CN107503760A - A kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel - Google Patents

A kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel Download PDF

Info

Publication number
CN107503760A
CN107503760A CN201710901489.3A CN201710901489A CN107503760A CN 107503760 A CN107503760 A CN 107503760A CN 201710901489 A CN201710901489 A CN 201710901489A CN 107503760 A CN107503760 A CN 107503760A
Authority
CN
China
Prior art keywords
hinged
platform
constructing tunnel
plane rotation
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710901489.3A
Other languages
Chinese (zh)
Inventor
张家放
陈祚进
侯连军
潘何冬
卢静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Electromechanical Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Electromechanical Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd, Electromechanical Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN201710901489.3A priority Critical patent/CN107503760A/en
Publication of CN107503760A publication Critical patent/CN107503760A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms
    • E21D9/122Working or loading platforms
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a kind of construction platform of the Multifunctional aloft-work chassis for constructing tunnel, it includes stage support and leveling cyclinder, one end of the stage support is fixedly connected on the Multifunctional aloft-work chassis cantilever of constructing tunnel, its other end is hinged on the stage casing of platform support, the bottom of the platform support is hinged with leveling cyclinder, its top is provided with plane rotation support meanss, the plane rotation support meanss are provided with hanging basket and hydraulic operating mechanism, and the other end of leveling cyclinder is hinged in stage support.The achievable out break for including face and crag processing, steel arch-shelf installation, reinforced mesh are hung, other work high above the ground and lifting operation in tunnel can also be completed simultaneously, realize the purpose of a tractor serves several purposes, equipment purchase cost is saved, whole work progress can realize Fully-mechanized operation, it is not necessary to set up shelf, substantially increase efficiency of construction, the safety coefficient of worker is also improved simultaneously, ensure that the construction quality of bow member installation.

Description

A kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel
Technical field
It is more particularly to a kind of for constructing tunnel the present invention relates to a kind of construction platform of Multifunctional aloft-work chassis The construction platform of Multifunctional aloft-work chassis, belong to construction machinery technical field.
Background technology
At present, there is the construction equipment that some are installed for steel arch-shelf in constructing tunnel, the main body of its function in the market The installation of steel arch-shelf is realized now, and hung for other out breaks such as face and crag processing, reinforced mesh, The work high above the ground such as filling explosive are not considered that the design having in other words is to consider part, but they do not have sufficiently The requirement of the grasp constructing tunnel high and medium operation of system, the construction platform of design are not well positioned to meet construction and client's It is required that.
The content of the invention
The technical problem to be solved in the present invention is:A kind of applying for Multifunctional aloft-work chassis for constructing tunnel is provided Work platform, construction platform collection steel arch-shelf installation, High Altitude Platform operation(Out break and crag processing, reinforcing bar including face Mesh sheet hangs, loads explosive)With it is small-sized(Within 1 ton)Function is lifted in one, is positioned at using one 17 cun of floating bearing On the three-level telescopic arm of the middle working arm of Multifunctional performing machine for tunnel, and made entirely by an automatic leveling oil cylinder Construction platform is in the plane close to level all the time.
It is directed to solving the work high above the ground such as preliminary bracing all in constructing tunnel and filling explosive, including face Out break and crag processing, steel arch-shelf installation, reinforced mesh hangs, while can also complete other work high above the ground in tunnel (Such as hang airduct, cable, installation illuminating lamp etc.)And lifting operation within 1 ton.
The technical scheme is that:A kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel, it Including stage support and leveling cyclinder, one end of the stage support is fixedly connected on the Multifunctional aloft-work platform of constructing tunnel On car cantilever, its other end is hinged on the stage casing of platform support, and bottom and the leveling cyclinder of the platform support are hinged, its top Provided with plane rotation support meanss, the plane rotation support meanss are provided with hanging basket and hydraulic operating mechanism, leveling cyclinder The other end is hinged in stage support.
The plane rotation support meanss are worm gear structure, and hanging basket and hydraulic operating mechanism are located at the shell branch of worm gear On frame.
The top of the plane rotation support meanss is additionally provided with hydraulic pressure winch and longitudinal slewing supporting device, and the longitudinal direction is returned It is worm gear structure to turn support meanss, and worm-wheel shaft is fixedly connected on the top end holder of plane rotation support meanss.
Clamp standoff device is connected with longitudinal slewing supporting device, the clamp standoff device includes clamping Head, steel arch-shelf fixture and clamping oil cylinder, clamping oil cylinder one end are hinged on the base of clamping head, and the other end is hinged on clamping head On, steel arch-shelf fixture steel wire rope is connected with hydraulic pressure winch.
The beneficial effects of the invention are as follows:Compared with prior art, the present invention is by above technical scheme, the device it is main Function is:The work high above the ground such as all preliminary bracings and filling explosive in constructing tunnel, include the out break and danger of face Rock processing, steel arch-shelf installation, reinforced mesh hang, while can also complete other work high above the ground in tunnel(Such as hang airduct, Cable, installation illuminating lamp etc.)And the lifting operation within 1 ton, realize the purpose of a tractor serves several purposes, saved equipment purchase into This, whole work progress can realize Fully-mechanized operation, it is not necessary to shelf is set up, substantially increases efficiency of construction, while The safety coefficient of worker is improved, ensure that the construction quality of bow member installation.
Brief description of the drawings
Fig. 1:A kind of construction platform structural representation of Multifunctional aloft-work chassis for constructing tunnel;
Fig. 2:A kind of working state figure of the construction platform of Multifunctional aloft-work chassis for constructing tunnel;
Fig. 3:A kind of construction platform working condition cooperation schematic diagram of Multifunctional aloft-work chassis for constructing tunnel.
Embodiment
To make the object, technical solutions and advantages of the present invention clearer, below with reference to this specification accompanying drawing to this hair It is bright to be described in further detail.
Embodiment:As shown in accompanying drawing 1~3, a kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel, It includes stage support 1 and leveling cyclinder 2, and one end of the stage support 1 is fixedly connected on the Multifunction altitude of constructing tunnel On Mobile workbench cantilever, its other end is hinged on the stage casing of platform support 13, bottom and the leveling cyclinder 2 of the platform support 13 Be hinged, its top is provided with plane rotation support meanss 3, and the plane rotation support meanss 3 are provided with hanging basket 12 and hydraulic operation Mechanism 11, the other end of leveling cyclinder 2 are hinged in stage support 1.Stage support 1 is the supporting construction of whole construction platform, It is welded on the third level telescopic arm of the working arm of the Multifunctional aloft-work chassis of constructing tunnel, and with platform support 13 Stage casing is hinged, automatically controlled by leveling cyclinder 2 realize whole platform all the time be in close to level plane, ensure safety and Reliable operation.
Further, plane rotation support meanss 3 are worm gear structure, and hanging basket 12 and hydraulic operating mechanism 11 are located at snail On the outer casing stand of wheel.Construction platform is realized by horizontal rotation support meanss 3 does 360 ° of revolutions in the plane close to level. When equipment needs to install steel arch-shelf and hang reinforced mesh, the clamp standoff device 8 of construction platform goes to front, now puts down The hanging basket 12 of platform is at rear, is easy to the clamping of steel arch-shelf 4 to construct, while that some can be carried out in hanging basket is complementary by worker Operation(See Fig. 1).
, can be by construction platform when needing to carry out out break and the work high above the ground such as crag processing and filling explosive of face 180 ° of rotation, clamp standoff device 8 and clamping head 5 are rotated to dead astern, now the hanging basket 12 of platform is at front(See Fig. 2), worker can be facilitated to carry out constructing operation.
Hanging basket 12 is the Multifunction working platform of the construction platform, can carry out the out break and crag processing, steel of face Muscle mesh sheet hangs, loads the work high above the ground such as explosive.It is arranged in plane rotation support, and 360 ° of revolutions can be achieved, be easy to construct.
Further, the top of plane rotation support meanss 3 is additionally provided with hydraulic pressure winch 9 and longitudinal slewing supporting device 10, Longitudinal slewing supporting device 10 is worm gear structure, and worm-wheel shaft is fixedly connected on the top of plane rotation support meanss 3 On support.Hoisting mechanism when hydraulic wireline winch 9 is the installation of interlude steel arch-shelf, its steel cord ends bolt have a special steel Bow member fixture 6.
Further, clamp standoff device 8 is connected with longitudinal slewing supporting device 10, the clamp standoff device 8 wraps Containing clamping head 5, steel arch-shelf fixture 6 and clamping oil cylinder 7, clamping oil cylinder 7 one end is hinged on the base of clamping head 5, the other end It is hinged on clamping head 5, steel arch-shelf fixture 6 is connected with steel wire rope with hydraulic pressure winch 9.Clamping head 5 is the clamping device of bow member, it Steel arch-shelf is clamped on clamp standoff device 8, and by clamping oil cylinder 7;Clamp standoff device 8 is clamping head 5 Installation connecting elements, it be arranged on longitudinal revolving support 10 on, can be flipped up around its 180 °.
Further, hydraulic operating mechanism is also equipped with hanging basket 12, mainly all execution of the construction platform are acted and carried out Worker is easy to regard near operation in manipulation, the mechanism, it is ensured that safe and efficient.
Its operation principle is as follows:
1st, construction platform is in place:Construction platform is moved to about 2 meters away from tunnel tunnel face by operation element arm, about 2 meters away from ground Position, by clamping head 5(Or clamp standoff device 8)Rotate to lowest order.
2nd, steel arch-shelf is clamped:Operation hydraulic wireline winch 9 first puts down steel wire rope and steel arch-shelf fixture 6, and steel arch-shelf fixture 6 is pressed from both sides The wing edge of steel arch-shelf 4 is handled, is then involved in rope hoisting steel arch-shelf fixture 6 and its clamping by operating the rotation of hydraulic wireline winch 9 Steel arch-shelf 4, when steel arch-shelf 4 is promoted in clamping head 5, then operate clamping oil cylinder 7 make clamping head 5 clamp steel arch-shelf 4, then pine Open steel arch-shelf fixture 6.
3rd, steel arch-shelf installation is in place:After clamping head 5 clamps steel arch-shelf 4, operate longitudinal slewing supporting device 10 and rotate up Clamp standoff device 8 (or clamping head 5)To vertical position, then operation element arm by construction platform it is slowly mobile forward upwards until Steel arch-shelf is bonded substantially with tunnel vault and face(Operation planar revolving support may be needed steel arch-shelf is put down with face OK), while also should ensure that steel arch-shelf 4 is in the middle in tunnel, realize interlude(Head sections)Steel arch-shelf it is in place.Now, stop The construction platform and working arm are only operated, ensures that its on-station position is constant.
The present invention meets the face out break and crag processing, steel arch-shelf installation, steel of constructing tunnel to greatest extent Muscle mesh sheet hangs, loads explosive, and usually hangs airduct, cable, all work high above the ground in the construction such as installation illuminating lamp Demand, the purpose of a tractor serves several purposes is realized, saved equipment purchase cost.
Part is not described in detail by the present invention, is the known technology of those skilled in the art of the present technique.Finally illustrate, the above is real Example is applied to be merely illustrative of the technical solution of the present invention and unrestricted, although having been carried out specifically to the present invention with reference to preferred embodiment It is bright, it will be understood by those within the art that, technical scheme can be modified or equivalent substitution, and The objective and scope of technical solution of the present invention are not departed from, it all should cover among scope of the presently claimed invention.

Claims (4)

1. a kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel, it includes stage support(1)And leveling Oil cylinder(2), it is characterised in that:The stage support(1)One end be fixedly connected on the Multifunctional aloft-work platform of constructing tunnel On car cantilever, its other end is hinged on platform support(13)Stage casing, the platform support(13)Bottom and leveling cyclinder(2) Be hinged, its top is provided with plane rotation support meanss(3), the plane rotation support meanss(3)It is provided with hanging basket(12)And liquid Press operation mechanism(11), leveling cyclinder(2)The other end be hinged on stage support(1)On.
2. a kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel according to claim 1, it is special Sign is:The plane rotation support meanss(3)For worm gear structure, hanging basket(12)And hydraulic operating mechanism(11)It is located at snail On the outer casing stand of wheel.
3. a kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel according to claim 1 or 2, its It is characterised by:The plane rotation support meanss(3)Top be additionally provided with hydraulic pressure winch(9)With longitudinal slewing supporting device (10), longitudinal slewing supporting device(10)For worm gear structure, worm-wheel shaft is fixedly connected on plane rotation support meanss (3)Top end holder on.
4. a kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel according to claim 3, it is special Sign is:Longitudinal slewing supporting device(10)On be connected with clamp standoff device(8), the clamp standoff device(8)Bag Contain clamping head(5), steel arch-shelf fixture(6)With clamping oil cylinder(7), clamp oil cylinder(7)One end is hinged on clamping head(5)Base On, the other end is hinged on clamping head(5)On, steel arch-shelf fixture(6)With steel wire rope and hydraulic pressure winch(9)Connection.
CN201710901489.3A 2017-09-28 2017-09-28 A kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel Pending CN107503760A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710901489.3A CN107503760A (en) 2017-09-28 2017-09-28 A kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710901489.3A CN107503760A (en) 2017-09-28 2017-09-28 A kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel

Publications (1)

Publication Number Publication Date
CN107503760A true CN107503760A (en) 2017-12-22

Family

ID=60699029

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710901489.3A Pending CN107503760A (en) 2017-09-28 2017-09-28 A kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel

Country Status (1)

Country Link
CN (1) CN107503760A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109882217A (en) * 2019-04-23 2019-06-14 中铁工程装备集团有限公司 A kind of novel intelligent steel arch-shelf assembling machine people and its assembling method
CN111764920A (en) * 2020-07-03 2020-10-13 北京市政建设集团有限责任公司 Excavating equipment for tunnel engineering
CN114439517A (en) * 2021-12-28 2022-05-06 洛阳中天建工机械有限公司 Telescopic reinforcing steel bar hanging cloth trolley
CN114439517B (en) * 2021-12-28 2024-05-17 洛阳中天建工机械有限公司 Telescopic steel bar cloth hanging trolley

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383809A (en) * 2011-11-08 2012-03-21 中铁岩锋成都科技有限公司 Arm support used for concrete jet and provided with movable rotary strut and operating method for arm support
CN103291330A (en) * 2013-05-16 2013-09-11 湖南江麓实业发展有限公司 All-round manipulator special for tunnels
JP2014114634A (en) * 2012-12-11 2014-06-26 Nihon Bisoh Co Ltd Multifunctional gondola device
CN204386615U (en) * 2014-12-24 2015-06-10 中铁四局集团第五工程有限公司 A kind of self-propelled tunnel invert construction trolley
CN205805583U (en) * 2016-07-20 2016-12-14 北京新能正源环境科技有限公司 Bow member chassis
CN106401476A (en) * 2016-12-01 2017-02-15 长沙科达智能装备股份有限公司 Multifunctional arching drill jambo
CN206521255U (en) * 2016-10-21 2017-09-26 中铁五局集团有限公司 A kind of hanging basket arm on bow member fitting machine
CN207348869U (en) * 2017-09-28 2018-05-11 中铁五局集团有限公司 A kind of construction platform of Multifunctional aloft-work trolley for constructing tunnel

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383809A (en) * 2011-11-08 2012-03-21 中铁岩锋成都科技有限公司 Arm support used for concrete jet and provided with movable rotary strut and operating method for arm support
JP2014114634A (en) * 2012-12-11 2014-06-26 Nihon Bisoh Co Ltd Multifunctional gondola device
CN103291330A (en) * 2013-05-16 2013-09-11 湖南江麓实业发展有限公司 All-round manipulator special for tunnels
CN204386615U (en) * 2014-12-24 2015-06-10 中铁四局集团第五工程有限公司 A kind of self-propelled tunnel invert construction trolley
CN205805583U (en) * 2016-07-20 2016-12-14 北京新能正源环境科技有限公司 Bow member chassis
CN206521255U (en) * 2016-10-21 2017-09-26 中铁五局集团有限公司 A kind of hanging basket arm on bow member fitting machine
CN106401476A (en) * 2016-12-01 2017-02-15 长沙科达智能装备股份有限公司 Multifunctional arching drill jambo
CN207348869U (en) * 2017-09-28 2018-05-11 中铁五局集团有限公司 A kind of construction platform of Multifunctional aloft-work trolley for constructing tunnel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
康宝生;: "一种新型隧道施工用拱架安装机", 隧道建设, no. 05, 20 October 2011 (2011-10-20) *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109882217A (en) * 2019-04-23 2019-06-14 中铁工程装备集团有限公司 A kind of novel intelligent steel arch-shelf assembling machine people and its assembling method
CN109882217B (en) * 2019-04-23 2024-03-26 中铁工程装备集团有限公司 Novel intelligent steel arch assembling robot and assembling method thereof
CN111764920A (en) * 2020-07-03 2020-10-13 北京市政建设集团有限责任公司 Excavating equipment for tunnel engineering
CN114439517A (en) * 2021-12-28 2022-05-06 洛阳中天建工机械有限公司 Telescopic reinforcing steel bar hanging cloth trolley
CN114439517B (en) * 2021-12-28 2024-05-17 洛阳中天建工机械有限公司 Telescopic steel bar cloth hanging trolley

Similar Documents

Publication Publication Date Title
CN100575237C (en) Hoisting crane
CN109882214A (en) A kind of multi-functional arch installation trolley
CN107697242A (en) One kind automation buoy recovery arranging device
CN107514264A (en) A kind of new Multifunctional performing machine for constructing tunnel
CN1955102B (en) Method and device for the assembly of a crane with a lifting jib
CN107521641A (en) A kind of submarine launch retracting device and lay recovery method
CN107420114A (en) A kind of Multifunctional aloft-work constructing device for constructing tunnel
CN107109816A (en) Stake centralizing system
CN204752005U (en) Mining vehicle -mounted hangs flatbed
CN207348868U (en) A kind of new Multifunctional performing machine for constructing tunnel
CN103663189B (en) Moving arm tower crane installation method
CN101357739B (en) Column crane special for movable arm type group tower
CN106219420A (en) A kind of fast erecting traveling tower crane
CN107472486A (en) An a kind of container set accepted way of doing sth lays reclaimer and lays recovery method
CN107503760A (en) A kind of construction platform of Multifunctional aloft-work chassis for constructing tunnel
CN210178382U (en) Multifunctional arch center mounting trolley
CN105384094B (en) The operating method and crane of crane
CN207348869U (en) A kind of construction platform of Multifunctional aloft-work trolley for constructing tunnel
CN205892575U (en) Fast set up traveling tower crane
CN207348881U (en) A kind of main clamping device for the installation of constructing tunnel bow member
CN103753207B (en) For the turning device of wind driven generator principal shaft
CN202322105U (en) Crane and device for installing auxiliary boom of crane
CN207348867U (en) A kind of Multifunctional aloft-work constructing device for constructing tunnel
CN203308404U (en) Compound derrick intelligent formation testing well repairing vehicle
CN207191349U (en) An a kind of container set accepted way of doing sth lays reclaimer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination