CN107513944A - Servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method - Google Patents

Servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method Download PDF

Info

Publication number
CN107513944A
CN107513944A CN201710856505.1A CN201710856505A CN107513944A CN 107513944 A CN107513944 A CN 107513944A CN 201710856505 A CN201710856505 A CN 201710856505A CN 107513944 A CN107513944 A CN 107513944A
Authority
CN
China
Prior art keywords
driving
bridge floor
wing
floor edge
workbench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710856505.1A
Other languages
Chinese (zh)
Inventor
褚超敏
叶文韬
来佳雯
林瀚
蔡佰成
胡潆之
陈玲
王欢
黄杭凯
戴贤斌
邬丹峰
祁俊
戴鹏
周勤
周一勤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Communication Engineering Construction Group Co Ltd
Original Assignee
Ningbo Communication Engineering Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Communication Engineering Construction Group Co Ltd filed Critical Ningbo Communication Engineering Construction Group Co Ltd
Priority to CN201710856505.1A priority Critical patent/CN107513944A/en
Publication of CN107513944A publication Critical patent/CN107513944A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method, it is related to field of bridge construction, its structure includes driving, crossbeam, perpendicular truss, workbench, hoist engine and balancing weight etc., the duct length both ends that mobile support is installed as needed for segmentation are respectively mainly set one, the track that two mobile supports are laid on bridge floor edge of a wing top surface along longitudinal direction is moved or fixed, pipeline is lifted by crane and is fixedly mounted on bridge floor edge of a wing bottom surface paragraph by paragraph, and pipe laying section length needed for the spacing-visible between two drivings carries out flexible arrangement;Simultaneously, the driving of every mobile support is bundled in railing bottom by steel wire rope, it conveniently the interim of driving can fix and effectively prevent transverse shifting of the driving along the bridge floor edge of a wing, servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method after improvement have the advantages that simple structure, work efficiency are notable, low-cost, safe and reliable and applied widely, therefore can wider popularization and application.

Description

Servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method
Technical field
The present invention relates to a kind of field of bridge construction, in particular to servicing bridges bridge floor edge of a wing bottom surface Pipe installing to move Support and operating method.
Background technology
After being built up across straits or across the large bridge of great rivers, demand or former design defect due to economic development Etc. reason, need to set up the line style facility such as pipeline on in-service operation bridge.These pipelines are generally located on bridge floor edge of a wing bottom surface, point Into certain length Piecemeal erection, more difficult installation of driving a vehicle such as is checked across structural base is existing using former bridge, because checking Driving is single, and longitudinal length is limited, it is impossible to a smoothly segment pipe of the fixed certain length of installation;Such as use bridge inspection vehicle Installation is, it is necessary to the operations simultaneously of two detection cars, somewhat expensive, and the bearing capacity for detecting car is limited, it is impossible to undertakes larger weight Pipe installing operation.
Disclosed China Patent No. is CN201710038004.2 " Pipe installing job platform and construction method ", the pipeline Speciality platform is a kind of large-scale special equipment, although the larger pipeline of single weight can be installed, due to being made by Pipe installing The limitation of industry platform longitudinal length, it is impossible to install the longer pipeline of section length, and the equipment manufacturing cost is higher, such as uses two phases Then expense is higher for same equipment installation slender pipeline.The substantially similar Application No. with above-mentioned Chinese patent CN201320089694.1 " laid with bridge under the movable type of gas pipeline engineering and hang operating platform ", Application No. CN201310061682.2 " laying gas pipeline engineering engineering method with bridge ", a kind of Application No. CN201621437469.2 " bridges The unsuitable Piecemeal erection of single device be present and exceed each of equipment longitudinal length in side duct installation removable job platform " Segmented conduit.
The content of the invention
The defects of technical problems to be solved by the invention are to overcome prior art and a kind of simple structure, work efficiency are provided Significantly, servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support low-cost, safe and reliable, applied widely and operation Method.
The technical problem of the present invention is achieved through the following technical solutions:
A kind of servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support, including the row vertically moved along bridge floor edge of a wing top surface Car, the crossbeam for being arranged on driving top, it is arranged on the perpendicular truss of crossbeam outer end and is arranged on perpendicular truss lower end and is located at the bridge floor wing Workbench below edge;Described crossbeam is provided with pulley;Hoist engine and balancing weight, the hoist engine are provided with described driving Pull rope bypass pulley connecting shackle, and pipeline lifting is fixed on bridge floor edge of a wing bottom surface through suspension hook;Described Mobile support respectively sets one by the duct length both ends of installation needed for segmentation, is provided with mobile support lateral outer side and is fixed on bridge Face edge of a wing top surfaceRailing, the driving of every mobile support is bundled on railing by steel wire rope.
Described bridge floor edge of a wing top surface is provided with along the track longitudinally laid, and the driving bottom described in every is along each before and after longitudinal direction If a wheel shaft, the both ends of every wheel shaft are all provided with movable pulley, and movable pulley makees longitudinal direction unblock along track and moves or pin fixation.
Described track is spaced centre distances and the movable pulley horizontal spacing center identical concave surface driven a vehicle upward for a pair Channel-section steel, the movable pulley at every wheel shaft both ends are separately positioned in a pair of tracks, and every segment length of every track is equal to 2 times of drivings and indulged To length+every section of duct segments length+rich length 1m~2m that need to be installed, number of tracks is at least two sections, every section of track it Between bolt connection, and make alternately spreading.
Described mobile support is provided with the water horse for being placed on bridge floor edge of a wing top surface along bridge floor edge of a wing top surface laterally inboard.
Described hoist engine is placed on the upper hoist engine synchronous working on railing side, two drivings of every driving, And installation fixed -piping is lifted by crane through suspension hook and hand fit;It is upper close to water horse one that described balancing weight is deposited in every driving Side, the balancing weight are coagulating cement soil block or bloom;Driving described in every is bundled in railing bottom by two steel wire ropes.
Described balancing weight configuration weight is calculated by equation below to be determined:
Formula one,
Formula two,
During mobile support lifting installation fixed -piping, a pair of movable pulleys of the close water horse side of every driving can not depart from rail Road, that is, it must is fulfilled for
Formula three,
Formula four,
In formula one, formula two, formula three, formula four, movable pulley of the every driving close to railing side is set to movable pulley A, Movable pulley close to water horse side is set to movable pulley B;Every driving is close to the lower end of railing side is set to A ends, upper end is set to E End;Every driving is set to B ends close to the lower end of water horse side, and upper end is set to D ends;On the crossbeam outer end and perpendicular truss of every driving End joint is set to F ends, and perpendicular truss lower end is set to G ends with workbench outer end joint, and workbench the inner is set to H ends, OK Balancing weight center of gravity application point is C on car, and each symbol implication is as follows:
--- driving need to stack the weight of balancing weight,
--- the track counter-force suffered by the close railing side movable pulley A of driving,
--- the track counter-force suffered by the close water horse side movable pulley B of driving,
--- weight of a pair of tracks per segment length,
--- the ultimate tension of steel wire rope,
--- the frictional resistance suffered by track,
--- the weight of perpendicular truss,
--- the gross weight of traveling load on workbench,
--- the gross weight carried in driving is by driving widthThe uniform weight shared out equally,
--- the gross weight of crossbeam presses crossbeam lengthThe uniform weight shared out equally,
--- the wind-force suffered by perpendicular truss cross-bridges face direction presses perpendicular truss depthThe uniform weight shared out equally,
--- the gross weight of workbench presses workbench widthThe uniform weight shared out equally,
--- operating personnel in auxiliary lifting on workbench or when pipeline is fixedly mounted, workbench G ends and H ends it Between move, the gross weight of traveling load on workbenchPosition be,
--- in driving balancing weight center of gravity application point C to A ends distance,
--- the width at driving A ends to B ends,
--- the height at driving D ends to B ends,
--- the length at crossbeam D ends to F ends,
--- the height at perpendicular truss F ends to G ends,
--- the length at workbench G ends to H ends,
--- wind load combination coefficient, chosen by relevant specification,
--- the global factor of safety of balancing weight, chosen by relevant specification,
--- the frictional resistance force coefficient of track bottom surface and bridge floor edge of a wing top surface, obtained by experiment or by relevant specification value,
--- the tensile-strength safety factor of steel wire rope,
Described driving is the hollow square frame of shaped steel welding, and described crossbeam is the quadra of shaped steel welding, should Crossbeam one end and the driving frame roof of driving are welded, and the top of the other end and perpendicular truss is welded;Described perpendicular truss is shaped steel The quadra of welding, the perpendicular truss lower end are welded with workbench outer end.
Described workbench is the hollow square framework of shaped steel welding, and bottom sets bottom plate, and hollow space is pacified for lifting The working space of fixed -piping is filled, brace is provided between workbench and perpendicular truss and is connected.
Described pipeline is plastic conduit or steel pipe, is divided into certain length Piecemeal erection, is used per segment pipe Anchor ear, setscrew are fixed on bridge floor edge of a wing bottom surface, and the lineament thing of insertion full-bridge is interconnected to form per segment pipe.
A kind of operating method of servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support, is operated in accordance with the following steps:
Step 1: traffic envelope road and delimitation boundary of works area
(1) according to the size of the grading scale of bridge and the volume of traffic, a car close to railing side is closed according to pertinent regulations Road, warning mark is set, boundary of works area delimited, is isolated with water horse or other safety devices, special messenger is implemented and induces commander to hand over It is logical, it is ensured that traffic and construction safety;
(2) construction machinery and material are stacked in order;
Step 2: mobile support is installed in place
(1) laying-down position attachment rail is pressed, track laying is needed to the position of pipe laying in first paragraph and second segment first Put, it is desirable to track and bridge floor edge of a wing top surface flat contact, there is gap to be leveled up with sheet rubber;
(2) a pair of movement mounts tie every mobile support in the both ends of first paragraph duct segments length, two steel wire ropes Tie up in railing bottom, movable pulley pins fixed driving, and hoist engine and balancing weight are in place;
Step 3: the first segment pipe of installation
(1) Pipe installing position laying-down, anchor ear and setscrew position are positioned;
(2) hoist engine, suspension hook and hand fit lift by crane first pipeline;
(3) operating personnel assist pipeline handling in place on workbench, and fix first pipeline with anchor ear, setscrew;
Step 4: second pipeline of mobile stent migration and installation
(1) two steel wire ropes for being bundled in railing bottom, movable pulley unblock driving are removed;
(2) a pair of movement supports are moved into second Pipe installing position in orbit, movable pulley pins fixed driving;
Every mobile support is bundled in railing bottom by (3) two steel wire ropes again;
(4) track of first paragraph Pipe installing position is dismantled, moves to the 3rd segment pipe installation site;
(5) second segment Pipe installing is completed by (1)~(3) of step 3;
Next segment pipe installation is completed paragraph by paragraph by step 4 until all Pipe installings of full-bridge are completed.
Compared with prior art, the present invention is mainly the track of servicing bridges bridge floor edge of a wing top surface laying longitudinal direction, and utilizes A pair of longitudinal arrangement length being made up of driving, crossbeam, perpendicular truss and workbench etc. are to be segmented the movement of pipe laying length Support, pipeline is lifted by crane and is fixedly mounted on bridge floor edge of a wing bottom surface paragraph by paragraph, and installed needed for the spacing-visible between two drivings Duct segments length carries out flexible arrangement, therefore can be suitably used for pipeline of the installation length more than separate unit movement stent length;Meanwhile often By steel wire rope binding in place in the railing bottom of mobile support lateral outer side, it can conveniently drive a vehicle for the driving of platform movement support It is interim fixed and effectively prevent transverse shifting of the driving along the bridge floor edge of a wing, the servicing bridges bridge floor edge of a wing bottom surface pipeline after improvement The mobile support of installation and operating method have simple structure, work efficiency notable, low-cost, safe and reliable and applied widely etc. excellent Point, therefore wider popularization and application can be obtained.
Brief description of the drawings
Fig. 1 is the facade structures schematic diagram of the present invention.
Fig. 2 is Fig. 1 left-hand view.
Fig. 3 is Fig. 1 A-A profiles.
Fig. 4 is the Force Calculation schema of mobile support.
Embodiment
The embodiment of the present invention will be elaborated again by above-mentioned accompanying drawing below.
As shown in Fig. 1 ~ Fig. 4, the 1. bridge floor edges of a wing, 2. railings, 3. pipelines, 4. water horses, 5. drivings, 51. tracks, 52. wheel shafts, 53. movable pulley, 54. hoist engines, 55. suspension hooks, 56. steel wire ropes, 6. balancing weights, 7. crossbeams, 8. perpendicular truss, 9. workbenches, 91. Bottom plate, 92. braces.
Servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method, as shown in Fig. 1 ~ Fig. 3, are mainly used in By pipeline 3 paragraph by paragraph quickly, conveniently, flexibly, be fixedly mounted in the bottom surface of the servicing bridges bridge floor edge of a wing 1.
Wherein, mobile support is to move installation along the longitudinal direction of the top surface of the bridge floor edge of a wing 1, and the structure of every mobile support is equal Identical, according to Fig. 1, the present embodiment is using the outer end on the left of view as mobile support, view right side as mobile branch The inner of frame, the fore-and-aft direction of view is as longitudinal direction, and the left and right directions of view is as laterally.
Described mobile contoured cradle is similar to the type of falling G, and its structure is by driving 5, crossbeam 7, perpendicular truss 8 and workbench 9 grades are formed, and are being moved support lateral outer side provided with the railing 2 for being fixed on the top surface of the bridge floor edge of a wing 1, are being moved support along the bridge floor edge of a wing 1 Top surface laterally inboard is provided with the water horse 4 for being placed on the top surface of the bridge floor edge of a wing 1;In actual use, mobile support is installed as needed for segmentation The length both ends of pipeline 3 respectively set one, when any segment pipe 3 is installed a pair of drivings 5 be fixed on track 51, install next section When driving 5 be moved to next section after fix again.
Described driving 5 is the hollow square frame that shaped steel is welded, and 5 bottoms of driving respectively set a wheel along before and after longitudinal direction Axle 52, the both ends of every wheel shaft set a movable pulley 53, and the movable pulley can make longitudinal direction unblock on track 51 along bridge floor and move Or pin and fix.
Described track 51 is a pair of interval centre distances and the horizontal spacing center identical concave surface of movable pulley 53 of driving 5 Channel-section steel upward, uses shaped steel firm welding between two channel-section steels, and the movable pulley 53 at the every both ends of wheel shaft 52 is separately positioned on a pair of rails In road 51, i.e., each movable pulley 53 can move in the concave surface of channel-section steel;It is vertical that every segment length of every track 51 is equal to 2 times of drivings To length+every section of duct segments length+rich length 1m~2m that need to be installed, the quantity of track 51 is at least two sections, every section of track It is connected between 51, can splices or dismantle, Pipe installing is carried out to carry out alternately spreading mobile for mobile support.
A hoist engine 54 is placed close to the side of railing 2 in described driving 5, the bottom of crossbeam 7 of every mobile support exists Fixed pulley is provided between driving 5 and perpendicular truss 8, the pull rope of hoist engine 54 bypasses pulley connecting shackle 55, two drivings 5 On hoist engine 54 work asynchronously, and pipeline 3 is lifted by crane through suspension hook and is manually fixedly mounted on the bottom surface of the bridge floor edge of a wing 1;Driving 5 is leaned on Balancing weight 6 is stacked in the nearly side of water horse 4, plays balanced sequence support transverse stabilization function, is toppled with preventing from moving support;The counterweight Block 6 is coagulating cement soil block or bloom;Every driving 5 is bundled in the bottom of railing 2 by two steel wire ropes 56, prevents driving 5 Along the transverse shifting of the bridge floor edge of a wing 1.
Described crossbeam 7 is the quadra that shaped steel is welded, one end and the driving frame roof welding jail of driving 5 Gu the upper end of the other end and perpendicular truss 8 is welded;Described perpendicular truss 8 is the quadra that shaped steel is welded, upper end and crossbeam 7 welding, lower end and the outer end firm welding of workbench 9;Perpendicular truss 8 is acted on by horizontal wind-force, and the intensity of wind-force is by having Specification is closed to choose;Described workbench 9 is the hollow square framework that shaped steel is welded, and bottom sets bottom plate 91, hollow bulb Divide and form working space, be available for operating personnel's auxiliary lifting pipeline 3, and Pipe installing is fixed on the bottom surface of the bridge floor edge of a wing 1;It is described Workbench 9 and perpendicular truss 8 between connected provided with brace 92, the brace is Steel section member, play strengthen workbench 9 with it is perpendicular The effect of truss 8.
Described pipeline 3 is that plastics or steel make, and is arranged on the bottom surface of the bridge floor edge of a wing 1 and is used to convey the things such as liquid or gas Matter, it is divided into certain length Piecemeal erection, bridge is fixed on using anchor ear, the setscrew of a determining deviation sum amount per segment pipe 3 The bottom surface of the face edge of a wing 1, the lineament thing of insertion full-bridge is interconnected to form per segment pipe 3.
In addition, the configuration weight of balancing weight 6 determines as shown in figure 4, can be calculated by equation below:
Formula one,
Formula two,
During mobile support lifting installation fixed -piping 3, a pair of movable pulleys 53 of the close side of water horse 4 of every driving 5 can not De-orbit 51, that is, must be fulfilled for
Formula three,
Formula four,
In formula one, formula two, formula three, formula four, every 5 movable pulley 53 close to the side of railing 2 of driving is set to mobile A is taken turns, the movable pulley 53 close to the side of water horse 4 is set to movable pulley B;Every driving 5 close to the lower end of the side of railing 2 be set to A ends, on End is set to E ends;Every driving 5 is set to B ends close to the lower end of the side of water horse 4, and upper end is set to D ends;Outside the crossbeam 7 of every driving 5 End is set to F ends with the perpendicular upper end joint of truss 8, and the perpendicular lower end of truss 8 is set to G ends, workbench with the outer end joint of workbench 9 9 the inners are set to H ends, and balancing weight center of gravity application point is C in driving, and each symbol implication is as follows:
--- driving 5 need to stack the weight of balancing weight 6,
--- driving 5 close to the track counter-force suffered by the side movable pulley A of railing 2,
--- driving 5 close to the track counter-force suffered by the side movable pulley B of water horse 4,
--- weight of a pair of tracks per segment length,
--- the ultimate tension of steel wire rope 56,
--- the frictional resistance suffered by track 51,
--- the weight of perpendicular truss 8,
--- the gross weight of the traveling load such as personnel on workbench 9, small-sized machine, equipment and the pipeline 3 that need to install,
--- 5 structures of driving include wheel shaft 52, movable pulley 53 and hoist engine 54, the gross weight of operating personnel's equivalent-load is pressed Driving widthThe uniform weight shared out equally,
--- the gross weight of crossbeam 7 presses crossbeam lengthThe uniform weight shared out equally,
--- the wind-force suffered by the perpendicular cross-bridges face direction of truss 8 presses perpendicular truss depthThe uniform weight shared out equally,
--- the gross weight of workbench 9 presses workbench widthThe uniform weight shared out equally,
--- operating personnel are in auxiliary lifting on workbench 9 or fixed installation pipeline 3, at workbench G ends and H ends Between move, the gross weight of the traveling load such as personnel on workbench 9, small-sized machine, equipment and the pipeline 3 that need to install's Position is,
--- driving 5 on the center of gravity application point C of balancing weight 6 to A ends distance,
--- the width at driving A ends to B ends,
--- the height at driving D ends to B ends,
--- the length at crossbeam D ends to F ends,
--- the height at perpendicular truss F ends to G ends,
--- the length at workbench G ends to H ends,
--- wind load combination coefficient, chosen by relevant specification,
--- the global factor of safety of balancing weight 6, chosen by relevant specification,
--- the bottom surface of track 51 and the frictional resistance force coefficient of the top surface of the bridge floor edge of a wing 1, obtained by experiment or taken by relevant specification Value,
--- the tensile-strength safety factor of steel wire rope 56,
The operating method of the present invention operates in accordance with the following steps:
Step 1: traffic envelope road and delimitation boundary of works area
(1) according to the size of the grading scale of bridge and the volume of traffic, a car close to the side of railing 2 is closed according to pertinent regulations Road, the marks such as warning, instruction are set, boundary of works area delimited, is isolated with water horse 4 or other safety devices, implement special messenger and lure Lead and direct traffic, it is ensured that traffic and construction safety;
(2) construction machinery and material are stacked in order, convenient operation;
Step 2: mobile support is installed in place
(1) laying-down position attachment rail 51 is pressed, track laying is needed into pipe laying in first paragraph and second segment first Position, it is desirable to track and the top surface flat contact of the bridge floor edge of a wing 1, there is gap to be leveled up with sheet rubber;
(2) a pair of movement mounts are at the both ends of the section length of the first segment pipe 3, and two steel wire ropes 56 are by every mobile support The bottom of railing 2 is bundled in, movable pulley 53 pins fixed driving 5, and hoist engine 54 and balancing weight 6 are in place;
Step 3: the first segment pipe of installation
(1) the installation site laying-down of pipeline 3, anchor ear and setscrew position are positioned;
(2) hoist engine 54, suspension hook 55 and hand fit lift by crane first pipeline 3;
(3) operating personnel assist pipeline handling in place on workbench 9, and fix first pipeline with anchor ear, setscrew;
Step 4: second pipeline of mobile stent migration and installation
(1) two steel wire ropes 56 for being bundled in the bottom of railing 2, the unblock of movable pulley 53 driving 5 are removed;
(2) a pair of movement supports are moved into second installation site of pipeline 3 on track 51, movable pulley 53 pins fixed driving 5;
Every mobile support is bundled in the bottom of railing 2 by (3) two steel wire ropes 56 again;
(4) track 51 of the installation site of the first segment pipe 3 is dismantled, moves to the installation site of the 3rd segment pipe 3;
(5) second segment Pipe installing is completed by (1)~(3) of step 3;
Next segment pipe installation is completed paragraph by paragraph by step 4 until all Pipe installings of full-bridge are completed.
The present invention is that the length both ends of pipeline 3 installed as needed for segmentation respectively set a mobile support, therefore even if installation is grown The pipeline spent well beyond separate unit movement stent length can also be applicable installation, and this mobile support used in pairs is applicable not only to Servicing bridges, new bridging beam is also applied for, in addition to pipe laying, can be used for detection, malfunction elimination of bridge etc..
Embodiment of the present invention is only illustrative of the invention and is not intended to limit the scope of the invention.It should additionally manage Solution, after the content of the invention lectured has been read, those skilled in the art can make various changes or modifications to the present invention, this A little equivalent form of values are equally fallen within the application appended claims limited range.

Claims (10)

1. a kind of servicing bridges bridge floor edge of a wing bottom surface Pipe installing moves support, including along the bridge floor edge of a wing(1)Top surface vertically moves Driving(5), be arranged on driving top crossbeam(7), be arranged on the perpendicular truss of crossbeam outer end(8)Be arranged on perpendicular truss lower end And it is located at the bridge floor edge of a wing(1)The workbench of lower section(9);Described crossbeam(7)It is provided with pulley;Described driving(5)Inside set There is hoist engine(54)And balancing weight(6), the hoist engine(54)Pull rope bypass pulley connecting shackle(55), and through suspension hook by institute State pipeline(3)Lifting is fixed on the bridge floor edge of a wing(1)Bottom surface, it is characterised in that described mobile support is installed as needed for segmentation Pipeline(3)Length both ends respectively set one, are provided with mobile support lateral outer side and are fixed on the bridge floor edge of a wing(1)The railing of top surface (2), the driving of every mobile support(5)Pass through steel wire rope(56)It is bundled in railing(2)On.
2. servicing bridges bridge floor edge of a wing bottom surface according to claim 1 Pipe installing moves support, it is characterised in that described The bridge floor edge of a wing(1)Top surface is provided with along the track longitudinally laid(51), the driving described in every(5)Bottom is respectively set along before and after longitudinal direction A piece wheel shaft(52), the both ends of every wheel shaft are all provided with movable pulley(53), and movable pulley is along track(51)Make longitudinal direction unblock it is mobile or Pin and fix.
3. servicing bridges bridge floor edge of a wing bottom surface according to claim 1 Pipe installing moves support, it is characterised in that described Track(51)For a pair of interval centre distances and driving(5)Movable pulley horizontal spacing center identical concave surface channel-section steel upward, Every wheel shaft(52)The movable pulley at both ends(53)It is separately positioned on a pair of tracks(51)Interior, every segment length of every track is equal to 2 Times vehicular longitudinal direction length+every section of duct segments length+rich length 1m~2m that need to be installed, track(51)Quantity is at least two Section, every section of track(51)Between bolt connection, and make alternately spreading.
4. servicing bridges bridge floor edge of a wing bottom surface according to claim 2 Pipe installing moves support, it is characterised in that described Mobile support along the bridge floor edge of a wing(1)Top surface laterally inboard is provided with and is placed on the bridge floor edge of a wing(1)The water horse of top surface(4).
5. servicing bridges bridge floor edge of a wing bottom surface according to claim 4 Pipe installing moves support, it is characterised in that described Hoist engine(54)It is placed on every driving(5)Upper close railing(2)Side, two drivings(5)On hoist engine(54)It is synchronous Work, and through suspension hook(55)Installation fixed -piping is lifted by crane with hand fit(3);Described balancing weight(6)It is deposited in every row Car(5)Upper close water horse(4)Side, the balancing weight(6)For coagulating cement soil block or bloom.
6. servicing bridges bridge floor edge of a wing bottom surface according to claim 5 Pipe installing moves support, it is characterised in that described Balancing weight(6)Configure weight and determination is calculated by equation below:
Formula one,
Formula two,
Mobile support lifting installation fixed -piping(3)When, every driving(5)Close water horse(4)A pair of movable pulleys of side (53)It can not de-orbit(51), that is, it must is fulfilled for
Formula three,
Formula four,
In formula one, formula two, formula three, formula four, every driving(5)Close to railing(2)The movable pulley of side(53)If For movable pulley A, close water horse(4)The movable pulley of side(53)It is set to movable pulley B;Every driving(5)Close to railing(2)Side Lower end is set to A ends, upper end is set to E ends;Every driving(5)Close to water horse(4)The lower end of side is set to B ends, and upper end is set to D ends; Every driving(5)Crossbeam(7)Outer end and perpendicular truss(8)Upper end joint is set to F ends, erects truss(8)Lower end and workbench (9)Outer end joint is set to G ends, workbench(9)The inner is set to H ends, and balancing weight center of gravity application point is C in driving, each symbol Implication is as follows:
--- driving(5)Balancing weight need to be stacked(6)Weight,
--- driving(5)Close to railing(2)Track counter-force suffered by the movable pulley A of side,
--- driving(5)Close to water horse(4)Track counter-force suffered by the movable pulley B of side,
--- weight of a pair of tracks per segment length,
--- steel wire rope(56)Ultimate tension,
--- track(51)Suffered frictional resistance,
--- perpendicular truss(8)Weight,
--- workbench(9)The gross weight of upper traveling load,
--- driving(5)The gross weight of upper carrying is by driving widthThe uniform weight shared out equally,
--- crossbeam(7)Gross weight press crossbeam lengthThe uniform weight shared out equally,
--- perpendicular truss(8)Wind-force suffered by the direction of cross-bridges face presses perpendicular truss depthThe uniform weight shared out equally,
--- workbench(9)Gross weight press workbench widthThe uniform weight shared out equally,
--- operating personnel are in workbench(9)Pipeline is fixedly mounted in upper auxiliary lifting(3)When, in workbench G ends and H Moved between end, workbench(9)The gross weight of upper traveling loadPosition be,
--- driving(5)Upper balancing weight(6)Center of gravity application point C to A ends distance,
--- the width at driving A ends to B ends,
--- the height at driving D ends to B ends,
--- the length at crossbeam D ends to F ends,
--- the height at perpendicular truss F ends to G ends,
--- the length at workbench G ends to H ends,
--- wind load combination coefficient, chosen by relevant specification,
--- balancing weight(6)Global factor of safety, by relevant specification choose,
--- track(51)Bottom surface and the bridge floor edge of a wing(1)The frictional resistance force coefficient of top surface, obtained or by relevant specification by experiment Value,
--- steel wire rope(56)Tensile-strength safety factor,
7. servicing bridges bridge floor edge of a wing bottom surface according to claim 1 Pipe installing moves support, it is characterised in that described Driving(5)For the hollow square frame of shaped steel welding, described crossbeam(7)For the quadra of shaped steel welding, the crossbeam(7) One end and driving(5)The welding of driving frame roof, the other end and perpendicular truss(8)Top welding;Described perpendicular truss(8)For The quadra of shaped steel welding, the perpendicular truss(8)Lower end and workbench(9)Weld outer end.
8. servicing bridges bridge floor edge of a wing bottom surface according to claim 1 Pipe installing moves support, it is characterised in that described Workbench(9)For the hollow square framework of shaped steel welding, bottom sets bottom plate(91), hollow space is lifting installation fixation Pipeline(3)Working space, in workbench(9)With perpendicular truss(8)Between be provided with brace(92)Connection.
9. servicing bridges bridge floor edge of a wing bottom surface according to claim 1 Pipe installing moves support, it is characterised in that described Pipeline(3)For plastic conduit or steel pipe, it is divided into certain length Piecemeal erection, per segment pipe(3)Using anchor ear, swollen Swollen screw is fixed on the bridge floor edge of a wing(1)Bottom surface, per segment pipe(3)It is interconnected to form the lineament thing of insertion full-bridge.
10. a kind of servicing bridges bridge floor edge of a wing bottom surface Pipe installing moves the operating method of support, it is characterised in that this method is pressed Operated according to following steps:
Step 1: traffic envelope road and delimitation boundary of works area
(1) according to the size of the grading scale of bridge and the volume of traffic, closed according to pertinent regulations close to railing(2)One of side Track, warning mark is set, boundary of works area delimited, with water horse(4)Or other safety devices are isolated, implement special messenger's induction and refer to Wave traffic, it is ensured that traffic and construction safety;
(2) construction machinery and material are stacked in order;
Step 2: mobile support is installed in place
(1) laying-down position attachment rail is pressed(51), track laying is needed into pipe laying in first paragraph and second segment first (3)Position, it is desirable to track and the bridge floor edge of a wing(1)Top surface flat contact, has gap to be leveled up with sheet rubber;
(2) a pair of movement mounts are in the first segment pipe(3)The both ends of section length, two steel wire ropes(56)By every movement Support is bundled in railing(2)Bottom, movable pulley(53)Pin fixed driving(5), hoist engine(54)And balancing weight(6)In place;
Step 3: the first segment pipe of installation
(1) pipeline(3)Installation site laying-down, position anchor ear and setscrew position;
(2) hoist engine(54), suspension hook(55)First pipeline is lifted by crane with hand fit(3);
(3) operating personnel are in workbench(9)Upper assistance pipeline(3)Handling is in place, and fixes first with anchor ear, setscrew Pipeline;
Step 4: second pipeline of mobile stent migration and installation
(1) two are removed and is bundled in railing(2)The steel wire rope of bottom(56), movable pulley(53)Unblock driving;
(2) by a pair of movement supports in track(51)On move to second pipeline(3)Installation site, movable pulley(53)Pin and fix Driving(5);
(3) two steel wire ropes(56)Every mobile support is bundled in railing again(2)Bottom;
(4) the first segment pipe is dismantled(3)The track of installation site(51), move to the 3rd segment pipe(3)Installation site;
(5) second segment Pipe installing is completed by (1)~(3) of step 3;
Next segment pipe installation is completed paragraph by paragraph by step 4 until all Pipe installings of full-bridge are completed.
CN201710856505.1A 2017-09-21 2017-09-21 Servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method Pending CN107513944A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710856505.1A CN107513944A (en) 2017-09-21 2017-09-21 Servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710856505.1A CN107513944A (en) 2017-09-21 2017-09-21 Servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method

Publications (1)

Publication Number Publication Date
CN107513944A true CN107513944A (en) 2017-12-26

Family

ID=60725757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710856505.1A Pending CN107513944A (en) 2017-09-21 2017-09-21 Servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method

Country Status (1)

Country Link
CN (1) CN107513944A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110886225A (en) * 2019-11-29 2020-03-17 湖北省路桥集团有限公司 Construction method of cable tower stay cable installation system
CN113215978A (en) * 2021-05-13 2021-08-06 中国化学工程第四建设有限公司 Construction method for laying pipeline along with bridge
CN114632698A (en) * 2022-03-17 2022-06-17 宁波交通工程建设集团有限公司 Filter screen for treating large-block muck impurities under trestle

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0860853A (en) * 1994-08-22 1996-03-05 Katsuyuki Furukawa Construction method of wall balustrade and mobile scaffold for use thereof
CN105133509A (en) * 2015-09-23 2015-12-09 北京中交桥宇科技有限公司 Truss type simple working platform based on bridge maintenance
CN106894342A (en) * 2017-01-18 2017-06-27 湖南瑞涪科技实业有限公司 Pipe installing job platform and construction method
CN207267963U (en) * 2017-09-21 2018-04-24 宁波交通工程建设集团有限公司 A kind of mobile stent of servicing bridges bridge floor edge of a wing bottom surface Pipe installing

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0860853A (en) * 1994-08-22 1996-03-05 Katsuyuki Furukawa Construction method of wall balustrade and mobile scaffold for use thereof
CN105133509A (en) * 2015-09-23 2015-12-09 北京中交桥宇科技有限公司 Truss type simple working platform based on bridge maintenance
CN106894342A (en) * 2017-01-18 2017-06-27 湖南瑞涪科技实业有限公司 Pipe installing job platform and construction method
CN207267963U (en) * 2017-09-21 2018-04-24 宁波交通工程建设集团有限公司 A kind of mobile stent of servicing bridges bridge floor edge of a wing bottom surface Pipe installing

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘瑛等: "燃气管道随桥敷设施工移动式操作平台设计", 《规划设计》 *
林盛佳: "燃气管道随特大桥架空敷设无脚手架施工", 《城市燃气》 *
潘志军等: "随桥敷设跨越赣江燃气管道施工技术", 《煤气与热力》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110886225A (en) * 2019-11-29 2020-03-17 湖北省路桥集团有限公司 Construction method of cable tower stay cable installation system
CN113215978A (en) * 2021-05-13 2021-08-06 中国化学工程第四建设有限公司 Construction method for laying pipeline along with bridge
CN113215978B (en) * 2021-05-13 2022-05-17 中国化学工程第四建设有限公司 Construction method for laying pipeline along with bridge
CN114632698A (en) * 2022-03-17 2022-06-17 宁波交通工程建设集团有限公司 Filter screen for treating large-block muck impurities under trestle

Similar Documents

Publication Publication Date Title
CN105484162B (en) Suspension bridge construction stiff girder secondary on the bank swings moving device and method
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN107513944A (en) Servicing bridges bridge floor edge of a wing bottom surface Pipe installing movement support and operating method
CN103030070B (en) A kind of can the transfer crane of traveling and operation on ramp
CN103422441A (en) Perforating method for erecting long-span highway box girders by using DJ180 bridge erecting machine
CN110374008A (en) A method of the erection of cable-stayed bridge steel truss is carried out in marine environment
CN106223303B (en) A kind of ship booster supporting compartment installation method
CN104831632B (en) A kind of bridge cable tower entablature and sill construction method
CN207267963U (en) A kind of mobile stent of servicing bridges bridge floor edge of a wing bottom surface Pipe installing
CN105544409B (en) Double guide beam bridge erecting machine sets up combination beam and now spells a section girder steel construction technology
CN105133509A (en) Truss type simple working platform based on bridge maintenance
CN114808747A (en) Multifunctional bridge girder erection machine and bridge girder erection construction method
CN205529923U (en) Sliding device of demolising of beiLei beam
CN114575251B (en) Large-span steel truss arch bridge construction system and construction method
CN203007843U (en) Variable amplitude deck derrick crane
CN205369040U (en) Suspension bridge is under construction on bank stiffening beam secondary and is swung and move device
CN106245531B (en) Steel structural bridge installation method is hung under bilateral derrick type
JP6873435B2 (en) Suspended scaffolding and its erection method
CN205046488U (en) Simple and easy work platform of truss -like based on bridge maintenance
CN208748534U (en) A kind of concrete box girder cast-in-place construction anchor ear support frame
CN210395127U (en) Assembled Bailey beam hanging basket upper walking system
CN114622498A (en) Self-walking operation platform for construction of cable-stayed bridge bottom and installation method
CN212771944U (en) Punching steel bar type adjustable operation platform
CN113774813A (en) Traction deviation rectifying equipment convenient for installing large-section steel truss box girder
CN208778011U (en) Concrete- liner tunnel side wall steel formwork trolley

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171226