two-way dual disaster tolerance control systems of turbine-generator units System and its method.
The technical solution adopted by the present invention is that:
The two-way dual disaster tolerance control system of turbine-generator units comprising adjustment of field excitation unit, demagnetization control mechanism and water Turbine automatic control unit, adjustment of field excitation unit connect by its master control circuit and control demagnetization control mechanism, adjustment of field excitation list Member connects and controls hydraulic turbine control mechanism by its backup control line road, and hydraulic turbine automatic control unit passes through its master control circuit Hydraulic turbine control mechanism is connected and controls, hydraulic turbine automatic control unit connects by its backup control line road and controls demagnetization control Mechanism processed, mutual high speed communication between adjustment of field excitation unit and hydraulic turbine automatic control unit.
Further, the hydraulic turbine control mechanism includes breaker, water valve and gate valve control mechanism.
The invention also discloses the two-way dual disaster tolerant control methods of turbine-generator units, applied to the hydrogenerator The two-way dual disaster tolerance control system of group, control method the following steps are included:
1) adjustment of field excitation unit and hydraulic turbine automatic control unit acquire the operation information of turbine-generator units respectively;
2) adjustment of field excitation unit and hydraulic turbine automatic control unit carry out high speed communication, and exchange the operation letter acquired in real time Breath;
3) adjustment of field excitation unit and hydraulic turbine automatic control unit mutually monitor and analyze the operation information of other side's transmission;
4) when adjustment of field excitation unit and hydraulic turbine automatic control unit work normally, adjustment of field excitation unit and the hydraulic turbine Automatic control unit issues corresponding switching on and shutting down control action instruction by respective master control circuit respectively and normally opens to realize Shutdown process completes corresponding relay protection movement;
5) when one of adjustment of field excitation unit or hydraulic turbine automatic control unit break down, then the water of monitoring is corresponded to Turbine automatic control unit or adjustment of field excitation unit enable the adjustment of field excitation unit or water that its backup control line road direction breaks down The control mechanism that turbine automatic control unit is controlled issues action command, completes separating brake and shuts down turbine-generator units work, And record corresponding fault message.
Further, the operation information includes network voltage, set end voltage, generator terminal electric current, revolving speed and opening and closing state.
The invention adopts the above technical scheme, and adjustment of field excitation unit is integrated in set of device and the hydraulic turbine automatically controls list Member.Adjustment of field excitation list and hydraulic turbine automatic control unit are respectively completed to network voltage, set end voltage, generator terminal electric current, revolving speed, divide The information such as "on" position are acquired, while adjustment of field excitation unit and hydraulic turbine automatic control unit carry out high speed communication (one 20ms cycle completes a data interaction), the data of sampling are sent to other side in real time, two units monitor mutually adopting for other side Sample data and operating status.When normal work, adjustment of field excitation unit and hydraulic turbine automatic control unit are respectively completed respective sending Corresponding switching on and shutting down control action instruction completes corresponding relay protection movement to realize normal switching on and shutting down process;Work as monitoring When another unit breaks down, spare control loop is enabled rapidly to corresponding operation mechanism and issues action command, completes separating brake And turbine-generator units work is shut down, and record corresponding fault message, immediately, efficiently ensure hydrogenerator automation control System processed is reliable, is safely operated, and provides effective analysis foundation for trouble hunting.
Generation control unit of the present invention and excitation con-trol unit close in set of system, and both sides are hot standby each other, when power generation is controlled When cell failure processed, excitation con-trol unit is automatically performed system closedown demagnetization process, otherwise when excitation con-trol unit breaks down When, generation control unit completes system closedown demagnetization process.
The present invention effectively meets the needs of turbine-generator units automatic control system two-way dual disaster tolerance, accomplishes system Simple at low cost, response timeliness height, protection reliability are high.
Detailed description of the invention
The present invention is described in further details below in conjunction with the drawings and specific embodiments;
Fig. 1 is the structural schematic diagram of the two-way dual disaster tolerance control system of turbine-generator units of the present invention;
Fig. 2 is the flow diagram of the two-way dual disaster tolerant control method of turbine-generator units of the present invention.
Specific embodiment
As shown in Figure 1, the invention discloses the two-way dual disaster tolerance control systems of turbine-generator units comprising adjustment of field excitation Unit, demagnetization control mechanism and hydraulic turbine automatic control unit, adjustment of field excitation unit, which is connected and controlled by its master control circuit, to go out Magnetic control mechanism, adjustment of field excitation unit connect by its backup control line road and control hydraulic turbine control mechanism, and the hydraulic turbine is automatic Control unit connects by its master control circuit and controls hydraulic turbine control mechanism, and hydraulic turbine automatic control unit passes through its spare control Connection processed simultaneously controls demagnetization control mechanism, and mutually high speed is logical between adjustment of field excitation unit and hydraulic turbine automatic control unit News.
Further, the hydraulic turbine control mechanism includes breaker, water valve and gate valve control mechanism.
As shown in Fig. 2, the invention also discloses the two-way dual disaster tolerant control methods of turbine-generator units, applied to described The two-way dual disaster tolerance control system of turbine-generator units, control method the following steps are included:
1) adjustment of field excitation unit and hydraulic turbine automatic control unit acquire the operation information of turbine-generator units respectively;
2) adjustment of field excitation unit and hydraulic turbine automatic control unit carry out high speed communication, and exchange the operation letter acquired in real time Breath;
3) adjustment of field excitation unit and hydraulic turbine automatic control unit mutually monitor and analyze the operation information of other side's transmission;
4) when adjustment of field excitation unit and hydraulic turbine automatic control unit work normally, adjustment of field excitation unit and the hydraulic turbine Automatic control unit issues corresponding switching on and shutting down control action instruction by respective master control circuit respectively and normally opens to realize Shutdown process completes corresponding relay protection movement;
5) when one of adjustment of field excitation unit or hydraulic turbine automatic control unit break down, then the water of monitoring is corresponded to Turbine automatic control unit or adjustment of field excitation unit enable the adjustment of field excitation unit or water that its backup control line road direction breaks down The control mechanism that turbine automatic control unit is controlled issues action command, completes separating brake and shuts down turbine-generator units work, And record corresponding fault message.
Further, the operation information includes network voltage, set end voltage, generator terminal electric current, revolving speed and opening and closing state.
The invention adopts the above technical scheme, and adjustment of field excitation unit is integrated in set of device and the hydraulic turbine automatically controls list Member.Adjustment of field excitation list and hydraulic turbine automatic control unit are respectively completed to network voltage, set end voltage, generator terminal electric current, revolving speed, divide The information such as "on" position are acquired, while adjustment of field excitation unit and hydraulic turbine automatic control unit carry out high speed communication (one 20ms cycle completes a data interaction), the data of sampling are sent to other side in real time, two units monitor mutually adopting for other side Sample data and operating status.When normal work, adjustment of field excitation unit and hydraulic turbine automatic control unit are respectively completed respective sending Corresponding switching on and shutting down control action instruction completes corresponding relay protection movement to realize normal switching on and shutting down process;Work as monitoring When another unit breaks down, spare control loop is enabled rapidly to corresponding operation mechanism and issues action command, completes separating brake And turbine-generator units work is shut down, and record corresponding fault message, immediately, efficiently ensure hydrogenerator automation control System processed is reliable, is safely operated, and provides effective analysis foundation for trouble hunting.
Generation control unit of the present invention and excitation con-trol unit close in set of system, and both sides are hot standby each other, when power generation is controlled When cell failure processed, excitation con-trol unit is automatically performed system closedown demagnetization process, otherwise when excitation con-trol unit breaks down When, generation control unit completes system closedown demagnetization process.
The present invention effectively meets the needs of turbine-generator units automatic control system two-way dual disaster tolerance, accomplishes system Simple at low cost, response timeliness height, protection reliability are high.

Claims (4)

1. the two-way dual disaster tolerance control system of turbine-generator units, it is characterised in that: it includes adjustment of field excitation unit, demagnetization control Mechanism and hydraulic turbine automatic control unit, adjustment of field excitation unit are connected and are controlled by its master control circuit demagnetization control mechanism, encourage Magnetically condition unit connects and controls hydraulic turbine control mechanism by its backup control line road, and hydraulic turbine automatic control unit passes through it Master control circuit connects and controls hydraulic turbine control mechanism, and hydraulic turbine automatic control unit is connected and controlled by its backup control line road Demagnetization control mechanism processed, mutual high speed communication between adjustment of field excitation unit and hydraulic turbine automatic control unit.
2. the two-way dual disaster tolerance control system of turbine-generator units according to claim 1, it is characterised in that: the water wheels Machine control mechanism includes breaker, water valve and gate valve control mechanism.
3. it is double to be applied to turbine-generator units of any of claims 1 or 2 for the two-way dual disaster tolerant control method of turbine-generator units To dual disaster tolerance control system, it is characterised in that: control method the following steps are included:
1) adjustment of field excitation unit and hydraulic turbine automatic control unit acquire the operation information of turbine-generator units respectively;
2) adjustment of field excitation unit and hydraulic turbine automatic control unit carry out high speed communication, and exchange the operation information acquired in real time;
3) adjustment of field excitation unit and hydraulic turbine automatic control unit mutually monitor and analyze the operation information of other side's transmission;
4) when adjustment of field excitation unit and hydraulic turbine automatic control unit work normally, adjustment of field excitation unit and the hydraulic turbine are automatic Control unit issues corresponding switching on and shutting down control action instruction by respective master control circuit to realize normal switching on and shutting down respectively Process completes corresponding relay protection movement;
5) when one of adjustment of field excitation unit or hydraulic turbine automatic control unit break down, then the hydraulic turbine of monitoring is corresponded to Automatic control unit or adjustment of field excitation unit enable the adjustment of field excitation unit or the hydraulic turbine that its backup control line road direction breaks down The control mechanism that automatic control unit is controlled issues action command, completes separating brake and shuts down turbine-generator units work, and remembers Record corresponding fault message.
4. the two-way dual disaster tolerant control method of turbine-generator units according to claim 3, it is characterised in that: the operation Information includes network voltage, set end voltage, generator terminal electric current, revolving speed and opening and closing state.
CN201710771494.7A 2017-08-31 2017-08-31 The two-way dual disaster tolerance control system of turbine-generator units and its method Active CN107575338B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710771494.7A CN107575338B (en) 2017-08-31 2017-08-31 The two-way dual disaster tolerance control system of turbine-generator units and its method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710771494.7A CN107575338B (en) 2017-08-31 2017-08-31 The two-way dual disaster tolerance control system of turbine-generator units and its method

