CN107572358A - Efficient petroleum pipeline boom hoisting - Google Patents
Efficient petroleum pipeline boom hoisting Download PDFInfo
- Publication number
- CN107572358A CN107572358A CN201711002405.9A CN201711002405A CN107572358A CN 107572358 A CN107572358 A CN 107572358A CN 201711002405 A CN201711002405 A CN 201711002405A CN 107572358 A CN107572358 A CN 107572358A
- Authority
- CN
- China
- Prior art keywords
- suspension ring
- petroleum pipeline
- pipeline
- block
- boom hoisting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The invention discloses efficient petroleum pipeline boom hoisting, including two pieces of boatswain chairs being sequentially connected, the both ends of a underlying side are connected with suspension ring by lifting rope respectively on every piece of boatswain chair, the size of suspension ring and the outside dimension of petroleum pipeline match, and suspension ring are made using elastomeric material, spacing block is provided between two pieces of boatswain chairs, the two sides of spacing block are circular arc and matched with the outside wall surface arc of petroleum pipeline, multiple support blocks are connected with spacing block side, the end face of support block is provided with damping spring.The petroleum pipeline suspender of the present invention; two pipelines can be sling simultaneously; greatly improve the efficiency of transport installation; the spacing block being arranged on simultaneously between two pipelines; the balance of pipeline both sides can not only be kept; avoid it that left and right whipping occurs, while two pipeline sides adjacents are played a good protection, play caused rolling power during buffering lifting.
Description
Technical field
The present invention relates to a kind of transport of petroleum pipeline, and in particular to efficient petroleum pipeline boom hoisting.
Background technology
One of oil, the main object of geological prospecting, it is a kind of sticky, dark brown liquid, is referred to as " the blood of industry
Liquid ".There is petroleum storage upper crustal some areas.Main component is the mixture of various alkane, cycloalkane, aromatic hydrocarbon.Oil
There is biogenic deposit to become oil and the oily two kinds of theories of petrochemical industry into oil machine reason, the former more widely receives, it is believed that oil be ancient times ocean or
Biology in lake is formed by very long evolution, is belonged to biogenic deposit and is become oil, non-renewable;The latter thinks that oil is by the earth's crust
The interior carbon generation of itself, it is unrelated with biology, it is renewable.Oil is mainly used as fuel oil and gasoline, and many chemical works
Industry product, such as solution, chemical fertilizer, the raw material of insecticide and plastics.Corresponding machining sector must be transported after oil exploitation,
Can more preferably it be utilized, wherein the petroleum pipeline of transfer oil is then essential equipment.Wherein, constructed in petroleum pipeline
Installation is with transport, in order to efficiently construct and ensure that pipeline does not damage outer corrosion resistant surfaces in lower ditch, necessarily using pipeline special
Use suspender.Suspender the most frequently used in pipeline construction both at home and abroad is the suspender belt of different loads at present.Suspender belt has many advantages, such as uses
It is lighter, it is simple to operate.But suspender belt can only disposably sling a pipeline, and pipeline sling it is mobile during,
Stationarity is poor, can be swung with rocking for suspender belt, and pipeline is difficult to keep balance, it is also possible to is slid out from suspender belt, so
Cause easily pipeline outer wall to be caused to damage in installation process.
The content of the invention
The technical problems to be solved by the invention are that existing pipeline spreader can only disposably sling a pipeline, Er Qieguan
During movement is sling, stationarity is poor in road, can be swung with rocking for suspender belt, and pipeline is difficult to keep balance, also may be used
It can be slid out from suspender belt, so cause easily to cause damage to pipeline outer wall, and it is an object of the present invention to provide efficiently in installation process
The petroleum pipeline boom hoisting of rate, two pipelines can be sling simultaneously, greatly improve the efficiency of transport installation, be arranged on simultaneously
Spacing block between two pipelines, the balance of pipeline both sides can not only be kept, avoid it that left and right whipping occurs, while to two
Pipeline sides adjacent plays a good protection, and plays caused rolling power during buffering lifting.
