CN107520472A - A kind of stainless steel production rig - Google Patents
A kind of stainless steel production rig Download PDFInfo
- Publication number
- CN107520472A CN107520472A CN201710825649.0A CN201710825649A CN107520472A CN 107520472 A CN107520472 A CN 107520472A CN 201710825649 A CN201710825649 A CN 201710825649A CN 107520472 A CN107520472 A CN 107520472A
- Authority
- CN
- China
- Prior art keywords
- collection box
- fixed
- stainless steel
- substrate
- steel production
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 14
- 229910001220 stainless steel Inorganic materials 0.000 title claims abstract description 13
- 239000010935 stainless steel Substances 0.000 title claims abstract description 13
- 239000000758 substrate Substances 0.000 claims abstract description 17
- 238000010276 construction Methods 0.000 claims abstract description 8
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 20
- 238000003860 storage Methods 0.000 claims description 14
- 230000005611 electricity Effects 0.000 claims description 2
- 241001074085 Scophthalmus aquosus Species 0.000 claims 1
- 238000005553 drilling Methods 0.000 description 5
- 238000013016 damping Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 238000011084 recovery Methods 0.000 description 2
- 239000002351 wastewater Substances 0.000 description 2
- 238000000889 atomisation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000001914 filtration Methods 0.000 description 1
- 239000012535 impurity Substances 0.000 description 1
- 238000009776 industrial production Methods 0.000 description 1
- 230000009191 jumping Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23B—TURNING; BORING
- B23B39/00—General-purpose boring or drilling machines or devices; Sets of boring and/or drilling machines
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23Q—DETAILS, COMPONENTS, OR ACCESSORIES FOR MACHINE TOOLS, e.g. ARRANGEMENTS FOR COPYING OR CONTROLLING; MACHINE TOOLS IN GENERAL CHARACTERISED BY THE CONSTRUCTION OF PARTICULAR DETAILS OR COMPONENTS; COMBINATIONS OR ASSOCIATIONS OF METAL-WORKING MACHINES, NOT DIRECTED TO A PARTICULAR RESULT
- B23Q11/00—Accessories fitted to machine tools for keeping tools or parts of the machine in good working condition or for cooling work; Safety devices specially combined with or arranged in, or specially adapted for use in connection with, machine tools
- B23Q11/08—Protective coverings for parts of machine tools; Splash guards
- B23Q11/0891—Protective coverings for parts of machine tools; Splash guards arranged between the working area and the operator
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23Q—DETAILS, COMPONENTS, OR ACCESSORIES FOR MACHINE TOOLS, e.g. ARRANGEMENTS FOR COPYING OR CONTROLLING; MACHINE TOOLS IN GENERAL CHARACTERISED BY THE CONSTRUCTION OF PARTICULAR DETAILS OR COMPONENTS; COMBINATIONS OR ASSOCIATIONS OF METAL-WORKING MACHINES, NOT DIRECTED TO A PARTICULAR RESULT
- B23Q11/00—Accessories fitted to machine tools for keeping tools or parts of the machine in good working condition or for cooling work; Safety devices specially combined with or arranged in, or specially adapted for use in connection with, machine tools
- B23Q11/10—Arrangements for cooling or lubricating tools or work
Abstract
The invention discloses a kind of stainless steel production rig,Including collection box,Frame,Borehole drill construction and clamping device,Frame includes the installing plate for being fixed on the column of collection box one end and being horizontally fixed at the top of column,The lower surface of installing plate is provided with guide rail,Sliding block is embedded with guide rail,Borehole drill construction includes the pneumatic cylinder being fixed on vertically on the sliding block,It is connected with pneumatic cylinder and points to the pressure liftable bar of collection box and be horizontally fixed on the support board of pressure liftable bar lift side,Motor is installed in the middle part of the lower surface of the support board,And the output shaft of motor is fixedly connected with a rotary shaft,The lower end of rotary shaft is provided with the drill bit for being secured to connection,The clamping device includes the substrate for being fixed on collection box upper surface,A pair of threaded posts for being fixed on substrate both ends and a pair of the nuts coordinated respectively with threaded post,The middle part of substrate is provided with the first through hole through substrate.The device has broad application prospects, and is adapted to commercially promote.
Description
Technical field
The present invention relates to technical field of mechanical manufacturing equipment, specially a kind of stainless steel production rig.
Background technology
Rig refers to utilize side of the instrument harder than object, sharper keen by rotary cutting or rotary squeezing
Formula, the machinery and equipment that cylindrical hole or hole are left on object are referred to as, played a very important role in the industrial production,
In drilling machine in use, shake bigger, existing drilling machine is while and existing in not certain damping
Rig in technology does not have processing mechanism to the water after cooled, causes workbench often to have ponding, is unfavorable for drillman
Work and the operation of user, therefore, are badly in need of a kind of new rig in the market.
The content of the invention
It is an object of the invention to provide a kind of stainless steel production rig, to solve to propose in above-mentioned background technology
The problem of.
To achieve the above object, the present invention provides following technical scheme:A kind of stainless steel production rig, including return
Case is received, the frame of collection box upper surface, the borehole drill construction being arranged in frame is fixed on and is fixed on collection box upper surface
Clamping device, the frame include being vertically fixed on the column of collection box one end and are horizontally fixed at the top of column and to recovery
The installing plate of case side extension, the lower surface of the installing plate are provided with the guide rail along the installing plate length direction, and described
Be embedded with sliding block in guide rail, pneumatic cylinder that the borehole drill construction includes being fixed on vertically on the sliding block, with the pneumatic cylinder phase
Connect and point to the pressure liftable bar of collection box and be horizontally fixed on the support board of pressure liftable bar lift side, the support board
Motor is installed in the middle part of lower surface, and the output shaft of the motor is fixedly connected with a rotary shaft, the rotary shaft
Lower end be provided with the drill bit for being secured to connection, the clamping device include being fixed on the substrate of collection box upper surface, a pair it is solid
A pair of the nuts for being scheduled on the threaded post at substrate both ends and coordinating respectively with the threaded post, the middle part of the substrate, which is provided with, to be run through
The first through hole of the substrate, and the motor is set in the same plane with the first through hole, the first through hole
To the tank wall of collection box be provided with the second through hole for connect with the first through hole, the upper surface of the support board, which is fixed, pacifies
Equipped with storage tank, and water pump is provided with the storage tank, the water pump is connected with an outlet pipe, and the water outlet of the outlet pipe
End is through the storage tank and points to the drill bit, circulating pump is provided with the collection box, and the circulating pump passes through a circulation
Pipe connects with the storage tank.
Further, the motor is servomotor.
Further, the both sides of the motor are equipped with the Rigid Projectiles being fixedly connected with the support board lower surface
Spring.
Further, the diameter of the first through hole is more than the diameter of the drill bit.
Further, the inside of the collection box is provided with filter screen.
Further, the water side of the outlet pipe is provided with shower nozzle.
Compared with prior art, the beneficial effects of the invention are as follows:The present invention is provided with Rigid Projectiles in the lower surface of support board
Spring, in drilling, stiffness spring can play a part of damping;The upper surface of collection box fortunately of the invention is provided with clamping simultaneously
Mechanism, drilled object can be fixed on clamping device, avoid drilled object from jumping out and hurt sb.'s feelings, therefore, the practicality pole of the device
By force, commercially promotion and application are especially suitable for.
Brief description of the drawings
Fig. 1 is the overall structure diagram of device in the present invention;
Fig. 2 is the schematic cross-section of collection box in the present invention;
In reference:1- collection boxes;2- columns;3- installing plates;4- guide rails;5- sliding blocks;6- pneumatic cylinders;7- pressure liftable bars;
8- support boards;9- motors;10- rotary shafts;11- drill bits;12- substrates;13- threaded posts;14- nuts;15- first through hole;
The through holes of 16- second;17- storage tanks;18- water pumps;19- outlet pipes;20- circulating pumps;21- circulation pipes;22- stiffness springs;23- is filtered
Net;24- shower nozzles.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of creative work is not made
Embodiment, belong to the scope of protection of the invention.
Fig. 1-2 is referred to, the present invention provides a kind of technical scheme:A kind of stainless steel production rig, including recovery
Case 1, the frame for being fixed on the upper surface of collection box 1, the borehole drill construction being arranged in frame and it is fixed on the upper surface of collection box 1
Clamping device, the frame include being vertically fixed on the column 2 of the one end of collection box 1 and be horizontally fixed on the top of column 2 and to
The installing plate 3 of the side of collection box 1 extension, the lower surface of the installing plate 3 is provided with the guide rail along the length direction of installing plate 3
4, and sliding block 5 is embedded with the guide rail 4, pneumatic cylinder 6 that the borehole drill construction includes being fixed on vertically on the sliding block 5, with
The pneumatic cylinder 6 is connected and points to the pressure liftable bar 7 of collection box 1 and be horizontally fixed on the load of the lift side of pressure liftable bar 7
Thing plate 8, the lower surface middle part of the support board 8 is provided with motor 9, and the output shaft of the motor 9 and one rotates
Axle 10 is fixedly connected, and the lower end of the rotary shaft 10 is provided with the drill bit 11 for being secured to connection, and the clamping device includes fixing
Substrate 12 in the upper surface of collection box 1, the threaded post 13 for being fixed on the both ends of substrate 12 for a pair and respectively with the threaded post 13
A pair of the nuts 14 coordinated, the middle part of the substrate 12 are provided with the first through hole 15 through the substrate 12, and the driving electricity
Machine 9 and the first through hole 15 are set in the same plane, the first through hole 15 to collection box 1 tank wall be provided with
The second through hole 16 that the first through hole 15 connects, the upper surface of the support board 8 is installed with storage tank 17, and the storage
Water pump 18 is provided with water tank 17, the water pump 18 is connected with an outlet pipe 19, and the water side of the outlet pipe 19 passes through institute
State storage tank 17 and point to the drill bit 11, circulating pump 20 is provided with the collection box 1, and the circulating pump 20 passes through a circulation
Pipe 21 connects with the storage tank 17.
Further, the motor 9 is servomotor;It is easy to control the rotating speed of motor 9.
Further, the both sides of the motor 9 are equipped with the Rigid Projectiles being fixedly connected with the lower surface of support board 8
Spring 22;Stiffness spring 22 can play a part of damping;
Further, the diameter of the first through hole 15 is more than the diameter of the drill bit 11;The structure can not only bore one it is recessed
Groove, moreover it is possible to bore a through hole.
Further, the inside of the collection box 1 is provided with filter screen 23;Impurity caused by removing drilling, is easy to recycle
Water resource.
Further, the water side of the outlet pipe 19 is provided with shower nozzle 24;Atomization can be played a part of.
Operation principle:In use, drilled object is placed at first through hole 15 first, and with nut 14 by drilled object
Both ends fix, now move sliding block 5, motor 9 moved to the surface of drilled object, and adjust pneumatic cylinder 6 so that
Drill bit 11 is directed at drilled object, and now starting motor 9 and water pump 18, drill bit 11 will drill on drilled object, simultaneously
Shower nozzle 24 will spray water to be cooled down to drill bit 11, you can completes boring work;Waste water caused by drilling can pass through first through hole
15 and second through hole 16 enter in the collection box 1, while filter screen 23 in collection box 1 can filter to waste water, after filtering
Water can be delivered to by circulating pump 20 in storage tank 17, be easy to next use, therefore, the practicality of the device is extremely strong, very
It is adapted to commercially promotion and application.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
A variety of changes, modification can be carried out to these embodiments, replace without departing from the principles and spirit of the present invention by understanding
And modification, the scope of the present invention is defined by the appended.
Claims (6)
1. a kind of stainless steel production rig, it is characterised in that including collection box(1), be fixed on collection box(1)Upper surface
Frame, the borehole drill construction that is arranged in frame and be fixed on collection box(1)The clamping device of upper surface, the frame include
It is vertically fixed on collection box(1)The column of one end(2)And it is horizontally fixed on column(2)Top and to collection box(1)Prolong side
The installing plate stretched(3), the installing plate(3)Lower surface be provided with along the installing plate(3)The guide rail of length direction(4), and
The guide rail(4)Inside it is embedded with sliding block(5), the borehole drill construction including being fixed on the sliding block vertically(5)On pneumatic cylinder
(6)And the pneumatic cylinder(6)It is connected and points to collection box(1)Pressure liftable bar(7)And it is horizontally fixed on pressure liftable bar
(7)The support board of lift side(8), the support board(8)Lower surface in the middle part of motor is installed(9), and the driving electricity
Machine(9)Output shaft and a rotary shaft(10)It is fixedly connected, the rotary shaft(10)Lower end be provided be secured to connection brill
Head(11), the clamping device is including being fixed on collection box(1)The substrate of upper surface(12), be fixed on substrate a pair(12)Both ends
Threaded post(13)And respectively with the threaded post(13)A pair of the nuts coordinated(14), the substrate(12)Middle part be provided with
Through the substrate(12)First through hole(15), and the motor(9)With the first through hole(15)It is arranged on same
In plane, the first through hole(15)To collection box(1)Tank wall be provided with and the first through hole(15)The of connection
Two through holes(16), the support board(8)Upper surface be installed with storage tank(17), and the storage tank(17)Inside it is provided with
Water pump(18), the water pump(18)With an outlet pipe(19)It is connected, and the outlet pipe(19)Water side pass through the water storage
Case(17)And point to the drill bit(11), the collection box(1)It is interior to be provided with circulating pump(20), and the circulating pump(20)Pass through one
Circulation pipe(21)With the storage tank(17)Connection.
A kind of 2. stainless steel production rig according to claim 1, it is characterised in that the motor(9)
For servomotor.
A kind of 3. stainless steel production rig according to claim 1, it is characterised in that the motor(9)
Both sides be equipped with and the support board(8)The stiffness spring that lower surface is fixedly connected(22).
A kind of 4. stainless steel production rig according to claim 1, it is characterised in that the first through hole(15)
Diameter be more than the drill bit(11)Diameter.
A kind of 5. stainless steel production rig according to claim 1, it is characterised in that the collection box(1)'s
Inside is provided with filter screen(23).
A kind of 6. stainless steel production rig according to claim 1, it is characterised in that the outlet pipe(19)'s
Water side is provided with shower nozzle(24).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710825649.0A CN107520472A (en) | 2017-09-14 | 2017-09-14 | A kind of stainless steel production rig |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710825649.0A CN107520472A (en) | 2017-09-14 | 2017-09-14 | A kind of stainless steel production rig |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107520472A true CN107520472A (en) | 2017-12-29 |
Family
ID=60736867
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710825649.0A Pending CN107520472A (en) | 2017-09-14 | 2017-09-14 | A kind of stainless steel production rig |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107520472A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108161053A (en) * | 2018-02-22 | 2018-06-15 | 德清宏晨铸造有限公司 | A kind of steel plate drilling equipment |
CN108296520A (en) * | 2018-02-22 | 2018-07-20 | 德清宏晨铸造有限公司 | A kind of steel plate drilling device |
CN108971570A (en) * | 2018-10-08 | 2018-12-11 | 德清微晶防水材料有限公司 | A kind of waterproof pipe drilling device with cooling effect |
CN111546091A (en) * | 2020-03-05 | 2020-08-18 | 吉林大学 | Numerical control machine tool considering equipment safety and safety protection mechanism thereof |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20110229280A1 (en) * | 2010-03-16 | 2011-09-22 | Kabushiki Kaisha Toshiba | Deep hole processing device |
CN205074575U (en) * | 2015-11-03 | 2016-03-09 | 嘉兴职业技术学院 | Electric drill support |
CN205816858U (en) * | 2016-06-21 | 2016-12-21 | 南昌工程学院 | A kind of shockproof from Cooling fixture radial drilling machine |
CN205949892U (en) * | 2016-06-30 | 2017-02-15 | 无锡正宜机械制造有限公司 | Drilling equipment is used in metal product processing |
CN106392121A (en) * | 2016-10-27 | 2017-02-15 | 林志城 | Drilling machine capable of relieving dill bit damage |
CN205996248U (en) * | 2016-08-29 | 2017-03-08 | 重庆宏雷机械制造有限公司 | The boring machine of coolant can be reclaimed |
CN206029356U (en) * | 2016-08-29 | 2017-03-22 | 赵圣雅 | Automatic steel sheet drilling machine of adjusting |
WO2017080060A1 (en) * | 2015-11-13 | 2017-05-18 | 太仓井林机械科技有限公司 | Automated multi-workpiece hole-drilling device |
CN207188824U (en) * | 2017-09-14 | 2018-04-06 | 德清宏晨铸造有限公司 | A kind of stainless steel production rig |
-
2017
- 2017-09-14 CN CN201710825649.0A patent/CN107520472A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20110229280A1 (en) * | 2010-03-16 | 2011-09-22 | Kabushiki Kaisha Toshiba | Deep hole processing device |
CN205074575U (en) * | 2015-11-03 | 2016-03-09 | 嘉兴职业技术学院 | Electric drill support |
WO2017080060A1 (en) * | 2015-11-13 | 2017-05-18 | 太仓井林机械科技有限公司 | Automated multi-workpiece hole-drilling device |
CN205816858U (en) * | 2016-06-21 | 2016-12-21 | 南昌工程学院 | A kind of shockproof from Cooling fixture radial drilling machine |
CN205949892U (en) * | 2016-06-30 | 2017-02-15 | 无锡正宜机械制造有限公司 | Drilling equipment is used in metal product processing |
CN205996248U (en) * | 2016-08-29 | 2017-03-08 | 重庆宏雷机械制造有限公司 | The boring machine of coolant can be reclaimed |
CN206029356U (en) * | 2016-08-29 | 2017-03-22 | 赵圣雅 | Automatic steel sheet drilling machine of adjusting |
CN106392121A (en) * | 2016-10-27 | 2017-02-15 | 林志城 | Drilling machine capable of relieving dill bit damage |
CN207188824U (en) * | 2017-09-14 | 2018-04-06 | 德清宏晨铸造有限公司 | A kind of stainless steel production rig |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108161053A (en) * | 2018-02-22 | 2018-06-15 | 德清宏晨铸造有限公司 | A kind of steel plate drilling equipment |
CN108296520A (en) * | 2018-02-22 | 2018-07-20 | 德清宏晨铸造有限公司 | A kind of steel plate drilling device |
CN108971570A (en) * | 2018-10-08 | 2018-12-11 | 德清微晶防水材料有限公司 | A kind of waterproof pipe drilling device with cooling effect |
CN111546091A (en) * | 2020-03-05 | 2020-08-18 | 吉林大学 | Numerical control machine tool considering equipment safety and safety protection mechanism thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107520472A (en) | A kind of stainless steel production rig | |
CN107775356A (en) | A kind of mechanical fitting polishing and drilling integration apparatus | |
CN207188824U (en) | A kind of stainless steel production rig | |
CN107489374A (en) | A kind of building lot construction adjustable drilling aperture apparatus | |
CN206689463U (en) | A kind of movable mechanical maintenance of equipment device with damping device | |
CN105798347B (en) | A kind of industrial drilling equipment | |
CN106826372A (en) | A kind of drilling machine with cleaning drill bit function | |
CN108166935A (en) | A kind of pneumatic column drill | |
CN207140100U (en) | A kind of bridge construction scene perforating device | |
CN204686094U (en) | Be equipped with the track punching drilling machine of cool cycles | |
CN201940647U (en) | Drilling machine | |
CN206011463U (en) | A kind of marble drilling equipment for building | |
CN209682348U (en) | A kind of processing dust guard of wiring board | |
CN207982356U (en) | A kind of simple and quick boring drilling device of hardware hanging part | |
CN107899861A (en) | A kind of waterproof coiled material tyre cloth bituminizing mechanism | |
CN207513176U (en) | A kind of form for construction engineering fast-supporting device | |
CN108237239A (en) | A kind of circuit boring equipment | |
CN201552166U (en) | Dry paraffin cleaning device of oil pipe | |
CN210679194U (en) | Automatic lifting drilling device for engineering construction | |
CN2383651Y (en) | Glass boring machine | |
CN107461145A (en) | A kind of construction piling equipment | |
CN206539345U (en) | A kind of cavern cutting machine | |
CN205927939U (en) | Clamping device of drilling machine | |
CN210977307U (en) | Novel petroleum drilling machine for sea heavy oil region artificial island well factory | |
CN206953296U (en) | Insulating brick draws nest drilling all-in-one machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171229 |
|
RJ01 | Rejection of invention patent application after publication |