CN107558613B - A kind of installation method of hexagonal pavilion - Google Patents

A kind of installation method of hexagonal pavilion Download PDF

Info

Publication number
CN107558613B
CN107558613B CN201710863046.XA CN201710863046A CN107558613B CN 107558613 B CN107558613 B CN 107558613B CN 201710863046 A CN201710863046 A CN 201710863046A CN 107558613 B CN107558613 B CN 107558613B
Authority
CN
China
Prior art keywords
terrace
hydraulic cylinder
device hydraulic
jacking device
jacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710863046.XA
Other languages
Chinese (zh)
Other versions
CN107558613A (en
Inventor
冯晓东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Xiangshan workshop Jing original construction Limited by Share Ltd
Original Assignee
Suzhou Yi Yuan Cultural Tourism Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Yi Yuan Cultural Tourism Development Co Ltd filed Critical Suzhou Yi Yuan Cultural Tourism Development Co Ltd
Priority to CN201710863046.XA priority Critical patent/CN107558613B/en
Publication of CN107558613A publication Critical patent/CN107558613A/en
Application granted granted Critical
Publication of CN107558613B publication Critical patent/CN107558613B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention relates to a kind of installation methods of hexagonal pavilion, each accessory of hexagonal pavilion can be produced according to demand first, then after the place for needing to build installs terrace, using terrace as fulcrum, each accessory assembly in hexagonal pavilion is got up by the jacking component on terrace, then assembly removal will be jacked again, the installation at scene can be quickly finished, it is easy to operate, save a large amount of set-up time, and be connected firmly stabilization, meets actual processing installation requirements.

