CN107570908A CN201710878529.7A CN201710878529A CN107570908A CN 107570908 A CN107570908 A CN 107570908A CN 201710878529 A CN201710878529 A CN 201710878529A CN 107570908 A CN107570908 A CN 107570908A
Authority
CN
China
Prior art keywords
steel band
steel
magnetic tape
lead
connecting device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710878529.7A
Other languages
Chinese (zh)
Inventor
刘伟
刘自然
卢威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hong Wang Investor Group Co Ltd
Zhaoqing Hongwang Metal Industrial Co Ltd
Original Assignee
Hong Wang Investor Group Co Ltd
Zhaoqing Hongwang Metal Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hong Wang Investor Group Co Ltd, Zhaoqing Hongwang Metal Industrial Co Ltd filed Critical Hong Wang Investor Group Co Ltd
Priority to CN201710878529.7A priority Critical patent/CN107570908A/en
Publication of CN107570908A publication Critical patent/CN107570908A/en
Pending legal-status Critical Current

Links

Landscapes

  • Arc Welding In General (AREA)

Abstract

The present invention discloses a kind of steel band and steel band connection method and device, the described method comprises the following steps:1) repair:Respectively by the first steel band take the lead and the shearing finishing of the magnetic tape trailer of the second steel band is concordant;2) centering is docked:The magnetic tape trailer for taking the lead second steel band concordant with finishing for repairing concordant first steel band is docking together with the state of centering;3) arch camber:Upwarped in first steel band for taking the lead side of first steel band curved into the first arch portion up or down, second steel band in the magnetic tape trailer side of second steel band upwarps curved into the second arch portion up or down;4) weld:First steel band being docking together is taken the lead to weld together with the magnetic tape trailer of second steel band.Compared with prior art, steel band of the invention and steel band connection method and device, can improve welding quality of the steel band in weld, improve fastness and flatness of the steel band in weld, improve production efficiency.

Description

A kind of steel band and steel band connection method and device
Technical field
The present invention relates to steel band processing technique field, more particularly, to a kind of steel band and steel band connection method and device.
Background technology
On steel band tinuous production, coiled steel band is uncoiled after machine uncoiling and transmitted successively in producing line, successively completes Each processing step.Between every coil band, by taking the lead the connection with magnetic tape trailer, so that steel band remains on a production line One complete steel band.
At present, the preceding a roll of steel band magnetic tape trailer after uncoiling takes the lead directly to utilize bonding machine welding to connect with rear a roll of steel band Connect, make to form a complete steel band.But this connection method at present is in the weld fastness deficiency of steel band, Er Qie The planarization of weld is also inadequate, and during subsequent transmission, steel band easily occurs being broken or holding steel band in above-mentioned weld Easily block, influence production efficiency.
The content of the invention
The invention aims to solve the problems of the prior art, a kind of steel band and steel band connection method and dress are proposed Put, welding quality of the steel band in weld can be improved, improve fastness and flatness of the steel band in weld, improve production effect Rate.
The technical solution adopted by the present invention is as follows:
A kind of steel band and steel band connection method, the described method comprises the following steps:
1) repair:Respectively by the first steel band take the lead and the shearing finishing of the magnetic tape trailer of the second steel band is concordant;
2) centering is docked:The band for taking the lead second steel band concordant with finishing of concordant first steel band will be repaired Tail is docking together with the state of centering;
3) arch camber:Upwarped in first steel band for taking the lead side of first steel band curved into up or down One arch portion, second steel band in the magnetic tape trailer side of second steel band upwarp curved into the second arch up or down Portion;
4) weld:By first steel band being docking together take the lead be welded on one with the magnetic tape trailer of second steel band Rise.
Further, methods described is further comprising the steps of:
Breach processed:After the completion of welding, steel band welding weld seam both sides produced respectively in a manner of removing material to A few breach.
Further, first arch portion is set with second arch portion towards identical direction.
A kind of steel band and steel band connecting device, the steel band include jig with steel band connecting device, and the welding is flat Platform both sides are respectively provided with a clamping claw, and a pinch roll set is respectively provided with the outside of the clamping claw of the both sides, and the installation is flat Welder, in addition to cutting means and centering detection means are provided with the upside of the middle part of platform, the cutting means are used to trim steel Take the lead, whether the centering detection means is placed in the middle for detecting position of the steel band on the jig.
Further, the cutting means are provided with one and the clamping claw on front side of the jig and institute State between pinch roll set.
Further, the centering detection means is optoelectronic switch, and the optoelectronic switch includes being located at the jig The first more than upper surface inductive probe and the second inductive probe below the jig upper surface, first sense The relative induction between second inductive probe that should pop one's head in is set.
Further, the clamping claw includes upper clamp and lower clamp, is set between the upper clamp and the lower clamp Have and horizontal pass through passageway;It is installed on including at least a clamping claw on horizontal transfer device.
Further, the steel band also includes jaw mounting bracket with steel band connecting device, and the lower clamp is fixed on described On jaw mounting bracket, the jaw mounting bracket on the upside of the lower clamp is provided with hydraulic pump, the hydraulic pump output shaft direction The lower clamp is set, and the hydraulic pump output shaft end is provided with mounting seat, and the upper clamp is in the mounting seat.
Further, the steel band and steel band connecting device also include horizontally disposed guide rail, on the jaw mounting bracket Provided with roller, the roller is on the guide rail, and the roller can be along the guide rail scroll forward and backward.
Further, also it is respectively provided with steering roller group on the outside of the pinch roll set of the both sides.
The beneficial effects of the invention are as follows:
A kind of steel band of the present invention and steel band connection method and device, when two bar steel tape weldings are connected into a steel band, Respectively by the first steel band repair after take the lead with the second steel band repair after magnetic tape trailer centering dock after, also respectively on the first steel band Warpage goes out the first arch portion, and warpage goes out the second arch portion on the second steel band, so as on the first steel band and on the second steel band Restoring force is produced, this restoring force acts on the end that the first steel band and the second steel band are mutually butted, makes the first steel band and second The end of steel band docking remains close contact, so that obtaining welding quality just after the completion of welding;After making welding Steel band it is more firm in weld;In addition, the first steel band and the second steel band are welded after trimmed, the thickness of steel band Spend it is basically identical, so as to substantially smooth steel band after being welded.Thus, a kind of steel band of the present invention and steel band connection method and dress Put, welding quality of the steel band in weld can be improved, improve fastness and flatness of the steel band in weld, improve production effect Rate.
The preferred embodiments of the invention and its advantage, embodiment will be combined and be further described.
Brief description of the drawings
Accompanying drawing be for providing a further understanding of the present invention, and a part for constitution instruction, it is and following specific Embodiment is used to explain the present invention together, but should not be construed as limiting the invention.In the accompanying drawings,
Fig. 1:The topology view of a kind of steel band and steel band connecting device in the embodiment of the present invention two;
Fig. 2:The present invention applies the clamping claw topology view for being provided with horizontal transfer device in example two.
Each component names and its label
1st, jig;2nd, clamping claw;3rd, pinch roll set;4th, welder;5th, cutting means;6th, roller group is turned to;7、 Arch portion;8th, jaw mounting bracket;9th, hydraulic pump;10th, roller;11st, guide rail;12nd, mounting seat;21st, upper clamp;22nd, lower clamp.
Embodiment
The embodiment of the present invention is described in detail below in conjunction with accompanying drawing.It should be appreciated that this place is retouched The embodiment stated is merely to illustrate and explain the present invention, and is not intended to limit the invention.
Embodiment one
Embodiments of the invention disclose a kind of steel band and steel band connection method, the described method comprises the following steps:
The first step, finishing:Respectively by the first steel band take the lead and the shearing finishing of the magnetic tape trailer of the second steel band is concordant.Because into The steel band of volume is taking the lead often have situations such as warpage, became uneven is even with magnetic tape trailer, is so alignment when not utilizing the steel band to weld Keep smooth after being welded with steel band, therefore, before steel band welding, will first take the lead or magnetic tape trailer is trimmed, and trimming is gone out one The uniform steel band of individual smooth and thickness is taken the lead or magnetic tape trailer.
Second step, centering docking:Concordant first steel band of finishing is taken the lead into second steel concordant with finishing The magnetic tape trailer of band is docking together with the state of centering.Two different steel bands are welded together, it is necessary to make taking the lead for steel band First contact with the magnetic tape trailer of another steel band, in addition, if the steel band being docking together can not keep mutual centering, that is, occur Offset from each other, two steps just occur in weld over there, be unfavorable for steel band and subsequently transmit on a production line.
3rd step, arch camber:First steel band for taking the lead side of first steel band upwarp it is curved into upwards or to Under the first arch portion, second steel band in the magnetic tape trailer side of second steel band upwarps curved into up or down Two arch portions.It should be noted that the first arch portion is from a distance from the taking the lead of the first steel band and the second arch portion is from the second steel The distance of the magnetic tape trailer of band should appropriateness distance, it is too near or too remote bad;When too near, easily make steel band docking take the lead with There is warpage in magnetic tape trailer;When too remote, formation in joint, compression dynamics is inadequate to steel band.Therefore, appropriate distance should root According to the thickness and width of steel band by being calculated.
4th step, welding:First steel band being docking together is taken the lead to weld with the magnetic tape trailer of second steel band Together.So far, the connection of steel band is completed, and obtained steel band is good in the welding quality of weld, improves steel band in weld Fastness and flatness.
Further, methods described is further comprising the steps of:
5th step, breach processed:After the completion of welding, in the weld seam both sides system in a manner of removing material respectively of steel band welding Make at least one breach.The reason for breach processed is:Although the above method has the step of Steel Belt Centering in steel band welding process Suddenly, still, due to the error of centralization and the reason for welding slag when welding, steel band after welding still has in both sides can not Ensure complete concordant.Therefore, the purpose of breach processed is exactly:In steel band both sides, a part of material is removed in not concordant enough commissure Material, a breach is formed, steel band is narrowed in weld.Because the steel band after narrowing is to have an impact in transmitting procedure , it can influence to transmit when only broadening.
Further, first arch portion is set with second arch portion towards identical direction.In the present embodiment In, first arch portion is set together upward with second arch portion.
Embodiment two
It refer to shown in Fig. 1-2, a kind of steel band and steel band connecting device, the steel band includes welding with steel band connecting device Platform 1, the both sides of jig 1 are respectively provided with a clamping claw 2, and the outside of clamping claw 2 of the both sides is respectively provided with one Pinch roll set 3, the middle part upside of the mounting platform 2 are provided with welder 4, in addition to cutting means 5 and centering detection means, The cutting means 5 are used to trim steel taping head, and the centering detection means is used to detect position of the steel band on the jig 1 Whether placed in the middle put.
The cutting means 5 are provided with one and the clamping claw 2 located at the front side of jig 1 and the pinch Between roller group 3.The pinch roll set 3 includes upper beaming roller and lower roller, and steel band passes through between upper beaming roller and lower roller, wherein, A drive roll is comprised at least between the upper beaming roller and lower roller, and the drive roll has main story and the function of back pass, rotates forward When, steel band can be fed forward by pinch roll set 3, and during reversion, pinch roll set 3 can convey steel band backward.
The centering detection means is optoelectronic switch, the optoelectronic switch include located at the upper surface of jig 1 with On the first inductive probe and the second inductive probe below the upper surface of jig 1, first inductive probe Relative induction is set between second inductive probe.
The clamping claw 2 includes upper clamp 21 and lower clamp 22, is set between the upper clamp 21 and the lower clamp 22 Have and horizontal pass through passageway;It is installed on including at least a clamping claw 2 on horizontal transfer device.Horizontal passes through passageway For steel band by, can be by steel belt clamping on described that is, when the upper clamp 21 and the lower clamp 22 mutually clamp Between clamp 21 and the lower clamp 22.The effect of the horizontal transfer device is for when end is docked between steel band and steel band Mobile effect, at least one steel band is moved towards the direction of docking by the horizontal transfer device, reach steel band end The purpose of portion's docking.
The steel band also includes jaw mounting bracket 8 with steel band connecting device, and the lower clamp 22 is fixed on the jaw peace Shelve on 8, the jaw mounting bracket 8 of the upside of lower clamp 22 is provided with hydraulic pump 9, the defeated 9 shaft direction of hydraulic pump The lower clamp 22 is set, and the output shaft end of the hydraulic pump 9 is provided with mounting seat 12, and the upper clamp 21 is located at the installation On seat 12.
The steel band also includes horizontally disposed guide rail 11 with steel band connecting device, and the jaw mounting bracket 8 is provided with rolling Wheel 10, the roller 10 is on the guide rail 11, and the roller 10 can be along the scroll forward and backward of guide rail 11.Therefore, at this In embodiment, above-mentioned horizontal transfer device is to be made up of the jaw mounting bracket 8, roller 10 and guide rail 11.
The outside of pinch roll set 3 of the both sides, which is also respectively provided with, turns to roller group 6.It is described steering roller group 6 also include upper beaming roller and Lower roller, steel band pass through between upper beaming roller and lower roller, are passive in the upper beaming roller and lower roller of steering roller group 6 still Roller, without the function of active rotation.Steering roller group 6 is usually arranged as horizontal line and is higher or lower than pinch roll set 3, for making steel band Excessively to another not on the transmission platform in same level direction.
It should be noted that in the present embodiment, the principle that the steel band on front side of jig forms arch portion is:It is located at The clamping claw 3 of the front side of jig 1 is by after the smooth preceding steel belt clamping of the trimming, by the pinch roll set 3 of front side forward Continue to send band, so as to which the steel band section between front side clamping claw 2 and front side pinch roll set 3 starts upturned, formation front side Arch portion 7.Similarly, the principle of the steel band formation arch portion of the rear side of jig 1 is:Positioned at the clamping clip of the rear side of jig 1 Mouth 2 send band, so as in rear side clamping clip backward by after the smooth rear steel belt clamping of the trimming by the pinch roll set 3 of rear side Steel band section between mouth 2 and rear side pinch roll set 3 starts upturned, formation rear side arch portion 7.It is understood that clamp Spacing between jaw 2 and pinch roll set 3 is also very crucial, should be determined in specific design by reasonable computation.
In the present embodiment, cutting means 5 only set one, and located at front side pinch roll set 3 and front side clamping claw 2 it Between, therefore, no matter steel band is taken the lead or when magnetic tape trailer passes through cutting means 5, and cutting means 5 unified will all trim to them Processing, makes to reach smooth requirement.
In summary, two bar steel tape weldings are being connected into one by a kind of steel band of the invention and steel band connection method and device During steel band, respectively by the first steel band repair after take the lead with the second steel band repair after magnetic tape trailer pair in dock after, also exist respectively Warpage goes out the first arch portion on first steel band, and warpage goes out the second arch portion on the second steel band, so as on the first steel band and Restoring force is produced on second steel band, this restoring force acts on the end that the first steel band and the second steel band are mutually butted, and makes first Steel band remains close contact with the end that the second steel band docks, so that obtaining welding matter just after the completion of welding Amount;Make the steel band after welding more firm in weld;In addition, the first steel band and the second steel band are welded after trimmed , the thickness of steel band is basically identical, so as to substantially smooth steel band after being welded.Thus, a kind of steel band of the present invention and steel band Connection method and device, can improve welding quality of the steel band in weld, improve steel band in the fastness of weld and smooth Degree, improve production efficiency.
Without departing from the thought of the invention, the various different embodiments of the present invention are combined, all should When being considered as present disclosure;In the range of the technology design of the present invention, a variety of simple modifications are carried out to technical scheme And any combination of the thought without prejudice to the invention that different embodiments are carried out, all should protection scope of the present invention it It is interior.

