A kind of bridge construction pours device with clump
Technical field
Device more particularly to a kind of bridge construction, which are poured, the present invention relates to one kind pours device with clump.
Background technique
Bridge refers generally to be erected in rivers,lakes and seas, the structures for making traffic etc. that can smoothly pass through.It is modern to adapt to
The transportation industry of high speed development, bridge be also extended to across mountain stream, unfavorable geology or meet other traffic need and set up make
Current more convenient and fast building.Bridge is generally made of superstructure, substructure, support and attached structure, top knot
Structure is also known as bridge span structure, is across the primary structure of obstacle;Substructure includes abutment, bridge pier and basis;Support is spanning knot
The load transfer device of the bearing place setting of structure and bridge pier or abutment;Attached structure then refer to transition slab at bridge head, truncated cone banking, shore protection,
Training works etc..
Building is the general name of building and structures, is people to meet social life needs, utilizes grasped object
Matter technological means, and the artificial environment created with certain scientific law, geomantic omen theory and aesthetic principle.
In bridge construction engineering, need to make clump, the manufacture craft of clump requires that cement is first poured into mould
In tool, after placing a period of time formation clump, when further taking out, and manually pouring into cement in mold, time-consuming and laborious, labour is by force
Degree is big, and during pouring mud, cement, which is easy to splash out, makes clothes dirty, thus need to research and develop it is a kind of it is time saving and energy saving, labor intensity is small,
Cement, which is not easy to splash out, makes clothes dirty, moreover it is possible to be compacted to cement, the bridge construction for improving clump quality is poured with clump
Build device.
Summary of the invention
(1) technical problems to be solved
When the present invention manually pours into cement in mold to overcome, time-consuming and laborious, large labor intensity, the process of pouring mud
In, cement is easy to splash out the shortcomings that making clothes dirty, and the technical problem to be solved in the present invention is to provide a kind of time saving and energy saving, labour by force
Spend it is small, cement be not easy splash out makes clothes dirty, moreover it is possible to cement is compacted, improve clump quality bridge construction cement
Pier pours device.
(2) technical solution
In order to solve the above-mentioned technical problems, the present invention provides such a bridge constructions to pour device with clump, packet
Bottom plate, mold, lifting device, tilting device and cement frame are included, bottom plate top left side is equipped with mold, mold bottom and base top
Portion's contact, bottom plate top right side are equipped with lifting device, and the lifting part of lifting device is equipped with tilting device, and tilting device inclines
Cement frame is connected on component, cement frame is located on the right side of mold.
Preferably, lifting device includes riser, the first sliding block, the first sliding rail, transverse slat, bracing wire and electronic reel, bottom
Plate top right side is equipped with riser, is equipped with the first sliding rail on the left of riser, the first sliding rail in being vertically arranged, the first sliding rail be equipped with
Its first sliding block cooperated, the first sliding block are slidably matched with the first sliding rail, and the first sliding block right side and riser left side lower part connect
It connects, the first sliding rail left side lower part is equipped with transverse slat, connect at the top of transverse slat with tilting device, is equipped with electronic coiling at the top of riser
It takes turns, is wound with bracing wire on electronic reel, bracing wire tail end is connect with the first sliding rail top center.
Preferably, tilting device includes first motor, screw rod, nut, connecting rope, bearing block, fixed block and supporting block,
Transverse slat top left side is equipped with fixed block, is equipped with supporting block, supporting block top at the top of fixed block in such a way that pin shaft connects
It is connect with cement outer frame bottom left, the first sliding rail left side is fitted with bearing block in two sides up and down, is connected between bearing block
Screw rod is equipped with nut on screw rod, and nut left side is connected with connecting rope, and connecting rope tail end and cement outer frame right side lower part connect
It connects, the first sliding rail left side lower part is equipped with first motor, and for first motor in being vertically arranged, the output shaft of first motor passes through connection
Axis device is connect with screw rod bottom end.
It preferably, further include having compaction apparatus, compaction apparatus includes 7 templates, sector gear, the second sliding rail, the second cunning
Block, rack gear, the first spring, vertical bar, the second motor and compression bar, bottom plate top left side are equipped with 7 templates, and 7 templates are located at a mold left side
Side, left side top is equipped with the second sliding rail in 7 templates, and in being vertically arranged, the second sliding rail is equipped with to be cooperated the second sliding rail with it
The second sliding block, the second sliding block is slidably matched with the second sliding rail, and the second sliding block right side is equipped with rack gear, and rack gear bottom is equipped with
Compression bar, compression bar are located in mold, and the first spring, peace on the right side of 7 template inner tops are connected at the top of rack gear and among 7 template inner tops
Equipped with vertical bar, vertical bar bottom end is equipped with the second motor, and the output shaft of the second motor is connected with sector gear by shaft coupling, fan-shaped
Gear is located on the right side of rack gear, and sector gear is engaged with rack.
It preferably, further include having shaking device, shaking device includes third sliding rail, third sliding block, fixed plate, the second bullet
Spring, cross bar, contact roller, connecting rod, third motor and cam, bottom plate top left side are equipped with third sliding rail, and third sliding rail is in water
Flat setting, third sliding rail are equipped with third sliding block engaged therewith, and third sliding block is slidably matched with third sliding rail, and mold bottom is also
It can be connect with third slider top, third sliding block right side top is equipped with cross bar, and cross bar right end is equipped with contact roller, bottom
Plate top left side is equipped with connecting rod, and connecting rod is located on the right side of third sliding rail, and connecting rod top is equipped with third motor, third motor it is defeated
Shaft is connected with cam by shaft coupling, and cam is located on the right side of contact roller, and bottom plate top left side is equipped with fixed plate, fixed plate
Between 7 templates and third sliding rail, second spring is connected between fixed plate right side top and third sliding block left side.
It preferably, further include having shaft, telescopic rod, link block and weight block, right side top, which is equipped with, in cement frame turns
Axis, is equipped with telescopic rod in shaft, and telescopic rod bottom end is equipped with link block, and link block bottom is equipped with weight block, weight block with
Bottom contacts in cement frame.
It preferably, further include having water tank, water pump, outlet pipe and spray head, bottom plate top right side is equipped with water tank, and water tank is located at
On the right side of riser, water pump is installed among bottom in water tank, outlet pipe is connected on water pump, outlet pipe tail end is in tank top
Between be located on the left of electronic reel, outlet pipe tail end is equipped with spray head, spray head with outlet pipe is interior is connected to, spray head is located on cement frame
Side.
Preferably, the material of bottom plate is Q235 steel.
Preferably, the material of cement frame is stainless steel.
Working principle: being operated first personnel and pour into cement in cement frame, restarts lifting device, the lifting of lifting device
Component drives tilting device to move up, and then cement frame is driven to move up, when cement frame is moved up positioned at mold upper right
Fang Shi closes lifting device, starts tilting device, tilting device is by cement frame inclining, and then the cement in cement frame pours into mould
In tool.After cement all pours into mold, cement frame is moved to original position by starting tilting device, closes tilting device, and starting rises
The lifting part of falling unit drives cement frame to move down recovery to original position, closes lifting device.When the cement in mold is formed
After clump, clump can be taken out.
Because lifting device includes riser, the first sliding block, the first sliding rail, transverse slat, bracing wire and electronic reel, base top
Riser is installed on the right side of portion, the first sliding rail is equipped on the left of riser, in being vertically arranged, the first sliding rail is equipped with matches the first sliding rail with it
The first sliding block closed, the first sliding block are slidably matched with the first sliding rail, and the first sliding block right side is connect with riser left side lower part, the
One sliding rail left side lower part is equipped with transverse slat, connect at the top of transverse slat with tilting device, is equipped with electronic reel at the top of riser, electricity
It is wound with bracing wire on dynamic reel, bracing wire tail end is connect with the first sliding rail top center, when cement is located in cement frame, operator
Member can start electronic reel and rotate forward, and then bracing wire pulls the first sliding rail to move up, and it is horizontal that the first sliding rail moves up drive
Plate moves up, and then drives cement frame to move up by tilting device, when cement frame is located at mold upper right side, closes electricity
Dynamic reel, can start tilting device and pour into cement in mold.When cement is located in mold, electronic reel can be started
It rotates forward, and then transverse slat drives cement frame to move down recovery to original position, closes electronic reel.
