CN107542474B - Tunnel oversized widened section surface controlled blasting excavation construction method - Google Patents

Tunnel oversized widened section surface controlled blasting excavation construction method Download PDF

Info

Publication number
CN107542474B
CN107542474B CN201710839644.3A CN201710839644A CN107542474B CN 107542474 B CN107542474 B CN 107542474B CN 201710839644 A CN201710839644 A CN 201710839644A CN 107542474 B CN107542474 B CN 107542474B
Authority
CN
China
Prior art keywords
section
excavation
widened section
blasting
widened
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710839644.3A
Other languages
Chinese (zh)
Other versions
CN107542474A (en
Inventor
李雷斌
张超
李�浩
肖涛
沈阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
CRECGZ Urban Rail Engineering Co Ltd
CRECGZ Port and Channel Engineering Co Ltd
Original Assignee
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
CRECGZ Port and Channel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Guangzhou Engineering Group Co Ltd CRECGZ, CRECGZ Port and Channel Engineering Co Ltd filed Critical China Railway Guangzhou Engineering Group Co Ltd CRECGZ
Priority to CN201710839644.3A priority Critical patent/CN107542474B/en
Publication of CN107542474A publication Critical patent/CN107542474A/en
Application granted granted Critical
Publication of CN107542474B publication Critical patent/CN107542474B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a construction method for controlling blasting excavation of an oversized widened section of a tunnel, which is used in the technical field of tunnel construction and comprises the following steps: s10, excavating a common section in advance; s20, after primary support of common section excavation is completed and settlement is stable, carrying out blasting excavation on a widening section, excavating the widening section by adopting a step method, and excavating a vault heightened part of the common section; s30, cutting in from one end of the widening section in a direction inclined to the side wall by a certain angle, advancing, excavating an end wall at the other end by using a smooth blasting method after the end wall is excavated to a design contour line, and then performing primary support; meanwhile, backward excavation is carried out, the method is pushed forward by using a smooth blasting method according to the excavation method of the common section, and then the primary support of the upper step excavation of the widened section is synchronously completed; and S40, finally blasting and excavating the lower step. The method accelerates the excavation progress of the widening section, avoids construction period risks and labor waste, and greatly reduces the construction cost. The construction process is simpler, and the requirement of using under the condition of a shorter widening section can be met.