Claims (10)

1. a kind of steel band and steel band connection method, it is characterised in that the described method comprises the following steps:
1) repair:Respectively by the first steel band take the lead and the shearing finishing of the magnetic tape trailer of the second steel band is concordant;
2) centering is docked:By the magnetic tape trailer for taking the lead second steel band concordant with finishing for repairing concordant first steel band with The state of centering is docking together;
3) arch camber:Upwarped in first steel band for taking the lead side of first steel band curved into the first arch up or down Shape portion, second steel band in the magnetic tape trailer side of second steel band upwarp curved into the second arch portion up or down;
4) weld:First steel band being docking together is taken the lead to weld together with the magnetic tape trailer of second steel band.
2. a kind of steel band according to claim 1 and steel band connection method, it is characterised in that methods described also includes following Step:
Breach processed:After the completion of welding, at least one is produced in a manner of removing material respectively in the weld seam both sides of steel band welding Individual breach.
3. a kind of steel band according to claim 1 or 2 and steel band connection method, it is characterised in that first arch portion Set with second arch portion towards identical direction.
4. a kind of steel band and steel band connecting device, it is characterised in that the steel band includes jig, institute with steel band connecting device State jig both sides and be respectively provided with a clamping claw, a pinch roll set, institute are respectively provided with the outside of the clamping claw of the both sides State and welder, in addition to cutting means and centering detection means are provided with the upside of the middle part of mounting platform, the cutting means are used It is whether placed in the middle for detecting position of the steel band on the jig in trimming steel taping head, the centering detection means.
5. a kind of steel band according to claim 4 and steel band connecting device, it is characterised in that the cutting means are provided with one Between the individual and clamping claw on front side of the jig and the pinch roll set.
6. a kind of steel band according to claim 4 and steel band connecting device, it is characterised in that the centering detection means is Optoelectronic switch, the optoelectronic switch include the first inductive probe being located at more than the jig upper surface and located at the welderings Connect the second inductive probe below platform upper surface, relative induction between first inductive probe and second inductive probe Set.
7. a kind of steel band according to claim 4 and steel band connecting device, it is characterised in that the clamping claw includes upper Clamp and lower clamp, pass through passageway provided with horizontal between the upper clamp and the lower clamp;Including at least a folder Clencher mouth is installed on horizontal transfer device.
8. a kind of steel band according to claim 7 and steel band connecting device, it is characterised in that the steel band is connected with steel band Device also includes jaw mounting bracket, and the lower clamp is fixed on the jaw mounting bracket, the pincers on the upside of the lower clamp Mouth mounting bracket is provided with hydraulic pump, and the hydraulic pump output shaft is set towards the lower clamp, and the hydraulic pump output shaft end Portion is provided with mounting seat, and the upper clamp is in the mounting seat.
9. a kind of steel band according to claim 7 and steel band connecting device, it is characterised in that the steel band is connected with steel band Device also includes horizontally disposed guide rail, and the jaw mounting bracket is provided with roller, and the roller is on the guide rail, and institute Stating roller can be along the guide rail scroll forward and backward.
10. a kind of steel band according to claim 4 and steel band connecting device, it is characterised in that the pinch roll of the both sides Group outside is also respectively provided with steering roller group.
CN201710878529.7A 2017-09-26 2017-09-26 A kind of steel band and steel band connection method and device Pending CN107570908A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710878529.7A CN107570908A (en) 2017-09-26 2017-09-26 A kind of steel band and steel band connection method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710878529.7A CN107570908A (en) 2017-09-26 2017-09-26 A kind of steel band and steel band connection method and device

Publications (1)

Publication Number Publication Date
CN107570908A true CN107570908A (en) 2018-01-12

Family

ID=61040327

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710878529.7A Pending CN107570908A (en) 2017-09-26 2017-09-26 A kind of steel band and steel band connection method and device

Country Status (1)

Country Link
CN (1) CN107570908A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108723622A (en) * 2018-05-31 2018-11-02 山西太钢不锈钢精密带钢有限公司 A kind of welding method of precise stainless steel strip material
CN109794733A (en) * 2019-01-15 2019-05-24 中国石油天然气集团有限公司 A kind of oil-gas transportation X90 grade of steel φ 1524mm super large caliber heavy wall SAW spiral welded pipe and its manufacturing method
CN111872679A (en) * 2020-08-10 2020-11-03 中石化石油机械股份有限公司沙市钢管分公司 Automatic strip steel centering, cutting and welding device and method for spiral steel pipe production line
CN113044629A (en) * 2021-03-09 2021-06-29 佛山市诚德新材料有限公司 Laser welding device on rolling line
CN113369729A (en) * 2021-04-30 2021-09-10 北新集团建材股份有限公司 Belt head adjusting mechanism of metal belt and metal belt continuous conveying equipment

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1190684A (en) * 1997-09-24 1999-04-06 Nissan Motor Co Ltd Positioning device for butting blank materials
JP2002361488A (en) * 2001-06-06 2002-12-18 Nissan Motor Co Ltd Gap correcting device for blank material
CN101011789A (en) * 2007-02-12 2007-08-08 大连三高应用技术发展公司 Shearing butt welding machine
CN101287572A (en) * 2005-10-14 2008-10-15 丰田自动车株式会社 System and method for butt-welding of steel plate
CN203566238U (en) * 2013-11-07 2014-04-30 江苏省南扬机械制造有限公司 Shearing butt welding machine
CN204413409U (en) * 2014-12-24 2015-06-24 福建鼎信科技有限公司 Except alice device during a kind of stainless steel annealing pickling line steel band welding

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1190684A (en) * 1997-09-24 1999-04-06 Nissan Motor Co Ltd Positioning device for butting blank materials
JP2002361488A (en) * 2001-06-06 2002-12-18 Nissan Motor Co Ltd Gap correcting device for blank material
CN101287572A (en) * 2005-10-14 2008-10-15 丰田自动车株式会社 System and method for butt-welding of steel plate
CN101011789A (en) * 2007-02-12 2007-08-08 大连三高应用技术发展公司 Shearing butt welding machine
CN203566238U (en) * 2013-11-07 2014-04-30 江苏省南扬机械制造有限公司 Shearing butt welding machine
CN204413409U (en) * 2014-12-24 2015-06-24 福建鼎信科技有限公司 Except alice device during a kind of stainless steel annealing pickling line steel band welding

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108723622A (en) * 2018-05-31 2018-11-02 山西太钢不锈钢精密带钢有限公司 A kind of welding method of precise stainless steel strip material
CN109794733A (en) * 2019-01-15 2019-05-24 中国石油天然气集团有限公司 A kind of oil-gas transportation X90 grade of steel φ 1524mm super large caliber heavy wall SAW spiral welded pipe and its manufacturing method
CN111872679A (en) * 2020-08-10 2020-11-03 中石化石油机械股份有限公司沙市钢管分公司 Automatic strip steel centering, cutting and welding device and method for spiral steel pipe production line
CN113044629A (en) * 2021-03-09 2021-06-29 佛山市诚德新材料有限公司 Laser welding device on rolling line
CN113369729A (en) * 2021-04-30 2021-09-10 北新集团建材股份有限公司 Belt head adjusting mechanism of metal belt and metal belt continuous conveying equipment

Similar Documents

Publication Publication Date Title
CN107570908A (en) A kind of steel band and steel band connection method and device
JP4500884B2 (en) Method and apparatus for joining metal plates
KR101333268B1 (en) Roll forming apparatus for long-rail frame
JP4500883B2 (en) Mash seam welding method and apparatus
JP2609405B2 (en) I-type steel production equipment
CN105690096A (en) Extrusion forming and welding combined device for straight seam steel pipe
JPWO2018181397A1 (en) Welding judgment device and welding judgment method for strip plate
CN104476192A (en) Automatic winding and forming device of tank and forming method
WO2018181398A1 (en) Welding determination device for belt-shaped sheets, and welding determination method
CN206415418U (en) A kind of middle base attachment means and system
JP3401496B2 (en) Method and apparatus for transferring a hollow molded body blank
CN205600303U (en) Transversal joint steel pipe extrusion welds composite set
JP5515423B2 (en) Large coil manufacturing equipment for ERW steel pipes
CN206047411U (en) A kind of production line for the full-automatic welding of electromobile frame
JP6684634B2 (en) Steel pipe manufacturing equipment and steel pipe manufacturing method
TWI721849B (en) Welding wire connecting device and operation method thereof
JP4606622B2 (en) Method for adjusting the joining position of workpieces
JP5780233B2 (en) Method and apparatus for cooling sheet bar joint in hot rolling
KR101170169B1 (en) Butt welding device for joining two fin material together for heat exchanger
JP3485414B2 (en) Hot butt joining method
JPH08300008A (en) Device for welding sheet bar in fully continuous hot rolling
JPH05161915A (en) Manufacture of spirally welded pipe
JP4474825B2 (en) Cutting device at both ends of steel strip width direction
JP6052782B2 (en) Manufacturing method of joining member
KR101862828B1 (en) Apparatus and method for connecting coil

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180112

RJ01 Rejection of invention patent application after publication