CN107499389A - A kind of full assembled of aluminium alloy is without crossbeam base arrangement - Google Patents
A kind of full assembled of aluminium alloy is without crossbeam base arrangement Download PDFInfo
- Publication number
- CN107499389A CN107499389A CN201710843699.1A CN201710843699A CN107499389A CN 107499389 A CN107499389 A CN 107499389A CN 201710843699 A CN201710843699 A CN 201710843699A CN 107499389 A CN107499389 A CN 107499389A
- Authority
- CN
- China
- Prior art keywords
- longeron
- floor
- floor unit
- bolt
- slot
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B62—LAND VEHICLES FOR TRAVELLING OTHERWISE THAN ON RAILS
- B62D—MOTOR VEHICLES; TRAILERS
- B62D25/00—Superstructure or monocoque structure sub-units; Parts or details thereof not otherwise provided for
- B62D25/20—Floors or bottom sub-units
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B62—LAND VEHICLES FOR TRAVELLING OTHERWISE THAN ON RAILS
- B62D—MOTOR VEHICLES; TRAILERS
- B62D33/00—Superstructures for load-carrying vehicles
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Transportation (AREA)
- Mechanical Engineering (AREA)
- Connection Of Plates (AREA)
Abstract
The invention discloses a kind of full assembled of aluminium alloy without crossbeam base arrangement,Including longeron,Floor unit,T-bolt,Gib head pressing plate and Angle connection part,Directly laid along longitudinal spliced floor unit on the longeron,Described floor unit one end is designed with floor unit end flange structure,Coordinate with the floor unit end T-slot of another unit end set,Floor unit end T-slot is by the T-bolt and is connected in the Angle connection part of the longeron outside of belly and is connected with longeron,By two layers of overlaying structure that three layers of overlaying structure of former " longeron+crossbeam+floor " are changed to " longeron+floor ",Eliminate crossbeam,Weight reduces more than 20% on year-on-year basis,And the T-slot structure for passing through floor unit mosaic,The fabricated construction that floor and longeron beam connected mode are connected by screw bolts,Soldering cramping apparatus and equipment need not be put into,Reduce effect on environment,Improving productivity more than 20%.
Description
Technical field
The invention belongs to logistics equipment field, is related to a kind of complete fabricated no crossbeam compartment bottom plate structure thereof.
Background technology
Floor pan assembly reaches 40%-50% part as weight accounting in compartment assembly, and steel are replaced using aluminum alloy materials
Making has obvious light weight effect.In in the market like product, essentially added using three stackings on longeron+crossbeam+floor
Structure, between total height reaches 250-300mm, and connected between floor unit, between floor and crossbeam using welding manner.
Existing bottom plate is formed by stacking by longitudinal and transverse beam, three layers of floor, total height >=250mm, and floor and crossbeam, floor
It is welding manner connection between unit.Bottom plate is that three stackings add, and deadweight is larger and vehicle center of gravity raises;Floor unit is guarantee
Water proofing property, it is extremely inefficient more using whole full welds, large-scale automatic welding equipment need to be put into, the strength of materials is had a great influence, simultaneously
Slab element is that adaptation is welded to each other and can not be thinned with beam welding demand, section bar thickness, and it is further to limit light weight effect
Lifting.
The content of the invention
It is an object of the invention to provide a kind of full assembled of aluminium alloy without crossbeam base arrangement, bottom plate is by longeron+floor
(It is longitudinal spliced)Two layers are formed by stacking, and for total height between 180-230mm, center of gravity reduces 70mm;Between floor unit and floor with
All it is connected by screw bolts between longeron, to solve the problems mentioned in the above background technology.
To achieve the above object, the present invention provides following technical scheme:
A kind of full assembled of aluminium alloy is without crossbeam base arrangement, including longeron, floor unit, T-bolt, gib head pressing plate and angular
Connector, directly laying is designed with floor unit along longitudinal spliced floor unit, described floor unit one end on the longeron
End flange structure, coordinate with the floor unit end T-slot of another unit end set, floor unit end T-slot passes through
The T-bolt and it is connected in the Angle connection part of the longeron outside of belly and is connected with longeron, passes through hook between each two Angle connection part
Head pressing plate and T-bolt are connected with longeron top airfoil.
As the further scheme of the present invention:Floor unit end T-slot compresses floor unit end flange, leads to
Cross T-bolt to be connected with longeron, piece together a complete split T-slot, split T-slot passes through T-bolt and the longeron
Connection.
As the further scheme of the present invention:The Angle connection part is fixed on longeron by angle-shaped piece connecting bolt.
As the further scheme of the present invention:The T-bolt connects increase waterproof knot in mosaic after two floor units
Structure and waterproof gluing.
Compared with prior art, the beneficial effects of the invention are as follows:By the way that three stackings of former " longeron+crossbeam+floor " are added
Structure is changed to two layers of overlaying structure of " longeron+floor ", eliminates crossbeam, weight reduces more than 20% on year-on-year basis, and passes through floor
The T-slot structure of unit mosaic, the fabricated construction that floor and longeron beam connected mode are connected by screw bolts, without input
Soldering cramping apparatus and equipment, reduce effect on environment, improving productivity more than 20%.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention.
Fig. 2 is the structural representation of floor unit in the present invention.
Fig. 3 is the structural representation of Angle connection part in the present invention.
Fig. 4 is the structural representation of waterproof construction in the present invention.
Fig. 5 is the structural representation of gib head pressing plate in the present invention.
In figure:1- longerons, 2- floor units, 3- floor units end T-slot, 4- splits T-slot, 5- floor units end
Flange, 6-T types bolt, 7- gib heads pressing plate, 8- waterproof constructions, 9- waterproofs gluing, 10- angle-shaped pieces connecting bolt, 11- Angle connections
Part.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of creative work is not made
Embodiment, belong to the scope of protection of the invention.
Refer to Fig. 1~5, in the embodiment of the present invention, a kind of full assembled of aluminium alloy is without crossbeam base arrangement, including longeron
1st, floor unit 2, T-bolt 6, gib head pressing plate 7 and Angle connection part 11, directly laying is along longitudinal spliced on the longeron 1
Floor unit 2, strength and stiffness demand when floor unit 2 has taken into full account carrying in design;The floor unit 2 one
End is designed with the structure of floor unit end flange 5, can coordinate with the floor unit end T-slot 3 of another unit end set, ground
Slab element end T-slot 3 compresses floor unit end flange 5, is connected by T-bolt 6 with longeron 1, piece together one it is complete
Whole split T-slot 9, split T-slot 9 are connected by T-bolt 6 with the longeron 1.
During assembling, every several floor units 2, floor unit end T-slot 3 is by the T-bolt 6 and is connected in vertical
The Angle connection part 11 of the outside of belly of beam 1 is connected with longeron 1, passes through gib head pressing plate 7 and T-bolt between each two Angle connection part 11
6 are connected with the top airfoil of longeron 1;The Angle connection part 13 is fixed on longeron 1 by angle-shaped piece connecting bolt 14.
After the longeron 1 is connected with floor unit 2, you can limit the movement of its Z-direction, ensure that its X is tight to split.
, can be by increasing waterproof construction 8 and waterproof gluing in mosaic after the T-bolt 6 connects two floor units 2
9 and realize without full weld to be waterproof sealing effect by coating technique.
The invention is not limited in above-described embodiment, on the basis of technical scheme disclosed by the invention, the skill of this area
Art personnel are according to disclosed technology contents, it is not necessary to which performing creative labour can makes one to some of which technical characteristic
A little simple modification, equivalent change and modifications, are belonged in the range of technical solution of the present invention.
, it is necessary to illustrate in the description of this specification, unless otherwise clearly defined and limited, term " setting ",
" connected " and " connection " should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or integratedly be connected
Connect;Can be joined directly together, can also be indirectly connected by intermediary, can be the connection of two element internals.For this
For the those of ordinary skill in field, the concrete meaning of above-mentioned term in the present invention can be understood with concrete condition.
Claims (4)
1. a kind of full assembled of aluminium alloy is without crossbeam base arrangement, including longeron (1), floor unit (2), T-bolt (6), hook
Head pressing plate (7) and Angle connection part (11), it is characterised in that directly laying is single along longitudinal spliced floor on the longeron (1)
First (2), described floor unit (2) one end is designed with floor unit end flange (5) structure, the ground with another unit end set
Slab element end T-slot (3) coordinates, and floor unit end T-slot (3) is by the T-bolt (6) and is connected in longeron (1)
The Angle connection part (11) of the outside of belly is connected with longeron (1), passes through gib head pressing plate (7) and T between each two Angle connection part (11)
Type bolt (6) is connected with longeron (1) top airfoil.
2. the full assembled of a kind of aluminium alloy according to claim 1 is without crossbeam base arrangement, it is characterised in that the floor
Unit end T-slot (3) compresses floor unit end flange (5), is connected, pieced together with longeron (1) by T-bolt (6)
One complete split T-slot (9), split T-slot (9) are connected by T-bolt (6) with the longeron (1).
3. the full assembled of a kind of aluminium alloy according to claim 1 is without crossbeam base arrangement, it is characterised in that described angular
Connector (13) is fixed on longeron (1) by angle-shaped piece connecting bolt (14).
4. the full assembled of a kind of aluminium alloy according to claim 1 is without crossbeam base arrangement, it is characterised in that described T-shaped
Bolt (6) connects two floor units (2) mosaic increase waterproof construction (8) and waterproof gluing (9) afterwards.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710843699.1A CN107499389A (en) | 2017-09-19 | 2017-09-19 | A kind of full assembled of aluminium alloy is without crossbeam base arrangement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710843699.1A CN107499389A (en) | 2017-09-19 | 2017-09-19 | A kind of full assembled of aluminium alloy is without crossbeam base arrangement |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107499389A true CN107499389A (en) | 2017-12-22 |
Family
ID=60697459
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710843699.1A Pending CN107499389A (en) | 2017-09-19 | 2017-09-19 | A kind of full assembled of aluminium alloy is without crossbeam base arrangement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107499389A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108583695A (en) * | 2018-06-19 | 2018-09-28 | 爱普车辆(中国)有限公司 | A kind of bearing-type aluminium alloy passenger-carrying chassis structure |
-
2017
- 2017-09-19 CN CN201710843699.1A patent/CN107499389A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108583695A (en) * | 2018-06-19 | 2018-09-28 | 爱普车辆(中国)有限公司 | A kind of bearing-type aluminium alloy passenger-carrying chassis structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103015537B (en) | Beam-column joint connecting device of assembled steel structure system | |
CN102733492B (en) | H-shaped steel beam and H-shaped steel column minor axis variable beam height fabricated node and construction method thereof | |
CN207160240U (en) | A kind of modular assembly formula multi and tall steel building beam-column connection | |
CN109958065A (en) | The construction method that a kind of bridge steel box girder segmental hoisting high-altitude closes up | |
CN109531029A (en) | A kind of steel construction people's air defense door skin welding equipment | |
CN206202587U (en) | A kind of ship bulkhead attachment structure | |
CN103015535B (en) | A kind of the H weak direction of principal axis of type post and the firm access node structure of H type beam and preparation method thereof | |
CN202969589U (en) | H-type steel beam and rectangular steel tube column variable-beam depth assembly type node | |
CN107499389A (en) | A kind of full assembled of aluminium alloy is without crossbeam base arrangement | |
CN207550321U (en) | A kind of full assembled of aluminium alloy is without crossbeam floor structure | |
CN206598890U (en) | A kind of new diagonal brace connection component of urban bus vehicle body aluminium skeleton | |
CN107979012A (en) | Modularization prefabricated cabin nacelle, modularization prefabricated cabin and substation | |
CN202706211U (en) | Assembly type nodal point of H-shaped steel beam with adjustable height in weak-axis direction and H-shaped steel column | |
CN207812771U (en) | A kind of multi-laminate plywood of framework of steel reinforcement interval adjustable | |
CN202625665U (en) | Sheet-like tower body of tower crane | |
CN107472379A (en) | A kind of full Fabricated Bottom Board structure of aluminium alloy | |
CN205116431U (en) | Eccentric connection structure who aligns of beam column | |
CN106672087A (en) | Aluminum alloy light composite frame type carriage structure | |
CN206829350U (en) | Steel structure support system for subway station | |
CN202969594U (en) | Rigid connection structure for H-shaped column and H-shaped beam in weak axis direction | |
CN207348089U (en) | One kind overlaps close corrugated steel | |
CN206360082U (en) | A kind of beam beam rigid joint of novel fabricated | |
CN208037823U (en) | A kind of hoisting fixture | |
CN108532809A (en) | Steel bar truss floor support plate, steel bar truss floor support plate production method and assembled floor | |
CN214653055U (en) | Two roof beam hoist sectional structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20171222 |