Description

A kind of installation method of hexagonal pavilion
Technical field
The invention belongs to garden architecture field more particularly to a kind of installation methods of hexagonal pavilion.
Background technique
Pavilion building is one of Ancient Times in China building pavilion style, and pavilion includes five jiaos of pavilions and hexagonal pavilion etc., wherein hexagonal pavilion Building is Ancient Times in China building one of pavilion style, in modern society scenic spot or when gardens construction everywhere, and hexagonal can usually be arranged Pavilion building is as decoration and sight spot.
The pavilion building in ancient times is made using wood material, and the hexagonal pavilion building created in modern society, part is still Wood material is so used, partially using the preparation such as metal or plastic material.Mode of the existing pavilion building in construction is most It is to build from ground previous step step by pavilion, wherein each accessory in pavilion is also all built in real time, in this way Installation at the scene is caused to need sequentially to be built, whole construction is inconvenient, and time-consuming and laborious, when the construction of whole building Between it is long, be unable to satisfy the efficient installation requirements of modern society.
Summary of the invention
It is convenient and strength-saving that a kind of convenient transportation is provided the invention aims to overcome the deficiencies in the prior art, and effect is installed The installation method of the high hexagonal pavilion of rate.
In order to achieve the above objectives, the technical solution adopted by the present invention is that: a kind of installation method of hexagonal pavilion, including walk as follows It is rapid:
The first step sets terrace in the place for needing to build hexagonal pavilion, six built-in fittings is pre-set on terrace, together When terrace be fixed by the ground riveting of terrace lower end;
Jacking device hydraulic cylinder is mounted in the intermediate port lid of terrace by second step, is inserted partially into jacking device hydraulic cylinder In hole, the six roots of sensation wing is rotated, is tightly attached to it on terrace, and ensure that wing support center is directed at the center of six built-in fittings, then used Fixing bolt fixes jacking device hydraulic cylinder and the wing;
Third step is inserted in steel pipe on the top of jacking device hydraulic cylinder, then umbrella frame is installed on steel pipe, while handle Transverse beam assembly is placed on terrace, and umbrella frame lower end is connected with transverse beam assembly, is supported umbrella frame by transverse beam assembly, Recycle safety rope that umbrella frame is connected with the wing;
4th step is inserted in Bao Ding in the upper end of steel pipe, the roofing that six integrally formed roofings, eaves tile and rafter are constituted Component circular array is mounted on umbrella frame, and then angle is clashed in installation between two connected roofing assemblies, and the upper end at angle will in an opposite direction The upper end of roofing assembly is pressed into precious top;
5th step, all accessory assembly in place, carry out the jacking work of jacking device hydraulic cylinder, the jacking of jacking device hydraulic cylinder To 1 meter of height, it is ensured that jacking device hydraulic cylinder be increased to require be greater than stem height, then check each safety rope, ensure every by The same state of power, and it is tight;
6th step holds up six roots of sensation column, the position of casing on adjustment stud end alignment transverse beam assembly, jacking component decline, So that the upper end of the column is inserted into casing internal expanding pin and is fixed, finally bounces back and jacking device hydraulic cylinder and unload step by step, remove insurance Rope removes jacking component;
7th step covers terrace intermediate cover, and optical collimator inspection is vertical, Realize, ensures to calibrate.
Preferably, the transverse beam assembly is made of the bearing plate that six pieces of annular arrays are distributed, and between every two bearing plates Equipped with casing corresponding with column.
Due to the application of the above technical scheme, compared with the prior art, the invention has the following advantages:
The installation method of the hexagonal pavilion of the present invention program can according to demand produce each accessory in pavilion first Come, then after the place for needing to build installs terrace, using terrace as fulcrum, by the jacking component on terrace by hexagonal Each accessory assembly in pavilion is got up, and in-site installation is convenient and efficient, saves a large amount of set-up time, and it is steady to be connected firmly It is fixed, meet actual processing installation requirements.
Detailed description of the invention
Attached drawing 1 is the structural schematic diagram of hexagonal pavilion after omitting jacking component and ground riveting;
Attached drawing 2 is the partial sectional view of the middle A-A of attached drawing 1;
Attached drawing 3 is the partial profile structure of hexagonal pavilion;
Attached drawing 4 is the structural schematic diagram that component is jacked in hexagonal pavilion;
Attached drawing 5 is the structural schematic diagram of hexagonal pavilion middle cross beam component;
Wherein: 1, terrace;2, component is jacked;3, steel pipe;4, Bao Ding;5, umbrella frame;6, transverse beam assembly;7, rafter;Watt 8, When;9, angle is clashed;10, column;11, built-in fitting;12, riveting;13, roofing;20, jacking device hydraulic cylinder;21, the wing;22, safety rope; 60, bearing plate;61, casing.
Specific embodiment
Below in conjunction with the accompanying drawings and specific embodiment, the present invention is described in further details.
A kind of installation method of hexagonal pavilion of the present invention, includes the following steps:
The first step sets terrace 1 in the place for needing to build hexagonal pavilion, six built-in fittings is pre-set on terrace 1 11, while terrace 1 is fixed by the ground riveting 12 of 1 lower end of terrace;
Jacking device hydraulic cylinder 20 is mounted in the intermediate port lid of terrace 1 by second step, inserts 20 part of jacking device hydraulic cylinder Enter into hole, rotate the six roots of sensation wing 21, be tightly attached to it on terrace 1, and ensures that 21 support center of the wing is directed at six built-in fittings 11 Center, it is then with fixing bolt that jacking device hydraulic cylinder 20 and the wing 21 is fixed;
Third step is inserted in steel pipe 3 on the top of jacking device hydraulic cylinder 20, and then umbrella frame 5 is installed on steel pipe 4, Transverse beam assembly 6 is placed on terrace 1 simultaneously, 5 lower end of umbrella frame is connected with transverse beam assembly 6, umbrella frame 5 is made to pass through crossbeam group Part 6 is supported, and recycles safety rope 22 that umbrella frame 5 is connected with the wing 21;
4th step is inserted in precious top 4 in the upper end of steel pipe 3, six integrally formed roofings 13, eaves tile 8 and rafter 7 is constituted Roofing assembly circular array be mounted on umbrella frame 5, then angle 9 is clashed in installation between two connected roofing assemblies, in an opposite direction angle 9 Upper end the upper end of roofing assembly is pressed into precious top 4;
5th step, all accessory assembly in place, carry out the jacking work of jacking device hydraulic cylinder 20, jacking device hydraulic cylinder 20 Jacking is to 1 meter of height, it is ensured that jacking device hydraulic cylinder 20 is increased to require to be greater than 10 height of column, then checks each safety rope, really The same state of every stress is protected, and tight;
6th step holds up six roots of sensation column 10, the position of casing 61, jacking group on adjustment 10 end of column alignment transverse beam assembly 6 Part 2 declines, so that 10 upper end of column is inserted into 61 internal expanding pin of casing and is fixed, finally bounce back jacking device hydraulic cylinder 20 and step by step It unloads, removes safety rope 22, remove jacking component 2;
7th step covers terrace intermediate cover, and optical collimator inspection is vertical, Realize, ensures to calibrate.
Above-mentioned hexagonal pavilion structure as shown in attached drawing 1-5, including terrace 1, built-in fitting 11, riveting 12, jacking component 2, steel Pipe 3, precious top 4, umbrella frame 5, transverse beam assembly 6, roofing assembly, in an opposite direction angle 9 and column 10;1 upper end of terrace is pre-buried, and there are six battle arrays The built-in fitting 11 of column distribution, lower end are equipped with multiple ground riveting 12;Jacking component 2 is equipped at the center of 1 upper end of terrace;The top Rising component 2 includes jacking device hydraulic cylinder 20, the wing 21 and safety rope 22;The lower end surrounding of the jacking device hydraulic cylinder 20 is distributed with six The wing 21 that can be rotated upwardly and downwardly, and the front end of the wing 21 is equipped with safety rope 22;20 upper end of jacking device hydraulic cylinder is equipped with steel pipe 3, And 3 upper end of steel pipe is equipped with precious top 4;The lower section for being located at precious top 4 on the steel pipe 3 is equipped with umbrella frame 5;The umbrella frame 5 passes through Safety rope 22 is connected with the wing 21, and 5 lower end of above-mentioned umbrella frame is additionally provided with transverse beam assembly 6;Six groups of array distribution on the umbrella frame 5 Roofing assembly, above-mentioned roofing assembly are made of the roofing 13, eaves tile 8 and rafter 7 being integrally connected;Between the adjacent roofing assembly Equipped with angle 9 in an opposite direction, for roofing assembly upper end to be pressed in precious top 4;It is equipped with column 10 in the built-in fitting 11, and on column 10 End is connected with transverse beam assembly 6;The material at the angle 9, rafter 7 and eaves tile 8 in an opposite direction is glass reinforced plastic;The transverse beam assembly is by six pieces of annulars The bearing plate 60 of array distribution is constituted, and casing 61 corresponding with column is equipped between every two bearing plate 60.
The installation method of hexagonal pavilion of the invention can according to demand produce each accessory in pavilion, so first It, will be in hexagonal pavilion by the jacking component on terrace using terrace as fulcrum afterwards after the place for needing to build installs terrace Each accessory assembly get up, in-site installation is convenient and efficient, saves a large amount of set-up time, and the stabilization that is connected firmly, full The actual processing installation requirements of foot.
The above is only specific application examples of the invention, are not limited in any way to protection scope of the present invention.All uses Equivalent transformation or equivalent replacement and the technical solution formed, all fall within rights protection scope of the present invention.