Publications (2)

Publication Number Publication Date
CN107575338A CN107575338A (en) 2018-01-12
CN107575338B true CN107575338B (en) 2019-06-14

Family

ID=61030992

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710771494.7A Active CN107575338B (en) 2017-08-31 2017-08-31 The two-way dual disaster tolerance control system of turbine-generator units and its method

Country Status (1)

Country Link
CN (1) CN107575338B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201629715U (en) * 2010-01-19 2010-11-10 武汉长江控制设备研究所 DSP microcomputer excitation and speed adjustor of hydraulic generator unit
CN201635917U (en) * 2010-01-19 2010-11-17 武汉长江控制设备研究所 Speed-regulation and excitation adjuster for PCC micro-computer of hydraulic generator unit
CN202937399U (en) * 2012-11-20 2013-05-15 天津市天骄水电成套设备有限公司 Double-mode double-microcomputer speed regulator
CN205383041U (en) * 2016-03-04 2016-07-13 华自科技股份有限公司 Low pressure packaged unit device
CN205605355U (en) * 2016-02-29 2016-09-28 福建省智能科技有限公司 Middle -size and small -size hydroelectric set DSPIC integrated controller

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201629715U (en) * 2010-01-19 2010-11-10 武汉长江控制设备研究所 DSP microcomputer excitation and speed adjustor of hydraulic generator unit
CN201635917U (en) * 2010-01-19 2010-11-17 武汉长江控制设备研究所 Speed-regulation and excitation adjuster for PCC micro-computer of hydraulic generator unit
CN202937399U (en) * 2012-11-20 2013-05-15 天津市天骄水电成套设备有限公司 Double-mode double-microcomputer speed regulator
CN205605355U (en) * 2016-02-29 2016-09-28 福建省智能科技有限公司 Middle -size and small -size hydroelectric set DSPIC integrated controller
CN205383041U (en) * 2016-03-04 2016-07-13 华自科技股份有限公司 Low pressure packaged unit device

Also Published As

Publication number Publication date
CN107575338A (en) 2018-01-12

Similar Documents

Publication Publication Date Title
CN103022994B (en) Method for achieving fault isolation and recovery of power distribution network with permeability distribution type power supply
CN102354977B (en) Feeder fault handling method
CN105548801B (en) Fault Locating Method suitable for power distribution network operation with closed ring
CN104767182A (en) Fault processing method for overhead line type power distribution network
CN204243896U (en) For the on off state monitoring device of power distribution network
CN104134996B (en) Containing the power distribution network large-area power-cuts recovery technology of distributed power source
CN104242467A (en) Intelligent self-healing controlling method of feeder line of distribution network
CN105896490A (en) Fault processing method and device of power distribution network
CN107766649B (en) System protection real-time closed-loop simulation test system and operation method thereof
CN104092305A (en) Power distribution network fault handling method
CN102545375B (en) Automatic switching on/off method for emergency power supply of power plant
CN103616598A (en) Testing method for dynamic simulation of linkage between protective channel faults and line faults
CN107575338B (en) The two-way dual disaster tolerance control system of turbine-generator units and its method
CN111327474B (en) Power system fault diagnosis method based on topology analysis
CN105785262A (en) Bus-conversion-current-analysis-based monitoring state for closing motion state of thermal inverted bus
CN202550668U (en) Distributed power distribution network management terminal
CN106452203A (en) Reliable drive control system, and control method thereof
CN104991525B (en) Power auto-control system
CN104009473A (en) Self-healing method of distribution network system
CN103728529B (en) A kind of switch gap condition discrimination method
CN104175884B (en) A kind of bus contactless switch network control method
CN116505493B (en) Distributed fault positioning and isolating method for power distribution network multi-power supply condition
CN207689955U (en) A kind of DC control protective device for realizing switching value circuit on-bne repair
CN205665518U (en) Become oar motor control means , system and wind generating set
CN106207992B (en) A kind of control method of the control system of fuse switch

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant