CN107558636A - Cast-in-place shear wall prefabricated doors and windows entrance construction method - Google Patents

Cast-in-place shear wall prefabricated doors and windows entrance construction method Download PDF

Info

Publication number
CN107558636A
CN107558636A CN201710809162.3A CN201710809162A CN107558636A CN 107558636 A CN107558636 A CN 107558636A CN 201710809162 A CN201710809162 A CN 201710809162A CN 107558636 A CN107558636 A CN 107558636A
Authority
CN
China
Prior art keywords
cast
windows
prefabricated
wall
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710809162.3A
Other languages
Chinese (zh)
Inventor
张晓峰
李晓亮
迟毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201710809162.3A priority Critical patent/CN107558636A/en
Publication of CN107558636A publication Critical patent/CN107558636A/en
Pending legal-status Critical Current

Links

Abstract

The present invention relates to a kind of cast-in-place shear wall prefabricated doors and windows entrance construction method, prefabricated doors and windows hole component;During cast-in-situ wall formwork, prefabricated doors and windows hole component is placed wherein in wall, and it is fixed with diagonal brace;Carry out cast-in-situ wall and tie up muscle, the Cast-in-Situ Segment reinforcing bar reserved on the component of prefabricated doors and windows hole carries out colligation with wall cast in place reinforced bar, and prefabricated doors and windows hole component and wall cast in place reinforced bar are connected into an entirety;By the reserved split bolt hole on the component of prefabricated doors and windows hole, by cast-in-situ wall template matched moulds and fixation, after beating ash, pouring and reaching prescribed strength, form removal, complete the cast-in-place shear wall with prefabricated doors and windows hole and construct.Cast-in-place shear wall prefabricated doors and windows entrance construction method of the present invention, the design size of door-window opening is ensure that, reduce task difficulty, improve speed of application, reduce construction cost, improve construction quality.

Description

Cast-in-place shear wall prefabricated doors and windows entrance construction method
Technical field
The present invention relates to a kind of construction techniques, is to be related to a kind of cast-in-place shear wall prefabricated doors and windows hole specifically Construction method.
Background technology
In cast-in-situ wall concrete works, corresponding wall all devises door and window.And in cast-in-place engineering, wall The reserved of door-window opening is to build template by the corresponding site in wall, is removed after casting concrete reaches prescribed strength Template, technical requirements are high in this method work progress, and difficulty of construction is big.
The content of the invention
For above-mentioned deficiency of the prior art, the present invention provides a kind of reduction task difficulty, improves speed of application, reduces The cast-in-place shear wall prefabricated doors and windows entrance construction method of construction cost.
The technical solution used in the present invention is:
A kind of cast-in-place shear wall prefabricated doors and windows entrance construction method,
Prefabricated doors and windows hole component;
During cast-in-situ wall formwork, prefabricated doors and windows hole component is placed wherein in wall, and it is fixed with diagonal brace;
Carry out cast-in-situ wall and tie up muscle, the Cast-in-Situ Segment reinforcing bar reserved on the component of prefabricated doors and windows hole is tied up with wall cast in place reinforced bar Prick, prefabricated doors and windows hole component and wall cast in place reinforced bar are connected into an entirety;
By the reserved split bolt hole on the component of prefabricated doors and windows hole, by cast-in-situ wall template matched moulds and fixation, wait to beat ash, After pouring and reaching prescribed strength, form removal, complete the cast-in-place shear wall with prefabricated doors and windows hole and construct.
Prefabricated doors and windows hole component includes prefabricated door opening component and prefabricated window hole component;
Prefabricated door opening component is in door shape,
Prefabricated window hole component is in groined type.
Prefabricated doors and windows hole component is provided with the horizontal reinforcement and longitudinal reinforcement being connected with wall cast in place reinforced bar.
The beneficial effect of the present invention compared with the prior art:
Cast-in-place shear wall prefabricated doors and windows entrance construction method of the present invention, the design size of door-window opening is ensure that, it is difficult to reduce operation Degree, speed of application is improved, reduce construction cost, improve construction quality.
Brief description of the drawings
Fig. 1 is the prefabricated door opening element structure schematic diagram of cast-in-place shear wall prefabricated doors and windows entrance construction method of the present invention;
Fig. 2 is the prefabricated window hole element structure schematic diagram of cast-in-place shear wall prefabricated doors and windows entrance construction method of the present invention;
Fig. 3 is the door opening construction schematic diagram of cast-in-place shear wall prefabricated doors and windows entrance construction method of the present invention;
Fig. 4 is the window hole construction schematic diagram of cast-in-place shear wall prefabricated doors and windows entrance construction method of the present invention.
In figure:
1st, door opening 2, prefabricated door opening component
3rd, window hole 4, prefabricated window hole component
5th, cast-in-place wall 6, wall cast in place reinforced bar.
Embodiment
Referring to the drawings and embodiment the present invention will be described in detail:
Knowable to accompanying drawing 1-4, a kind of cast-in-place shear wall prefabricated doors and windows entrance construction method,
Prefabricated doors and windows hole component;
During cast-in-situ wall formwork, prefabricated doors and windows hole component is placed wherein in wall, and it is fixed with diagonal brace;
Carry out cast-in-situ wall and tie up muscle, the Cast-in-Situ Segment reinforcing bar reserved on the component of prefabricated doors and windows hole is tied up with wall cast in place reinforced bar Prick, prefabricated doors and windows hole component and wall cast in place reinforced bar are connected into an entirety;
By the reserved split bolt hole on the component of prefabricated doors and windows hole, by cast-in-situ wall template matched moulds and fixation, wait to beat ash, After pouring and reaching prescribed strength, form removal, complete the cast-in-place shear wall with prefabricated doors and windows hole and construct.
Prefabricated doors and windows hole component includes prefabricated door opening component and prefabricated window hole component;
Prefabricated door opening component 2 is in door shape,
Prefabricated window hole component 4 is in groined type.
Prefabricated doors and windows hole component is provided with the horizontal reinforcement and longitudinal reinforcement being connected with wall cast in place reinforced bar.
Cast-in-place shear wall prefabricated doors and windows entrance construction method of the present invention, the design size of door-window opening is ensure that, reduce and make Industry difficulty, speed of application is improved, reduce construction cost, improve construction quality.
The above described is only a preferred embodiment of the present invention, not the structure of the present invention is made any formal Limitation.Any simple modification, equivalent change and modification that every technical spirit according to the present invention is made to above example, Belong in the range of technical scheme.

