CN107476271A - A kind of marine steel pipe pile sinking construction technology - Google Patents
A kind of marine steel pipe pile sinking construction technology Download PDFInfo
- Publication number
- CN107476271A CN107476271A CN201610400100.2A CN201610400100A CN107476271A CN 107476271 A CN107476271 A CN 107476271A CN 201610400100 A CN201610400100 A CN 201610400100A CN 107476271 A CN107476271 A CN 107476271A
- Authority
- CN
- China
- Prior art keywords
- pile
- steel pipe
- construction technology
- marine steel
- pipe pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B17/02—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The invention discloses a kind of marine steel pipe pile sinking construction technology, and it includes following job step:Measurement prepares, pile driving barge is in place, pile tube lifting, positioning pitching pile, fuller injection, checks absolute altitude, unloads hammer and pile frame displacement.Penetration power of the present invention is strong, efficiency of construction is high, vertical missing degree is small, can be applicable various rough seas, meet needed for engineering construction.
Description
Technical field
The present invention relates to ocean engineering construction technique field, and in particular to a kind of offshore steel
Pile tube sinking construction technology.
Background technology
Since 20 middle of century, the ocean offshore engineerings such as mobile semi-submerged platform, jack-up unit, oil and gas prospect production platform, seadrome and ton harbour are constantly risen, also more and more higher, particularly carrying foundation stone-steel pipe pile foundation are particularly important for requirement for engineering foundation construction.The distance that steel-pipe pile sinks to b.s.l. is deeper, directly subjects the heavy burden of superstructure and the etch of seawater, therefore the requirement to itself quality is relatively strict outer, and it is also to ensure the premise of construction quality to take rational pipe pile construction method or construction technology.
The content of the invention
It is applicable various rough seas it is an object of the invention to provide a kind of, meets marine steel pipe pile sinking construction technology needed for engineering construction.
In order to solve the above technical problems, the technical scheme is that:A kind of marine steel pipe pile sinking construction technology, it includes following job step:Measurement prepares, pile driving barge is in place, pile tube lifting, positioning pitching pile, fuller injection, checks absolute altitude, unloads hammer and pile frame displacement.
Further, the measurement preparation process includes surveying before sweeping sea, engineering and material prepares.
Further, pile driving barge step in place is driven into including stake ship, GPS location and cast anchor.
Further, the positioning pitching pile step carries out stake position-finding using ship as reference with laser ranging instrument on ship.
Further, in 30~35cm of stake top laying thickness sandalwood before the fuller injection.Beneficial effect:Penetration power of the present invention is strong, efficiency of construction is high, vertical missing degree is small, can be applicable various rough seas, meet needed for engineering construction.
Embodiment
In order to deepen the understanding of the present invention, the present invention is described in further detail with reference to embodiment.
Marine steel pipe pile sinking construction technology, it includes following job step:Measurement prepares, pile driving barge is in place, pile tube lifting, positioning pitching pile, fuller injection, checks absolute altitude, unloads hammer and pile frame displacement.
The measurement preparation process includes surveying before sweeping sea, engineering and the preparation of material.
The pile driving barge step in place is driven into including stake ship, GPS location and casts anchor.
The positioning pitching pile step carries out stake position-finding using ship as reference with laser ranging instrument on ship.
In 30~35cm of stake top laying thickness sandalwood before the fuller injection.
Specific implementation process
First, observing and controlling is carried out using total powerstation according to the stake point that owner provides, establishes this engineering construction Control coordinate system system, and report higher level's management department to check and accept accreditation.
2nd, it is dragged to according to the data that double-frequency GPS-RTK GPSs are shown on pile driving barge, pile driving barge by tugboat near stake point, the admiral anchor for being thrown into 6 10 tons of counterpoises carries out precise positioning.
3rd, pile transport ship approaching pile driving barge side, after two center line of boat are vertical, gantry stile on pile driving barge is tilted to the diameter center of the suspension hook alignment pile tube to be hung, put down after major-minor suspension hook is firmly linked with pile tube, main suspension hook rises, and secondary suspension hook declines, and is reached to a certain degree with rising to, secondary suspension hook solution is gone, and makes pile tube into erectility.
4th, hypsokinesis gantry stile, make pile tube and pile frame into after parallel shape, pile tube is embraced using pile gripper and is locked, in OPS pile frame gradient is adjusted by observing the angel measuring instrument on rangefinder and console on pile driving barge, stake is set to reach design attitude, main suspension hook is slowly put down, pile gripper is opened, makes pile tube automatically instrument under gravity.
5th, main suspension hook is released, in 30~35cm of stake top laying thickness sandalwood, first hammer tip-tap, with anti-slip stake, hammer force degree is progressively increased after injection is normal, in pile driving process, the change of stake position can be finely adjusted in the range of allowable error, abnormal if there is injection, and pile body inclining is excessive or during shifting phenomena, pile sinking should be stopped immediately, and reported to project supervision department and designing unit.
6th, pile tube stops hammering after reaching designed elevation, and carries out pile penetration check.
7th, unload and hammer and remove pile frame into shape.
Claims (5)
1. a kind of marine steel pipe pile sinking construction technology, it is characterised in that it includes following job step:Measurement prepares, pile driving barge is in place, pile tube lifting, positioning pitching pile, fuller injection, checks absolute altitude, unloads hammer and pile frame displacement.
2. marine steel pipe pile sinking construction technology according to claim 1, it is characterised in that:The measurement preparation process includes surveying before sweeping sea, engineering and material prepares.
3. marine steel pipe pile sinking construction technology according to claim 1, it is characterised in that:The pile driving barge step in place is driven into including stake ship, GPS location and casts anchor.
4. marine steel pipe pile sinking construction technology according to claim 1, it is characterised in that:The positioning pitching pile step carries out stake position-finding using ship as reference with laser ranging instrument on ship.
5. marine steel pipe pile sinking construction technology according to claim 1, it is characterised in that:In 30~35cm of stake top laying thickness sandalwood before the fuller injection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610400100.2A CN107476271A (en) | 2016-06-08 | 2016-06-08 | A kind of marine steel pipe pile sinking construction technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610400100.2A CN107476271A (en) | 2016-06-08 | 2016-06-08 | A kind of marine steel pipe pile sinking construction technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107476271A true CN107476271A (en) | 2017-12-15 |
Family
ID=60593404
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610400100.2A Pending CN107476271A (en) | 2016-06-08 | 2016-06-08 | A kind of marine steel pipe pile sinking construction technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107476271A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114032893A (en) * | 2021-12-13 | 2022-02-11 | 湖北工业大学工程技术学院 | Pile sinking construction process for super-long inclined rock-socketed pile of offshore bearing platform |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102312436A (en) * | 2010-07-02 | 2012-01-11 | 南通市海洋水建工程有限公司 | Steel pipe pile sinking construction technology |
CN102425167A (en) * | 2011-11-25 | 2012-04-25 | 天津港航工程有限公司 | Pile sinking method for driving large-diameter steel pipe pile in intertidal zone |
CN105178316A (en) * | 2015-08-17 | 2015-12-23 | 中交第三航务工程局有限公司 | Vibrating pile-sinking pile driving barge used for global position system (GPS) overwater pile-sinking control |
-
2016
- 2016-06-08 CN CN201610400100.2A patent/CN107476271A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102312436A (en) * | 2010-07-02 | 2012-01-11 | 南通市海洋水建工程有限公司 | Steel pipe pile sinking construction technology |
CN102425167A (en) * | 2011-11-25 | 2012-04-25 | 天津港航工程有限公司 | Pile sinking method for driving large-diameter steel pipe pile in intertidal zone |
CN105178316A (en) * | 2015-08-17 | 2015-12-23 | 中交第三航务工程局有限公司 | Vibrating pile-sinking pile driving barge used for global position system (GPS) overwater pile-sinking control |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114032893A (en) * | 2021-12-13 | 2022-02-11 | 湖北工业大学工程技术学院 | Pile sinking construction process for super-long inclined rock-socketed pile of offshore bearing platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109629568A (en) | The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating | |
CN206826891U (en) | A kind of offshore wind turbine single pile pile sinking operation based on barge with deck transformation is refuted | |
CN105386408A (en) | Deep-water bridge pile foundation construction method | |
CN109853567A (en) | A kind of pile sinking process of offshore wind farm steel tube pile embeded in rock | |
CN208235570U (en) | A kind of embedding rock single pile construction system of offshore wind turbine base expanding and base expanding formula | |
CN109024525B (en) | Artificial island structure considering underground space development and utilization and construction method thereof | |
CN108532604A (en) | A kind of steady stake platform construction technique | |
CN103603364B (en) | Deepwater suction-type gravity foundation and deepwater mounting device and deepwater mounting method thereof | |
CN104631602A (en) | Construction method of pipeline in sea area for sewage deep sea disposal engineering | |
CN101200898A (en) | Construction method of drilling pile base for bare rock and shallow overburden | |
CN109853531A (en) | A kind of pile foundation construction process of cast-in-situ bored pile | |
CN103015442A (en) | Method for constructing split type cofferdam | |
CN104164886A (en) | Sinking leveling and reinforcing method for caisson | |
CN107761751A (en) | A kind of Double-Wall Steel Boxed Cofferdam and its construction method | |
CN107476271A (en) | A kind of marine steel pipe pile sinking construction technology | |
CN102991646B (en) | Manufacturing methods for gravity anchor | |
CN203583509U (en) | Deepwater suction type gravity foundation and deepwater mounting device thereof | |
CN102561454B (en) | Water intake method utilizing pipe jacking vertically | |
CN104088280A (en) | Combined construction process of pre-assembling integrated driving and splicing and separable driving of secondary cell of cellular steel sheet pile large cylinder | |
CN111119181A (en) | Pile head cutting method for underwater concrete pile construction | |
CN108677978A (en) | A kind of bridge prestressing without bondn splicing Double-Wall Steel Boxed Cofferdam sinking construction engineering method | |
CN204690772U (en) | A kind of pile foundation in deep water location, guide frame | |
CN207176709U (en) | A kind of Double-Wall Steel Boxed Cofferdam | |
CN211368838U (en) | Underwater milling groove guiding and positioning device suitable for deepwater embedded foundation | |
CN203924089U (en) | For the pile foundation of offshore wind farm facility |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20171215 |
|
WD01 | Invention patent application deemed withdrawn after publication |