CN107558805A - Municipal road construction enclosing board mounting structure and its construction method - Google Patents

Municipal road construction enclosing board mounting structure and its construction method Download PDF

Info

Publication number
CN107558805A
CN107558805A CN201710478538.7A CN201710478538A CN107558805A CN 107558805 A CN107558805 A CN 107558805A CN 201710478538 A CN201710478538 A CN 201710478538A CN 107558805 A CN107558805 A CN 107558805A
Authority
CN
China
Prior art keywords
barrier
conveyer belt
engineering truck
anchoring
doorframe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710478538.7A
Other languages
Chinese (zh)
Other versions
CN107558805B (en
Inventor
渠承明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Haoyuan Construction Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910097175.1A priority Critical patent/CN109812129B/en
Priority to CN201710478538.7A priority patent/CN107558805B/en
Publication of CN107558805A publication Critical patent/CN107558805A/en
Application granted granted Critical
Publication of CN107558805B publication Critical patent/CN107558805B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses municipal road construction enclosing board mounting structure, including anchoring, engineering truck, barrier, it is characterised in that:The engineering truck is connected by draw-gear with anchoring;Barrier is overall one block of plate, and its top is provided with the hook for catching on steel wire rope;The leading portion of the engineering truck is provided with push arm, the push arm is connected with the hydraulic push rod being fixed on above engineering truck, and the hydraulic push rod is with being provided with baffle plate, the stage casing installation conveyer belt of the engineering truck at push arm contact, rear end is provided with support body, and the side of support body is provided with doorframe;Driving wheel by motor driven is installed, the driving wheel is laid in the top of the discharge end of conveyer belt, and the driving wheel drives auxiliary wheel rotation, and the auxiliary wheel is provided with barrier conveyer belt one up and down on support body;The invention has the advantages that the present invention builds and removed mechanization by designing automanual machine application in surrounding baffle Fast Installation the arrangement achieves surrounding baffle, speed is fast, and automaticity is high, reduces manual operation and saves human cost, and it is safe, it is adapted to promote the use of.

Description

Municipal road construction enclosing board mounting structure and its construction method
Technical field
The present invention relates to a kind of municipal road construction enclosing board mounting structure and its construction method, belongs to civil engineering technology neck Domain.
Background technology
Surrounding baffle be a kind of a kind of building site after the processing such as machine die mould, spray painting, bending safeguard and with the external world every From a kind of section bar, suitable for construction site, highway maintenance, a kind of light-duty sheet material that is isolated from the outside of job site.It is prevented fires, Waterproof, it is moistureproof in light weight the features such as be widely used.
As Publication No. CN106285195A discloses, the present invention relates to a kind of Novel engineering height adjustable construction enclosing Plate, it is made up of overhead gage and lower baffle plate, overhead gage is plugged on lower baffle plate top, to adjust the height of overall surrounding baffle.By upper gear Plate is moved down, and shank is inserted in inserting groove, the panel of overhead gage is embedded into panel slot and pinched, by fixed lockhole and grafting The fixed via of bar bottom is coaxial, and runs through a pin, upper lower baffle plate is fixed together, and then have adjusted the height of surrounding baffle Degree.The Novel engineering height adjustable construction that the application provides is formed with air vent with surrounding baffle on baffle plate, ensures wind from air vent By reducing the pressure of surrounding baffle, increasing the stability of surrounding baffle.
And for example the Publication No. CN203783244U utility models disclose a kind of angle-inserting type fast-assembling enclosing plate, including plate Block matrix and the reinforcement being arranged on plate matrix, the transverse ends of the plate matrix are respectively equipped with one in the of C fonts One fastener and one be in J fonts the second fastener, wherein, the breach of the C fonts of the first fastener is towards the second fastener;Second fastener The circular arc shaped portion of J fonts is connected with plate matrix, and the center of circle of the circular arc shaped portion deviates from the first fastener, and the circular arc shaped portion Internal diameter matched with the external diameter of the C fonts of the first fastener.The utility model is by cleverly designing, by between existing enclosing plate C-J type attachment structures are changed into by C-C type attachment structures, enable the first fastener of C fonts direct by way of oblique cutting Stretch into and snapping positioning is carried out in the second fastener of J fonts, complete the interplate splicing of enclosing, it is very convenient quick, form oblique cutting The enclosing that formula fast-assembling enclosing plate is formed is time saving and energy saving.
Existing surrounding baffle is all that packing is transported to building site, is then barricaded as barricade by one piece of block splicing of workmen, this Sample, which is built, needs a large amount of manpowers, and the speed built and removed is very slow, and low construction efficiency, speed is slow, long in time limit.
The content of the invention
For above-mentioned deficiency, the invention of this reality provides a kind of municipal road construction enclosing board mounting structure and its construction party Method, by the present invention in that constructed with semi-automated mechanism, it is easy to operate, manpower and materials have been saved, have saved the engineering time.
The concrete technical scheme that the present invention carries is as follows:
Municipal road construction enclosing board mounting structure, including anchoring, engineering truck, barrier, it is characterised in that:The work Journey car is connected by draw-gear with anchoring;Barrier is overall one block of plate, and its top is provided with the hook for catching on steel wire rope;
The leading portion of the engineering truck is provided with push arm, and the push arm and the hydraulic push rod being fixed on above engineering truck connect Connect, the hydraulic push rod is with being provided with baffle plate at push arm contact, the stage casing installation conveyer belt of the engineering truck, rear end is provided with Support body, the side of support body are provided with doorframe;Driving wheel by motor driven is installed, the driving wheel is laid in transmission on support body The top of the discharge end of band, the driving wheel drive auxiliary wheel rotation, and the auxiliary wheel is provided with barrier conveyer belt one up and down;Institute The rotating disk for being also equipped with driving in support body by bottom motors two is stated, four faces of the rotating disk are equipped with armlet, the armlet Bottom carry on a shoulder pole plate for transition, the triangular rack being fixed on above support body, the connection installation of hydraulic cylinder two are installed above the armlet Push rod two is installed on the lower section of triangular rack, the hydraulic cylinder two and is directed at doorframe, the both sides of the doorframe are also equipped with leading to Cross the barrier conveyer belt two that motor three drives rotation material transfer;
The anchoring includes base, and the base is mounted below universal wheel, and electric reel and mechanical arm are arranged on bottom Above, the tool arm is spaced above to be provided with pulley to seat, and cable wire fixator on the doorframe, steel wire rope one end is fixed on cable wire and consolidated Determine on device, be then passed through after the pulley above anchoring, the other end is wound on electric reel.
Preferentially, be also equipped with the inside of the armlet gear buckle, it is described gear button one end be hinged on pin, the other end and The spring connection being fixed on armlet.
Based on said apparatus, the present invention also provides a kind of municipal road construction surrounding baffle construction method of installation, and its feature exists In comprising the following steps:
1) engineering truck being connected by draw-gear with anchoring, engineering truck drives anchoring to reach job site, Reached the spot simultaneously using charge of trucks barrier;
2) both anchoring and engineering truck are separated according to site operation situation, and anchoring is transferred to specific bit After putting, steel wire rope one end is fixed on cable wire fixator, is then passed through after the pulley above anchoring, the other end is wound on On electric reel, start electric reel and tense steel wire rope;
3) charge of trucks barrier is directly unloaded on conveyer belt, barrier is advanced slowly under the drive of hydraulic stem;
4) push arm advances the barrier conveyer belt one that barrier is entangled and is pushed into and is symmetrically installed under the drive of hydraulic push rod Interior, barrier conveyer belt one advances under the indirect drive of motor is sent into barrier on the armlet on rotating disk, and gear button clasps barrier;
5) barrier is sent into frame side by rotating disk constantly rotation, when barrier reaches doorframe face, band of the push rod two in hydraulic cylinder two Barrier is pushed open under dynamic and is sent into barrier conveyer belt two, then during this:Spring is elongated, and gear button rotates along pin, so Barrier just departs from the constraint of gear button, while keeps off button and also spring back to original position;
6) when when barrier is sent to doorframe by barrier conveyer belt two, the hook above barrier catches on steel wire rope automatically On;
7) continuous repeat step 3) -6), such barrier is just constantly admitted to arrangement form surrounding baffle on steel wire rope, construction Terminate.
The invention has the advantages that the present invention is by designing automanual machine application in surrounding baffle Fast Installation, Mechanization is built and removed the arrangement achieves surrounding baffle, and speed is fast, and automaticity is high, reduces manual operation and saves people Power cost, and it is safe, it is adapted to promote the use of.
Brief description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Schematic diagram when Fig. 1 is municipal road construction enclosing board mounting structure construction of the present invention;
Another view direction schematic diagram when Fig. 2 is municipal road construction enclosing board mounting structure construction of the present invention;
Fig. 3 is the structure chart of barrier of the present invention;
Fig. 4 is the side view of barrier of the present invention;
Fig. 5 is the structure chart of gear button;
Fig. 6 is the structural representation of engineering truck second half section of the present invention;
Fig. 7 is anchoring structure chart of the present invention;
Fig. 8 is the structure chart of another view direction of engineering truck second half section of the present invention.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to Limit the present invention.
Embodiment 1
Municipal road construction enclosing board mounting structure, including anchoring 1, engineering truck 4, barrier 2, the engineering truck 4 are logical Draw-gear is crossed to be connected with anchoring 1;In the present embodiment, barrier 2 is overall one block of plate, and its top, which is provided with, catches on steel wire rope 3 Hook.
The leading portion of engineering truck 4 is provided with push arm 8, the push arm 8 and the hydraulic push rod 22 being fixed on above engineering truck 4 Connection, the hydraulic push rod 22 and push arm 8 contact position are provided with baffle plate 23, and baffle plate 23 is in order to prevent barrier 2 from falling down.The work The stage casing installation conveyer belt 10 of journey car 4, conveyer belt 10 can be moved in work progress, can not also moved, meanwhile, transmission Speed can also be adjusted, and in the present embodiment, conveyer belt 10 slowly moves.
The rear end of engineering truck 4 is provided with support body 24, and the side of support body 24 is provided with doorframe 26;It is provided with support body 24 and passes through electricity The driving wheel 14 that machine drives, the driving wheel 14 are laid in the top of the discharge end of conveyer belt 10, and the driving wheel 14 drives auxiliary The rotation of wheel 16 is helped, the auxiliary wheel is provided with barrier conveyer belt 1 about 16;It is also equipped with passing through bottom in the support body 24 The rotating disk 25 that motor two drives, four faces of the rotating disk 25 are equipped with armlet 12, and plate is carried on a shoulder pole in the bottom of the armlet 12 for transition 11, the top of the armlet 12 is provided with the triangular rack 17 being fixed on above support body 24, and the connection of hydraulic cylinder 2 18 is arranged on three The lower section of angle hanger 17, push rod 2 19 is installed on the hydraulic cylinder 2 18 and is directed at doorframe 26, the both sides of the doorframe 26 are also pacified Equipped with the barrier conveyer belt 2 20 that rotation material transfer is driven by motor three;
Anchoring 1 includes base 107, and the base 107 is mounted below universal wheel 108, electric reel 106 and mechanical arm 103 are arranged on above base 107, and the tool arm 103 is spaced above to be provided with pulley 101, cable wire fixator on the doorframe 26 9, the one end of steel wire rope 3 is fixed on cable wire fixator 9, is then passed through after the pulley 101 above anchoring 1, the other end is wound on On electric reel 106.
The inner side of armlet 12 is also equipped with gear and buckle 13, and one end of the gear button 13 is hinged on pin 31, the other end with admittedly The spring 32 being scheduled on armlet 12 connects.
Based on said apparatus, the present invention also proposes a kind of municipal road construction surrounding baffle construction method of installation, including as follows Step:
1) engineering truck 4 is connected by draw-gear with anchoring 1, it is existing that engineering truck 4 drives anchoring 1 to reach construction , while reached the spot using charge of trucks barrier 2;
2) according to site operation situation, by anchoring 1 and engineering truck 4, both are separated, and anchoring 1 is transferred into finger After positioning is put, the one end of steel wire rope 3 is fixed on cable wire fixator 9, is then passed through after the pulley 101 above anchoring 1, The other end is wound on electric reel 106.Start electric reel 106 to tense steel wire rope 3;
3) charge of trucks barrier 2 is directly unloaded on conveyer belt 10, barrier 2 is advanced slowly under the drive of hydraulic stem;
4) push arm 8 advances under the drive of hydraulic push rod 22 entangles and is pushed into the barrier that is symmetrically installed by barrier 2 and transmit In band 1, barrier conveyer belt 1 advances under the indirect drive of motor is sent into barrier 2 on the armlet 12 on rotating disk 25, Gear button 13 clasps barrier 2;
5) barrier 2 is sent into the side of doorframe 26 by the constantly rotation of rotating disk 25, and when barrier 2 reaches 26 face of doorframe, push rod 2 19 is in liquid Barrier 2 is pushed open under the drive of cylinder pressure 2 18 and is sent into barrier conveyer belt 2 20, then during this:Spring 32 is elongated, gear button 13 rotate along pin 31, and such barrier 2 just departs from the constraint of gear button 13, while keeps off button 13 and also spring back to original position;
6) when when barrier 2 is sent to doorframe 26 by barrier conveyer belt 2 20, the hook above barrier 2 catches on steel automatically In cord 3;
7) continuous repeat step 3) -6), such barrier 2 is just constantly admitted to arrangement form surrounding baffle on steel wire rope 3, applies Work terminates.
Embodiment 2
Municipal road construction enclosing board mounting structure, including anchoring 1, engineering truck 4, barrier 2, the engineering truck 4 are logical Draw-gear is crossed to be connected with anchoring 1;It is sufficiently bulky due to barrier 2 in work progress, what such lorry transported every time Limited amount, in order to solve this problem, save the volume of barrier, increase freight volume, in the present embodiment, barrier barrier 2 includes upper Barrier 210 and lower barrier 211, the both sides of the upper barrier 210 are provided with side chute 202 and slip into barrier 210 for lower barrier 211 Inside;The upper barrier 210, top hanging groove 203 is installed, cable wire lock 204 is arranged on upper barrier 210, thereon Face is locked with to be connected with lower barrier 211 simultaneously from the back side through the cable wire 201 come, the cable wire 201, while can also use folding Folded barrier.
The leading portion of engineering truck 4 is provided with push arm 8, the push arm 8 and the hydraulic push rod 22 being fixed on above engineering truck 4 Connection, the hydraulic push rod 22 and push arm 8 contact position are provided with baffle plate 23, and baffle plate 23 is in order to prevent barrier 2 from falling down.The work The stage casing installation conveyer belt 10 of journey car 4, conveyer belt 10 can be moved in work progress, can not also moved, meanwhile, transmission Speed can also be adjusted, and in the present embodiment, conveyer belt 10 slowly moves.
The rear end of engineering truck 4 is provided with support body 24, and the side of support body 24 is provided with doorframe 26;It is provided with support body 24 and passes through electricity The driving wheel 14 that machine drives, the driving wheel 14 are laid in the top of the discharge end of conveyer belt 10, and the driving wheel 14 drives auxiliary The rotation of wheel 16 is helped, the auxiliary wheel is provided with barrier conveyer belt 1 about 16;It is also equipped with passing through bottom in the support body 24 The rotating disk 25 that motor two drives, four faces of the rotating disk 25 are equipped with armlet 12, and plate is carried on a shoulder pole in the bottom of the armlet 12 for transition 11, the top of the armlet 12 is provided with the triangular rack 17 being fixed on above support body 24, and the connection of hydraulic cylinder 2 18 is arranged on three The lower section of angle hanger 17, push rod 2 19 is installed on the hydraulic cylinder 2 18 and is directed at doorframe 26, the both sides of the doorframe 26 are also pacified Equipped with the barrier conveyer belt 2 20 that rotation material transfer is driven by motor three;
Anchoring 1 includes base 107, and the base 107 is mounted below universal wheel 108, electric reel 106 and mechanical arm 103 are arranged on above base 107, and the tool arm 103 is spaced above to be provided with pulley 101, cable wire fixator on the doorframe 26 9, the one end of steel wire rope 3 is fixed on cable wire fixator 9, is then passed through after the pulley 101 above anchoring 1, the other end is wound on On electric reel 106.
The inner side of armlet 12 is also equipped with gear and buckle 13, and one end of the gear button 13 is hinged on pin 31, the other end with admittedly The spring 32 being scheduled on armlet 12 connects.
Based on said apparatus, the present invention also proposes a kind of municipal road construction surrounding baffle construction method of installation, including as follows Step:
1) engineering truck 4 is connected by draw-gear with anchoring 1, it is existing that engineering truck 4 drives anchoring 1 to reach construction , while reached the spot using charge of trucks barrier 2;
2) according to site operation situation, by anchoring 1 and engineering truck 4, both are separated, and anchoring 1 is transferred into finger After positioning is put, the one end of steel wire rope 3 is fixed on cable wire fixator 9, is then passed through after the pulley 101 above anchoring 1, The other end is wound on electric reel 106.Start electric reel 106 to tense steel wire rope 3;
3) charge of trucks barrier 2 is directly unloaded on conveyer belt 10, barrier 2 is advanced slowly under the drive of hydraulic stem;
4) push arm 8 advances under the drive of hydraulic push rod 22 entangles and is pushed into the barrier that is symmetrically installed by barrier 2 and transmit In band 1, barrier conveyer belt 1 advances under the indirect drive of motor is sent into barrier 2 on the armlet 12 on rotating disk 25, Gear button 13 clasps barrier 2;
5) barrier 2 is sent into the side of doorframe 26 by the constantly rotation of rotating disk 25, and when barrier 2 reaches 26 face of doorframe, push rod 2 19 is in liquid Barrier 2 is pushed open under the drive of cylinder pressure 2 18 and is sent into barrier conveyer belt 2 20, then during this:Spring 32 is elongated, gear button 13 rotate along pin 31, and such barrier 2 just departs from the constraint of gear button 13, while keeps off button 13 and also spring back to original position;
6) when when barrier 2 is sent to doorframe 26 by barrier conveyer belt 2 20, hanging groove 203 above upper barrier 210 from It is dynamic to catch on steel wire rope 3;
7) continuous repeat step 3) -6), such barrier 2 is just constantly admitted to arrangement form surrounding baffle on steel wire rope 3;Row After the completion of row, workmen releases cable wire 201, lower barrier 211 is extracted out from the inside of upper barrier 210, leads to during to certain position Cross cable wire lock 204 to lock cable wire 201, construction terminates.
Embodiment 3
Municipal road construction enclosing board mounting structure, including anchoring 1, engineering truck 4, barrier 2, the engineering truck 4 are logical Draw-gear is crossed to be connected with anchoring 1;It is sufficiently bulky due to barrier 2 in work progress, what such lorry transported every time Limited amount, in order to solve this problem, save the volume of barrier, increase freight volume, in the present embodiment, barrier barrier 2 includes upper Barrier 210 and lower barrier 211, the both sides of the upper barrier 210 are provided with side chute 202 and slip into barrier 210 for lower barrier 211 Inside;The upper barrier 210, top hanging groove 203 is installed, cable wire lock 204 is arranged on upper barrier 210, thereon Face is locked with to be connected with lower barrier 211 simultaneously from the back side through the cable wire 201 come, the cable wire 201, while can also use folding Folded barrier.In addition, in order to solve the problems, such as that barrier is easily waved by wind, the bottom of lower barrier 211 is provided with the He of upper pin 208 Lower bearing pin 205, interior plate 206 is hinged with the upper pin 208, outer panel 207, interior plate 206 are hinged with lower bearing pin 205 It is hinged again with outer panel 207 and forms triangle branch frame, is propped up on the ground by the triangle branch frame of lower section, the stability of barrier carries significantly It is high.
The leading portion of engineering truck 4 is provided with push arm 8, the push arm 8 and the hydraulic push rod 22 being fixed on above engineering truck 4 Connection, the hydraulic push rod 22 and push arm 8 contact position are provided with baffle plate 23, and baffle plate 23 is in order to prevent barrier 2 from falling down.The work The stage casing installation conveyer belt 10 of journey car 4, conveyer belt 10 can be moved in work progress, can not also moved, meanwhile, transmission Speed can also be adjusted, and in the present embodiment, conveyer belt 10 does not move.
The rear end of engineering truck 4 is provided with support body 24, and the side of support body 24 is provided with doorframe 26;It is provided with support body 24 and passes through electricity The driving wheel 14 that machine drives, the driving wheel 14 are laid in the top of the discharge end of conveyer belt 10, and the driving wheel 14 drives auxiliary The rotation of wheel 16 is helped, the auxiliary wheel is provided with barrier conveyer belt 1 about 16;It is also equipped with passing through bottom in the support body 24 The rotating disk 25 that motor two drives, four faces of the rotating disk 25 are equipped with armlet 12, and plate is carried on a shoulder pole in the bottom of the armlet 12 for transition 11, the top of the armlet 12 is provided with the triangular rack 17 being fixed on above support body 24, and the connection of hydraulic cylinder 2 18 is arranged on three The lower section of angle hanger 17, push rod 2 19 is installed on the hydraulic cylinder 2 18 and is directed at doorframe 26, the both sides of the doorframe 26 are also pacified Equipped with the barrier conveyer belt 2 20 that rotation material transfer is driven by motor three;
Anchoring 1 includes base 107, and the base 107 is mounted below universal wheel 108, electric reel 106 and mechanical arm 103 are arranged on above base 107, and the tool arm 103 is spaced above to be provided with pulley 101, cable wire fixator on the doorframe 26 9, the one end of steel wire rope 3 is fixed on cable wire fixator 9, is then passed through after the pulley 101 above anchoring 1, the other end is wound on On electric reel 106.
The inner side of armlet 12 is also equipped with gear and buckle 13, and one end of the gear button 13 is hinged on pin 31, the other end with admittedly The spring 32 being scheduled on armlet 12 connects.
In order to save the artificial labour for unloading barrier, the side of engineering truck 4 is also movably installed with portable plate 7, the activity Hydraulic cylinder 46 is installed, the hydraulic cylinder 46 is connected with lifter plate 5, can directly unload barrier 2 and be attached to lifter plate 5 on plate 7 On.
Based on said apparatus, the present invention also proposes a kind of municipal road construction surrounding baffle construction method of installation, including as follows Step:
1) engineering truck 4 is connected by draw-gear with anchoring 1, it is existing that engineering truck 4 drives anchoring 1 to reach construction , while reached the spot using charge of trucks barrier 2;
2) according to site operation situation, by anchoring 1 and engineering truck 4, both are separated, and anchoring 1 is transferred into finger After positioning is put, the one end of steel wire rope 3 is fixed on cable wire fixator 9, is then passed through after the pulley 101 above anchoring 1, The other end is wound on electric reel 106.Start electric reel 106 to tense steel wire rope 3;
3) charge of trucks barrier 2 is directly discharged on lifter plate 5 from lorry, hydraulic cylinder 46 is by the barrier on lifter plate 5 (2) rise with conveyer belt 10 side by side, barrier 2 is pushed on conveyer belt 10 by workmen;
4) push arm 8 advances under the drive of hydraulic push rod 22 entangles and is pushed into the barrier that is symmetrically installed by barrier 2 and transmit In band 1, barrier conveyer belt 1 advances under the indirect drive of motor is sent into barrier 2 on the armlet 12 on rotating disk 25, Gear button 13 clasps barrier 2;
5) barrier 2 is sent into the side of doorframe 26 by the constantly rotation of rotating disk 25, and when barrier 2 reaches 26 face of doorframe, push rod 2 19 is in liquid Barrier 2 is pushed open under the drive of cylinder pressure 2 18 and is sent into barrier conveyer belt 2 20, then during this:Spring 32 is elongated, gear button 13 rotate along pin 31, and such barrier 2 just departs from the constraint of gear button 13, while keeps off button 13 and also spring back to original position;
6) when when barrier 2 is sent to doorframe 26 by barrier conveyer belt 2 20, hanging groove 203 above upper barrier 210 from It is dynamic to catch on steel wire rope 3;
7) continuous repeat step 3) -6), such barrier 2 is just constantly admitted on steel wire rope 3 and arranged;After the completion of arrangement, Workmen releases cable wire 201, lower barrier 211 is extracted out from the upper the inside of barrier 210, is locked to during certain position by cable wire Device 204 locks cable wire 201, and construction terminates.
Although the illustrative embodiment of the present invention is described above, in order to the technology of the art Personnel are it will be appreciated that the present invention, but the present invention is not limited only to the scope of embodiment, to the common skill of the art For art personnel, as long as long as various change in the spirit and scope of the invention that appended claim limits and determines, one The innovation and creation using present inventive concept are cut in the row of protection.

Claims (3)

1. municipal road construction enclosing board mounting structure, including anchoring (1), engineering truck (4), barrier (2), its feature exist In:The engineering truck (4) is connected by draw-gear with anchoring (1);Barrier (2) is overall one block of plate, and its top is provided with Catch on the hook of steel wire rope (3);
The leading portion of the engineering truck (4) is provided with push arm (8), and the push arm (8) is with being fixed on the liquid of engineering truck (4) above Push rod (22) connection is pressed, the hydraulic push rod (22) is provided with baffle plate (23), the engineering truck (4) with push arm (8) contact position Stage casing installation conveyer belt (10), rear end is provided with support body (24), and the side of support body (24) is provided with doorframe (26);On support body (24) Driving wheel (14) by motor driven is installed, the driving wheel (14) is laid in the top of the discharge end of conveyer belt (10), The driving wheel (14) drives auxiliary wheel (16) rotation, and the auxiliary wheel (16) is provided with barrier conveyer belt one (15) up and down;Institute The rotating disk (25) for being also equipped with driving in support body (24) by bottom motors two is stated, four faces of the rotating disk (25) are equipped with shield Arm (12), the bottom of the armlet (12) carry on a shoulder pole plate (11) for transition, are provided with above the armlet (12) and are fixed on support body (24) triangular rack (17) above, hydraulic cylinder two (18) connection is installed in the lower section of triangular rack (17), the hydraulic cylinder two (18) push rod two (19) alignment doorframe (26) is installed, the both sides of the doorframe (26), which are also equipped with driving by motor three, revolves on Turn the barrier conveyer belt two (20) of material transfer;
The anchoring (1) includes base (107), and the base (107) is mounted below universal wheel (108), electric reel (106) and mechanical arm (103) is arranged on base (107) above, and the tool arm (103) is spaced above to be provided with pulley (101), institute Cable wire fixator (9) on doorframe (26) is stated, steel wire rope (3) one end is fixed on cable wire fixator (9), is then passed through anchoring (1) after pulley (101) above, the other end is wound on electric reel (106).
2. municipal road construction enclosing board mounting structure according to claim 1, it is characterised in that:The armlet (12) Inner side is also equipped with gear button (13), and one end of the gear button (13) is hinged on pin (31), and the other end is with being fixed on armlet (12) spring (32) connection on.
3. municipal road construction surrounding baffle construction method of installation, it is characterised in that comprise the following steps:
1) engineering truck (4) is connected by draw-gear with anchoring (1), engineering truck (4) drives anchoring (1) to reach and applied Work scene, while reached the spot using charge of trucks barrier (2);
2) both anchoring (1) and engineering truck (4) are separated according to site operation situation, and anchoring (1) is transferred to After specified location, steel wire rope (3) one end is fixed on cable wire fixator (9), is then passed through the pulley of anchoring (1) above (101) after, the other end is wound on electric reel (106), is started electric reel (106) and is tensed steel wire rope (3);
3) charge of trucks barrier (2) is directly unloaded on conveyer belt (10), before barrier (2) is slow under the drive of hydraulic stem Enter;
4) push arm (8) advance under the drive of hydraulic push rod (22) and barrier (2) is entangled and is pushed into the barrier biography being symmetrically installed Send in band one (15), barrier conveyer belt one (15) advances under the indirect drive of motor is sent into barrier (2) on rotating disk (25) On armlet (12), gear button (13) clasps barrier (2);
5) barrier (2) is sent into doorframe (26) side by rotating disk (25) constantly rotation, when barrier (2) reaches doorframe (26) face, push rod two (19) barrier (2) is pushed open under the drive of hydraulic cylinder two (18) and be sent into barrier conveyer belt two (20), then during this:Spring (32) it is elongated, gear button (13) rotates along pin (31), and such barrier (2) just departs from the constraint of gear button (13), while keeps off button (13) original position is also sprung back to;
6) when when barrier (2) is sent to doorframe (26) by barrier conveyer belt two (20), the hook of barrier (2) above hooks automatically Firmly on steel wire rope (3);
7) continuous repeat step 3) -6), such barrier (2) is just constantly admitted to arrangement form surrounding baffle on steel wire rope (3), applies Work terminates.
CN201710478538.7A 2017-06-21 2017-06-21 Municipal road construction enclosing board mounting structure and its construction method Active CN107558805B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201910097175.1A CN109812129B (en) 2017-06-21 2017-06-21 Municipal road construction baffle mounting structure and construction method thereof
CN201710478538.7A CN107558805B (en) 2017-06-21 2017-06-21 Municipal road construction enclosing board mounting structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710478538.7A CN107558805B (en) 2017-06-21 2017-06-21 Municipal road construction enclosing board mounting structure and its construction method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201910097175.1A Division CN109812129B (en) 2017-06-21 2017-06-21 Municipal road construction baffle mounting structure and construction method thereof

Publications (2)

Publication Number Publication Date
CN107558805A true CN107558805A (en) 2018-01-09
CN107558805B CN107558805B (en) 2019-06-04

Family

ID=60973454

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201910097175.1A Active CN109812129B (en) 2017-06-21 2017-06-21 Municipal road construction baffle mounting structure and construction method thereof
CN201710478538.7A Active CN107558805B (en) 2017-06-21 2017-06-21 Municipal road construction enclosing board mounting structure and its construction method

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201910097175.1A Active CN109812129B (en) 2017-06-21 2017-06-21 Municipal road construction baffle mounting structure and construction method thereof

Country Status (1)

Country Link
CN (2) CN109812129B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110748230B (en) * 2019-09-23 2020-11-27 深圳市市政工程总公司 Intelligent backplate base installation device for construction
CN110748235B (en) * 2019-09-23 2020-12-01 江西省连城建筑工程有限公司 Building workpiece installation construction method
CN111661594B (en) * 2020-06-01 2021-03-30 广东联创建筑工程有限公司 Construction is with enclosing fender installation device
CN113047688B (en) * 2021-03-31 2022-07-22 九江职业技术学院 Automatic laying device of fender is enclosed in construction

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1888318A (en) * 2006-07-14 2007-01-03 常熟华东汽车有限公司 Road barricade vehicle
US20090014702A1 (en) * 2004-01-13 2009-01-15 Stephen Graham Patrick Rawcliffe Apparatus for dispensing and tensioning wire
US20110121125A1 (en) * 2009-07-15 2011-05-26 E-Z Stretcher Llc Roll Fencing Unfurling and Stretching Apparatus
CN201901854U (en) * 2010-12-25 2011-07-20 常熟华东汽车有限公司 Vehicle and barrier separating mechanism for combined type net barrier
CN103015790A (en) * 2013-01-16 2013-04-03 明光市浩淼消防科技发展有限公司 Mesh laying and collecting device of barbed wire mesh
CN103306227A (en) * 2013-07-08 2013-09-18 中铁第四勘察设计院集团有限公司 Light reflecting fence capable of being folded movably
CN103470097A (en) * 2013-09-25 2013-12-25 北京安龙特种车辆有限公司 Isolating net piece and carrier vehicle for loading isolating net pieces
CN204511024U (en) * 2015-02-04 2015-07-29 台州市泰辉市政工程有限公司 Municipal construction fence
CN104831651A (en) * 2014-02-11 2015-08-12 罗德里戈和西奎拉联营-城市设计有限公司 Demountable modular safety panel and a respective assembly process
CN105421854A (en) * 2015-12-23 2016-03-23 杨光明 Liftable guardrail applicable to stereo garage
AU2015249062A1 (en) * 2014-11-10 2016-05-26 Malcolm Robertson Rail vehicle for constructing safety barrier fences
CN205330278U (en) * 2016-01-26 2016-06-22 国网安徽省电力公司检修公司 Electronic car of arranging of primary equipment safety measure
CN206205477U (en) * 2016-11-25 2017-05-31 南通华达重工科技有限公司 A kind of safety barrier support for constructions work

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090014702A1 (en) * 2004-01-13 2009-01-15 Stephen Graham Patrick Rawcliffe Apparatus for dispensing and tensioning wire
CN1888318A (en) * 2006-07-14 2007-01-03 常熟华东汽车有限公司 Road barricade vehicle
US20110121125A1 (en) * 2009-07-15 2011-05-26 E-Z Stretcher Llc Roll Fencing Unfurling and Stretching Apparatus
CN201901854U (en) * 2010-12-25 2011-07-20 常熟华东汽车有限公司 Vehicle and barrier separating mechanism for combined type net barrier
CN103015790A (en) * 2013-01-16 2013-04-03 明光市浩淼消防科技发展有限公司 Mesh laying and collecting device of barbed wire mesh
CN103306227A (en) * 2013-07-08 2013-09-18 中铁第四勘察设计院集团有限公司 Light reflecting fence capable of being folded movably
CN103470097A (en) * 2013-09-25 2013-12-25 北京安龙特种车辆有限公司 Isolating net piece and carrier vehicle for loading isolating net pieces
CN104831651A (en) * 2014-02-11 2015-08-12 罗德里戈和西奎拉联营-城市设计有限公司 Demountable modular safety panel and a respective assembly process
AU2015249062A1 (en) * 2014-11-10 2016-05-26 Malcolm Robertson Rail vehicle for constructing safety barrier fences
CN204511024U (en) * 2015-02-04 2015-07-29 台州市泰辉市政工程有限公司 Municipal construction fence
CN105421854A (en) * 2015-12-23 2016-03-23 杨光明 Liftable guardrail applicable to stereo garage
CN205330278U (en) * 2016-01-26 2016-06-22 国网安徽省电力公司检修公司 Electronic car of arranging of primary equipment safety measure
CN206205477U (en) * 2016-11-25 2017-05-31 南通华达重工科技有限公司 A kind of safety barrier support for constructions work

Also Published As

Publication number Publication date
CN109812129A (en) 2019-05-28
CN109812129B (en) 2020-03-27
CN107558805B (en) 2019-06-04

Similar Documents

Publication Publication Date Title
CN107558805A (en) Municipal road construction enclosing board mounting structure and its construction method
CN207525746U (en) Side slope protection construction platform and slope protection system
CN103195460B (en) Hydraulic support steering platform
CN215322694U (en) Building construction brick masonry material handling device machines
CN107269114A (en) Road safety job execution barrier structure and its construction method
CN205241046U (en) Wire turn hoist and mount transport means is received to coping saw
CN205099292U (en) Portable sheep platform
CN209922752U (en) Special lifting support for electromechanical installation
CN204057795U (en) Electronic down-hole lifting means
CN207406013U (en) A kind of FRAME ON THE ROOF OF HIGH-RISE BUILDING curtain wall lifting device
CN212316918U (en) Movable punching pile driver
CN108798714A (en) A kind of working portable shifting formwork trolley of channel wall body and its construction method
CN205022430U (en) Self - discharging truck of environmental protection brick
CN202645043U (en) Automatic wall dismantling device
CN209974150U (en) Chinese character 'kou' shaped piece crane
CN220056115U (en) Cutter transferring device of shield tunneling machine and shield tunneling machine
CN112357785A (en) Efficient lifting equipment for tool for construction of engineering roads and bridges
CN202111873U (en) Energy-saving movable self-supporting lift base station
CN218809971U (en) Fixed large crane
CN220011924U (en) Small gantry crane
CN210764021U (en) Simple hoisting device of road repairing machine
CN214638842U (en) Silo cleaning robot
CN220432201U (en) Lifting machine
CN2613540Y (en) Apparatus for lifting moulded tile to roof
CN220449740U (en) Maintenance electric power engineering car

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zheng Daming

Inventor after: Qu Chengming

Inventor before: Qu Chengming

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20190509

Address after: 510000 self-designed 9 rooms (for office use only) on the 1st floor of 101 Dongyan Street, Dongguanzhuang Road, Tianhe District, Guangzhou City, Guangdong Province (not for factory use)

Applicant after: Guangdong Haoyuan Construction Co., Ltd.

Address before: 277524 No. 174, Bashangcun, Guanqiao Town, Tengzhou City, Zaozhuang City, Shandong Province

Applicant before: Qu Chengming

TA01 Transfer of patent application right