Claims (3)

  1. A kind of 1. cast-in-place shear wall prefabricated doors and windows entrance construction method, it is characterised in that
    Prefabricated doors and windows hole component;
    During cast-in-situ wall formwork, prefabricated doors and windows hole component is placed wherein in wall, and it is fixed with diagonal brace;
    Carry out cast-in-situ wall and tie up muscle, the Cast-in-Situ Segment reinforcing bar reserved on the component of prefabricated doors and windows hole is tied up with wall cast in place reinforced bar Prick, prefabricated doors and windows hole component and wall cast in place reinforced bar are connected into an entirety;
    By the reserved split bolt hole on the component of prefabricated doors and windows hole, by cast-in-situ wall template matched moulds and fixation, wait to beat ash, After pouring and reaching prescribed strength, form removal, complete the cast-in-place shear wall with prefabricated doors and windows hole and construct.
  2. 2. cast-in-place shear wall prefabricated doors and windows entrance construction method according to claim 1, it is characterised in that:The prefabricated doors and windows Hole component includes prefabricated door opening component and prefabricated window hole component;
    Prefabricated door opening component is in door shape,
    Prefabricated window hole component is in groined type.
  3. 3. cast-in-place shear wall prefabricated doors and windows entrance construction method according to claim 1, it is characterised in that:The prefabricated doors and windows Hole component is provided with the horizontal reinforcement and longitudinal reinforcement being connected with wall cast in place reinforced bar.
CN201710809162.3A 2017-09-10 2017-09-10 Cast-in-place shear wall prefabricated doors and windows entrance construction method Pending CN107558636A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710809162.3A CN107558636A (en) 2017-09-10 2017-09-10 Cast-in-place shear wall prefabricated doors and windows entrance construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710809162.3A CN107558636A (en) 2017-09-10 2017-09-10 Cast-in-place shear wall prefabricated doors and windows entrance construction method

Publications (1)

Publication Number Publication Date
CN107558636A true CN107558636A (en) 2018-01-09

Family

ID=60980358

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710809162.3A Pending CN107558636A (en) 2017-09-10 2017-09-10 Cast-in-place shear wall prefabricated doors and windows entrance construction method

Country Status (1)

Country Link
CN (1) CN107558636A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109057326A (en) * 2018-08-16 2018-12-21 徽都建设有限公司 One kind pouring shear wall prefabricated doors and windows entrance construction method
CN113653263A (en) * 2021-07-07 2021-11-16 广东二十冶建设有限公司 Pre-buried protective closed sleeve with hole reinforcing steel bars and construction method thereof
CN115814321A (en) * 2022-11-21 2023-03-21 中建八局第二建设有限公司 Fire hydrant prefabricated assembly type fireproof protection structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3630893B2 (en) * 1996-11-25 2005-03-23 クリオン株式会社 ALC vertical wall opening panel mounting structure
CN202227511U (en) * 2011-09-02 2012-05-23 中国京冶工程技术有限公司 Window-integrated precast concrete external wall
CN204510519U (en) * 2015-01-20 2015-07-29 常熟建工建设集团有限公司 A kind of prefabricated metope containing window framework
CN205000487U (en) * 2015-08-06 2016-01-27 文登蓝岛建筑工程有限公司 Integral type wall body containing door frame
CN106088537A (en) * 2016-07-07 2016-11-09 中国建筑第二工程局有限公司 A kind of window auxiliary frame pre-embedded construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3630893B2 (en) * 1996-11-25 2005-03-23 クリオン株式会社 ALC vertical wall opening panel mounting structure
CN202227511U (en) * 2011-09-02 2012-05-23 中国京冶工程技术有限公司 Window-integrated precast concrete external wall
CN204510519U (en) * 2015-01-20 2015-07-29 常熟建工建设集团有限公司 A kind of prefabricated metope containing window framework
CN205000487U (en) * 2015-08-06 2016-01-27 文登蓝岛建筑工程有限公司 Integral type wall body containing door frame
CN106088537A (en) * 2016-07-07 2016-11-09 中国建筑第二工程局有限公司 A kind of window auxiliary frame pre-embedded construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109057326A (en) * 2018-08-16 2018-12-21 徽都建设有限公司 One kind pouring shear wall prefabricated doors and windows entrance construction method
CN113653263A (en) * 2021-07-07 2021-11-16 广东二十冶建设有限公司 Pre-buried protective closed sleeve with hole reinforcing steel bars and construction method thereof
CN115814321A (en) * 2022-11-21 2023-03-21 中建八局第二建设有限公司 Fire hydrant prefabricated assembly type fireproof protection structure

Similar Documents

Publication Publication Date Title
CN205530667U (en) Prefabricated assembled concrete member
CN107558636A (en) Cast-in-place shear wall prefabricated doors and windows entrance construction method
CN106545109A (en) Overlaid plate type concrete shear wall longitudinal connection structure and method of attachment
CN108343148B (en) A kind of frame structure system and its construction method
CN204435542U (en) Integration bean column node formwork structure
CN209482591U (en) Prefabricated molds shell structure column construction structure
CN103737718B (en) Prefabricated reinforced concrete hollow column template and preparation method thereof
CN206917087U (en) A kind of prefabricated assembling type reinforced concrete framework open tubular column and its making mould
CN103711065B (en) Cantilever construction Composite Steel-Concrete Bridges and construction method thereof
CN106400982A (en) Stirrup-densified splicing joint for fabricated reinforced concrete columns
CN109057326A (en) One kind pouring shear wall prefabricated doors and windows entrance construction method
CN103741883B (en) Prefabricated reinforced concrete column template and preparation method thereof
CN107687281A (en) A kind of prestressing force pull end slip-form template installation method
CN206752693U (en) A kind of assembled steel reinforced concrete column of stirrup encryption and post splicing node
CN106337530A (en) Construction method for plugging construction joint of frame beam
CN204780943U (en) H type precast concrete pile and excavation supporting device
CN108589970A (en) The construction method of prefabricated window frame shear wall
CN209742151U (en) fiber reinforcement masonry structure
CN106968334A (en) A kind of construction method of cast-in-place concrete framework secondary structure constructional column
CN203684057U (en) Cantilever construction steel-concrete combined bridge
CN106401191A (en) Grouting device for steel shear structure assembling type building and construction method of grouting device
CN206267351U (en) A kind of inclined hole grouting shear wall of in-line
CN107386528A (en) Method for making the template free of demolition of beams of concrete and making beams of concrete
CN104712139B (en) Construction method for radian column formwork erection
CN212802096U (en) T-shaped cavity shear wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180109