CN107461198A - The construction method that EBZ160 development machines acute angle is turned - Google Patents

The construction method that EBZ160 development machines acute angle is turned Download PDF

Info

Publication number
CN107461198A
CN107461198A CN201710819162.1A CN201710819162A CN107461198A CN 107461198 A CN107461198 A CN 107461198A CN 201710819162 A CN201710819162 A CN 201710819162A CN 107461198 A CN107461198 A CN 107461198A
Authority
CN
China
Prior art keywords
development machine
machine
construction
development
cut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710819162.1A
Other languages
Chinese (zh)
Inventor
李存禄
范吉宏
高敬东
李国辉
孙玉超
孙成强
徐国华
杨尊胜
方志明
崔红启
解孝华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Dongshan Xinyi Coal Mine Co Ltd
Original Assignee
Shandong Dongshan Xinyi Coal Mine Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Dongshan Xinyi Coal Mine Co Ltd filed Critical Shandong Dongshan Xinyi Coal Mine Co Ltd
Priority to CN201710819162.1A priority Critical patent/CN107461198A/en
Publication of CN107461198A publication Critical patent/CN107461198A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Abstract

The technical scheme for the construction method turned the invention provides EBZ160 development machines acute angle, before construction, first modeling is made according to tunnel and development machine parameter on CAD to turn, the related data of tunnel turning is determined by demonstrating, in analog demenstration, surplus coefficiert is reserved apart from lane side, to ensure that development machine rear molding does not scratch lane side.When development machine walks cut, supporting must be closelyed follow and met head on, often moved ahead by development machine 3m when development machine the amplitude of oscillation determine subsequent cycle cut scope, when cut to bend becomes anxious section, walking step pitch can suitably be shortened, reduce development machine to move back, put machine number, specific cut walking step pitch can be depending on live physical condition.When development machine reaches the maximum amplitude of oscillation, the bearing pin connection between development machine and two fortune need to be changed to be flexible coupling.The present invention opens the door to construct for tunnel provides a kind of new construction method, has more widened the use range of development machine, has enhanced adaptability of the development machine to field condition.

Description

The construction method that EBZ160 development machines acute angle is turned
Technical field
The present invention relates to the construction method that EBZ160 development machines acute angle is turned.
Background technology
1st, my ore deposit tunnel open the door, tunneling construction when, constructed using the raking loader of rope traction, according to my ore deposit in 2016 3 coal coal dust explosion hazard qualification results are 40.5%, have coal dust explosion hazard.And safety regulations in coal mine the 61st article (Seven)Item clear stipulaties:High methane, coal and gas prominent and there are the coal road of coal dust explosion hazard mine, half-coal rock roadway headwork Face and stone door punching coal working face, forbid to construct using the raking loader of rope traction, therefore currently employed rope traction Raking loader construction technology has not met the construction requirement of my ore deposit;
2nd, tunnel is opened the door according to artificial, and not only labor intensity is big, and efficiency of construction is slow, and enabling technology is original, falls behind, with working as Preceding industrial technology development is not consistent;
3rd, either raking loader waist rope opens the door or manually opened the door, and is both needed to blow out construction, the lane for especially having coal dust explosion hazard Road is constructed, and its hidden danger degree and disaster accident incidence are higher, and overall safety coefficient of production is relatively low." the peace carried out with mine The work safety policies of complete first, put prevention first, the comprehensive regulation " are not consistent;
4th, because development machine own dimensions and construction site condition limit, it is always the difficulty for influenceing speedy drivage that tunnel, which is turned round, Point is more using auxiliary preparation measures before construction.At present, the domestic technology for having construction of being turned round using development machine obtuse angle, it is but not sharp Angle tunnel is completely using development machine and not against the precedent and technology of the enabling construction of other auxiliary equipments.
The content of the invention
The technical problems to be solved by the invention, aiming at the deficiency present in prior art, and provide EBZ160 picks Enter the construction method technical scheme of machine acute angle turning.
This programme is achieved by the following technical measures:The construction method that EBZ160 development machines acute angle is turned, including Following construction procedure,
Step 1, min. turning radius is determined, learnt according to EBZ160 development machine related datas, EBZ160 development machines are minimum to turn Radius is 6.5m, and when determining that min. turning radius 6.5m turns, now the roof span at turning is minimum;
Step 2, Theoretical Design simulation is turned, and before construction, first makes modeling according to tunnel and development machine parameter on CAD Turn, determine the related data of tunnel turning by demonstrating, in analog demenstration, surplus coefficiert is reserved apart from lane side, to protect Card development machine rear molding does not scratch lane side;
Step 3,1511 skins, from the straight lane construction of side opening position is split, side construction are split after permanent support along meeting head on;
Step 4, when 1511 skins cut eye along construction to 1511 leads the left side of cave, development machine steps back 10m, and reserved 1511, which cut eye, leads cave Enabling mouth, and the floor level clicked here plays bottom, horizontal sliding, it is ensured that the floor level in the range of the 10m of development machine turning is same Absolute altitude platform;
Step 5,1511, which cut eye, leads cave self-opening door position, and construction of being turned round in the form of splitting side, it is 1m to split side cyclic advance, because turning It is curved cause 1511 cut eye lead cave it is right side construction less than place, constructed in step 10;
Step 6, prepared before being turned round for development machine;
Step 7, the mode for taking development machine to turn around realize flipper turn;
Step 8, the connection bearing pin between development machine and two fortune belts is changed to be flexible coupling;
Step 9, big swing angle continue to construct;
Step 10, adjustment turn direction, eye is cut by do not constructed in the original step 5 of cutterhead cut construction 1511 Cave bottom right side corner is led, eye is cut by 1511 and leads cave and meet head on that brush is neat, centering;
Step 11, development machine centering continue to construct forward after meeting head on, until the two anti-sides of fortune belt holder;
Step 12, dismounting are flexible coupling, and lay a 40T scraper-trough conveyer transshipment;
Step 13, belt transfer is transported using development machine heel two, the mode that two fortune belts ride 40T scraper-trough conveyers is constructed, so far, scene Construction enters normal cyclic, and development machine acute angle turn construction terminates.
Further improvement of the present invention also has, and in the step 3,1511 skins start to split side opening position certainly along meeting head on, and first press Normal cyclic drilling depth constructs 1511 skins along just meeting head on, after top plate and 1511 skins are along left side permanent support, then it is direct using cutterhead The mode of cut splits side construction, and every meter of cyclic advance is split side cut face and tiltedly faced directly into one from starting point to side end is split when splitting side.
Further improvement of the present invention also has, and in the step 6, is most put on when the fortune belt construction of development machine band two reaches During width, machine is moved back, shovel board of development machine front end is cut eye to 1511 and leads at cave enabling mouth, and adjusts development machine again, makes development machine left , along left side, the preparation before development machine turn construction is carried out against 1511 skins in side.
Further improvement of the present invention also has, and in the step 7, tunneling machine cutting crown reality bottom, side angle, passes through Control cutting arm to extend, be lower sleeping, shovel board of development machine and crawler belt front end are propped up, now the quality of whole development machine, which is entirely fallen within, cuts Cut at head and two crawler belt rear end fulcrums, then by controlling cutting arm to turn left to move joystick, it is produced one and turn left Dynamic power, but because cut crown reality bottom, side junction can not move, tail is against 1511 skins along left side, and limitation tail is to the left Mobile, the dynamic reaction that now cutting arm turns left will tunnel mechanical shovel in development machine finally by reaction force to the right Plate elapses to the right about 20cm, after at this moment development machine slightly bends to right, the rectilinear direction after pendulum machine that can be turned around along first continue to Preceding construction, when cutterhead cut to 1511 cut eye lead cave it is left side design attitude after, continued using above-mentioned identical operating method Head, pendulum machine construction.
Further improvement of the present invention also has, in the step 8, when development machine repeatedly turns around, pendulum machine to the maximum amplitude of oscillation When, the connection bearing pin at development machine and two fortune belt tails is removed, after removing bearing pin, development machine separates with two fortune belts, for ease of Turn round and construct, need to be sling two fortune belt machine ends to lap position with 2 5T chain block, it is then special by using 2 40T With hanging chain, two fortune tail hangings are transported on the hanging nose slipped under head to development machine one, it is ensured that be flexible coupling firm, effective.
Further improvement of the present invention also has, in the step 9, when development machine and two fortune belt machine ends are changed to be flexible coupling Afterwards, development machine can big swing angle continue to construct, when shovel board of development machine abutted in step 5 " construct less than 1511 cut eye and lead cave bottom right Help corner " when, shovel board of development machine is mobile restricted, it is impossible to be further continued for 1511 cut eye lead cave it is right side move down, now development machine cut Cut and crouched under head to bottom plate, as fulcrum, to make it produce a power to the right by operating cutting arm right turn at the side of shovel board top, Because of cutterhead, shovel board real 1511 have been pushed up to cut eye and lead the right side of cave and can not move right again, so just development machine is generated one to Left reaction force, by operating pendulum machine by force, reaches the purpose that development machine is wagged the tail, so as to ajust the mesh that development machine reaches turn 's.
Further improvement of the present invention also has, and in the step 12, when development machine can not continue to construct forward, marks 1511, which cut eye, leads cave construction center line, and development machine band two is transported along center line and moves back machine to 1511 skins along left side, now removes two fortune belt tails Be flexible coupling, and two fortune belt tails are placed by 1511 skins along left side, and be fixed on roadway floor, then by development machine Reach 1511 cut eye lead cave construction meet head on, development machine and two fortune belt tails between lay a 40T scraper-trough conveyer transshipment.
Further improvement of the present invention also has, and in the step 13, the side of 40T scraper-trough conveyer transshipments is ridden by development machine Formula continues construction 1511 forward and cut after eye leads cave 40m, and the 40T that dismantles slips head, two sections, removes two fortune belts and is transported to 1511 Cut eye and lead that cave is standby, then draw to move on to 1511 and cut eye and lead along interior contracting belt tail by 1511 skins and fixed at cave enabling mouth, again Laying 40T slips head, two sections, it is ensured that overlap joint is reasonable, recovers two fortune belts after last development machine, belt is transported using development machine heel two Reprint, the mode that two fortune belts ride 40T scraper-trough conveyers is constructed, and so far, site operation enters normal cyclic, and development machine acute angle, which turns round, constructs Terminate.
It is an advantage of the invention that:1st, when tunneler construction in place after, open the door after construction 30m, then use instead according to raking loader Tunneler construction, then need to coordinate development machine to go out bastard coal during raking loader rake cash, therefore contrast tunneler construction, except pick can be saved Enter outside the process and expense of machine gun head cut, its shovel board of development machine, a fortune, two operating loads are both needed to run well.So using Raking loader construction period, increased expense have following several respects.(1)3 people are needed to transport raking loader and fixation, about 2 day time;(2) Raking loader construction period need to consume priming system;(3)Raking loader needs to increase power consumption during operating;(4)After raking loader is constructed, need Withdraw equipment;(5)Raking loader construction it is bigger than the labor intensity of tunneler construction, efficiency is slow, it is front and rear installation, withdraw it is required Time is grown;
2nd, because my the coal coal dust explosion hazard qualification result of ore deposit 3 is 40.5%, the project, which is applied to coal dust, has the ore deposit of explosion hazard Well and other there is the colliery of analogue, it solves my ore deposit always using the backwardness construction technology manually opened the door;
3rd, EBZ160 types development machine appearance and size is 9.3 × 3 × 1.6m.1511, which cut eye, leads cave and 1511 skins along into 72 ° of angles, cuts Eye is led cave and opened the door from skin along using development machine acute angle, is national colliery first hand construction, without scene it is real-trample experience, be a kind of Challenge and trial, also opening the door to construct for tunnel provides a kind of new construction method, has more widened the use range of development machine, has increased Strong adaptability of the development machine to field condition.
As can be seen here, the present invention is compared with prior art, with prominent substantive distinguishing features and significantly progressive, its implementation Beneficial effect be also obvious.
Brief description of the drawings
Fig. 1 is the structural representation that present invention simulation is turned.
Fig. 2 is the structural representation of the specific embodiment of the invention.
In figure, 1 is splits side opening position, and 2 be 3 ° of angles, and 3 be 3 ° of angle Pi Bang areas of right side, and 4 is smear angle construction area, and 5 are 1511, which cut eye, leads ketone, and 6 turn round for third time splits side construction area, and 7 turn round for second splits side construction area, and 8 split to turn round for the first time Construction area is helped, 9 lead cave enabling mouth to cut eye, and 10 be 1511 belt crossheadings, and 11 is meet head on, and 12 be that 1511 skins are along left side, 13 1511 cut eye leads cave bottom right side, 15 be skin it is suitable, 16 be 1511 skins along right side, 17 be development machine profile, and 18 be maximum supporting chi Very little, 19 be center line, and 20 cut eye for 1511 leads the right side of cave, and 21 cut eye for 1511 leads the left side of cave, and 22 be 72 ° of angles.
Embodiment
For the technical characterstic for illustrating this programme can be understood, below by an embodiment, and its accompanying drawing is combined, it is right This programme is illustrated.
Name involved by the application is done explained below:
Supporting:Empty top tunnel after tunneler construction is complete, the permanent support of progress.
Two fortune:Two belt conveyers supporting with development machine.
The two anti-sides of fortune:After development machine is turned to certain position, two belt conveyers, along right side 16, make against 1511 skins Development machine can not be further continued for constructing forward.
Cutting arm:On development machine, what is be connected between cutterhead and body cranks arm.
Cut scope:When development machine swings cutterhead, the boundary of works area that can reach.
The amplitude of oscillation:When development machine swings cutterhead, the full-size that can reach.
Pendulum machine:Development machine drives development machine not by crawler travel, but by cutterhead branch by operating cutting arm It is mobile.
The construction method that EBZ160 development machines acute angle is turned, including following construction procedure,
Step 1:Determine min. turning radius,
When designing tunnel turning, fuselage is longer, and required radius of turn is bigger, and fuselage is wider, and required enabling tunnel is wider, and Machine body of boring machine height is on turning to without influence.Learnt according to development machine related data, EBZ160 development machine min. turning radius is 6.5m.Because 1511 skins along 15 with to cut eye to lead the angle of cave 14 be 72 °, arrangement at an acute angle, to reduce roof span when turning round, it is determined that Turned using min. turning radius (6.5m), now roof span is minimum.
Step 2:Theoretical Design simulation is turned,
Before construction, modeling is first made according to tunnel and development machine parameter on CAD and turned, determine that tunnel turns by demonstrating Curved related data, in analog demenstration, surplus coefficiert is reserved apart from lane side, to ensure that development machine rear molding does not scratch lane side;
When selecting min. turning radius (6.5m), activity space is narrow and small when easily causing development machine turning, advances, retreats difficulty. But turning length is short, and construction volume is relatively small, as long as development machine activity space can meet operational requirements, now maximum supporting size 18 minimum 11m (select by maximum supporting size:Interior curved center during digging laneway is to tunnel profile most ledge).Work as selection During more than 6.5m radius of turn, easily cause that area of suspension roof is excessive, cause the unsafe factor of setting, while later stage supporting is stranded It is difficult.
Step 3,1511 skins split side construction along meeting head on 11 from the construction of 1 straight lane of side opening position is split after permanent support,
(1)1511 skins are first just being met head on along meeting head on 11 from starting to split side opening position 1 by normal cyclic drilling depth 1511 skins of constructing along 15, After top plate and skin are along 12 permanent supports of left side, then side construction is split by the way of the direct cut of cutterhead.Every meter of circulation when splitting side Drilling depth is split side cut face and tiltedly faced directly into one from starting point to side end is split;
(2)Split side position:From 1511 cut eye lead cave it is right side 20 and 1511 skins along it is right help 16 point of intersection step back 21m(One whole two fortune The length of belt conveyer)Opening position, side construction is split by 3 ° of angles 2.For ease of execute-in-place, it need in advance provide and split side size, That is every meter of cyclic advance extends out 0.05m to 1511 skins along right side 16, and second meter of opening position extends out 0.1m to 1511 skins along right side 16, It is incremented by successively, split side width 1.05m to 21m opening position maximums.
Step 4, when 1511 skins along 15 construction to 1511 cut eye lead cave it is left side 21 when, development machine steps back 10m, reserve 1511 Cut eye and lead cave enabling mouth 9, and the floor level clicked here plays bottom, horizontal sliding, it is ensured that the bottom plate mark in the range of the 10m of development machine turning A height of same absolute altitude platform.