Claims (2)

1. a kind of installation method of hexagonal pavilion, includes the following steps, terrace, terrace are set in the place for needing to build hexagonal pavilion On pre-set six built-in fittings, while terrace is fixed by the ground riveting of terrace lower end, which is characterized in that further include as Lower step:
Jacking device hydraulic cylinder is mounted in the intermediate port lid of terrace by the first step, is inserted partially into jacking device hydraulic cylinder in hole, The six roots of sensation wing is rotated, is tightly attached to it on terrace, and ensures that wing support center is directed at the center of six built-in fittings, then with fixed spiral shell Bolt fixes jacking device hydraulic cylinder and the wing;
Second step is inserted in steel pipe on the top of jacking device hydraulic cylinder, then umbrella frame is installed on steel pipe, while crossbeam Component is placed on terrace, and umbrella frame lower end is connected with transverse beam assembly, is supported umbrella frame by transverse beam assembly, then benefit Umbrella frame is connected with the wing with safety rope;
Third step is inserted in Bao Ding in the upper end of steel pipe, the roofing assembly that six integrally formed roofings, eaves tile and rafter are constituted Circular array is mounted on umbrella frame, and then angle is clashed in installation between two connected roofing assemblies, and the upper end at angle is by roofing in an opposite direction The upper end of component is pressed into precious top;
4th step, all accessory assembly in place, carry out the jacking work of jacking device hydraulic cylinder, jacking device hydraulic cylinder is jacked to 1 Meter Gao Du, it is ensured that jacking device hydraulic cylinder is increased to require to be greater than stem height, then checks each safety rope, ensures every stress one Sample state, and it is tight;
5th step holds up six roots of sensation column, the position of casing on adjustment stud end alignment transverse beam assembly, jacking component decline, so that The upper end of the column is inserted into casing internal expanding pin and is fixed, and finally bounces back and jacking device hydraulic cylinder and unloads step by step, removes safety rope, shifting Except jacking component;
6th step covers terrace intermediate cover, and optical collimator inspection is vertical, Realize, ensures to calibrate.
2. the installation method of hexagonal pavilion according to claim 1, it is characterised in that: the transverse beam assembly is by six pieces of circular arrays The bearing plate of column distribution is constituted, and casing corresponding with column is equipped between every two bearing plates.
CN201710863046.XA 2017-09-22 2017-09-22 A kind of installation method of hexagonal pavilion Active CN107558613B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710863046.XA CN107558613B (en) 2017-09-22 2017-09-22 A kind of installation method of hexagonal pavilion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710863046.XA CN107558613B (en) 2017-09-22 2017-09-22 A kind of installation method of hexagonal pavilion