The present invention is achieved through the following technical solutions:
Efficient petroleum pipeline boom hoisting, including two pieces of boatswain chairs being sequentially connected, the angle between two pieces of boatswain chairs are
120-150 ° and angle it is opening down, the both ends of a underlying side are connected with by lifting rope respectively on every piece of boatswain chair hangs
Ring, the size of suspension ring and the outside dimension of petroleum pipeline match, and suspension ring are made using elastomeric material, are set between two pieces of boatswain chairs
There is spacing block, the two sides of spacing block match for circular arc and with the outside wall surface arc of petroleum pipeline, spacing block circular arc
Multiple support blocks are vertically connected with successively along arc length direction on side, and the end face of support block is provided with damping spring.
The petroleum pipeline suspender of the present invention, can sling two pipelines simultaneously, greatly improve the efficiency of transport installation, together
When be arranged on spacing block between two pipelines, the balance of pipeline both sides can not only be kept, avoid its that left and right whipping occurs, together
When two pipeline sides adjacents are played a good protection, play buffering lifting during caused rolling power.To oil
When pipeline is lifted by crane, two suspension ring below one piece of boatswain chair are set in the both ends of a pipeline, such two pieces of boatswain chairs
Just two pipelines can be realized while lifted by crane, suspension ring are made using elastomeric material and size and the size of pipeline match completely,
So suspension ring are to be brought into close contact completely between duct wall, and the frictional force of elastomeric material is big, hangs after installing on road pipeline
Ring will not slidably reciprocate on duct wall;When slinging, two pieces of pipelines are to sling side by side, therefore spacing block can be by two pipelines
Adjacent side separates, and avoids two pieces of pipelines from colliding, while damping spring and the outer wall of pipeline on support block end face
Contact, so when pipeline shakes, damping spring can play a part of buffering so as to improve stability, Er Qiefen
Spacer block also plays good protective effect to the side of pipeline.
Tube edge fixture is connected with by static line on the suspension ring, the tube edge fixture is used for the end for being clamped in petroleum pipeline
Portion, the tube edge fixture on the suspension ring that will be arranged on pipeline one end are clamped to the other end, i.e., the suspension ring on a pipeline with it is corresponding
Tube edge fixture intersects connection, suspension ring can be avoided to be slid away from both ends.
The support block has stretching structure, and support block can extend along the direction vertical with the side of spacing block circular arc
, can be according to the diameter of lifting pipeline so as to adjust the length of support block, to ensure that damping spring can be with pipe with shortening
Road avoids contact with.
The both ends of the surface of the suspension ring are provided with limited block, and the end face of limited block and suspension ring is slidably connected, and limited block being capable of edge
The radial direction for suspension ring slidably reciprocates, and is provided with spacing sucker close to one end of suspension ring central point on limited block, suspension ring are arranged
After outside pipeline, by adjusting the position of limited block, so that spacing sucker contacts with tube wall, so as to which sucker is fixed on into pipe
On wall, avoid suspension ring from being slided on tube wall, play a part of fixed suspension ring.
Fur layer is equipped with the inwall of the suspension ring, can avoid producing damage to the anticorrosive coat on tube wall.
The present invention compared with prior art, has the following advantages and advantages:
1st, the efficient petroleum pipeline boom hoisting of the present invention, can sling two pipelines simultaneously, greatly improve transport
The efficiency of installation, while the spacing block being arranged between two pipelines, the balance of pipeline both sides can not only be kept, avoids its hair
Raw left and right whipping, while two pipeline sides adjacents are played a good protection, play caused rolling during buffering lifting
Power;
2nd, the efficient petroleum pipeline boom hoisting of the present invention, tube edge fixture, institute are connected with by static line on the suspension ring
State tube edge fixture and be used to being clamped in the end of petroleum pipeline, the tube edge fixture on the suspension ring that will be arranged on pipeline one end is clamped to separately
One end, i.e. suspension ring on a pipeline and corresponding tube edge fixture are intersected connection, and suspension ring can be avoided to be slided from both ends
Drop out, the support block has stretching structure, and support block can extend along the direction vertical with the side of spacing block circular arc
, can be according to the diameter of lifting pipeline so as to adjust the length of support block, to ensure that damping spring can be with pipe with shortening
Road avoids contact with;
3rd, the efficient petroleum pipeline boom hoisting of the present invention, the both ends of the surface of the suspension ring are provided with limited block, limited block
It is slidably connected with the end face of suspension ring, limited block can slidably reciprocate along the radial direction of suspension ring, on limited block in suspension ring
One end of heart point is provided with spacing sucker, after suspension ring are set in outside pipeline, by adjusting the position of limited block, so that spacing
Sucker contacts with tube wall, so as to which sucker is fixed on tube wall, avoids suspension ring from being slided on tube wall, plays the work of fixed suspension ring
With, fur layer is equipped with the inwall of the suspension ring, can avoid on tube wall anticorrosive coat produce damage.
Brief description of the drawings
Accompanying drawing described herein is used for providing further understanding the embodiment of the present invention, forms one of the application
Point, do not form the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is schematic structural view of the invention.
Mark and corresponding parts title in accompanying drawing:
1- boatswain chairs, 2- lifting ropes, 3- suspension ring, 4- spacing blocks, 5- support blocks, 6- static lines, 7- tube edge fixtures, 8- limited blocks.
Embodiment
For the object, technical solutions and advantages of the present invention are more clearly understood, with reference to embodiment and accompanying drawing, to this
Invention is described in further detail, and exemplary embodiment of the invention and its explanation are only used for explaining the present invention, do not make
For limitation of the invention.
Embodiment
As shown in figure 1, the efficient petroleum pipeline boom hoisting of the present invention, including two pieces of boatswain chairs 1 being sequentially connected, two pieces
Angle between boatswain chair 1 is 120-150 ° and opening down, the both ends of a underlying side point on every piece of boatswain chair 1 of angle
Suspension ring 3 are not connected with by lifting rope 2, the size of suspension ring 3 and the outside dimension of petroleum pipeline match, and suspension ring 3 use rubber
Material is made, and is provided with spacing block 4 between two pieces of boatswain chairs 1, the two sides of spacing block 4 for circular arc and with the outside wall surface of petroleum pipeline
Arc matches, and multiple support blocks 5, support block 5 are vertically connected with successively along arc length direction on the side of the circular arc of spacing block 4
End face be provided with damping spring.
The petroleum pipeline suspender of the present invention, can sling two pipelines simultaneously, greatly improve the efficiency of transport installation, together
When be arranged on spacing block between two pipelines, the balance of pipeline both sides can not only be kept, avoid its that left and right whipping occurs, together
When two pipeline sides adjacents are played a good protection, play buffering lifting during caused rolling power.To oil
When pipeline is lifted by crane, two suspension ring below one piece of boatswain chair are set in the both ends of a pipeline, such two pieces of boatswain chairs
Just two pipelines can be realized while lifted by crane, suspension ring are made using elastomeric material and size and the size of pipeline match completely,
So suspension ring are to be brought into close contact completely between duct wall, and the frictional force of elastomeric material is big, hangs after installing on road pipeline
Ring will not slidably reciprocate on duct wall;When slinging, two pieces of pipelines are to sling side by side, therefore spacing block can be by two pipelines
Adjacent side separates, and avoids two pieces of pipelines from colliding, while damping spring and the outer wall of pipeline on support block end face
Contact, so when pipeline shakes, damping spring can play a part of buffering so as to improve stability, Er Qiefen
Spacer block also plays good protective effect to the side of pipeline.
Preferably, tube edge fixture 7 is connected with by static line 6 on the suspension ring, the tube edge fixture is used to be clamped in oil
The end of pipeline, the tube edge fixture on the suspension ring that will be arranged on pipeline one end are clamped to the other end, i.e. suspension ring on a pipeline
Intersected connection with corresponding tube edge fixture, suspension ring can be avoided to be slid away from both ends.
