CN107574817A - A kind of constructing device and construction method for superpressure retaining wall cast-in-situ bored pile - Google Patents

A kind of constructing device and construction method for superpressure retaining wall cast-in-situ bored pile Download PDF

Info

Publication number
CN107574817A
CN107574817A CN201710846274.6A CN201710846274A CN107574817A CN 107574817 A CN107574817 A CN 107574817A CN 201710846274 A CN201710846274 A CN 201710846274A CN 107574817 A CN107574817 A CN 107574817A
Authority
CN
China
Prior art keywords
steel pipe
bored pile
top layer
base
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710846274.6A
Other languages
Chinese (zh)
Inventor
黄大维
冯青松
刘为民
李明华
杨成忠
兰彬
王威
龚凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Jiaotong University
Original Assignee
East China Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Jiaotong University filed Critical East China Jiaotong University
Priority to CN201710846274.6A priority Critical patent/CN107574817A/en
Publication of CN107574817A publication Critical patent/CN107574817A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a kind of constructing device and construction method for superpressure retaining wall cast-in-situ bored pile, constructing device includes the base, top layer steel pipe and some middle level steel pipes for being embedded with embedded steel tube;The both ends that embedded steel tube extends the upper end of base, the lower end of top layer steel pipe, and middle level steel pipe are equipped with the flange mutually fastened and connect for three;Embedded steel tube forms the centre bore entered for cast-in-situ bored pile in chassis interior;The side wall of top layer steel pipe is provided with sludge discharge pipe.During construction, determine that sludge discharge pipe apart from ground level, installs middle level steel pipe and top layer steel pipe successively from the bottom to top on embedded steel tube according to the design mud pressure size in hole during bored pile construction.Its advantage is:Face loose crushing, the complex random systems such as soft, cementing properties is poor when, to provide bigger lateral mud pressure, therefore by the mud pressure increase in hole, the problems such as being reduced the hole wall collapse that solves to occur in the work progress of cast-in-situ bored pile, aperture.

