CN107486354B - A kind of high efficiency surface of steel plate glue spraying equipment - Google Patents

A kind of high efficiency surface of steel plate glue spraying equipment Download PDF

Info

Publication number
CN107486354B
CN107486354B CN201710636604.9A CN201710636604A CN107486354B CN 107486354 B CN107486354 B CN 107486354B CN 201710636604 A CN201710636604 A CN 201710636604A CN 107486354 B CN107486354 B CN 107486354B
Authority
CN
China
Prior art keywords
glue spraying
glue
pipe
spraying
workbench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710636604.9A
Other languages
Chinese (zh)
Other versions
CN107486354A (en
Inventor
聂金红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Xinkaiyuan Technology Innovation Development Co ltd
Yangxin Dongtai Precision Metal Co ltd
Original Assignee
Wangjiang Jingmeixin Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wangjiang Jingmeixin Steel Structure Co Ltd filed Critical Wangjiang Jingmeixin Steel Structure Co Ltd
Priority to CN201710636604.9A priority Critical patent/CN107486354B/en
Publication of CN107486354A publication Critical patent/CN107486354A/en
Application granted granted Critical
Publication of CN107486354B publication Critical patent/CN107486354B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B13/00Machines or plants for applying liquids or other fluent materials to surfaces of objects or other work by spraying, not covered by groups B05B1/00 - B05B11/00
    • B05B13/02Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work
    • B05B13/0221Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work characterised by the means for moving or conveying the objects or other work, e.g. conveyor belts
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B13/00Machines or plants for applying liquids or other fluent materials to surfaces of objects or other work by spraying, not covered by groups B05B1/00 - B05B11/00
    • B05B13/02Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work
    • B05B13/0278Arrangement or mounting of spray heads
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B13/00Machines or plants for applying liquids or other fluent materials to surfaces of objects or other work by spraying, not covered by groups B05B1/00 - B05B11/00
    • B05B13/02Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work
    • B05B13/04Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work the spray heads being moved during spraying operation
    • B05B13/0405Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work the spray heads being moved during spraying operation with reciprocating or oscillating spray heads
    • B05B13/041Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work the spray heads being moved during spraying operation with reciprocating or oscillating spray heads with spray heads reciprocating along a straight line
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B13/00Machines or plants for applying liquids or other fluent materials to surfaces of objects or other work by spraying, not covered by groups B05B1/00 - B05B11/00
    • B05B13/02Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work
    • B05B13/04Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work the spray heads being moved during spraying operation
    • B05B13/0421Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work the spray heads being moved during spraying operation with rotating spray heads
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B13/00Machines or plants for applying liquids or other fluent materials to surfaces of objects or other work by spraying, not covered by groups B05B1/00 - B05B11/00
    • B05B13/02Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work
    • B05B13/04Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work the spray heads being moved during spraying operation
    • B05B13/0447Installation or apparatus for applying liquid or other fluent material to conveyed separate articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29CSHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
    • B29C65/00Joining or sealing of preformed parts, e.g. welding of plastics materials; Apparatus therefor
    • B29C65/48Joining or sealing of preformed parts, e.g. welding of plastics materials; Apparatus therefor using adhesives, i.e. using supplementary joining material; solvent bonding
    • B29C65/52Joining or sealing of preformed parts, e.g. welding of plastics materials; Apparatus therefor using adhesives, i.e. using supplementary joining material; solvent bonding characterised by the way of applying the adhesive
    • B29C65/522Joining or sealing of preformed parts, e.g. welding of plastics materials; Apparatus therefor using adhesives, i.e. using supplementary joining material; solvent bonding characterised by the way of applying the adhesive by spraying, e.g. by flame spraying

Abstract

The invention proposes a kind of high efficiency surface of steel plate glue spraying equipments, including workbench, mounting plate, synchronous belt, the first synchronizing wheel, the second synchronizing wheel, the first driving mechanism, the first glue-spraying mechanism, the second glue-spraying mechanism, first guide rail one end is equipped with the first sliding block being slidably connected with it, and the second guide rail is equipped with the second sliding block being slidably connected with it far from first sliding block one end;Synchronous belt is sleeved on the first synchronizing wheel, engages in the second synchronizing wheel and with the first synchronizing wheel, the second synchronizing wheel, synchronous belt is connect with the first sliding block, the second sliding block, and the first driving mechanism connect with the first synchronizing wheel, the second synchronizing wheel and drive the first synchronizing wheel, the second synchronizing wheel to rotate synchronously;First glue-spraying mechanism is mounted on the first sliding block, and the second glue-spraying mechanism is mounted on the second sliding block, and the first glue-spraying mechanism, the second glue-spraying mechanism, which are worked together, carries out glue spraying processing to the steel plate of glue spraying on workbench.The present invention can be realized the automatic glue-spraying processing to steel plate, improve work efficiency.

Description

A kind of high efficiency surface of steel plate glue spraying equipment
Technical field
The present invention relates to movable plank house technical field more particularly to a kind of high efficiency surface of steel plate glue spraying equipments.
Background technique
Movable plank house is that frame is propped after Land leveling at present, and then compoboard slices are fixed on frame and are combined At house, a combination thereof plate is three ply board structure, and middle layer is polyurethane foamed material, and ectonexine is sheet metal, the thin steel of ectonexine It is bonded together between plate and polyurethane foam material using viscose, when production and processing, often first spraying viscose is again on the steel plate It is covered with polyurethane foam material, but mostly uses artificial glue spraying when current glue spraying, production efficiency is low, and produces to operator Raw certain injury.
Summary of the invention
Based on technical problem present in background technique, the invention proposes a kind of high efficiency surface of steel plate glue spraying equipments.
A kind of high efficiency surface of steel plate glue spraying equipment proposed by the present invention, including workbench, mounting plate, synchronous belt, first Synchronizing wheel, the second synchronizing wheel, the first driving mechanism, the first glue-spraying mechanism, the second glue-spraying mechanism;
Workbench length both ends are respectively feed end and discharge end, and the feed end two sides of workbench are equipped with the first side frame, The discharge end two sides of workbench are equipped with the second side frame;
Mounting plate is located above workbench and is parallel to workbench, installation board ends respectively with the first side frame, the second side frame Connection, mounting plate are set close to workbench side there are two the first guide rail being arranged in parallel, the second guide rail, and the first guide rail, second are led Rail arranges that first guide rail one end is equipped with the first sliding block being slidably connected with it along workbench length direction, and the second guide rail is separate First sliding block one end is equipped with the second sliding block being slidably connected with it;
First synchronizing wheel, the second synchronizing wheel be rotatablely installed on a mounting board and be located at the first guide rail and the second guide rail it Between, synchronous belt is sleeved on the first synchronizing wheel, engages in the second synchronizing wheel and with the first synchronizing wheel, the second synchronizing wheel, synchronous belt with First sliding block, the connection of the second sliding block, the first driving mechanism is for driving the first synchronizing wheel, the second synchronizing wheel to rotate synchronously;
First glue-spraying mechanism is mounted on the first sliding block and can slide with sliding of first sliding block on the first guide rail, Second glue-spraying mechanism is mounted on the second sliding block and can slide, the first glue spraying with sliding of second sliding block on the second guide rail Mechanism, the second glue-spraying mechanism, which are worked together, carries out glue spraying processing to the steel plate of glue spraying on workbench.
Preferably, the first guide rail is fixed with the first limited block close to workbench feed end one end, and the first guide rail is close to work Platform discharge end one end is fixed with the second limited block, and the first limited block, the second limited block are located at the two sides of the first sliding block, and first is sliding Block and the first limited block against when the starting of the first glue-spraying mechanism start to carry out glue spraying processing to steel plate, when the first sliding block and the second limit Position block against when the first glue-spraying mechanism complete to process the glue spraying of steel plate.
Preferably, the second guide rail is fixed with third limited block close to workbench discharge end one end, and the second guide rail is close to work Platform feed end one end is fixed with the 4th limited block, and third limited block, the 4th limited block are located at the two sides of the second sliding block, the second sliding block With third limited block against when the second glue-spraying mechanism be in starting start to steel plate carry out glue spraying processing, when the second sliding block and the 4th Limited block against when the second glue-spraying mechanism complete to process the glue spraying of steel plate.
It preferably, further include the first transport mechanism, the feed end that workbench is arranged in the first transport mechanism is used for work Platform transmits the steel plate to glue spraying.
It preferably, further include the second transport mechanism, the discharge end that workbench is arranged in the second transport mechanism is used for glue spraying Steel plate afterwards is sent out.
Preferably, the first glue-spraying mechanism includes the second driving mechanism, first rotating shaft and the first glue spraying component, the second driving machine Structure is mounted on the first sliding block and is connect by first rotating shaft with the first glue spraying component, and the second driving mechanism is for driving first turn Axis rotation.
Preferably, the first glue spraying component includes first annular pipe, multiple first glue spraying pipes and multiple second glue spraying pipes, and first Shaft is connect by multiple first connecting rods with first annular inside pipe wall, and first annular tube cavity, which stores, viscose, and multiple first Glue spraying pipe first end connect with first annular pipe and multiple first glue spraying pipes centered on the center of first annular pipe circumferentially It is uniformly distributed, the first glue spraying tube cavity is connected to first annular tube cavity, and the first glue spraying pipe second end is ejection end and is equipped with First glue-spraying spout, the first glue spraying pipe tilts down setting and the projection of the first glue spraying pipe on the table is located at first annular pipe and exists Outside projection on workbench;Multiple second glue spraying pipe first ends are connect with first annular pipe and multiple second glue spraying pipes are with first It is circularly and evenly distributed centered on the center of ring pipe, multiple second glue spraying pipes and multiple first glue spraying pipe interlaced arrangements, second Glue spraying tube cavity is connected to first annular tube cavity, and the second glue spraying pipe second end is ejection end and is equipped with the second glue-spraying spout, the Two glue spraying pipes tilt down setting and the projection of the second glue spraying pipe on the table is located at the throwing of first annular pipe on the table In shadow.
Preferably, the second glue-spraying mechanism includes third driving mechanism, the second shaft and the second glue spraying component, third driving machine Structure is mounted on the second sliding block and is connect by the second shaft with the second glue spraying component, and third driving mechanism is for driving second turn Axis rotation.
Preferably, the second glue spraying component include the second ring pipe, multiple third glue spraying pipes and multiple 4th glue spraying pipes, second Shaft is connect by multiple second connecting rods with the second annular inside pipe wall, and the second annular tube cavity storage has viscose, multiple thirds Glue spraying pipe first end connect with the second ring pipe and multiple third glue spraying pipes centered on the center of the second ring pipe circumferentially It is uniformly distributed, third glue spraying tube cavity is connected to the second annular tube cavity, and third glue spraying pipe second end is ejection end and is equipped with Third glue-spraying spout, third glue spraying pipe tilts down setting and the projection of third glue spraying pipe on the table is located at the second ring pipe and exists Outside projection on workbench;Multiple 4th glue spraying pipe first ends are connect with the second ring pipe and multiple 4th glue spraying pipes are with second It is circularly and evenly distributed centered on the center of ring pipe, multiple 4th glue spraying pipes and multiple third glue spraying pipe interlaced arrangements, the 4th Glue spraying tube cavity is connected to the second annular tube cavity, and the 4th glue spraying pipe second end is ejection end and is equipped with the 4th glue-spraying spout, the Four glue spraying pipes tilt down setting and the projection of the 4th glue spraying pipe on the table is located at the throwing of the second ring pipe on the table In shadow.
High efficiency surface of steel plate glue spraying equipment proposed by the present invention is conveyed to workbench to glue spraying by the first transport mechanism Steel plate, when steel plate front end is moved to workbench discharge end, the first transport mechanism stops transmission steel plate, while the first glue sprayer Structure, the second glue-spraying mechanism are started to work, and the first driving mechanism drives the first sliding block, the second sliding block respectively along the first guide rail, second Guide rail sliding, so that the first glue-spraying mechanism, the second glue-spraying mechanism is driven to move respectively along the first guide rail, the second guide rail, completion pair The glue spraying of steel plate is processed, and after the completion of glue spraying, the second transport mechanism sends out the steel plate after glue spraying on workbench.The present invention is logical Crossing setting synchronous belt drives the first sliding block, the second sliding block mobile, effectively improve the mobile synchronism of the first sliding block, the second sliding block and Stability improves glue spraying effect;The present invention can realize the automatic glue-spraying processing to steel plate, improve work efficiency, effectively It reduces costs, the operation is stable, glue spraying is comprehensively without leak source.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of high efficiency surface of steel plate glue spraying equipment proposed by the present invention;
Fig. 2 is the structural schematic diagram of mounting plate in a kind of high efficiency surface of steel plate glue spraying equipment proposed by the present invention;
Fig. 3 is the structural representation of the first glue spraying component in a kind of high efficiency surface of steel plate glue spraying equipment proposed by the present invention Figure;
Fig. 4 is the structural representation of the second glue spraying component in a kind of high efficiency surface of steel plate glue spraying equipment proposed by the present invention Figure.
Specific embodiment
- Fig. 4 referring to Fig.1, the present invention propose that a kind of high efficiency surface of steel plate glue spraying equipment, including workbench 1, first transmit Mechanism 2, the second transport mechanism 3, mounting plate 4, synchronous belt 15, the first synchronizing wheel 16, the second synchronizing wheel 17, the first driving mechanism, First glue-spraying mechanism, the second glue-spraying mechanism;Wherein:
1 length both ends of workbench are respectively feed end and discharge end, and the feed end two sides of workbench 1 are equipped with the first side frame 5, the discharge end two sides of workbench 1 are equipped with the second side frame 6.
The feed end that workbench 1 is arranged in first transport mechanism 2 is used to transmit the steel plate 34 to glue spraying to workbench 1.
The discharge end of workbench 1 is arranged in for sending out the steel plate 34 after glue spraying on workbench 1 in second transport mechanism 3 It goes.
Mounting plate 4 is located at the top of workbench 1 and is parallel to workbench 1,4 both ends of mounting plate respectively with the first side frame 5, second Side frame 6 connects, and mounting plate 4 is set close to 1 side of workbench there are two the first guide rail 7 being arranged in parallel, the second guide rail 8, and first leads Rail 7, the second guide rail 8 arrange that 7 one end of the first guide rail is equipped with the first sliding block being slidably connected with it along 1 length direction of workbench 9, the second guide rail 8 is equipped with the second sliding block 10 being slidably connected with it far from 9 one end of the first sliding block.First guide rail 7 is close to workbench 1 Feed end one end is fixed with the first limited block 11, and the first guide rail 7 is fixed with the second limited block close to 1 discharge end one end of workbench 12, the first limited block 11, the second limited block 12 are located at the two sides of the first sliding block 9;Second guide rail 8 is close to 1 discharge end one of workbench End is fixed with third limited block 13, and the second guide rail 8 is fixed with the 4th limited block 14, third limit close to 1 feed end one end of workbench Position block 13, the 4th limited block 14 are located at the two sides of the second sliding block 10.
First synchronizing wheel 16, the second synchronizing wheel 17 are rotatably installed on mounting plate 4 and are located at the first guide rail 7 and lead with second Between rail 8, synchronous belt 15 is sleeved on the first synchronizing wheel 16, in the second synchronizing wheel 17 and with the first synchronizing wheel 16, the second synchronizing wheel 17 engagements, synchronous belt 15 connect with the first sliding block 9, the second sliding block 10, and the first driving mechanism is used for the first synchronizing wheel 16 of driving, the Two synchronizing wheels 17 rotate synchronously, and the first synchronizing wheel 16, the rotation of the second synchronizing wheel 17 drive synchronous belt 15 to rotate, and synchronous belt 15 drives First sliding block 9, the second sliding block 10 slide on the first guide rail 7, the second guide rail 8 respectively.
First glue-spraying mechanism, the second glue-spraying mechanism, which are worked together, carries out glue spraying processing to the steel plate of glue spraying on workbench. First glue-spraying mechanism includes the second driving mechanism 18, first rotating shaft 19 and the first glue spraying component, and the second driving mechanism 18 is mounted on It is connect on first sliding block 9 and by first rotating shaft 19 with the first glue spraying component, the second driving mechanism 18 is for driving first rotating shaft 19 rotations.Second glue-spraying mechanism includes third driving mechanism 26, the second shaft 27 and the second glue spraying component, third driving mechanism 26 It is mounted on the second sliding block 10 and connect with the second glue spraying component by the second shaft 27, third driving mechanism 26 is used for driving the The rotation of two shafts 27.
In a particular embodiment, the first glue spraying component includes first annular pipe 20, multiple first glue spraying pipes 21 and multiple Two glue spraying pipes 22, first rotating shaft 19 are connect by multiple first connecting rods 23 with first annular 20 inner wall of pipe, first annular pipe 20 Inner cavity storage has a viscose, multiple first glue spraying pipe, 21 first ends connect with first annular pipe 20 and multiple first glue spraying pipes 21 with It is circularly and evenly distributed centered on the center of first annular pipe 20,21 inner cavity of the first glue spraying pipe connects with first annular 20 inner cavity of pipe Logical, 21 second end of the first glue spraying pipe is ejection end and is equipped with the first glue-spraying spout 24, and the first glue spraying pipe 21 tilts down setting and the Projection of the one glue spraying pipe 21 on workbench 1 is located at first annular pipe 20 outside the projection on workbench 1;Multiple second glue spraying pipes 22 first ends are connect with first annular pipe 20 and multiple second glue spraying pipes 22 are in circle centered on the center of first annular pipe 20 Week is uniformly distributed, multiple second glue spraying pipes 22 and multiple first glue spraying pipe, 21 interlaced arrangements, and 22 inner cavity of the second glue spraying pipe is with the The connection of one ring pipe, 20 inner cavity, 22 second end of the second glue spraying pipe are ejection end and are equipped with the second glue-spraying spout 25, the second glue spraying pipe 22 It tilts down setting and projection of the second glue spraying pipe 22 on workbench 1 is located at projection of the first annular pipe 20 on workbench 1 It is interior.
In a particular embodiment, the second glue spraying component includes the second ring pipe 28, multiple third glue spraying pipes 29 and multiple the Four glue spraying pipes 30, the second shaft 27 are connect by multiple second connecting rods 31 with 28 inner wall of the second ring pipe, the second ring pipe 28 Inner cavity storage has a viscose, multiple 29 first ends of third glue spraying pipe connect with the second ring pipe 28 and multiple third glue spraying pipes 29 with It is circularly and evenly distributed centered on the center of second ring pipe 28,29 inner cavity of third glue spraying pipe connects with 28 inner cavity of the second ring pipe Logical, 29 second end of third glue spraying pipe is ejection end and is equipped with third glue-spraying spout 32, and third glue spraying pipe 29 tilts down setting and the Projection of the three glue spraying pipes 29 on workbench 1 is located at the second ring pipe 28 outside the projection on workbench 1;Multiple 4th glue spraying pipes 30 first ends are connect with the second ring pipe 28 and multiple 4th glue spraying pipes 30 are in circle centered on the center of the second ring pipe 28 Week is uniformly distributed, multiple 4th glue spraying pipes 30 and multiple 29 interlaced arrangements of third glue spraying pipe, and 30 inner cavity of the 4th glue spraying pipe is with the The connection of 28 inner cavity of second ring pipe, 30 second end of the 4th glue spraying pipe are ejection end and are equipped with the 4th glue-spraying spout 33, the 4th glue spraying pipe 30 It tilts down setting and projection of the 4th glue spraying pipe 30 on workbench 1 is located at projection of second ring pipe 28 on workbench 1 It is interior.
Specific work process of the present invention is as follows: the steel plate 34 that the first transport mechanism 2 works to the conveying of workbench 1 to glue spraying, When the steel plate 34 of glue spraying is moved to 1 discharge end of workbench, the first transport mechanism 2 stops working, the driving of the first driving mechanism First synchronizing wheel 16, the second synchronizing wheel 17 are rotated clockwise to drive synchronous belt 15 to rotate clockwise, to drive the first sliding block 9, the second sliding block 10 is mobile to the first limited block 11, third limited block 13 respectively;When the first sliding block 9, the second sliding block 10 respectively with First limited block 11, third limited block 13 against when, the first glue spraying component, the second glue spraying component starting starts to steel plate 34 carry out Glue spraying processing, while the second driving mechanism 18, third driving mechanism 26 respectively drive first rotating shaft 19, the second shaft 27 rotation with The first glue spraying component, the rotation of the second glue spraying component are driven, then the first driving mechanism drives the first synchronizing wheel 16, the second synchronizing wheel 17 rotate counterclockwise to drive synchronous belt 15 to rotate counterclockwise, to drive the first sliding block 9, the second sliding block 10 respectively to the second limit Position block 12, the 4th limited block 14 are mobile;When the first sliding block 9, the second sliding block 10 respectively with the second limited block 12, the 4th limited block 14 Against when, the first glue spraying component, the second glue spraying component stop working and the second driving mechanism 18, third driving mechanism 26 distinguish Stop driving first rotating shaft 19, the rotation of the second shaft 27, the first driving mechanism stops driving the first synchronizing wheel 16, the second synchronizing wheel 17 rotations are mobile to stop driving the first sliding block 9, the second sliding block 10, while the second transport mechanism works the steel plate 34 after glue spraying It sends out;Above-mentioned movement is repeated, the glue spraying processing of next steel plate 34 is carried out.
A kind of high efficiency surface of steel plate glue spraying equipment proposed by the present invention drives the first sliding block 9, the by setting synchronous belt Two sliding blocks 10 are mobile, effectively improve the first sliding block 9, the second sliding block 10 mobile synchronism and stability, improve glue spraying effect;This Invention can be realized the automatic glue-spraying processing to steel plate 34, improve work efficiency, and effectively reduce cost, the operation is stable, spray Glue is comprehensively without leak source
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (7)

1. a kind of high efficiency surface of steel plate glue spraying equipment, which is characterized in that including workbench (1), mounting plate (4), synchronous belt (15), the first synchronizing wheel (16), the second synchronizing wheel (17), the first driving mechanism, the first glue-spraying mechanism, the second glue-spraying mechanism;
Workbench (1) length both ends are respectively feed end and discharge end, and the feed end two sides of workbench (1) are equipped with the first side frame (5), the discharge end two sides of workbench (1) are equipped with the second side frame (6);
Mounting plate (4) is located above workbench (1) and is parallel to workbench (1), mounting plate (4) both ends respectively with the first side frame (5), the second side frame (6) connect, mounting plate (4) close to workbench (1) side set there are two be arranged in parallel the first guide rail (7), Second guide rail (8), the first guide rail (7), the second guide rail (8) arrange that the first guide rail is set on (7) along workbench (1) length direction There is the first sliding block (9) being slidably connected with it, the second guide rail (8) is equipped with the second sliding block (10) being slidably connected with it;
First synchronizing wheel (16), the second synchronizing wheel (17) are rotatably installed on mounting plate (4) and are located at the first guide rail (7) and the Between two guide rails (8), synchronous belt (15) is sleeved on the first synchronizing wheel (16), in the second synchronizing wheel (17) and with the first synchronizing wheel (16), the second synchronizing wheel (17) engages, and synchronous belt (15) is connect with the first sliding block (9), the second sliding block (10), the first driving mechanism For drive the first synchronizing wheel (16),
Second synchronizing wheel (17) rotates synchronously;
First glue-spraying mechanism be mounted on the first sliding block (9) and can with sliding of the first sliding block (9) on the first guide rail (7) and Sliding, the second glue-spraying mechanism are mounted on the second sliding block (10) and can be with cunning of the second sliding block (10) on the second guide rail (8) It moves and slides, the first glue-spraying mechanism, the second glue-spraying mechanism, which work together, adds the steel plate progress glue spraying on workbench (1) to glue spraying Work;
First glue-spraying mechanism includes the second driving mechanism (18), first rotating shaft (19) and the first glue spraying component, the second driving mechanism (18) it is mounted on the first sliding block (9) and is connect by first rotating shaft (19) with the first glue spraying component, the second driving mechanism (18) For driving first rotating shaft (19) to rotate;First glue spraying component include first annular pipe (20), multiple first glue spraying pipes (21) and Multiple second glue spraying pipes (22), first rotating shaft (19) are connected by multiple first connecting rods (23) and first annular pipe (20) inner wall It connects, first annular pipe (20) inner cavity storage has viscose, and multiple first glue spraying pipe (21) first ends connect with first annular pipe (20) It connects and multiple first glue spraying pipes (21) is circularly and evenly distributed centered on the center of first annular pipe (20), the first glue spraying pipe (21) inner cavity is connected to first annular pipe (20) inner cavity, and the first glue spraying pipe (21) second end is ejection end and is equipped with the first glue spraying Mouth (24), the first glue spraying pipe (21) tilts down setting and projection of the first glue spraying pipe (21) on workbench (1) is located at first Ring pipe (20) is outside the projection on workbench (1);Multiple second glue spraying pipe (22) first ends connect with first annular pipe (20) It connects and multiple second glue spraying pipes (22) is circularly and evenly distributed centered on the center of first annular pipe (20), multiple second glue sprayings (22) and multiple first glue spraying pipe (21) interlaced arrangements are managed, second glue spraying pipe (22) inner cavity connects with first annular pipe (20) inner cavity Logical, the second glue spraying pipe (22) second end is ejection end and is equipped with the second glue-spraying spout (25), and the second glue spraying pipe (22), which tilts down, to be set It sets and the second glue spraying pipe (22) in the projection on workbench (1) is located at first annular pipe (20) in the projection on workbench (1).
2. high efficiency surface of steel plate glue spraying equipment according to claim 1, which is characterized in that the first guide rail (7) is close to work Make platform (1) feed end one end to be fixed with the first limited block (11), the first guide rail (7) is fixed close to workbench (1) discharge end one end Have the second limited block (12), and the first limited block (11), the second limited block (12) are located at the two sides of the first sliding block (9), first is sliding Block (9) and the first limited block (11) against when the first glue-spraying mechanism be in starting and start to carry out glue spraying processing to steel plate, when first Sliding block (9) and the second limited block (12) against when the first glue-spraying mechanism complete to process the glue spraying of steel plate.
3. high efficiency surface of steel plate glue spraying equipment according to claim 1, which is characterized in that the second guide rail (8) is close to work Make platform (1) discharge end one end to be fixed with third limited block (13), the second guide rail (8) is fixed close to workbench (1) feed end one end There is the 4th limited block (14), and third limited block (13), the 4th limited block (14) are located at the two sides of the second sliding block (10), second is sliding Block (10) and third limited block (13) against when the second glue-spraying mechanism be in starting and start to carry out glue spraying processing to steel plate, when second Sliding block (10) and the 4th limited block (14) against when the second glue-spraying mechanism complete to process the glue spraying of steel plate.
4. high efficiency surface of steel plate glue spraying equipment according to any one of claim 1-3, which is characterized in that further include The feed end in workbench (1) is arranged for transmitting to workbench (1) to glue spraying in one transport mechanism (2), the first transport mechanism (2) Steel plate.
5. high efficiency surface of steel plate glue spraying equipment according to any one of claim 1-3, which is characterized in that further include The discharge end in workbench (1) is arranged for sending out the steel plate after glue spraying in two transport mechanisms (3), the second transport mechanism (3) It goes.
6. high efficiency surface of steel plate glue spraying equipment according to any one of claim 1-3, which is characterized in that the second glue spraying Mechanism includes third driving mechanism (26), the second shaft (27) and the second glue spraying component, and third driving mechanism (26) is mounted on It is connect on two sliding blocks (10) and by the second shaft (27) with the second glue spraying component, third driving mechanism (26) is for driving second Shaft (27) rotation.
7. high efficiency surface of steel plate glue spraying equipment according to claim 6, which is characterized in that the second glue spraying component includes the Second ring pipe (28), multiple third glue spraying pipes (29) and multiple 4th glue spraying pipes (30), the second shaft (27) pass through multiple second Connecting rod (31) is connect with the second ring pipe (28) inner wall, and the storage of the second ring pipe (28) inner cavity has viscose, multiple third glue sprayings Pipe (29) first end is connect with the second ring pipe (28) and multiple third glue spraying pipes (29) are with the center of the second ring pipe (28) Centered on be circularly and evenly distributed, third glue spraying pipe (29) inner cavity is connected to the second ring pipe (28) inner cavity, third glue spraying pipe (29) second end is ejection end and is equipped with third glue-spraying spout (32), and third glue spraying pipe (29) tilts down setting and third glue spraying pipe (29) it is located at the second ring pipe (28) outside the projection on workbench (1) in the projection on workbench (1);Multiple 4th glue spraying pipes (30) first end is connect with the second ring pipe (28) and multiple 4th glue spraying pipes (30) with the center of the second ring pipe (28) are Center is circularly and evenly distributed, multiple 4th glue spraying pipes (30) and multiple third glue spraying pipe (29) interlaced arrangements, the 4th glue spraying pipe (30) inner cavity is connected to the second ring pipe (28) inner cavity, and the 4th glue spraying pipe (30) second end is ejection end and is equipped with the 4th glue spraying Mouth (33), the 4th glue spraying pipe (30) tilts down setting and projection of the 4th glue spraying pipe (30) on workbench (1) is located at second Ring pipe (28) is in the projection on workbench (1).
CN201710636604.9A 2017-07-31 2017-07-31 A kind of high efficiency surface of steel plate glue spraying equipment Active CN107486354B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710636604.9A CN107486354B (en) 2017-07-31 2017-07-31 A kind of high efficiency surface of steel plate glue spraying equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710636604.9A CN107486354B (en) 2017-07-31 2017-07-31 A kind of high efficiency surface of steel plate glue spraying equipment

Publications (2)

Publication Number Publication Date
CN107486354A CN107486354A (en) 2017-12-19
CN107486354B true CN107486354B (en) 2019-07-19

Family

ID=60645031

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710636604.9A Active CN107486354B (en) 2017-07-31 2017-07-31 A kind of high efficiency surface of steel plate glue spraying equipment

Country Status (1)

Country Link
CN (1) CN107486354B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110884146B (en) * 2019-12-17 2021-10-15 河北实达集团诺格橡胶科技有限公司 Sizing equipment for foamed rubber sealing strip

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4041587A1 (en) * 1990-12-22 1992-07-02 Duerr Gmbh & Co SKID CONVEYOR FOR PAINTING PLANTS
DE202006009372U1 (en) * 2006-06-13 2006-08-31 Daunquart, Alfred Transport unit moving bar carrying two nozzles back and forth along a straight path, includes two spaced wheels carrying e.g. chain or V-belt connected to bar
CN105149145B (en) * 2015-10-14 2017-12-08 成都市智联环境保护设备有限公司 A kind of Novel steel cylinder surface lacquer equipment
CN106493019B (en) * 2016-11-14 2022-02-11 联德(广州)机械有限公司 Five-axis linkage plate spraying machine
CN206276553U (en) * 2016-12-14 2017-06-27 安徽纪兴源科技股份有限公司 A kind of sheet material flush coater shower nozzle vertically moves belt gear

Also Published As

Publication number Publication date
CN107486354A (en) 2017-12-19

Similar Documents

Publication Publication Date Title
CN110976176B (en) Coating equipment for building material surface
CN106024685B (en) A kind of wafer disk driving means
CN108357921B (en) A kind of eccentric wheel feed device
CN107225060B (en) A kind of self-interacting type surface of steel plate spraying colloid system
CN107486354B (en) A kind of high efficiency surface of steel plate glue spraying equipment
CN104842255B (en) Polishing machine
CN105479292A (en) Glass edge grinding machine and glass edge grinding technology
CN104386458A (en) Motorcycle vehicle frame pin shaft feeding device
CN108972807A (en) A kind of efficiently two-way rotary-cut assembly line
CN105108604A (en) Glass edge grinding machine
CN104549839A (en) Paint spraying machine for production and processing of computer host case
CN107952714A (en) A kind of thread cavity cleaning device of cylindrical work
CN106743437A (en) A kind of stainless steel service plate retracting device
CN105583725A (en) Automatic feeding machine
CN106348001B (en) A kind of fire-fighting host shell mobile mechanism between workbench
CN107282364B (en) A kind of continuous quick glue spraying equipment of surface of steel plate
CN107377270B (en) A kind of surface of steel plate automatic glue-spraying control system
CN210173334U (en) Novel sanding air mill
CN209226833U (en) A kind of glass bar cutter device
CN109649950B (en) Automatic film conveying equipment for automobile maintenance
CN110977783A (en) Shot blasting device for processing four corners of H-shaped steel
CN205184457U (en) Glass edge grinding machine
CN205571740U (en) Automatic feed device of button radium carving machine
CN206553390U (en) 3D glass bending forming machines
CN104260090A (en) Multi-degree-of-freedom manipulator

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210105

Address after: 251800 no.377, Gongye 2nd Road, economic development zone, Yangxin County, Binzhou City, Shandong Province

Patentee after: Shandong xinkaiyuan Technology Innovation Development Co.,Ltd.

Address before: 246200 beside Anli Road, Gaoshi Town, Gaoshi village, Wangjiang County, Anqing City, Anhui Province

Patentee before: WANGJIANG JINGMEIXIN STEEL STRUCTURE Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221123

Address after: 251800 no.377, Gongye 2nd Road, economic development zone, Yangxin County, Binzhou City, Shandong Province

Patentee after: Shandong xinkaiyuan Technology Innovation Development Co.,Ltd.

Patentee after: YANGXIN DONGTAI PRECISION METAL Co.,Ltd.

Address before: 251800 no.377, Gongye 2nd Road, economic development zone, Yangxin County, Binzhou City, Shandong Province

Patentee before: Shandong xinkaiyuan Technology Innovation Development Co.,Ltd.

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A high efficiency adhesive spraying equipment for steel plate surface

Effective date of registration: 20221205

Granted publication date: 20190719

Pledgee: Industrial and Commercial Bank of China Limited Yangxin sub branch

Pledgor: YANGXIN DONGTAI PRECISION METAL Co.,Ltd.

Registration number: Y2022980024683