Because tilting device includes first motor, screw rod, nut, connecting rope, bearing block, fixed block and supporting block, cross
Plate top left side is equipped with fixed block, is equipped with supporting block at the top of fixed block in such a way that pin shaft connects, at the top of supporting block with
The connection of cement outer frame bottom left, the first sliding rail left side are fitted with bearing block in two sides up and down, are connected with silk between bearing block
Bar is equipped with nut on screw rod, and nut left side is connected with connecting rope, and connecting rope tail end and cement outer frame right side lower part connect
It connects, the first sliding rail left side lower part is equipped with first motor, and for first motor in being vertically arranged, the output shaft of first motor passes through connection
Axis device is connect with screw rod bottom end, and when cement frame is located at mold upper right side, operator can start first motor and rotate forward, and first
Motor, which rotates forward, drives screw rod to rotate forward, and screw rod, which rotates forward, drives nut to move up, and nut moves upwardly through connecting rope and drives cement
Frame inclining, and then the cement in cement frame is fallen in mold.After cement all pours into mold, starting first motor is anti-
Turn, and then cement frame is driven to move down recovery to original position, closes first motor.
Because further including having compaction apparatus, compaction apparatus include 7 templates, sector gear, the second sliding rail, the second sliding block,
Rack gear, the first spring, vertical bar, the second motor and compression bar, bottom plate top left side are equipped with 7 templates, and 7 templates are located on the left of mold, and 7
Left side top is equipped with the second sliding rail in template, and for the second sliding rail in being vertically arranged, the second sliding rail is equipped with engaged therewith the
Two sliding blocks, the second sliding block are slidably matched with the second sliding rail, and the second sliding block right side is equipped with rack gear, and rack gear bottom is equipped with pressure
Bar, compression bar are located in mold, and the first spring, installation on the right side of 7 template inner tops are connected at the top of rack gear and among 7 template inner tops
There is vertical bar, vertical bar bottom end is equipped with the second motor, and the output shaft of the second motor is connected with sector gear, sector by shaft coupling
Wheel is located on the right side of rack gear, and sector gear is engaged with rack, and when cement is located in mold, operator can start the second motor
Rotation, the rotation of the second motor drive sector gear rotation, and because of the effect of the first spring, sector gear rotation band carry-over bar moves up and down
Dynamic, the second sliding rail play the guiding role with the second sliding block, and rack gear, which moves up and down, drives compression bar to move up and down, and compression bar is moved up and down to mould
Cement in tool is compacted.After cement compacting, the second motor is closed, and compression bar is made to be moved to original position.In this way, to water
Clump after mud progress compactioncan forms cement is more solid.
Because further including having shaking device, shaking device include third sliding rail, third sliding block, fixed plate, second spring,
Cross bar, contact roller, connecting rod, third motor and cam, bottom plate top left side are equipped with third sliding rail, and third sliding rail is set in level
It sets, third sliding rail is equipped with third sliding block engaged therewith, and third sliding block is slidably matched with third sliding rail, and mold bottom can be with
It is connect with third slider top, third sliding block right side top is equipped with cross bar, and cross bar right end is equipped with contact roller, base top
Connecting rod is installed, connecting rod is located on the right side of third sliding rail, and connecting rod top is equipped with third motor, the output shaft of third motor on the left of portion
It is connected with cam by shaft coupling, cam is located on the right side of contact roller, and bottom plate top left side is equipped with fixed plate, and fixed plate is located at
Between 7 templates and third sliding rail, it is connected with second spring between fixed plate right side top and third sliding block left side, works as compression bar
While being compacted to cement, starting third motor rotation, third motor rotation band moving cam is rotated, and cam is rotated and connect
Idler wheel contact is touched, because of the effect of second spring, and then cam driven contact roller moves left and right, and contact roller moves left and right drive
Third sliding block moves left and right, and third sliding block moves left and right driven mold and moves left and right, and mold, which moves left and right, shakes cement, in turn
It is compacted compression bar preferably to cement.After cement compacting, third motor is closed.In this way, cement is shaken,
Compression bar can be made preferably to be compacted to cement, it is further more solid.
Because further including having shaft, telescopic rod, link block and weight block, right side top is equipped with shaft in cement frame,
Telescopic rod is installed, telescopic rod bottom end is equipped with link block, and link block bottom is equipped with weight block, weight block and cement in shaft
Bottom contacts in frame, when cement frame inclining, because gravity influences, and weight block also slide downward, and then telescopic rod constantly extends, weight
Object block, which moves down, pushes the cement in cement frame.When cement is entirely located in mold, weight block is restored again to original
Position.In this way, weight block pushes cement, cement can be accelerated and fallen in mold, and then improve working efficiency.
Because further including having water tank, water pump, outlet pipe and spray head, bottom plate top right side is equipped with water tank, and water tank is located at perpendicular
On the right side of plate, water pump is installed among bottom in water tank, outlet pipe is connected on water pump, outlet pipe tail end is among tank top
On the left of electronic reel, outlet pipe tail end is equipped with spray head, is connected in spray head and outlet pipe, spray head is located on cement frame
, there is suitable water in side when initial, in water tank, after cement frame restores to original position, operator can start water pump, and water pump is by water
Water in case is pumped into outlet pipe, and then the water in outlet pipe is sprayed by spray head, and water ejection in cement frame to cleaning.When
After cement frame is cleaned, switch off the pump.In this way, cleaning to cement frame can enable cement frame preferably use next time.
Because the material of bottom plate is Q235 steel, the load-bearing capacity of Q235 steel is strong, acidproof corrosion-resistant, increases the use of bottom plate
Service life.
Because the material of cement frame is stainless steel, stainless steel corrosion resistance and acid resistance are strong, make the service life of cement frame
It is longer.
(3) beneficial effect
The present invention is compacted cement by compression bar, and then improves the quality of clump, meanwhile, also improve work
Efficiency, has reached that time saving and energy saving, labor intensity is small, and cement is not easy to splash out makes clothes dirty, moreover it is possible to be compacted, improve to cement
The effect of clump quality.
Detailed description of the invention
Fig. 1 is schematic view of the front view of the invention.
Fig. 2 is the schematic view of the front view of lifting device of the present invention.
Fig. 3 is the schematic view of the front view of tilting device of the present invention.
Fig. 4 is the schematic view of the front view of compaction apparatus of the present invention.
Fig. 5 is the schematic view of the front view of shaking device of the present invention.
Fig. 6 is the first part schematic view of the front view of the invention.
Fig. 7 is second of part schematic view of the front view of the invention.
The label in accompanying drawing is: 1- bottom plate, 2- mold, 3- lifting device, 31- riser, the first sliding block of 32-, 33- first are sliding
Rail, 34- transverse slat, 35- bracing wire, the electronic reel of 36-, 4- tilting device, 41- first motor, 42- screw rod, 43- nut, 44- connect
Splicing, 45- bearing block, 46- fixed block, 47- supporting block, 5- cement frame, 6- compaction apparatus, 61-7 template, 62- sector gear,
The second sliding rail of 63-, the second sliding block of 64-, 65- rack gear, the first spring of 66-, 67- vertical bar, the second motor of 68-, 69- compression bar, 7- shake
Dynamic device, 71- third sliding rail, 72- third sliding block, 73- fixed plate, 74- second spring, 75- cross bar, 76- contact roller, 77-
Connecting rod, 78- third motor, 79- cam, 8- shaft, 9- telescopic rod, 10- link block, 11- weight block, 12- water tank, 13- water pump,
14- outlet pipe, 15- spray head.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment 1
A kind of bridge construction pours device with clump, as shown in figs. 1-7, include bottom plate 1, mold 2, lifting device 3,
Tilting device 4 and cement frame 5,1 top left side of bottom plate are equipped with mold 2, contact at the top of 2 bottom of mold and bottom plate 1,1 top of bottom plate
Right side is equipped with lifting device 3, and the lifting part of lifting device 3 is equipped with tilting device 4, connects on the dumping part of tilting device 4
It is connected to cement frame 5, cement frame 5 is located at 2 right side of mold.
Embodiment 2
A kind of bridge construction pours device with clump, as shown in figs. 1-7, include bottom plate 1, mold 2, lifting device 3,
Tilting device 4 and cement frame 5,1 top left side of bottom plate are equipped with mold 2, contact at the top of 2 bottom of mold and bottom plate 1,1 top of bottom plate
Right side is equipped with lifting device 3, and the lifting part of lifting device 3 is equipped with tilting device 4, connects on the dumping part of tilting device 4
It is connected to cement frame 5, cement frame 5 is located at 2 right side of mold.
Lifting device 3 includes riser 31, the first sliding block 32, the first sliding rail 33, transverse slat 34, bracing wire 35 and electronic reel
36,1 top right side of bottom plate is equipped with riser 31, and the first sliding rail 33 is equipped on the left of riser 31, and the first sliding rail 33 is in be vertically arranged, the
One sliding rail 33 is equipped with the first sliding block 32 engaged therewith, and the first sliding block 32 is slidably matched with the first sliding rail 33, the first sliding block 32
Right side is connect with 31 left side lower part of riser, and 33 left side lower part of the first sliding rail is equipped with transverse slat 34,34 top of transverse slat with incline
Focusing device 4 connects, and is equipped with electronic reel 36 at the top of riser 31, bracing wire 35,35 tail end of bracing wire are wound on electronic reel 36
It is connect with 33 top center of the first sliding rail.
Embodiment 3
A kind of bridge construction pours device with clump, as shown in figs. 1-7, include bottom plate 1, mold 2, lifting device 3,
Tilting device 4 and cement frame 5,1 top left side of bottom plate are equipped with mold 2, contact at the top of 2 bottom of mold and bottom plate 1,1 top of bottom plate
Right side is equipped with lifting device 3, and the lifting part of lifting device 3 is equipped with tilting device 4, connects on the dumping part of tilting device 4
It is connected to cement frame 5, cement frame 5 is located at 2 right side of mold.
Lifting device 3 includes riser 31, the first sliding block 32, the first sliding rail 33, transverse slat 34, bracing wire 35 and electronic reel
36,1 top right side of bottom plate is equipped with riser 31, and the first sliding rail 33 is equipped on the left of riser 31, and the first sliding rail 33 is in be vertically arranged, the
One sliding rail 33 is equipped with the first sliding block 32 engaged therewith, and the first sliding block 32 is slidably matched with the first sliding rail 33, the first sliding block 32
Right side is connect with 31 left side lower part of riser, and 33 left side lower part of the first sliding rail is equipped with transverse slat 34,34 top of transverse slat with incline
Focusing device 4 connects, and is equipped with electronic reel 36 at the top of riser 31, bracing wire 35,35 tail end of bracing wire are wound on electronic reel 36
It is connect with 33 top center of the first sliding rail.
Tilting device 4 includes first motor 41, screw rod 42, nut 43, connecting rope 44, bearing block 45,46 and of fixed block
Supporting block 47,34 top left side of transverse slat are equipped with fixed block 46, and 46 top of fixed block is equipped with branch in such a way that pin shaft connects
Bracer 47,47 top of supporting block and 5 outer bottom of cement frame left side are connect, and 33 left side of the first sliding rail is fitted with axis in two sides up and down
Seat 45 is held, screw rod 42 is connected between bearing block 45, nut 43 is installed on screw rod 42,43 left side of nut is connected with connecting rope
44,44 tail end of connecting rope is connect with 5 external right side face lower part of cement frame, and 33 left side lower part of the first sliding rail is equipped with first motor
41, in being vertically arranged, the output shaft of first motor 41 is connect by shaft coupling with 42 bottom end of screw rod first motor 41.
Embodiment 4
A kind of bridge construction pours device with clump, as shown in figs. 1-7, include bottom plate 1, mold 2, lifting device 3,
Tilting device 4 and cement frame 5,1 top left side of bottom plate are equipped with mold 2, contact at the top of 2 bottom of mold and bottom plate 1,1 top of bottom plate
Right side is equipped with lifting device 3, and the lifting part of lifting device 3 is equipped with tilting device 4, connects on the dumping part of tilting device 4
It is connected to cement frame 5, cement frame 5 is located at 2 right side of mold.
Lifting device 3 includes riser 31, the first sliding block 32, the first sliding rail 33, transverse slat 34, bracing wire 35 and electronic reel
36,1 top right side of bottom plate is equipped with riser 31, and the first sliding rail 33 is equipped on the left of riser 31, and the first sliding rail 33 is in be vertically arranged, the
One sliding rail 33 is equipped with the first sliding block 32 engaged therewith, and the first sliding block 32 is slidably matched with the first sliding rail 33, the first sliding block 32
Right side is connect with 31 left side lower part of riser, and 33 left side lower part of the first sliding rail is equipped with transverse slat 34,34 top of transverse slat with incline
Focusing device 4 connects, and is equipped with electronic reel 36 at the top of riser 31, bracing wire 35,35 tail end of bracing wire are wound on electronic reel 36
It is connect with 33 top center of the first sliding rail.
Tilting device 4 includes first motor 41, screw rod 42, nut 43, connecting rope 44, bearing block 45,46 and of fixed block
Supporting block 47,34 top left side of transverse slat are equipped with fixed block 46, and 46 top of fixed block is equipped with branch in such a way that pin shaft connects
Bracer 47,47 top of supporting block and 5 outer bottom of cement frame left side are connect, and 33 left side of the first sliding rail is fitted with axis in two sides up and down
Seat 45 is held, screw rod 42 is connected between bearing block 45, nut 43 is installed on screw rod 42,43 left side of nut is connected with connecting rope
44,44 tail end of connecting rope is connect with 5 external right side face lower part of cement frame, and 33 left side lower part of the first sliding rail is equipped with first motor
41, in being vertically arranged, the output shaft of first motor 41 is connect by shaft coupling with 42 bottom end of screw rod first motor 41.
It further include having compaction apparatus 6, compaction apparatus 6 includes 7 templates 61, sector gear 62, the second sliding rail 63, second cunning
Block 64, rack gear 65, the first spring 66, vertical bar 67, the second motor 68 and compression bar 69,1 top left side of bottom plate are equipped with 7 templates 61,7
Template 61 is located at 2 left side of mold, and left side top is equipped with the second sliding rail 63 in 7 templates 61, and the second sliding rail 63 is in be vertically arranged,
Second sliding rail 63 is equipped with the second sliding block 64 engaged therewith, and the second sliding block 64 is slidably matched with the second sliding rail 63, the second sliding block
64 right sides are equipped with rack gear 65, and 65 bottom of rack gear is equipped with compression bar 69, and compression bar 69 is located in mold 2,65 top of rack gear and 7 types
It is connected among 61 inner top of plate on the right side of 61 inner top of the first 66,7 template of spring and vertical bar 67 is installed, 67 bottom end of vertical bar is equipped with
The output shaft of second motor 68, the second motor 68 is connected with sector gear 62 by shaft coupling, and sector gear 62 is located at rack gear 65
Right side, sector gear 62 are engaged with rack gear 65.
It further include having shaking device 7, shaking device 7 includes third sliding rail 71, third sliding block 72, fixed plate 73, second
Spring 74, cross bar 75, contact roller 76, connecting rod 77, third motor 78 and cam 79, it is sliding that 1 top left side of bottom plate is equipped with third
Rail 71, for third sliding rail 71 in horizontally disposed, third sliding rail 71 is equipped with third sliding block 72 engaged therewith, third sliding block 72 and the
Three sliding rails 71 are slidably matched, 2 bottom of mold can also with connected at the top of third sliding block 72,72 right side top of third sliding block installation
There is cross bar 75,75 right end of cross bar is equipped with contact roller 76, and 1 top left side of bottom plate is equipped with connecting rod 77, and connecting rod 77 is located at third
71 right side of sliding rail, 77 top of connecting rod are equipped with third motor 78, and the output shaft of third motor 78 is connected with cam by shaft coupling
79, cam 79 is located at the right side of contact roller 76, and 1 top left side of bottom plate is equipped with fixed plate 73, fixed plate 73 be located at 7 templates 61 with
Between third sliding rail 71, second spring 74 is connected between 73 right side top of fixed plate and 72 left side of third sliding block.
It further include having shaft 8, telescopic rod 9, link block 10 and weight block 11, right side top, which is equipped with, in cement frame 5 turns
Axis 8 is equipped with telescopic rod 9 in shaft 8, and 9 bottom end of telescopic rod is equipped with link block 10, and 10 bottom of link block is equipped with weight block
11, weight block 11 is contacted with bottom in cement frame 5.
It further include having water tank 12, water pump 13, outlet pipe 14 and spray head 15,1 top right side of bottom plate is equipped with water tank 12, water tank
12 are located at 31 right side of riser, are equipped with water pump 13 among bottom in water tank 12, outlet pipe 14, outlet pipe 14 are connected on water pump 13
Tail end is located at 36 left side of electronic reel through 12 top center of water tank, and 14 tail end of outlet pipe is equipped with spray head 15, spray head 15 with
Connection in outlet pipe 14, spray head 15 are located at 5 top of cement frame.
The material of bottom plate 1 is Q235 steel.
The material of cement frame 5 is stainless steel.
Working principle: being operated first personnel and pour into cement in cement frame 5, restarts lifting device 3, lifting device 3
Lifting part drives tilting device 4 to move up, and then cement frame 5 is driven to move up, when cement frame 5 is moved up positioned at mould
When having 2 upper right side, lifting device 3 is closed, starts tilting device 4, tilting device 4 tilts cement frame 5, and then in cement frame 5
Cement pour into mold 2.After cement all pours into mold 2, starts tilting device 4 for cement frame 5 and be moved to original position, close
Tilting device 4, the lifting part of starting lifting device 3 drive cement frame 5 to move down recovery to original position, close lifting device 3.
After the cement in mold 2 forms clump, clump can be taken out.
Because lifting device 3 include riser 31, the first sliding block 32, the first sliding rail 33, transverse slat 34, bracing wire 35 and it is electronic around
Line wheel 36,1 top right side of bottom plate are equipped with riser 31, and the first sliding rail 33 is equipped on the left of riser 31, and the first sliding rail 33 is in set vertically
It sets, the first sliding rail 33 is equipped with the first sliding block 32 engaged therewith, and the first sliding block 32 is slidably matched with the first sliding rail 33, and first is sliding
32 right side of block is connect with 31 left side lower part of riser, and 33 left side lower part of the first sliding rail is equipped with transverse slat 34,34 top of transverse slat
It is connect with tilting device 4, electronic reel 36 is installed at the top of riser 31, bracing wire 35, bracing wire 35 are wound on electronic reel 36
Tail end is connect with 33 top center of the first sliding rail, and when cement is located in cement frame 5, operator can start electronic reel
36 rotate forward, and then bracing wire 35 pulls the first sliding rail 33 to move up, and the first sliding rail 33 moves up band motion plate 34 and moves up,
And then drive cement frame 5 to move up by tilting device 4, when cement frame 5 is located at 2 upper right side of mold, close electronic coiling
Wheel 36, can start tilting device 4 and pour into cement in mold 2.When cement is located in mold 2, electronic reel can be started
36 rotate forward, and then transverse slat 34 drives cement frame 5 to move down recovery to original position, closes electronic reel 36.
Because tilting device 4 includes first motor 41, screw rod 42, nut 43, connecting rope 44, bearing block 45, fixed block
46 and supporting block 47,34 top left side of transverse slat is equipped with fixed block 46, and 46 top of fixed block is installed in such a way that pin shaft connects
There is supporting block 47, is connect on the left of 47 top of supporting block and 5 outer bottom of cement frame, 33 left side of the first sliding rail is all installed two sides up and down
There is bearing block 45, screw rod 42 is connected between bearing block 45, nut 43 is installed on screw rod 42,43 left side of nut is connected with
Splicing 44,44 tail end of connecting rope are connect with 5 external right side face lower part of cement frame, and 33 left side lower part of the first sliding rail is equipped with the first electricity
Machine 41, in being vertically arranged, the output shaft of first motor 41 is connect by shaft coupling with 42 bottom end of screw rod first motor 41, works as cement
When frame 5 is located at 2 upper right side of mold, operator can start the rotating forward of first motor 41, and first motor 41, which rotates forward, drives screw rod 42
It rotating forward, screw rod 42, which rotates forward, drives nut 43 to move up, and nut 43 moves upwardly through connecting rope 44 and cement frame 5 is driven to tilt,
And then the cement in cement frame 5 is fallen in mold 2.After cement all pours into mold 2, starting first motor 41 is inverted,
And then cement frame 5 is driven to move down recovery to original position, close first motor 41.
Because further including having compaction apparatus 6, compaction apparatus 6 includes 7 templates 61, sector gear 62, the second sliding rail 63,
Two sliding blocks 64, rack gear 65, the first spring 66, vertical bar 67, the second motor 68 and compression bar 69,1 top left side of bottom plate are equipped with 7 templates
61,7 templates 61 are located at 2 left side of mold, and left side top is equipped with the second sliding rail 63 in 7 templates 61, and the second sliding rail 63 is in vertical
Setting, the second sliding rail 63 are equipped with the second sliding block 64 engaged therewith, and the second sliding block 64 is slidably matched with the second sliding rail 63, and second
64 right side of sliding block is equipped with rack gear 65, and 65 bottom of rack gear is equipped with compression bar 69, and compression bar 69 is located in mold 2,65 top of rack gear
Vertical bar 67,67 bottom end of vertical bar are installed with being connected on the right side of 61 inner top of the first 66,7 template of spring among 7 template, 61 inner top
Second motor 68 is installed, the output shaft of the second motor 68 is connected with sector gear 62 by shaft coupling, and sector gear 62 is located at
65 right side of rack gear, sector gear 62 is engaged with rack gear 65, and when cement is located in mold 2, operator can start the second electricity
Machine 68 rotates, and the rotation of the second motor 68 drives sector gear 62 to rotate, and because of the effect of the first spring 66, sector gear 62 rotates band
Carry-over bar 65 moves up and down, and the second sliding rail 63 play the guiding role with the second sliding block 64, and rack gear 65, which moves up and down, to be driven on compression bar 69
Lower movement, compression bar 69, which moves up and down, is compacted the cement in mold 2.After cement compacting, the second motor 68 is closed, and make
Compression bar 69 is moved to original position.In this way, the clump after forming cement cement progress compactioncan is more solid.
Because further including having shaking device 7, shaking device 7 include third sliding rail 71, third sliding block 72, fixed plate 73,
Second spring 74, cross bar 75, contact roller 76, connecting rod 77, third motor 78 and cam 79,1 top left side of bottom plate are equipped with
Three sliding rails 71, for third sliding rail 71 in being horizontally disposed with, third sliding rail 71 is equipped with third sliding block 72 engaged therewith, third sliding block 72
Be slidably matched with third sliding rail 71,2 bottom of mold can also with connected at the top of third sliding block 72,72 right side top of third sliding block
Cross bar 75 is installed, 75 right end of cross bar is equipped with contact roller 76, and 1 top left side of bottom plate is equipped with connecting rod 77, and connecting rod 77 is located at
71 right side of third sliding rail, 77 top of connecting rod are equipped with third motor 78, and the output shaft of third motor 78 is connected with by shaft coupling
Cam 79, cam 79 are located at 76 right side of contact roller, and 1 top left side of bottom plate is equipped with fixed plate 73, and fixed plate 73 is located at 7 templates
Between 61 and third sliding rail 71, it is connected with second spring 74 between 73 right side top of fixed plate and 72 left side of third sliding block,
When compression bar 69 is while being compacted cement, starting third motor 78 is rotated, and 79 turns of moving cam of band of the rotation of third motor 78
Dynamic, the rotation of cam 79 is contacted with contact roller 76, and because of the effect of second spring 74, and then cam 79 drives contact roller 76 or so
Mobile, contact roller 76, which moves left and right, drives third sliding block 72 to move left and right, and third sliding block 72 moves left and right driven mold 2 or so
Mobile, mold 2, which moves left and right, shakes cement, and then is compacted compression bar 69 preferably to cement.After cement compacting, close
Close third motor 78.In this way, shaking to cement, compression bar 69 can be made preferably to be compacted to cement, further
It is more solid.
Because further including having shaft 8, telescopic rod 9, link block 10 and weight block 11, right side top is installed in cement frame 5
There is shaft 8, telescopic rod 9 is installed in shaft 8,9 bottom end of telescopic rod is equipped with link block 10, and 10 bottom of link block is equipped with weight
Block 11, weight block 11 are contacted with bottom in cement frame 5, and when cement frame 5 tilts, because gravity influences, weight block 11 is also to downslide
It is dynamic, and then telescopic rod 9 constantly extends, weight block 11, which moves down, pushes the cement in cement frame 5.When cement whole position
When in mold 2, weight block 11 is restored again to original position.In this way, weight block 11 pushes cement, cement can be accelerated and fallen to
In mold 2, and then improve working efficiency.
Because further including having water tank 12, water pump 13, outlet pipe 14 and spray head 15,1 top right side of bottom plate is equipped with water tank 12,
Water tank 12 is located at 31 right side of riser, is equipped with water pump 13 among bottom in water tank 12, outlet pipe 14 is connected on water pump 13, is discharged
14 tail end of pipe is located at electronic 36 left side of reel through 12 top center of water tank, and 14 tail end of outlet pipe is equipped with spray head 15, spray head
15 be connected in outlet pipe 14, spray head 15 is located above cement frame 5, when initial, there is suitable water in water tank 12, when cement frame 5
Restore to original position, operator can start water pump 13, and the water in water tank 12 is pumped into outlet pipe 14 by water pump 13, and then is gone out
Water in water pipe 14 is sprayed by spray head 15, and water is sprayed to cleaning in cement frame 5.After cement frame 5 is cleaned, water is closed
Pump 13.In this way, cleaning to cement frame 5 can enable cement frame preferably use for 5 next time.
Because the material of bottom plate 1 is Q235 steel, the load-bearing capacity of Q235 steel is strong, acidproof corrosion-resistant, increases making for bottom plate 1
Use the service life.
Because the material of cement frame 5 is stainless steel, stainless steel corrosion resistance and acid resistance are strong, and make cement frame 5 uses the longevity
It orders longer.
The preferred embodiment of the present invention above described embodiment only expresses, the description thereof is more specific and detailed, but simultaneously
Limitations on the scope of the patent of the present invention therefore cannot be interpreted as.It should be pointed out that for those of ordinary skill in the art
For, without departing from the inventive concept of the premise, several deformations can also be made, improves and substitutes, these belong to this hair
Bright protection scope.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.