Description

A kind of constructing device and construction method for superpressure retaining wall cast-in-situ bored pile
Technical field
The invention belongs to drilling hole bored concrete pile technology field, and in particular to a kind of construction for superpressure retaining wall cast-in-situ bored pile Device and construction method.
Background technology
When carrying out construction operation using the holing with slurry wall protection bored concrete pile of routine, because the balance of original place ply stress is destroyed, Large effect can be produced to the stability of hole wall.In the presence of reservoir stress, cause hole wall destroy form can be divided into it is crowded Bad and tension failure is crushed, wherein it is again failure mode main in drilling construction that extruding, which destroys,.It is poor in loose crushing, cementing properties Or when bored pile construction is carried out in soft stratum, conventional bored pile construction method carries out pore-forming, and hole wall is easily Cave in, or aperture occurs and shrinks, influence pile quality, and closely structures are influenceed big.
In order to prevent hole wall collapse from being shunk with aperture, to reduce the influence to closely structures, Patent No. A kind of ZL201210242665.4 (cast-in-situ bored pile construction method with tiny disturbance) patent proposes the steel sleeve of rotation press-in in advance, Carry out again mud circulation pore-forming bored pile construction method, but the steel sleeve spinning of this engineering method bury operating expenses height, Easily closely structures are had an impact when steel sleeve spinning buries, and steel sleeve does not further take out, and thus causes cast-in-situ bored pile Construction cost it is high, and the bearing capacity of drilling pouring stake will be influenceed.Recycled if steel sleeve is taken out again, to low coverage Secondary effect is produced from structures.
In order to reduce hole wall collapse, dewatering well will be being beaten around bored pile construction in the prior art, in pore-forming Precipitation is carried out to dewatering well during operation, to increase the difference of mud pressure and surrounding formation water pressure in hole.But this technology is constructed Process is more, and construction cost is high, and the difference of mud pressure and surrounding formation water pressure is limited in maximum hole.
The content of the invention
According to the deficiencies of the prior art described above, It is an object of the present invention to provide one kind is used for superpressure retaining wall drill-pouring The constructing device of stake and construction method, the constructing device and construction method face loose crushing, the complexity such as soft, cementing properties is poor During soil layer, to provide bigger lateral mud pressure, therefore the mud pressure in hole is increased, to solve applying in cast-in-situ bored pile The problems such as hole wall collapse that occurs during work, aperture reduce.
The object of the invention is realized and completed by following technical scheme:
A kind of constructing device for superpressure retaining wall cast-in-situ bored pile, it is characterised in that:The constructing device is pre- including being embedded with Bury the base, top layer steel pipe and some middle level steel pipes of steel pipe;The embedded steel tube and the top layer steel pipe, the middle level steel pipe Caliber is identical, and the embedded steel tube extends the upper end of the base, the lower end of the top layer steel pipe, and the middle level steel pipe Both ends be equipped with the flange mutually fastened and connect for three;The embedded steel tube forms in the chassis interior and supplies cast-in-situ bored pile The centre bore of entrance, the axis of the centre bore are located on the base center axis line;The side wall of the top layer steel pipe is provided with mud Discharge pipe, the sludge discharge pipe end are provided with flange.
The constructing device also includes some elastic sealing gaskets, the flange of the elastic sealing gasket and the top layer steel pipe and Screw shape is adapted on the flange.
The base is columned reinforced concrete structure, and its outer radius is 3-5 times of cast-in-situ bored pile diameter, and thickness is 1-2m;The center pore radius is more than design hole radius 3-5cm.
The flange of the embedded steel tube is higher by the base top surface 15-20cm, the interval between the embedded steel tube screw For 5-15cm.
The joint portion of the sludge discharge pipe and the top layer steel pipe is to the top layer steel pipe top distance 30-70cm.
A kind of construction method for being related to the constructing device for superpressure retaining wall cast-in-situ bored pile described in any one, it is special Sign is that the construction method comprises the following steps:
A, place is reconnoitred, determines the diameter and depth of cast-in-situ bored pile, and during the bored pile construction in hole Design mud pressure size;And make embedded steel tube, top layer steel pipe and Duo Gen middle levels steel pipe based on surveys;
B, smooth hardening is carried out to place, and excavates base at design hole and pours groove, it is 3-5 that the base, which pours groove radius, The cast-in-situ bored pile diameter again, depth 1-2m;
The base is poured to the plain concrete cushion layer that 10cm is set in groove, and reinforcing bar is installed c,;Laid at the design hole The embedded steel tube;Poured in place concrete forms base afterwards;Afterwards according to setting in hole during the bored pile construction Meter mud pressure size determines sludge discharge pipe apart from ground level, on the embedded steel tube from the bottom to top successively described in installation Middle level steel pipe and the top layer steel pipe, and the embedded steel tube, the middle level steel pipe and the top are sealed by elastic sealing gasket Gap at joint between layer steel pipe;The mud effuser of installation connection sedimentation basin on the sludge discharge pipe of the top layer steel pipe;
D, the mud prepared is pressed into the hollow drill pipe of pore-forming equipment by drilling machine equipment;
E, drilling machine equipment carries out mud Drilling by inverse circulation operation;
F, after pore-forming to projected depth, then borehole cleaning, steel reinforcement cage is laid, and carries out filling concrete, and filling concrete height is not The base top surface can be exceeded;
G, after the filling concrete of the cast-in-situ bored pile completes 48-60 hours, then the middle level steel pipe and the top are removed Layer steel pipe, and by the Partial Resection above ground level of the embedded steel tube on the base.
It is an advantage of the invention that:(1)Any pore size can generally be adapted to, the cast-in-situ bored pile of various complex random systems is applied Work;Compared with conventional bored pile construction, the present invention enables the situation of hole wall collapse largely to suppress, and more makes aperture The incidence of diminution greatly reduces, and avoids the unnecessary damage to property in work progress;(2)The present invention is neatly controlled System beyond ground mud liquid level, so as to the mud pressure in control hole, to prevent hole wall collapse in pore forming process, contracting Phenomena such as footpath;And by the fixation of base, solve hole position deflection, the problems such as aperture collapses;In device between steel pipe, steel Connected between pipe and base by flange, improve the overall stability of device.
Brief description of the drawings
Fig. 1 is the constructing device schematic diagram for being used for superpressure retaining wall cast-in-situ bored pile in the present invention;
Fig. 2 is the close-up schematic view at A in Fig. 1 of the present invention.
Embodiment
The feature of the present invention and other correlated characteristics are described in further detail by embodiment below in conjunction with accompanying drawing, with It is easy to the understanding of technical staff of the same trade:
Such as Fig. 1,2, mark 1-12 is respectively in figure:Base 1, embedded steel tube 2, centre bore 21, ring flange 22, middle level steel pipe 3, method Blue disk 31, bolt 32, top layer steel pipe 4, sludge discharge pipe 41, elastic sealing gasket 5, mud effuser 6, hardened ground 7, sedimentation basin 8th, hollow drill pipe 9, drill bit 10, slush pump 11, mud flow into pipe 12.
Embodiment:As shown in Figure 1, 2, the present embodiment provides a kind of construction for superpressure retaining wall cast-in-situ bored pile and filled first Put, including:
Base 1
Base 1 is cylinder, using reinforced concrete structure.The outer radius of base 1 is 3-5 times of cast-in-situ bored pile diameter, and thickness is 1—2m.The outer rim of base 1 rotates about the axis thereof symmetrical reserved steel bar ring provided with 4.Reserved steel bar ring is circular or ellipse, Radius is 3-5cm, and its bottom and the plane of base 1 are tangent.
Base 1 is embedded with embedded steel tube 2.The axis of embedded steel tube 2 is located at the geometric center of base 1, and embedded steel tube 2 is the bottom of at Seat 1 is internally formed the centre bore 21 entered for cast-in-situ bored pile, the big 3-5cm of the radius ratio of centre bore 21 design hole radius.In advance Bury the upper end of steel pipe 2 and be additionally provided with ring flange 22.Ring flange 22 is higher by the top surface 15-20cm of base 1, thereon between screw at intervals of 5- 15cm。
Middle level steel pipe 3 and top layer steel pipe 4
Embedded steel tube 2, middle level steel pipe 3 and top layer steel pipe 4 have identical caliber.Wherein:
The lower end of top layer steel pipe 4, and the both ends of middle level steel pipe 3 are equipped with the flange being adapted with ring flange 22.Top layer steel pipe Side wall away from being provided with sludge discharge pipe 41 at the 30-70cm of its upper end.The end of sludge discharge pipe 41, which is provided with, to be used to install mud outflow The flange of pipe 6, the radius of sludge discharge pipe 41 are not less than 10cm.