Description

A kind of tunnel super large widened section face control Excavation Blasting method
Technical field
The present invention is used for technical field of tunnel construction, controls Blasting Excavation more particularly to a kind of tunnel super large widened section face Construction method.
Background technique
With the Large scale construction of the highway in China network of communication lines, and the Large scale construction in oil reserve base in recent years, tunnel Road design becomes increasingly complex, in order to meet the needs of safety and line equipment installation, the section of widened section therein relative to Conventional section constantly expands.Especially petroleum pipeline tunnel, conventional section design is smaller, and wants to meet the space of expansion joint It asks, the ratio standard paragraphs of widened section design broaden one times or more, and height also increases by three or four meters, and it is smaller to widen segment length, more For a widened section respectively in different positions, this just brings great challenge to constructing tunnel.
For the tunnel for being distributed super large widened section in narrow-bore tunnel, in the construction process, how safely, fast and accurately Completion widened section excavate, become the emphasis of construction method research.
Conventional tunnel widened section excavation method:
Two side-wall pilot tunnel construction.This kind of method is suitable for the longer situation of widened section, is excavated to and widens to conventional section Start to use when section, first have to open one section of working face, then start to push ahead, main sequence of construction are as follows: excavates right side base tunnel Get out of a predicament or an embarrassing situation-one Core Soil top bar of base tunnel top bar one Core Soil in left side gets out of a predicament or an embarrassing situation-right side base tunnel top bar.
Widened section uses the shortcomings that two side-wall pilot tunnel excavation construction:
(1), working procedure is more complicated, is only useful in the longer situation of widened section and uses.
(2), when using the method, conventional section construction will be severely impacted, and cannot achieve cross-operation, to duration shadow Sound is larger, and causes the work holdup, hence it is evident that increases construction cost.
(3), widened section out break is difficult to effectively control.
Summary of the invention
To solve the above problems, the present invention provides a kind of tunnel super large widened section face control Excavation Blasting method, Can relatively accurate control Tunnel Overbreak & Underbreak, and accelerate construction progress, reduce construction cost, reduce construction safety risk.
The technical solution adopted by the present invention to solve the technical problems is: a kind of control explosion of tunnel super large widened section face is opened Cut construction method, comprising the following steps:
S10. conventional section is excavated in advance;
S20. after conventional section excavates just branch completion and settlement stability, widened section Blasting Excavation is carried out, widened section uses Benching tunnelling method excavates, and first excavates conventional section vault Elevated section;
S30. it is then cut, and pushed ahead with the direction being tilted a certain angle to side wall in one end from widened section, to It is excavated to after design profile line, the headwall of the other end is excavated using smooth blasting method, then carry out just branch;It reversely opens simultaneously It digs, is pushed ahead according to the excavation method of conventional section using photoface exploision method, then synchronously complete widened section top bar excavation Just branch;
S40. last Blasting Excavation is got out of a predicament or an embarrassing situation.
It is further used as the improvement of technical solution of the present invention, in step S10, when Blasting Excavation conventional section, in widened section Place is appropriate to increase light blast hole camber angle, and excavates reserved notch to widened section.
It is further used as the improvement of technical solution of the present invention, when being excavated using benching tunnelling method, get out of a predicament or an embarrassing situation height take widened section compared with The height that conventional section is increased.
It is further used as the improvement of technical solution of the present invention, in step S20, when excavating conventional section vault Elevated section, It first slots, excavates after being excavated to design profile line and then horizontally forward obliquely, finally excavate at the residue of back.
It is further used as the improvement of technical solution of the present invention, and after conventional section vault Elevated section is completed, construction is common The first branch of section and widened section radian same section.
It is further used as the improvement of technical solution of the present invention, in step S30, from one end of widened section to tilt to side wall The direction incision at 30 ° of angles, and pushing ahead, not scarfing cinder after explosion, quick-fried heap is carried out it is smooth, as temporary construction platform, with The propulsion of explosion, platform are constantly increased, and until meeting vault construction height requirement, dig to side wall to the contour line of widened section When, it carries out other end headwall light and pops diggings, after the completion of excavation at headwall, carry out the first branch in the region, it is complete to supporting at headwall Cheng Hou starts reversed excavation, is excavated along widened section tunnel contour line, constructed according to smooth Surface Blasting Technology, and strict control is super It owes to dig, and constructs one section one section of supporting.
It is further used as the improvement of technical solution of the present invention, removes temporary construction platform, carries out Blasting Excavation of getting out of a predicament or an embarrassing situation.
Beneficial effects of the present invention: then the present invention presses specific process excavation widened section by excavating conventional section in advance New process has the advantage that
(1), it accelerates widened section and excavates progress, avoid duration risk, avoid the work holdup.
(2), the control of the out break of contour line and headwall is fairly proper.
(3), existing machinery equipment can be made full use of, construction cost is greatly reduced.
(4), working procedure is fairly simple, uses in the case where can satisfy shorter widened section.
Detailed description of the invention
The present invention will be further explained below with reference to the attached drawings:
Fig. 1 is that widened section vault Elevated section of the present invention excavates schematic diagram;
Fig. 2 is widened section side wall excavation construction schematic diagram of the present invention;
Fig. 3 is widened section side wall sequence of excavation figure of the present invention.
Specific embodiment
Referring to figs. 1 to Fig. 3, that show the specific structures of the preferred embodiments of the invention.It will be detailed below this Invent the design feature of each element, and when if there is being described to direction (upper and lower, left and right, before and after), it is with knot shown in FIG. 1 Structure is reference description, but actual use direction of the invention is not limited thereto.Widened section described below: in some traffic or It is arranged in pipeline tunnel, is used as one or more local sections of emergency lane or equipment installation space relative to common disconnected The tunnel section that face size is widened or increased.
The present invention provides a kind of tunnel super large widened section faces to control Excavation Blasting method, comprising the following steps:
S10. conventional section is excavated in advance, suitably increases light blast hole camber angle at widened section, and excavate in advance to widened section Stay notch;
S20. after conventional section excavates just branch completion and settlement stability, widened section Blasting Excavation is carried out, widened section uses Benching tunnelling method excavates, and height of getting out of a predicament or an embarrassing situation takes widened section compared with the height that conventional section is increased, and first excavates conventional section vault Elevated section, When excavating conventional section vault Elevated section, referring to Fig. 1, first slot obliquely, the then water after being excavated to design profile line It is flat to excavate forward, finally excavate at the residue of back, after conventional section vault Elevated section is completed, construction conventional section with widen The first branch of section radian same section;
S30. referring to fig. 2, Fig. 3, cut from one end of widened section with the direction for tilting 30 ° of angles to side wall, and push ahead, Not scarfing cinder after explosion, the progress of quick-fried heap is smooth, and as temporary construction platform, with the propulsion of explosion, platform is constantly increased, until Meet vault construction height requirement, when side wall is digged to the contour line of widened section, carries out other end headwall light and pop digging, wait hold After the completion of excavating at wall, the first branch in the region is carried out, after the completion of supporting at headwall, starts reversed excavation, along widened section tunnel Contour line is excavated, and is constructed according to smooth Surface Blasting Technology, strict control out break, and is constructed one section one section of supporting;
S40. temporary construction platform is finally removed, Blasting Excavation of getting out of a predicament or an embarrassing situation is carried out.
Then the present invention presses the new process that specific process excavates widened section by excavating conventional section in advance, have following excellent Point:
(1), it accelerates widened section and excavates progress, widened section is excavated can be avoided pair with common section supporting with crossed construction The influence of duration avoids duration risk, avoids the work holdup.
(2), the control of the out break of contour line and headwall is fairly proper.
(3), existing machinery equipment can be made full use of, construction cost is greatly reduced.
(4), working procedure is fairly simple, uses in the case where can satisfy shorter widened section.
Certainly, the invention is not limited to above embodiment, and those skilled in the art are without prejudice to originally Equivalent deformation or replacement can be also made under the premise of spirit, these equivalent variation or replacement are all contained in the application right It is required that in limited range.

Claims (7)

1. a kind of tunnel super large widened section face controls Excavation Blasting method, which comprises the following steps:
S10. conventional section is excavated in advance;
S20. after conventional section excavates just branch completion and settlement stability, widened section Blasting Excavation is carried out, widened section uses step Method is excavated, and conventional section vault Elevated section is first excavated;
S30. the then direction incision from one end of widened section to be tilted a certain angle to side wall, and push ahead, wait be excavated to After design profile line, the headwall of the other end is excavated using smooth blasting method, then carries out just branch;It is reversed simultaneously to excavate, it presses Excavation method according to conventional section is pushed ahead using photoface exploision method, is then synchronously completed widened section top bar and is excavated just branch;
S40. last Blasting Excavation is got out of a predicament or an embarrassing situation.
2. tunnel super large widened section face according to claim 1 controls Excavation Blasting method, it is characterised in that: step In S10, when Blasting Excavation conventional section, suitably increase light blast hole camber angle at widened section, and excavate reserved cut to widened section Mouthful.
3. tunnel super large widened section face according to claim 1 controls Excavation Blasting method, it is characterised in that: use When benching tunnelling method excavates, height of getting out of a predicament or an embarrassing situation takes widened section compared with the height that conventional section is increased.
4. tunnel super large widened section face according to claim 1 controls Excavation Blasting method, it is characterised in that: step In S20, when excavating conventional section vault Elevated section, first slot obliquely, it is then horizontal after being excavated to design profile line It excavates forward, finally excavates at the residue of back.
5. tunnel super large widened section face according to claim 4 controls Excavation Blasting method, it is characterised in that: common After section vault Elevated section is completed, the first branch of construct conventional section and widened section radian same section.
6. tunnel super large widened section face according to claim 1 controls Excavation Blasting method, it is characterised in that: step In S30, cut from one end of widened section with the direction for tilting 30 ° of angles to side wall, and push ahead, not scarfing cinder after explosion, it will be quick-fried Heap progress is smooth, and as temporary construction platform, with the propulsion of explosion, platform is constantly increased, until meeting vault construction height It is required that when side wall is digged to the contour line of widened section, carries out other end headwall light and pop diggings, after the completion of excavation at headwall, The first branch for carrying out the region starts reversed excavation, is excavated along widened section tunnel contour line after the completion of supporting at headwall, It constructs according to smooth Surface Blasting Technology, strict control out break, and construct one section one section of supporting.
7. tunnel super large widened section face according to claim 6 controls Excavation Blasting method, it is characterised in that: remove Temporary construction platform carries out Blasting Excavation of getting out of a predicament or an embarrassing situation.
CN201710839644.3A 2017-09-18 2017-09-18 Tunnel oversized widened section surface controlled blasting excavation construction method Active CN107542474B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710839644.3A CN107542474B (en) 2017-09-18 2017-09-18 Tunnel oversized widened section surface controlled blasting excavation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710839644.3A CN107542474B (en) 2017-09-18 2017-09-18 Tunnel oversized widened section surface controlled blasting excavation construction method

Publications (2)

Publication Number Publication Date
CN107542474A CN107542474A (en) 2018-01-05
CN107542474B true CN107542474B (en) 2019-04-23

Family

ID=60963781

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710839644.3A Active CN107542474B (en) 2017-09-18 2017-09-18 Tunnel oversized widened section surface controlled blasting excavation construction method

Country Status (1)

Country Link
CN (1) CN107542474B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222950B (en) * 2018-02-07 2020-03-24 宁波市交通规划设计研究院有限公司 Communicating and deviation rectifying method for water diversion and water delivery tunnel under weak and broken surrounding rock geological condition
CN109751054B (en) * 2019-03-27 2020-06-12 中铁隧道局集团有限公司 Construction method of U-shaped large-section tunnel
CN110924974B (en) * 2019-11-28 2022-03-04 云南省建设投资控股集团有限公司 Construction method of branch tunnel
CN111663946B (en) * 2020-06-03 2022-03-22 中国水利水电第四工程局有限公司 Variable-diameter excavation method for cavern
CN113338953A (en) * 2021-07-16 2021-09-03 中铁二十局集团有限公司 Construction method for extra-large section tunnel with turnout line led out from railway tunnel
CN113338952A (en) * 2021-07-16 2021-09-03 中铁二十局集团有限公司 Construction method for large-section tunnel with turnout line led out from railway tunnel

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10280861A (en) * 1997-04-01 1998-10-20 Shimizu Corp Construction method for tunnel junction part
JP2000192788A (en) * 1998-12-25 2000-07-11 Maeda Corp Construction method for branch part of tunnel
JP3352649B2 (en) * 1999-06-16 2002-12-03 前田建設工業株式会社 Cross section widening method of existing tunnel by middle wall dividing method
JP3888993B2 (en) * 2003-06-26 2007-03-07 佐藤工業株式会社 Tunnel widening method
CN101545376A (en) * 2009-05-07 2009-09-30 中铁四局集团第四工程有限公司 Execution method for feeding tiny tunnel into ultra heavy section tunnel transversally
CN102102521A (en) * 2010-12-29 2011-06-22 上海浦东工程建设管理有限公司 Method for broadening and rebuilding soft soil shallow tunnel in operation state
CN104329095A (en) * 2014-09-03 2015-02-04 福州市规划设计研究院 Construction method for widening existing tunnel
CN106869944A (en) * 2017-02-14 2017-06-20 中国电建集团华东勘测设计研究院有限公司 The extra small clear-distance tunnel construction method in underground interchange intersection under complex environment

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10280861A (en) * 1997-04-01 1998-10-20 Shimizu Corp Construction method for tunnel junction part
JP2000192788A (en) * 1998-12-25 2000-07-11 Maeda Corp Construction method for branch part of tunnel
JP3352649B2 (en) * 1999-06-16 2002-12-03 前田建設工業株式会社 Cross section widening method of existing tunnel by middle wall dividing method
JP3888993B2 (en) * 2003-06-26 2007-03-07 佐藤工業株式会社 Tunnel widening method
CN101545376A (en) * 2009-05-07 2009-09-30 中铁四局集团第四工程有限公司 Execution method for feeding tiny tunnel into ultra heavy section tunnel transversally
CN102102521A (en) * 2010-12-29 2011-06-22 上海浦东工程建设管理有限公司 Method for broadening and rebuilding soft soil shallow tunnel in operation state
CN104329095A (en) * 2014-09-03 2015-02-04 福州市规划设计研究院 Construction method for widening existing tunnel
CN106869944A (en) * 2017-02-14 2017-06-20 中国电建集团华东勘测设计研究院有限公司 The extra small clear-distance tunnel construction method in underground interchange intersection under complex environment

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
金鸡山隧道拓宽改造方案研究;陈七林;《隧道建设》;20111031(第5期);第577-582页、第592页 *
隧道扩建合理开挖步序的研究;谭仪忠等;《后勤工程学院学报》;20110930(第5期);第8-12页、第16页 *

Also Published As

Publication number Publication date
CN107542474A (en) 2018-01-05

Similar Documents

Publication Publication Date Title
CN107542474B (en) Tunnel oversized widened section surface controlled blasting excavation construction method
CN101775988B (en) Method for constructing from inclined shaft to main tunnel in weak surrounding rock
CN105888703B (en) Super Shallow Covered Metro Station construction method under lateral canopy lid is performed in micro- pilot tunnel
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN102392648A (en) Method for building subway station by expansively digging large-diameter shield tunnel
CN105298507A (en) Underground pipe gallery construction method of machine performing open excavation on upper portion and tunneling on lower portion
CN103277118B (en) Joint steel frame supporting system for excavating auxiliary tunnel on main-tunnel arch wall and construction method of joint steel frame supporting system
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN104632235A (en) Method for expanding excavation of large-diameter shield tunnel for subway station construction through pile arch wall support
CN107165664A (en) A kind of slope thick seam tunnels superelevation stope drift active workings Qie Dingliu lanes method along top
CN102373930A (en) Rapid construction method of weak surrounding rock large-section multi-arc tunnel
CN110259490B (en) Subway underground excavation station construction method
CN106869935B (en) Bidirectional trenching method for strip mine
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN107060772A (en) Large section construction method is mutated for Line for Passenger Transportation standard section
CN104632245A (en) Method using multi-pilot-tunnel expanding excavation large-diameter shield tunnel for building subway station
CN104975606A (en) Method for handling high-low strides at adjacent parts of reverse building foundation pit and adjacent foundation pit
CN110486021B (en) Construction method for converting large-section tunnel into two small-section tunnels
CN104712342A (en) Method of providing working plane for station expanding excavation construction in large-diameter shield tunnel
CN204457789U (en) A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build
CN113107500A (en) Variable cross-section tunnel construction method
CN104963693A (en) Construction method for rectangular parallel top pipe connection channel
CN112727484A (en) Shield-pipe-jacking up-down parallel overlapping tunnel structure and construction method thereof
CN107120119A (en) The construction method of Underground Subway Station
CN107269283B (en) A kind of big cross section tunneling subway station and running tunnel penetrate through construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220518

Address after: 511400 No. 2502, ganghanghuating No. 1 office complex building, No. 1, Ganghang 1st Street, Nansha street, Nansha District, Guangzhou, Guangdong

Patentee after: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP URBAN RAIL ENGINEERING Co.,Ltd.

Patentee after: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP Co.,Ltd.

Patentee after: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP HARBOR AND SHIPPING ENGINEERING CO.,LTD.

Address before: 511458 No. 582, Jingang Avenue, Nansha District, Guangzhou, Guangdong

Patentee before: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP Co.,Ltd.

Patentee before: China Railway Guangzhou Engineering Bureau Group port and Shipping Engineering Co., Ltd

TR01 Transfer of patent right