Publications (2)

Publication Number Publication Date
CN107558613A CN107558613A (en) 2018-01-09
CN107558613B true CN107558613B (en) 2019-07-16

Family

ID=60982626

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710863046.XA Active CN107558613B (en) 2017-09-22 2017-09-22 A kind of installation method of hexagonal pavilion

Country Status (1)

Country Link
CN (1) CN107558613B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107542286B (en) * 2017-09-22 2023-05-05 苏州艺库文化旅游发展有限公司 Structure of pavilion
CN111425017B (en) * 2020-04-27 2021-07-16 明道合创智能科技有限公司 Construction method of assembled multifunctional modeling pavilion
CN111749497B (en) * 2020-05-19 2021-10-22 宁波市风景园林设计研究院有限公司 Construction process of four-corner pavilion of ancient building

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2835444Y (en) * 2005-10-20 2006-11-08 黄鸣 Bower with solar thermal-arrest device
CN201817913U (en) * 2010-09-29 2011-05-04 邓世超 Combined house capable of adjusting lifting
JP2012132145A (en) * 2010-12-19 2012-07-12 Takenaka Komuten Co Ltd Lifting device for building
CN202416913U (en) * 2011-12-31 2012-09-05 赵立峰 Combined pavilion
CN204703548U (en) * 2015-02-15 2015-10-14 上海天演建筑物移位工程股份有限公司 Whole building is rectified a deviation, is raised lifting means

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2835444Y (en) * 2005-10-20 2006-11-08 黄鸣 Bower with solar thermal-arrest device
CN201817913U (en) * 2010-09-29 2011-05-04 邓世超 Combined house capable of adjusting lifting
JP2012132145A (en) * 2010-12-19 2012-07-12 Takenaka Komuten Co Ltd Lifting device for building
CN202416913U (en) * 2011-12-31 2012-09-05 赵立峰 Combined pavilion
CN204703548U (en) * 2015-02-15 2015-10-14 上海天演建筑物移位工程股份有限公司 Whole building is rectified a deviation, is raised lifting means

Also Published As

Publication number Publication date
CN107558613A (en) 2018-01-09

Similar Documents

Publication Publication Date Title
CN107558613B (en) A kind of installation method of hexagonal pavilion
US9444396B2 (en) Solar photovoltaic power generation panel mount
KR101067629B1 (en) Pagora pillar structure
KR101208892B1 (en) Prefabricated pavilion
CN211714015U (en) House building structure built in underground space
CN204475921U (en) The dismountable firm structural construction factory building of a kind of safety
CN102828614A (en) Building template system capable of being quickly detached and installed and installation method thereof
CN207348509U (en) A kind of structure in pavilion
KR101029360B1 (en) Pagora pillar structure
CN107542286B (en) Structure of pavilion
CN106894650B (en) Reinforcement structure for mortise and tenon joints of wood structure beam column and construction method thereof
CN106988520B (en) Construction method and support system for high-rise suspension structure
KR102114477B1 (en) Construction Structure of Pole Plate, Comprising Column Head with Upper/Lower Combining Structure for Enhanced Durability of Column and Buildability of Pole Plate
KR102332718B1 (en) Deck road
KR101113991B1 (en) Connection structure of pavillion roof and construction method of the same
JP5386214B2 (en) Foundation structure
CN204475919U (en) The steel-structure factory building that a kind of antidetonation is windproof
CN211173008U (en) Operating platform for variable cross-section cross box column
KR101387702B1 (en) Structure for connects beam on the coulmn of korena-style house and construction methode for there of
CN208845017U (en) Large span stone wood composite structure decorated archway
CN209779863U (en) Reinforced concrete frame beam column node
KR20090006141U (en) A prefabricated pillar for structure
CN204174848U (en) A kind of precast reinforced skeleton of sets of brackets on top of the columns of building in the style of the ancients
CN205777870U (en) A kind of tent column exempting to weld and can fix with ground
CN209413130U (en) A kind of dendriform support rod structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191009

Address after: 215000 Room 302, building 6, business and tourism building, 381 East Suzhou Avenue, Suzhou Industrial Park, Suzhou City, Jiangsu Province

Patentee after: Suzhou Xiangshan workshop Jing original construction Limited by Share Ltd

Address before: 215100 Lingshan Road, Xikou Town, Wuzhong District, Suzhou, Jiangsu, No. 505, No. 1

Patentee before: Suzhou Yi Yuan Cultural Tourism Development Co., Ltd.

TR01 Transfer of patent right