Offered at the top outer rim of top layer steel pipe 4 identical with reserved steel bar number of rings amount(It is 4 in the present embodiment)Pair Claim the hole of distribution.Each distance of the hole away from the top edge of top layer steel pipe 4 is 3-5cm, and the radius of hole is 3-5cm.Pass through steel The connection ring of the hole of top layer steel pipe 4 and base 1 is attached fixation by cable, to increase its stability.
In addition, constructing device can also include some elastic sealing gaskets 5.Method between elastic sealing gasket 5 and middle level steel pipe 3 Blue disk 31 and eyelet is adapted thereon.In assembling, sealed between ring flange 31 by elastic sealing gasket 5, mud is prevented to reach Seepage is starched, and is fixedly connected by bolt 32.
Below in conjunction with using the novel construction method after the device, above-mentioned constructing device occupation mode is described in detail. Construction method comprises the following steps:
A, place is reconnoitred, highly determined according to the stability of the soil body, physical and mechanical property, dense state, level of ground water The diameter and depth of cast-in-situ bored pile, and design mud pressure size during bored pile construction in hole;
And make embedded steel tube 2, top layer steel pipe 4 and Duo Gen middle levels steel pipe 3 as described above based on surveys;Middle level steel pipe 3 Quantity and length should according to design mud pressure size be designed;In a preferred embodiment, middle level steel pipe 3 should be divided into 2 meters of specifications(More)With 1 meter of specification(1), so no matter design mud pressure be it is how many, can be by error by combinations thereof Control is within 0.5m.It should be noted that during each steel pipe excessive height more than ground, need to take appropriate prevents middle level Steel pipe 3 and the run-off the straight of top layer steel pipe 4 or the measure toppled over, such as add diagonal brace or oblique pull steel wire rope;
B, smooth hardening is carried out to place, and excavates base at design hole and pours groove, base pours groove radius and bored for 3-5 times Hole pouring pile diameter, depth 1-2m;
C, base is poured into the plain concrete cushion layer that trench bottom sets 10cm, and reinforcing bar is installed;Pre-buried steel is laid at design hole Pipe 2, the flange of embedded steel tube 2 basset at least 15-20cm;Poured in place concrete forms base 1 afterwards;Base 1 hardens Hardened ground 7 is done after complete thereon;
Determine sludge discharge pipe 41 apart from ground height according to the design mud pressure size in hole during bored pile construction afterwards Degree, middle level steel pipe 3 and top layer steel pipe 4 are installed successively from the bottom to top on embedded steel tube 2, and sealed by elastic sealing gasket 5 pre- Bury the gap between steel pipe 2, middle level steel pipe 3 and top layer steel pipe 4.Installation connection precipitation on the sludge discharge pipe 41 of top layer steel pipe 4 The mud effuser 6 in pond 8.Now, sludge discharge pipe 41 is big apart from ground level as design mud pressure on top layer steel pipe 4 It is small;
D, the mud prepared is pressed into mud and flows into pipe 12 by slush pump 11, enters finally into the hollow drill pipe 9 of pore-forming equipment It is interior;
E, drilling machine equipment carries out mud Drilling by inverse circulation operation;
F, after pore-forming to projected depth, then borehole cleaning, steel reinforcement cage is laid, and carries out filling concrete, and filling concrete height is not The top surface of base 1 can be exceeded(Ground);
G, after the filling concrete of hole pouring pile to be drilled completes 48-60 hours, then middle level steel pipe 3 and top layer steel pipe 4 are removed, and will The Partial Resection above ground level of embedded steel tube 2 on base 1.
In above-mentioned steps, completed from bored pile construction to filling concrete, mud remains at top layer steel pipe 4 The height of sludge discharge pipe 41, so as to the mud pressure in the bored pile construction process mesopore that improves.
The beneficial effect of the present embodiment is:The present embodiment can generally adapt to any pore size, the brill of various complex random systems Hole pouring pile is constructed.Compared with conventional bored pile construction, the present invention enables the situation of hole wall collapse largely to press down System, more greatly reduce the incidence that aperture is shunk, avoid the unnecessary damage to property in work progress.
The present embodiment neatly controls the mud liquid level beyond ground, so that the mud pressure in control hole, to prevent Only pore forming process middle hole wall cave in, undergauge phenomena such as.And by the fixation of base, solve hole position deflection, aperture collapses The problems such as.Connected by flange between steel pillar in device, connected between steel pillar and base by flange;It is complete more than ground When total height is larger after portion's fastener for connection, shaped steel diagonal brace or surrounding stretching wire rope further reinforcing group can be applied by surrounding again Steel loading pipe, improve the overall stability of assembling steel pipe.

Claims (6)

  1. A kind of 1. constructing device for superpressure retaining wall cast-in-situ bored pile, it is characterised in that:The constructing device includes being embedded with Base, top layer steel pipe and some middle level steel pipes of embedded steel tube;The embedded steel tube and the top layer steel pipe, the middle level steel pipe Caliber it is identical, the embedded steel tube extends the upper end of the base, the lower end of the top layer steel pipe, and the middle level steel The both ends of pipe are equipped with the flange mutually fastened and connect for three;The embedded steel tube forms in the chassis interior and supplies drill-pouring The centre bore that stake enters, the axis of the centre bore are located on the base center axis line;The side wall of the top layer steel pipe is provided with mud Discharge pipe is starched, the sludge discharge pipe end is provided with flange.
  2. A kind of 2. constructing device for superpressure retaining wall cast-in-situ bored pile according to claim 1, it is characterised in that:It is described Constructing device also includes some elastic sealing gaskets, the elastic sealing gasket and spiral shell on the flange of the top layer steel pipe and the flange Hole shape is adapted.
  3. A kind of 3. constructing device for superpressure retaining wall cast-in-situ bored pile according to claim 1, it is characterised in that:It is described Base is columned reinforced concrete structure, and its outer radius is 3-5 times of cast-in-situ bored pile diameter, thickness 1-2m;In described Heart pore radius is more than design hole radius 3-5cm.
  4. A kind of 4. constructing device for superpressure retaining wall cast-in-situ bored pile according to claim 1, it is characterised in that:It is described The flange of embedded steel tube is higher by the base top surface 15-20cm, between the embedded steel tube screw at intervals of 5-15cm.
  5. A kind of 5. constructing device for superpressure retaining wall cast-in-situ bored pile according to claim 1, it is characterised in that:It is described The joint portion of sludge discharge pipe and the top layer steel pipe is to the top layer steel pipe top distance 30-70cm.
  6. A kind of 6. construction for being related to the constructing device for superpressure retaining wall cast-in-situ bored pile described in claim 1-5 any one Method, it is characterised in that the construction method comprises the following steps:
    A, place is reconnoitred, determines the diameter and depth of cast-in-situ bored pile, and during the bored pile construction in hole Design mud pressure size;And make embedded steel tube, top layer steel pipe and Duo Gen middle levels steel pipe based on surveys;
    B, smooth hardening is carried out to place, and excavates base at design hole and pours groove, it is 3-5 that the base, which pours groove radius, The cast-in-situ bored pile diameter again, depth 1-2m;
    The base is poured to the plain concrete cushion layer that 10cm is set in groove, and reinforcing bar is installed c,;Laid at the design hole The embedded steel tube;Poured in place concrete forms base afterwards;Afterwards according to setting in hole during the bored pile construction Meter mud pressure size determines sludge discharge pipe apart from ground level, on the embedded steel tube from the bottom to top successively described in installation Middle level steel pipe and the top layer steel pipe, and the embedded steel tube, the middle level steel pipe and the top are sealed by elastic sealing gasket Gap at joint between layer steel pipe;The mud effuser of installation connection sedimentation basin on the sludge discharge pipe of the top layer steel pipe;
    D, the mud prepared is pressed into the hollow drill pipe of pore-forming equipment by drilling machine equipment;
    E, drilling machine equipment carries out mud Drilling by inverse circulation operation;
    F, after pore-forming to projected depth, then borehole cleaning, steel reinforcement cage is laid, and carries out filling concrete, and filling concrete height is not The base top surface can be exceeded;
    G, after the filling concrete of the cast-in-situ bored pile completes 48-60 hours, then the middle level steel pipe and the top are removed Layer steel pipe, and by the Partial Resection above ground level of the embedded steel tube on the base.
CN201710846274.6A 2017-09-19 2017-09-19 A kind of constructing device and construction method for superpressure retaining wall cast-in-situ bored pile Pending CN107574817A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710846274.6A CN107574817A (en) 2017-09-19 2017-09-19 A kind of constructing device and construction method for superpressure retaining wall cast-in-situ bored pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710846274.6A CN107574817A (en) 2017-09-19 2017-09-19 A kind of constructing device and construction method for superpressure retaining wall cast-in-situ bored pile

Publications (1)

Publication Number Publication Date
CN107574817A true CN107574817A (en) 2018-01-12

