CN107558363A - A kind of bridge facility - Google Patents

A kind of bridge facility Download PDF

Info

Publication number
CN107558363A
CN107558363A CN201710804227.5A CN201710804227A CN107558363A CN 107558363 A CN107558363 A CN 107558363A CN 201710804227 A CN201710804227 A CN 201710804227A CN 107558363 A CN107558363 A CN 107558363A
Authority
CN
China
Prior art keywords
water storehouse
rotating shaft
groove
storehouse
leads
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710804227.5A
Other languages
Chinese (zh)
Other versions
CN107558363B (en
Inventor
张晓彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gaoyu intelligent sanitary Technology (Jiangsu) Co.,Ltd.
Original Assignee
张晓彬
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 张晓彬 filed Critical 张晓彬
Priority to CN201710804227.5A priority Critical patent/CN107558363B/en
Publication of CN107558363A publication Critical patent/CN107558363A/en
Application granted granted Critical
Publication of CN107558363B publication Critical patent/CN107558363B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of bridge facility of the present invention, including the storage tank being fixedly mounted on stand, stand angle bottom is fixed with firm block, each firm block bottom is equipped with slipmat, it is provided with the first water storehouse in the storage tank one by one from top to bottom, second water storehouse and installation storehouse, be provided with the top of first water storehouse lead to first water storehouse lead inlet pipe, the installation orlop portion is provided with delivery line, first led to, which is provided with, between first water storehouse and the second water storehouse leads to groove, second led to, which is provided with, between second water storehouse and installation storehouse leads to groove, second water storehouse, which is centrally located at described first and leads to groove lower right, is rotatably mounted with the first rotating shaft being connected with generator, lead to groove lower right positioned at described second in the installation storehouse and be rotatably mounted with the second rotating shaft.

Description

A kind of bridge facility
Technical field
The present invention relates to bridge field, specifically a kind of bridge facility.
Background technology
There are many electric appliance components for needing power supply to use on bridge(Such as:Illuminating lamp, electronic display etc.), but these Electrical equipment is all often the waste that civil power is greatly added by being electrically connected with city, and it is at the same time existing in bridge blowdown Device is only limited to bridge blowdown use, and has the formation compared with mass-flow during bridge blowdown, it is well known that current can be used for Generate electricity, therefore, it is existing in bridge blowdown apparatus do not possess generating function and larger defect be present, be badly in need of providing a kind of and generate electricity, The bridge facility of blowdown integral type, to reduce the waste of civil power.
The content of the invention
For the deficiency of above-mentioned technology, the present invention proposes a kind of bridge facility.
A kind of bridge facility of the present invention, including the storage tank being fixedly mounted on stand, stand angle bottom are fixed Provided with firm block, each firm block bottom is equipped with slipmat, and first is provided with one by one from top to bottom in the storage tank Water storehouse, the second water storehouse and installation storehouse, be provided with the top of first water storehouse lead to first water storehouse lead inlet pipe, The installation orlop portion is provided with delivery line, and being provided with first led between first water storehouse and the second water storehouse leads to Groove, it is provided with second led between second water storehouse and installation storehouse and leads to groove, second water storehouse is centrally located at institute State first and lead to groove lower right and be rotatably mounted with the first rotating shaft being connected with generator, positioned at described the in the installation storehouse Two, which lead to groove lower right, is rotatably mounted with the second rotating shaft, and rotation is installed with the first rotating shaft and the second rotating shaft Portion, multiple pivoting leafs that the rotating part includes pivoted housing and is uniformly arranged on the outside of the pivoted housing, the pivoted housing and described the One rotating shaft is fixedly connected with the second rotating shaft, and the first rotating shaft and the second rotating shaft pass the storage tank and be separately installed with backward First gear and second gear, are provided with cingulum in the first gear and second gear, and described first leads to groove and second logical Even groove upper end is respectively arranged with the first fitting recess and the second fitting recess, and first fitting recess and the second fitting recess left end pass through the Three rotating shafts are respectively rotatably provided with the first folding valve and the second folding valve, divide in first water storehouse and the second water storehouse First management and control portion and the second management and control portion are not installed, the first management and control portion includes upper rocker piece, upper cotton rope and upper ejector pin, described Upper cotton rope one end is fixed on the upper rocker piece lower end, and the other end is fixedly connected with the first folding valve right-hand member, and described second Management and control portion includes lower rocker piece, lower cotton rope and lower push rod, and described lower cotton rope one end is fixed on the lower rocker piece lower end, the other end It is fixedly connected with the second folding valve right-hand member,
Upper guide groove is respectively arranged with further technical scheme, first water storehouse and the second water storehouse both sides end wall with Guide groove, slide respectively in the upper guide groove and lower guide channel and sliding block and lower sliding block are installed, it is solid between two upper sliding blocks Dingan County is equipped with upper connective pole, and lower connective pole, the upper connective pole and lower connective pole point are installed between two lower sliding blocks It is not fixedly connected with the upper rocker piece and lower rocker piece.
Further technical scheme, first water storehouse, the second water storehouse and installation orlop portion are respectively arranged with first Scarf, the second scarf and the 3rd scarf, first scarf are located at the 3rd rotating shaft left end and are installed with Projection, the upper protruding block right-hand member are installed with magnetite, and second scarf is located at the 3rd rotating shaft left end and fixes peace Equipped with lower protruding block, the lower protruding block right-hand member is installed with lower magnetite, and the first folding valve and the second folding valve upper surface are leaned on Iron-stone is fixedly installed at nearly 3rd rotating shaft.
Further technical scheme, described first lead to groove and second lead to groove lower end be respectively arranged with conduit and under lead Pipe, the equal face pivoting leaf of upper conduit and downcomer.
Further technical scheme, the pivoting leaf end are provided with oppositely arranged bent plate, pushed away so as to increase current Power.
Further technical scheme, upper ejector pin and the lower push rod end be provided with it is spherical, and the upper ejector pin and under Push rod is tilted to the right setting.
The beneficial effects of the invention are as follows;
Apparatus of the present invention can concentrate on sewage in the first water storehouse, can when the water in the first water storehouse reach a certain height The first folding valve is opened, after the first folding valve is opened, current can drive first rotating shaft to rotate and make generator operation, the Water in one water storehouse can be flowed into the second water storehouse, and after the first folding valve leads to groove by first closes, described second is logical Even groove is opened, and current can lead to from described second to be flowed out in groove and drive second axis of rotation, and second rotating shaft is led to Crossing cingulum can drive the first rotating shaft to rotate, and thus can act on generator again, so as to make generator task again, and Water after use can flow out from delivery line, delivery line can be connected into cistern;Apparatus of the present invention first can concentrate bridge sewage Accumulation of energy, then generated electricity during blowdown using current, and caused electric energy can be directly used for bridge electricity consumption device Power supply, can greatly reduce the waste of civil power.
Brief description of the drawings
, below will be to embodiment or prior art in order to illustrate more clearly of inventive embodiments or technical scheme of the prior art The required accompanying drawing used is briefly described in description, it should be apparent that, drawings in the following description are only one invented A little embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can also be according to these Accompanying drawing obtains other accompanying drawings.
Fig. 1 is a kind of structural representation of bridge facility of the present invention;
Fig. 2 is structural representation when the first folding valve pivots to the left in Fig. 1;
Fig. 3 is the mplifying structure schematic diagram at the first folding valve in Fig. 1;
Fig. 4 is the right view of upper rocker piece in Fig. 3.
Embodiment
All features disclosed in this specification, or disclosed all methods or during the step of, except mutually exclusive spy Beyond sign and/or step, it can combine in any way.
This specification(Including any accessory claim, summary and accompanying drawing)Disclosed in any feature, except non-specifically chatting State, can alternative features equivalent by other or with similar purpose replaced.I.e., unless specifically stated otherwise, each feature It is an example in a series of equivalent or similar characteristics.
As shown in Figures 1 to 4, a kind of bridge facility of apparatus of the present invention, including the water storage being fixedly mounted on stand 10 Case 18, described 10 jiaos of bottoms of stand are fixed with firm block 101, and each firm bottom of block 101 is equipped with slipmat 102, The firm block 101 is used to increasing with the contact area on ground, stability during so as to improve support, and passes through the slipmat 102 can effectively prevent ground wet and slippery and the skiddings of appearance, and the first storage is provided with one by one from top to bottom in the storage tank 18 Sump 20, the second water storehouse 17 and installation storehouse 12, the top of the first water storehouse 20, which is provided with, leads to first water storehouse 20 Lead inlet pipe 21, the installation bottom of storehouse 12 is provided with delivery line 37, between the water storehouse 17 of the first water storehouse 20 and second It is provided with first led to and leads to groove 26, being provided with second led between second water storehouse 17 and installation storehouse 12 leads to groove 32, second water storehouse 17, which is centrally located at described first and leads to the lower right of groove 26, is rotatably mounted with what is be connected with generator First rotating shaft 28, lead to the lower right of groove 32 positioned at described second and be rotatably mounted with the second rotating shaft 34 in the installation storehouse 12, Rotating part is installed with the rotating shaft 34 of first rotating shaft 28 and second, the rotating part includes pivoted housing 27 and uniformly peace Multiple pivoting leafs 29 mounted in the outside of pivoted housing 27, the pivoted housing 27 is fixed with the rotating shaft 34 of first rotating shaft 28 and second to be connected Connect, the rotating shaft 34 of first rotating shaft 28 and second passes the storage tank 18 and is separately installed with first gear and second backward Gear, cingulum is installed in the first gear and second gear, described first, which leads to groove 26 and second, leads to the upper end of groove 32 point The first fitting recess 35 and the second fitting recess are not provided with, and the fitting recess left end of the first fitting recess 35 and second passes through the 3rd rotating shaft First folding valve 42 and the second folding valve 13 be respectively rotatably installed, in the water storehouse 17 of the first water storehouse 20 and second It is separately installed with the first management and control portion and the second management and control portion, the first management and control portion and the second management and control portion are respectively controlling described One folding valve 42 and the second folding valve 13, the first management and control portion includes upper rocker piece 23, upper cotton rope 25 and upper ejector pin 47, described Upper one end of cotton rope 25 is fixed on the lower end of upper rocker piece 23, and the other end is fixedly connected with the right-hand member of the first folding valve 42, institute Stating the second management and control portion includes lower rocker piece 40, lower cotton rope 38 and lower push rod 39, and described lower one end of cotton rope 38 is fixed on described float downward The lower end of motion block 40, the other end are fixedly connected with the right-hand member of the second folding valve 13,
Valuably or exemplarily, wherein, it is respectively arranged with the both sides end wall of 20 and second water storehouse of the first water storehouse 17 Upper guide groove 19 and lower guide channel 16, slide respectively in the upper guide groove 19 and lower guide channel 16 and sliding block 36 and lower sliding block are installed 31, connective pole 24 is installed between two upper sliding blocks 36, is installed with down in succession between two lower sliding blocks 31 Bar 30, the upper connective pole 24 and lower connective pole 30 are fixedly connected with the upper rocker piece 23 and lower rocker piece 40 respectively.
Valuably or exemplarily, wherein, first water storehouse 20, the second water storehouse 17 and the installation bottom of storehouse 12 are distinguished The first scarf 22, the second scarf 15 and the 3rd scarf 11 are provided with, first scarf 22 is located at described 3rd turn Axle left end is installed with upper protruding block 45, and the right-hand member of upper protruding block 45 is installed with magnetite 44, second scarf 15 Lower protruding block 14 is installed with positioned at the 3rd rotating shaft left end, the right-hand member of lower protruding block 14 is installed with lower magnetite, described First folding valve 42 and the upper surface of the second folding valve 13 are fixedly installed iron-stone 46 at the 3rd rotating shaft.
Valuably or exemplarily, wherein, described first, which leads to groove 26 and second, leads to the lower end of groove 32 and is respectively arranged with Conduit 41 and downcomer 33, the equal face pivoting leaf 29 of the upper conduit 41 and downcomer 33.
Valuably or exemplarily, wherein, the end of pivoting leaf 29 is provided with oppositely arranged bent plate 290, so as to Increase hydro-flow thrust.
Valuably or exemplarily, wherein, upper ejector pin 47 and lower push rod 39 end is provided with spherical 43, and described Upper ejector pin 47 and lower push rod 39 are tilted to the right setting.
During apparatus of the present invention original state, the first folding valve 42 and the second folding valve 13 lead to described first respectively Groove 26 and second leads to groove 32 and blocked, and the upper rocker piece 23 and lower rocker piece are respectively in itself gravity and upper connective pole 24 Be located at the water storage of the first water storehouse 20 and second under the Action of Gravity Field of lower connective pole 30, upper sliding block 36 and lower sliding block 31 The bottom of storehouse 17, and on the upper ejector pin 47 and lower push rod 39 it is spherical respectively with the first folding valve 42 and the second folding valve 13 Upper surface offsets.
In use, lead the water storage into first water storehouse 20 of inlet pipe 21 by described, with the rise of water level, it is described on Rocker piece 23 can follow water level to rise, and after the upper cotton rope 25 is tensioned, after water level continues rising, the upper rocker piece 23 can lead to Cotton rope 25 is crossed to pivot the first folding valve 42 to the left, when the first folding valve 42 pivots to the left, the upper magnetite 44 The adsorbable iron-stone 46, so that the first folding valve 42 is opened, after the first folding valve 42 is opened, described first Water in water storehouse 20 leads to from described first to be flowed into groove 26 in second water storehouse 17, the process that water flows downward out In, current can impact the pivoting leaf 29, and so as to drive the first rotating shaft 28 to rotate, the rotation of first rotating shaft 28 makes can Act on generator and make generator operation, with the water level decreasing of first water storehouse 20, in second water storehouse 17 Water level constantly raise, during water level decreasing in first water storehouse 20, the upper rocker piece 23 constantly declines, the floating During motion block 23 declines, spherical 43 on the upper ejector pin 47 may act on the first folding valve 42, and described first opens Thuban turn can be driven to by closing valve 42, when the first folding valve 42 leads to groove 26 by described first to be blocked, second storage Water level in sump 17 reaches high point, and the lower rocker piece 40 is pulled up the second folding valve 13 by the lower cotton rope 38 Rise, and after the second folding valve 13 pivots to the left, lead to groove 32 by described second and open, current lead to groove 32 from described second In be flowed into it is described installation storehouse 12 in, current be flowed into it is described installation storehouse 12 in during, current can impact the lower section Pivoting leaf 29, the pivoting leaf 29 can drive second rotating shaft 34 to rotate, and second rotating shaft 34 can drive when rotating Second gear rotates, and the second gear can drive the first gear to rotate by cingulum, and the first gear can when rotating The first rotating shaft 28 is driven, the first rotating shaft 28 can make generator operation when rotating, when in second water storehouse 17 After water outflow, the second folding valve 13 can return to original state.
The beneficial effects of the invention are as follows:Apparatus of the present invention can concentrate on sewage in the first water storehouse, when the first water storehouse In water when reaching a certain height, can open the first folding valve, after the first folding valve is opened, current can drive first turn Axle is rotated and makes generator operation, and the water in the first water storehouse can be flowed into the second water storehouse, when the first folding valve is by first After leading to groove closing, described second, which leads to groove, is opened, and current can lead to from described second to flow out in groove and drive described second Axis of rotation, second rotating shaft can drive the first rotating shaft to rotate, thus can act on generator again by cingulum, from And generator task again can be made, and the water after use can flow out from delivery line, delivery line can be connected into cistern;The present invention Bridge sewage first can be concentrated accumulation of energy by device, then be generated electricity during blowdown using current, and caused electric energy can The power supply of bridge electricity consumption device is directly used in, the waste of civil power can be greatly reduced.
General principle, principal character and the advantages of the present invention of the present invention has been shown and described above.The technology of the industry For personnel it should be appreciated that the present invention is not limited to the above embodiments, that described in above-described embodiment and specification is the present invention Principle, without departing from the spirit and scope of the present invention, various changes and modifications of the present invention are possible, these change and Improvement is both fallen within claimed invention.The claimed scope of the invention is by appended claims and its equivalent circle It is fixed.

Claims (6)

1. a kind of bridge facility, including the storage tank being fixedly mounted on stand, it is characterised in that:Stand angle bottom is fixed Provided with firm block, each firm block bottom is equipped with slipmat, and first is provided with one by one from top to bottom in the storage tank Water storehouse, the second water storehouse and installation storehouse, be provided with the top of first water storehouse lead to first water storehouse lead inlet pipe, The installation orlop portion is provided with delivery line, and being provided with first led between first water storehouse and the second water storehouse leads to Groove, it is provided with second led between second water storehouse and installation storehouse and leads to groove, second water storehouse is centrally located at institute State first and lead to groove lower right and be rotatably mounted with the first rotating shaft being connected with generator, positioned at described the in the installation storehouse Two, which lead to groove lower right, is rotatably mounted with the second rotating shaft, and rotation is installed with the first rotating shaft and the second rotating shaft Portion, multiple pivoting leafs that the rotating part includes pivoted housing and is uniformly arranged on the outside of the pivoted housing, the pivoted housing and described the One rotating shaft is fixedly connected with the second rotating shaft, and the first rotating shaft and the second rotating shaft pass the storage tank and be separately installed with backward First gear and second gear, are provided with cingulum in the first gear and second gear, and described first leads to groove and second logical Even groove upper end is respectively arranged with the first fitting recess and the second fitting recess, and first fitting recess and the second fitting recess left end pass through the Three rotating shafts are respectively rotatably provided with the first folding valve and the second folding valve, divide in first water storehouse and the second water storehouse First management and control portion and the second management and control portion are not installed, the first management and control portion includes upper rocker piece, upper cotton rope and upper ejector pin, described Upper cotton rope one end is fixed on the upper rocker piece lower end, and the other end is fixedly connected with the first folding valve right-hand member, and described second Management and control portion includes lower rocker piece, lower cotton rope and lower push rod, and described lower cotton rope one end is fixed on the lower rocker piece lower end, the other end It is fixedly connected with the second folding valve right-hand member.
A kind of 2. bridge facility according to claim 1, it is characterised in that:First water storehouse and the second water storehouse two Upper guide groove and lower guide channel are respectively arranged with the wall of side, slided respectively in the upper guide groove and lower guide channel be provided with sliding block and Lower sliding block, connective pole is installed between two upper sliding blocks, is installed with down in succession between two lower sliding blocks Bar, the upper connective pole and lower connective pole are fixedly connected with the upper rocker piece and lower rocker piece respectively.
A kind of 3. bridge facility according to claim 1, it is characterised in that:First water storehouse, the second water storehouse and Installation orlop portion is respectively arranged with the first scarf, the second scarf and the 3rd scarf, and first scarf is positioned at described 3rd rotating shaft left end is installed with upper protruding block, and the upper protruding block right-hand member is installed with magnetite, the second scarf position Lower protruding block is installed with the 3rd rotating shaft left end, the lower protruding block right-hand member is installed with lower magnetite, and described first opens Close valve and the second folding valve upper surface is fixedly installed iron-stone at the 3rd rotating shaft.
A kind of 4. bridge facility according to claim 1, it is characterised in that:Described first, which leads to groove and second, leads under groove End is respectively arranged with conduit and downcomer, the equal face pivoting leaf of upper conduit and downcomer.
A kind of 5. bridge facility according to claim 1, it is characterised in that:The pivoting leaf end is provided with oppositely arranged Bent plate.
A kind of 6. bridge facility according to claim 1, it is characterised in that:Upper ejector pin and the lower push rod end is respectively provided with Have spherical.
CN201710804227.5A 2017-09-08 2017-09-08 A kind of bridge facility Active CN107558363B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710804227.5A CN107558363B (en) 2017-09-08 2017-09-08 A kind of bridge facility

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710804227.5A CN107558363B (en) 2017-09-08 2017-09-08 A kind of bridge facility

Publications (2)

Publication Number Publication Date
CN107558363A true CN107558363A (en) 2018-01-09
CN107558363B CN107558363B (en) 2018-12-14

Family

ID=60979828

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710804227.5A Active CN107558363B (en) 2017-09-08 2017-09-08 A kind of bridge facility

Country Status (1)

Country Link
CN (1) CN107558363B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101235813B1 (en) * 2010-10-27 2013-02-21 우성건설 주식회사 Method of waterproof construction of the expansion joint
CN205443934U (en) * 2016-02-02 2016-08-10 杨风岗 Multi -functional energy -conserving illumination bridge railing
CN205874970U (en) * 2016-06-17 2017-01-11 山东融汇管通股份有限公司 Novel overpass rainwater collection system
JP2017036546A (en) * 2015-08-07 2017-02-16 株式会社竹中土木 Method for real time visualization of temperature measurement information in concrete structure pipe cooling system
CN206157623U (en) * 2016-11-02 2017-05-10 中安安轩安全产业发展有限公司 Elastic guardrail street lamp
CN206233101U (en) * 2016-11-29 2017-06-09 河北工程大学 A kind of road and bridge guard rail
CN206337496U (en) * 2016-11-16 2017-07-18 石家庄交通勘察设计院 A kind of bridge flowing water electric supply installation

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101235813B1 (en) * 2010-10-27 2013-02-21 우성건설 주식회사 Method of waterproof construction of the expansion joint
JP2017036546A (en) * 2015-08-07 2017-02-16 株式会社竹中土木 Method for real time visualization of temperature measurement information in concrete structure pipe cooling system
CN205443934U (en) * 2016-02-02 2016-08-10 杨风岗 Multi -functional energy -conserving illumination bridge railing
CN205874970U (en) * 2016-06-17 2017-01-11 山东融汇管通股份有限公司 Novel overpass rainwater collection system
CN206157623U (en) * 2016-11-02 2017-05-10 中安安轩安全产业发展有限公司 Elastic guardrail street lamp
CN206337496U (en) * 2016-11-16 2017-07-18 石家庄交通勘察设计院 A kind of bridge flowing water electric supply installation
CN206233101U (en) * 2016-11-29 2017-06-09 河北工程大学 A kind of road and bridge guard rail

Also Published As

Publication number Publication date
CN107558363B (en) 2018-12-14

Similar Documents

Publication Publication Date Title
CN107558363A (en) A kind of bridge facility
CN105221442A (en) A kind of lifting Verticle vortex pipeline mounted pump
CN107559125A (en) A kind of novel bridge facility
CN208770900U (en) A kind of gs-oil separator with agitating function
CN107893731A (en) A kind of novel hydroelectric device
CN203964307U (en) A kind of draining starting switch and apply the air conditioner drainer of this switch
CN108468841A (en) It is a kind of integrate check-valves, regulating valve, three function of shut-off valve pump multifunction valve
CN203821569U (en) Structure for automatically adjusting water outlet flow of pool
CN204613767U (en) Fluid level controller
CN108221656A (en) A kind of improved bridge facility
CN207672722U (en) Rain dirt terminal shunts self-con-tained unit
CN207004717U (en) A kind of water-energy generating electricity unit and the water-energy generating electricity circulatory system
US20180104623A1 (en) Floating weir skimmer
CN104863253A (en) Central shaft waterpower automatic gate capable of being automatically opened by inducting water level
CN205896354U (en) Novel float valve
CN106641409B (en) Floating control flow regulating valve capable of automatically cleaning blockage
CN107605643A (en) A kind of hydroelectric installation
CN209475671U (en) A kind of environment protection treating sewage-treatment plant
CN107537393A (en) A kind of environmental protection coating material device
CN107558586A (en) A kind of urban sewage well device of the utilization of resources
CN107620665A (en) A kind of sewage-treatment plant
KR102359903B1 (en) Conductive moving beam
CN108223237A (en) A kind of modified sewage-treatment plant
CN103850333B (en) Pond water flow self-regulation structure
CN207499114U (en) A kind of building, waterpower, highway engineering chute and building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20181015

Address after: 317100 No. 3, Hai You street, Hai You street, three gate County, Taizhou, Zhejiang

Applicant after: Three county Licheng Electronic Technology Co., Ltd.

Address before: 434000 Jiangjin West Road, Shashi, Jingzhou, Hubei 1099

Applicant before: Zhang Xiaobin

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201126

Address after: 221351, Jiangsu City, Xuzhou province Pizhou City Town Hardware Machinery Industry Park

Patentee after: Gaoyu intelligent sanitary Technology (Jiangsu) Co.,Ltd.

Address before: 317100 No. 3, Hai You street, Hai You street, three gate County, Taizhou, Zhejiang

Patentee before: SANMEN LICHENG ELECTRONIC TECHNOLOGY Co.,Ltd.