Preferably, the support block has a stretching structure, and support block can be along vertical with the side of spacing block circular arc
Direction extends and shortened, can be according to the diameter of lifting pipeline so as to adjust the length of support block, to ensure damping spring
It can be avoided contact with pipeline.
Preferably, the both ends of the surface of the suspension ring are provided with limited block 8, and the end face of limited block and suspension ring is slidably connected, spacing
Block can be slidably reciprocated along the radial direction of suspension ring, and spacing sucker is provided with close to one end of suspension ring central point on limited block,
After suspension ring are set in outside pipeline, by adjusting the position of limited block, so that spacing sucker contacts with tube wall, so that by sucker
It is fixed on tube wall, avoids suspension ring from being slided on tube wall, plays a part of fixed suspension ring.
Preferably, fur layer is equipped with the inwall of the suspension ring, can avoid producing damage to the anticorrosive coat on tube wall.
Above-described embodiment, the purpose of the present invention, technical scheme and beneficial effect are carried out further
Describe in detail, should be understood that the embodiment that the foregoing is only the present invention, be not intended to limit the present invention
Protection domain, within the spirit and principles of the invention, any modification, equivalent substitution and improvements done etc., all should include
Within protection scope of the present invention.
Claims (5)
1. efficient petroleum pipeline boom hoisting, it is characterised in that including two pieces of boatswain chairs being sequentially connected (1), two pieces of boatswain chairs
(1) angle between is 120-150 ° and opening down, the both ends of a underlying side point on every piece of boatswain chair (1) of angle
Suspension ring (3) are not connected with by lifting rope (2), the size of suspension ring (3) and the outside dimension of petroleum pipeline match, and suspension ring (3)
It is made using elastomeric material, spacing block (4) is provided between two pieces of boatswain chairs (1), the two sides of spacing block (4) are circular arc and and stone
The outside wall surface arc of oil-piping matches, and is vertically connected with successively along arc length direction on the side of spacing block (4) circular arc more
Individual support block (5), the end face of support block (5) are provided with damping spring.
2. efficient petroleum pipeline boom hoisting according to claim 1, it is characterised in that lead on the suspension ring (3)
Cross static line (6) and be connected with tube edge fixture (7), the tube edge fixture (7) is used for the end for being clamped in petroleum pipeline.
3. efficient petroleum pipeline boom hoisting according to claim 1, it is characterised in that support block (5) tool
There is stretching structure, support block (5) can be along the direction elongation vertical with the side of spacing block (4) circular arc and shortening.
4. efficient petroleum pipeline boom hoisting according to claim 1, it is characterised in that the two of the suspension ring (3)
End face is provided with limited block (8), and the end face of limited block (8) and suspension ring (3) is slidably connected, and limited block (8) can be along suspension ring (3)
Radial direction slidably reciprocate, be provided with spacing sucker close to one end of suspension ring (3) central point on limited block (8).
5. efficient petroleum pipeline boom hoisting according to claim 1, it is characterised in that the suspension ring (3) it is interior
Fur layer is equipped with wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711002405.9A CN107572358A (en) | 2017-10-24 | 2017-10-24 | Efficient petroleum pipeline boom hoisting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711002405.9A CN107572358A (en) | 2017-10-24 | 2017-10-24 | Efficient petroleum pipeline boom hoisting |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107572358A true CN107572358A (en) | 2018-01-12 |
Family
ID=61038248
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711002405.9A Pending CN107572358A (en) | 2017-10-24 | 2017-10-24 | Efficient petroleum pipeline boom hoisting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107572358A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111005698A (en) * | 2020-01-16 | 2020-04-14 | 刘翠霞 | Christmas tree oil pipe hanger |
CN113104742A (en) * | 2021-04-14 | 2021-07-13 | 潘归强 | Steel structure tower crane for building bridge road construction |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203740876U (en) * | 2014-04-03 | 2014-07-30 | 李学进 | Sliding-off prevention steel bar bundle lifting and transporting device |
CN204079223U (en) * | 2014-07-30 | 2015-01-07 | 天津市金立钢管有限公司 | A kind of steel pipe lifting tool |
CN204549788U (en) * | 2015-04-23 | 2015-08-12 | 青岛力磁电气有限公司 | A kind of chain type magnetic force suspender |
CN205114800U (en) * | 2015-10-16 | 2016-03-30 | 天津市金立钢管有限公司 | Steel pipe anti -drop tool |
CN207404708U (en) * | 2017-10-24 | 2018-05-25 | 成都科盛石油科技有限公司 | The petroleum pipeline suspender of stability can be improved |
-
2017
- 2017-10-24 CN CN201711002405.9A patent/CN107572358A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203740876U (en) * | 2014-04-03 | 2014-07-30 | 李学进 | Sliding-off prevention steel bar bundle lifting and transporting device |
CN204079223U (en) * | 2014-07-30 | 2015-01-07 | 天津市金立钢管有限公司 | A kind of steel pipe lifting tool |
CN204549788U (en) * | 2015-04-23 | 2015-08-12 | 青岛力磁电气有限公司 | A kind of chain type magnetic force suspender |
CN205114800U (en) * | 2015-10-16 | 2016-03-30 | 天津市金立钢管有限公司 | Steel pipe anti -drop tool |
CN207404708U (en) * | 2017-10-24 | 2018-05-25 | 成都科盛石油科技有限公司 | The petroleum pipeline suspender of stability can be improved |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111005698A (en) * | 2020-01-16 | 2020-04-14 | 刘翠霞 | Christmas tree oil pipe hanger |
CN111005698B (en) * | 2020-01-16 | 2022-07-01 | 刘翠霞 | Christmas tree oil pipe hanger |
CN113104742A (en) * | 2021-04-14 | 2021-07-13 | 潘归强 | Steel structure tower crane for building bridge road construction |
CN113104742B (en) * | 2021-04-14 | 2023-05-09 | 长沙三远钢结构有限公司 | Steel structure tower crane for construction of building bridge road |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207404708U (en) | The petroleum pipeline suspender of stability can be improved | |
CN107572358A (en) | Efficient petroleum pipeline boom hoisting | |
CN102815373A (en) | Hybrid deep water mooring system | |
CN107985516A (en) | A kind of flank extension type dynamic driving anchor | |
CN204038849U (en) | A kind of cable drum lifting device | |
CN207330136U (en) | Clamping device for petroleum pipeline transport | |
CN203892714U (en) | Petroleum pipeline supporting frame | |
CN203532957U (en) | Gas pipeline penetration fixing and roller-sliding device applied in casing pipe or tunnel | |
CN103984989A (en) | Method and system for optimizing layout of oil rig device | |
CN205025383U (en) | Well drilling pressure device | |
CN208163442U (en) | A kind of mobile fixed vehicle of portable pipe docking correction | |
CN103526612A (en) | Steel wire rope for offshore drilling platform | |
CN206606922U (en) | A kind of multitube suspender | |
CN201842225U (en) | Semi-submersible platform | |
CN204138197U (en) | The defeated cable device of a kind of packaged type | |
CN204224190U (en) | A kind of steam injection pipeline fastening means | |
CN204079223U (en) | A kind of steel pipe lifting tool | |
CN209482343U (en) | Jacket steel bucket foundation | |
CN203513104U (en) | Hoisting sling for pipeline | |
CN202379584U (en) | Adjustable suspension arm assembly | |
CN203558717U (en) | Grab bucket stabilizer for crane | |
CN208899515U (en) | A kind of T-type wing plate offshore wind turbine steel pipe pile foundation | |
CN202596237U (en) | Cantilever for wind measurement tower | |
CN204001010U (en) | Cone is grabbed in a kind of punching | |
CN105442905A (en) | Automation device of steel tube tower |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180112 |
|
RJ01 | Rejection of invention patent application after publication |