Family

ID=61035545

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710846274.6A Pending CN107574817A (en) 2017-09-19 2017-09-19 A kind of constructing device and construction method for superpressure retaining wall cast-in-situ bored pile

Country Status (1)

Country Link
CN (1) CN107574817A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442371A (en) * 2018-05-17 2018-08-24 中铁十六局集团第三工程有限公司 One kind stake combination casing structure and its construction method suitable for Soft Clay water

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967032A (en) * 2014-04-16 2014-08-06 青岛理工大学 Double-protective-cylinder cast-in-situ bored pile used for highly-corrosive salty soil and construction method of double-protective-cylinder cast-in-situ bored pile
CN204456094U (en) * 2015-01-28 2015-07-08 沈阳铁道勘察设计院有限公司 Bored pile environmental protection casing
CN206090520U (en) * 2015-12-08 2017-04-12 南京林业大学 Solid native dado drilling bored concrete pile of microorganism
CN207244614U (en) * 2017-09-19 2018-04-17 华东交通大学 A kind of constructing device for superpressure retaining wall cast-in-situ bored pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967032A (en) * 2014-04-16 2014-08-06 青岛理工大学 Double-protective-cylinder cast-in-situ bored pile used for highly-corrosive salty soil and construction method of double-protective-cylinder cast-in-situ bored pile
CN204456094U (en) * 2015-01-28 2015-07-08 沈阳铁道勘察设计院有限公司 Bored pile environmental protection casing
CN206090520U (en) * 2015-12-08 2017-04-12 南京林业大学 Solid native dado drilling bored concrete pile of microorganism
CN207244614U (en) * 2017-09-19 2018-04-17 华东交通大学 A kind of constructing device for superpressure retaining wall cast-in-situ bored pile

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
胡文俊等: "忠县长江大桥3m钻孔桩施工技术", 《忠县长江大桥3M钻孔桩施工技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442371A (en) * 2018-05-17 2018-08-24 中铁十六局集团第三工程有限公司 One kind stake combination casing structure and its construction method suitable for Soft Clay water

Similar Documents

Publication Publication Date Title
CN105350562B (en) Inserting type column leg with accurate leveling device and construction method of inserting type column leg
CN107905811B (en) Inverted arch-free lining of foundation hollow longitudinal beam bearing arch structure
CN109024721B (en) Reinforced foundation and method for improving bending and shearing resistance of existing building rigid foundation
CN111021172B (en) Road construction process
CN108316328A (en) A kind of pressurization sinking device and its construction method for open caisson construction
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN103334371A (en) Roadbed subsidence grouting treatment structure and construction method thereof
CN101324064A (en) Controllable expansion extrusion soil body apparatus for geotechnical engineering and use thereof
CN207244614U (en) A kind of constructing device for superpressure retaining wall cast-in-situ bored pile
CN101793027B (en) Core-grouted static pressure anchor rod pile
CN107574817A (en) A kind of constructing device and construction method for superpressure retaining wall cast-in-situ bored pile
CN212670613U (en) Anti prefabricated open caisson section of jurisdiction unit and open caisson structure that floats
CN210315592U (en) Supporting system for supporting high and steep slope
CN111622216A (en) Construction method of pile foundation joist weighing type retaining wall
CN106759264A (en) One kind grouting pipe network and its construction method
CN108301402B (en) Novel construction method of cast-in-situ bored pile
CN111636899B (en) Tunnel inverted arch structure for preventing bottom bulging and construction process
CN216108526U (en) Underground continuous wall structure for foundation pit support
CN110645003B (en) Completely weathered granite bias steep slope tunnel entry construction method
CN105178356A (en) Setting-up construction method for vertical joint bars of columns in reverse building method
CN201635072U (en) Centrally grouted static-pressured anchor pile former
CN212656218U (en) Heavy pile machine load underpinning structure
CN210151705U (en) Reinforcing pile for soft soil foundation
CN212248272U (en) Concrete body supporting system for high-strength precipitation
CN210888953U (en) Tunnel pile and arch combined primary support system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination