CN107571966A - A kind of method that shipping rudder system is installed under water - Google Patents

A kind of method that shipping rudder system is installed under water Download PDF

Info

Publication number
CN107571966A
CN107571966A CN201710863796.7A CN201710863796A CN107571966A CN 107571966 A CN107571966 A CN 107571966A CN 201710863796 A CN201710863796 A CN 201710863796A CN 107571966 A CN107571966 A CN 107571966A
Authority
CN
China
Prior art keywords
rudder
ship
stock
blade
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710863796.7A
Other languages
Chinese (zh)
Inventor
许国华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Hong Kong Marine Mating Machinery Co Ltd
Original Assignee
Nantong Hong Kong Marine Mating Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Hong Kong Marine Mating Machinery Co Ltd filed Critical Nantong Hong Kong Marine Mating Machinery Co Ltd
Priority to CN201710863796.7A priority Critical patent/CN107571966A/en
Publication of CN107571966A publication Critical patent/CN107571966A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Ship Loading And Unloading (AREA)

Abstract

The present invention discloses a kind of method that shipping rudder system is installed under water, 1. first ship launching prelocalization install rudder sleeve and rudder axis is delivered for a check together it is qualified, then assembling is carried out to rudder stock, rudder blade and makes an integral unit, ship enters to carry out after water the installation of rudder system under moored condition;2. adjust ship trim by adjusting ballast for cruising situation;3. rudder blade and rudder stock are moved to the underface of rudder sleeve hole;4. using the chain block of ship stern coaster hoisting mechanism by rudder stock/rudder blade integral translation to rudder sleeve underface, while lifting the bottle gouard moved by hands in steering gear flat and rudder blade being hung into upper top surface, there is certain distance between upper top surface and rudder sleeve bottom surface;5. the component of neck bearing zero is inserted on rudder stock;6. continuing to lift up rudder stock and rudder blade, then rudder carrier, steering wheel are installed again and only jump block;7. removing the coaster hoisting mechanism of ship stern, after being inspected for acceptance to whole rudder system, the set workflow can be completed.

Description

A kind of method that shipping rudder system is installed under water
Technical field
The present invention relates to a kind of method that shipping rudder system is installed under water.
Background technology
In the manufacture and installation process of ship, it is frequently encountered that berth period is tight, and during current shipbuilding The installation of rudder system must be installed before lower water, but manufacture and the installation process of the ship just made when running into building berth anxiety Stop, shipbuilding and installation process may so interrupted, manufacture and installation to ship make troubles.
The content of the invention
The invention provides a kind of method that shipping rudder system is installed under water, and it is the safety that can guarantee that equipment, and and can is quick It is accurately finished the underwater installing engineering of rudder system.
Present invention employs following technical scheme:A kind of method that shipping rudder system is installed under water, it comprises the following steps:Step Step 1, first ship launching prelocalization install rudder sleeve and rudder axis is delivered for a check together it is qualified, then to rudder stock, Rudder blade carries out assembling and makes an integral unit, and ship enters to carry out after water the installation of rudder system under moored condition;
Step 2, ship trim is adjusted by adjusting ballast for cruising situation, make to have between rudder sleeve baseplane and the water surface Spacing simultaneously keeps parallel with the water surface as far as possible, can so ensure to have the enough depth of water to meet that rudder blade bottom is not touched to the bottom What mud;Step 3, rudder blade and rudder stock are moved to the underface of rudder sleeve hole;Step 4, using ship stern coaster hoisting machine Rudder stock/rudder blade integral translation to immediately below rudder sleeve, while is lifted the bottle gouard moved by hands in steering gear flat by rudder by the chain block of structure Leaf is hung to top surface, has certain distance between upper top surface and rudder sleeve bottom surface;Step 5, the component of neck bearing zero is inserted in rudder stock On;Step 6, rudder stock and rudder blade are continued to lift up, then rudder carrier, steering wheel are installed again and only jump block;Step 7, remove ship stern Coaster hoisting mechanism, after being inspected for acceptance to whole rudder system, the set workflow can be completed.
The installation of rudder system can be carried out under water after employing technical scheme, can equally reach and install on the bank The requirement of rudder system, so not only method is simple, easy to install and use, and can alleviate the pressure that building berth lacks, Bu Huiyou Lack in building berth and interrupt the manufacture of ship and installation process, ensure that the manufacture and installation of ship, it is applied in addition The rudder system installation of various ships, it is applied widely, and can reuse.The present invention must be by the exposed surface of rudder stock before lifting The protection of grease, parcel brown paper or rubber is carried out, so can not only prevent rudder stock from being sent out during moving integrally Also can effectively it be protected when giving birth to collision and damage surface, and rudder stock being entered in water.
Embodiment
The method that a kind of shipping rudder system of the present invention is installed under water, it comprises the following steps:Step 1, first in ship launching Prelocalization install rudder sleeve and rudder axis is delivered for a check together it is qualified, it is then enterprising in platform or moulding bed to rudder stock, rudder blade Row assembling makes an integral unit, and ship enters to carry out after water the installation of rudder system under moored condition, necessary before lifting The exposed surface of rudder stock is carried out to the protection of grease, parcel brown paper or rubber;Step 2, by adjusting ballast for cruising Situation adjusts ship trim, makes to have spacing between rudder sleeve baseplane and the water surface and keeps, rudder parallel with the water surface as far as possible Spacing at least 1M between sleeve baseplane and the water surface, it can so ensure to have the enough depth of water to meet that rudder blade bottom does not touch To water-bed what mud;Step 3, rudder blade/rudder stock is hung using crane barge or wharf crane, then with four pull electrified monorail system by rudder blade/ Rudder stock is sling, and come loose wharf crane or crane barge, and rudder blade/rudder stock is moved to the underface of rudder sleeve hole;Step 4, using ship The chain block of stern coaster hoisting mechanism to immediately below rudder sleeve, while lifts rudder stock/rudder blade integral translation in steering gear flat Bottle gouard moved by hands rudder blade be hung between upper top surface and rudder sleeve bottom surface have certain distance, upper top surface and rudder sleeve bottom surface it Between distance be 1M, during lifting side rise buttonhole selvage the rudder stock surface protection oil stain removing for exposing outside water surface part is clean; Step 5, the component of neck bearing zero is inserted on rudder stock, the component of neck bearing zero includes packing box seal circle, gland, pressing plate;Step Six, rudder stock and rudder blade are continued to lift up, then rudder carrier, steering wheel are installed again and only jump block;Step 7, the coaster for removing ship stern are hung Mounting mechanism, after being inspected for acceptance to whole rudder system, the set workflow can be completed.

Claims (1)

1. a kind of method that shipping rudder system is installed under water, it comprises the following steps:
Step 1, first ship launching prelocalization install rudder sleeve and rudder axis is delivered for a check together it is qualified, it is then right Rudder stock, rudder blade carry out assembling and make an integral unit, and ship enters to carry out after water the installation of rudder system under moored condition;
Step 2, ship trim is adjusted by adjusting ballast for cruising situation, make have spacing between rudder sleeve baseplane and the water surface And keep parallel with the water surface as far as possible, it can so ensure to have the enough depth of water to meet that rudder blade bottom does not touch water-bed what Mud;
Step 3, rudder blade and rudder stock are moved to the underface of rudder sleeve hole;
Step 4, using the chain block of ship stern coaster hoisting mechanism by under rudder stock/rudder blade integral translation to rudder sleeve just Side, while lift the bottle gouard moved by hands in steering gear flat and rudder blade is hung to upper top surface, have between upper top surface and rudder sleeve bottom surface certain Distance;
Step 5, the component of neck bearing zero is inserted on rudder stock;
Step 6, rudder stock and rudder blade are continued to lift up, then rudder carrier, steering wheel are installed again and only jump block;
Step 7, the coaster hoisting mechanism of ship stern is removed, after being inspected for acceptance to whole rudder system, the set workflow is It can complete.
CN201710863796.7A 2017-09-22 2017-09-22 A kind of method that shipping rudder system is installed under water Withdrawn CN107571966A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710863796.7A CN107571966A (en) 2017-09-22 2017-09-22 A kind of method that shipping rudder system is installed under water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710863796.7A CN107571966A (en) 2017-09-22 2017-09-22 A kind of method that shipping rudder system is installed under water

Publications (1)

Publication Number Publication Date
CN107571966A true CN107571966A (en) 2018-01-12

Family

ID=61033842

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710863796.7A Withdrawn CN107571966A (en) 2017-09-22 2017-09-22 A kind of method that shipping rudder system is installed under water

Country Status (1)

Country Link
CN (1) CN107571966A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110877672A (en) * 2019-10-17 2020-03-13 沪东中华造船(集团)有限公司 Method for installing steering engine in cabin
CN111661275A (en) * 2020-05-29 2020-09-15 广州文冲船舶修造有限公司 Rudder stock replacing process
CN112319728A (en) * 2020-11-19 2021-02-05 渤海船舶重工有限责任公司 Method for fixing zero position of rudder blade of launching ship of inclined slipway
CN112606970A (en) * 2020-12-18 2021-04-06 武昌船舶重工集团有限公司 Vertical alignment tool and ship rudder system alignment hoisting method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101254821A (en) * 2008-04-15 2008-09-03 泰州口岸船舶有限公司 Underwater installation method of ship rudder system
CN101367426A (en) * 2008-06-24 2009-02-18 中国长江航运集团江东船厂 Shaft, rudder system mounting process of ten-thousand-ton grade special multipurpose vessel
CN101475045A (en) * 2008-11-14 2009-07-08 大连船舶重工集团有限公司 Hoisting method for rudder blade during shipbuilding process
CN107600315A (en) * 2017-09-15 2018-01-19 南通如港船舶配套机械有限公司 A kind of method of underwater installation rudder

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101254821A (en) * 2008-04-15 2008-09-03 泰州口岸船舶有限公司 Underwater installation method of ship rudder system
CN101367426A (en) * 2008-06-24 2009-02-18 中国长江航运集团江东船厂 Shaft, rudder system mounting process of ten-thousand-ton grade special multipurpose vessel
CN101475045A (en) * 2008-11-14 2009-07-08 大连船舶重工集团有限公司 Hoisting method for rudder blade during shipbuilding process
CN107600315A (en) * 2017-09-15 2018-01-19 南通如港船舶配套机械有限公司 A kind of method of underwater installation rudder

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110877672A (en) * 2019-10-17 2020-03-13 沪东中华造船(集团)有限公司 Method for installing steering engine in cabin
CN111661275A (en) * 2020-05-29 2020-09-15 广州文冲船舶修造有限公司 Rudder stock replacing process
CN111661275B (en) * 2020-05-29 2021-06-08 广州文冲船舶修造有限公司 Rudder stock replacing process
CN112319728A (en) * 2020-11-19 2021-02-05 渤海船舶重工有限责任公司 Method for fixing zero position of rudder blade of launching ship of inclined slipway
CN112606970A (en) * 2020-12-18 2021-04-06 武昌船舶重工集团有限公司 Vertical alignment tool and ship rudder system alignment hoisting method
CN112606970B (en) * 2020-12-18 2022-02-01 武昌船舶重工集团有限公司 Vertical alignment tool and ship rudder system alignment hoisting method

Similar Documents

Publication Publication Date Title
CN107571966A (en) A kind of method that shipping rudder system is installed under water
CN101254821A (en) Underwater installation method of ship rudder system
CN103112553B (en) The latent maintenance and repair ship of self-propulsion type half and using method
CN104443260B (en) A kind of all-direction propeller underwater portion erecting device and method
CN103661801B (en) The installation ancillary system of ocean engineering underwater propeller and installation method
AU2011250767B2 (en) Method for thruster withdrawal for maintenance or vessel transit without the need for an external crane, remote operated vehicle, or driver
CN105539749B (en) A kind of liftable floating box device of partly latent cargo ship
CN105905245B (en) The cage of recycling is laid for unmanned surface vehicle
CN101475046B (en) Large-sized thruster underwater installing process based on L type floating platform
CN103883273A (en) Method for utilizing two cranes on saturation diving support vessel to mount vertical pipe
CN106741603A (en) The flow container fast and accurately localization method when liquefaction vessel is built
CN107600315A (en) A kind of method of underwater installation rudder
CN109292040B (en) Multidirectional full-rotation rudder propeller main section installation method
CN104340336B (en) A kind of overweight sectional turn-over method of ship
CN101092161A (en) Method for final assembling transverse bulkhead and deck on ship
CN106741668B (en) The mounting process of floating production storage offloading's tieback
CN204674802U (en) A kind of ship escape system
CN105644713B (en) Propeller mounting process method
CN206243392U (en) A kind of lifeboat lowering or hoisting gear
CN205442370U (en) Whole horse mounting structure and fluid reservoir of hanging of fluid reservoir
CN108545148A (en) A kind of method of manned underwater vehicle retracting device and Emergency recovery manned underwater vehicle
CN201596891U (en) Tooling for mounting and positioning rudder propeller
CN104649139B (en) Gantry running gear peculiar to vessel
CN203318640U (en) Marine suspension type multifunctional platform
CN203904959U (en) Ship tank door anti-collision device of ship lift capable of adapting to different water level changes

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180112

WW01 Invention patent application withdrawn after publication