Step 5,1511, which cut eye, leads cave self-opening door position, and construction of being turned round in the form of splitting side, it is 1m to split side cyclic advance. By currently normal connection, it is supporting in a manner of, 1511, which cut eye, leads cave can turn round construction 3m into obtuse angle, and 1511 cut eye and lead cave bottom right side The construction of 13 corners is less than needing step 10 to construct.
Step 6, when development machine band two, which transports belt construction, reaches the maximum amplitude of oscillation, machine is moved back, makes shovel board of development machine front end extremely 1511, which cut eye, leads at cave enabling mouth 9, and adjusts development machine again, makes on the left of development machine to carry out pick along left side 12 against 1511 skins The preparation entered before machine turn construction.
Step 7, because working space is limited, field condition limitation, when development machine is advanced into 1511 along 1511 skins along left side 12 After skin is just met head on along 15, advance, retrogressing, left crawler travel, the right-hand track chiain walking of crawler belt are manipulated by, to reach levelling pick Enter that the construction direction of machine is more difficult, now need to take the mode of driving head effectively to realize flipper turn.That is development machine Cut crown reality bottom, side angle(Underworkings is the coffin excavated in entity coal petrography, is above top plate, and lower is bottom plate, two Side is side.Two help and push up, angle in 90 ° between bottom plate, and cutterhead prevents it from again against bottom plate and the angle in portion of side Continue to portion of side to be moved below inner, bottom plate), by controlling cutting arm to extend, lower sleeping, shovel board of development machine and crawler belt front end are supportted Rise,(Now the quality of whole development machine is entirely fallen within cutterhead and two crawler belt rear end fulcrums), then by controlling cut Arm turns left to move joystick, its is produced the power to turn left, and because cut crown reality bottom, side junction can not be moved Dynamic, tail is moved to the left against 1511 skins along left side 12, limitation tail, and the dynamic reaction that now cutting arm turns left is in pick Enter machine, shovel board of development machine is elapsed to the right to about 20cm finally by reaction force to the right, at this moment development machine slightly bends to right Afterwards, can continue to construct forward along first rectilinear direction after pendulum machine that turns around.Eye, which is cut, when cutterhead cut to 1511 leads the left side 21 of cave After design attitude, continue to turn around using above-mentioned identical operating method, pendulum machine is constructed.
Step 8, when development machine repeatedly turns around, pendulum machine to the maximum amplitude of oscillation when, remove development machine and company at belt tails transported with two Pin axle.After removing bearing pin, development machine separates with two fortune belts.Constructed for ease of turning round, need to be with 2 5T chain block by two Fortune belt machine end is sling to lap position, then by using special suspension chain of 2 40T, by two fortune tail hangings to driving Machine one is transported on the hanging nose slipped under head, it is ensured that is flexible coupling firm, effective.
Step 9, when development machine and two fortune belt machine ends be changed to be flexible coupling after, development machine can big swing angle continue to construct.Work as pick Enter mechanical shovel plate in the 3rd step " construct less than 1511 cut eye and lead cave bottom right help 13 corners " when, shovel board of development machine movement by Limit, it is impossible to be further continued for cutting eye to 1511 and lead the right side of cave and 20 move down, now crouched under cutting head of roadheader to bottom plate, at the side of shovel board top For fulcrum, it is set to produce a power to the right by operating cutting arm right turn, as a same reason, because cutterhead, shovel board have been pushed up Real 1511, which cut eye, which leads the right side 20 of cave, to move right again, and a reaction force to the left is so just generated to development machine, is led to Operation pendulum machine by force is crossed, reaches the purpose that development machine is wagged the tail, so as to ajust the purpose that development machine reaches turn.
Step 10, continuously put machine to the right because of development machine and turn round, and walk forward so that development machine rear have it is certain The safe space constructed, at this moment the development machine after ajusting is retreated to 1511 skins along left side 12, now shovel board of development machine is no longer It is mobile restricted, turn direction can be adjusted again, and 1511 not constructed by the original step 5 of cutterhead cut construction are cut eye and led 13 corners are helped in cave bottom right, cut eye by 1511 and lead cave and meet head on that brush is neat, centering.
Step 11, development machine centering continue to construct forward after meeting head on, until the two anti-sides of fortune belt holder(Because of development machine and two Belt or connection mode are transported, when development machine turn construction flushes to two fortune tails with 1511 skins along right side 16, two fortune belts Frame by 1511 skins along it is right side 16 entity coal stop, cause development machine can not band two fortune continue construct forward), now 1511 cut eye Lead cave turned round construction about 10.9m(Split the side long 0.6m of deep 1m+ driving captain's 9.3m+ telescoping cylinders).
Step 12, when development machine can not continue to construct forward, mark 1511 cut eye lead cave construction center line 19, development machine Band two is transported along center line 19 and moves back machine to 1511 skins along left side 12, now removes being flexible coupling for two fortune belt tails, and transport belt tail by two Place, and be fixed on roadway floor along left side 12 by 1511 skins, development machine is then reached 1511 cut eye and lead cave construction Meet head on 11, a 40T scraper-trough conveyer transshipment is laid between development machine and two fortune belt tails.
Step 13, continue to construct forward by way of development machine rides 40T scraper-trough conveyer transshipments and 1511 cut eye and lead cave 40m Afterwards, the 40T that dismantles slips head, two sections, removes two fortune belts and is transported to 1511 and cut eye to lead cave standby, then by 1511 skins along 15 Interior contracting belt tail draws to move on to 1511 and cut eye and lead and fixed at cave enabling mouth, lays 40T again and slips head, two sections, it is ensured that overlap joint closes Manage, recover two fortune belts after last development machine, belt transfer is transported using development machine heel two, two fortune belts ride the side of 40T scraper-trough conveyers Formula is constructed.So far, site operation enters normal cyclic, and development machine acute angle turn construction terminates.
Although above-mentioned the embodiment of invention is described with reference to accompanying drawing, not to the scope of the present invention Limitation, one of ordinary skill in the art should be understood that on the basis of technical scheme those skilled in the art are not required to Various modifications or deformation that creative work can make are paid still within protection scope of the present invention.

Claims (8)

  1. The construction method that 1.EBZ160 development machines acute angle is turned, it is characterized in that, including following construction procedure,
    Step 1, min. turning radius is determined, learnt according to EBZ160 development machine related datas, EBZ160 development machines are minimum to turn Radius is 6.5m, and when determining that min. turning radius 6.5m turns, now the roof span at turning is minimum;
    Step 2, Theoretical Design simulation is turned, and before construction, first makes modeling according to tunnel and development machine parameter on CAD Turn, determine the related data of tunnel turning by demonstrating, in analog demenstration, surplus coefficiert is reserved apart from lane side, to protect Card development machine rear molding does not scratch lane side;
    Step 3,1511 skins, from the straight lane construction of side opening position is split, side construction are split after permanent support along meeting head on;
    Step 4, when 1511 skins cut eye along construction to 1511 leads the left side of cave, development machine steps back 10m, and reserved 1511, which cut eye, leads cave Enabling mouth, and the floor level clicked here plays bottom, horizontal sliding, it is ensured that the floor level in the range of the 10m of development machine turning is same Absolute altitude platform;
    Step 5,1511, which cut eye, leads cave self-opening door position, and construction of being turned round in the form of splitting side, it is 1m to split side cyclic advance, because turning It is curved cause 1511 cut eye lead cave it is right side 20 construction less than place, constructed in step 10;
    Step 6, prepared before being turned round for development machine;
    Step 7, the mode for taking development machine to turn around realize flipper turn;
    Step 8, the connection bearing pin between development machine and two fortune belts is changed to be flexible coupling;
    Step 9, big swing angle continue to construct;
    Step 10, adjustment turn direction, eye is cut by do not constructed in the original step 5 of cutterhead cut construction 1511 Cave bottom right side corner is led, eye is cut by 1511 and leads cave and meet head on that brush is neat, centering;
    Step 11, development machine centering continue to construct forward after meeting head on, until the two anti-sides of fortune belt holder;
    Step 12, dismounting are flexible coupling, and lay a 40T scraper-trough conveyer transshipment;
    Step 13, belt transfer is transported using development machine heel two, the mode that two fortune belts ride 40T scraper-trough conveyers is constructed, so far, scene Construction enters normal cyclic, and development machine acute angle turn construction terminates.
  2. 2. the construction method that EBZ160 development machines acute angle according to claim 1 is turned, it is characterized in that, the step 3 In, 1511 skins start to split side opening position certainly along meeting head on, and first being constructed by normal cyclic drilling depth, 1511 skins are suitable just to meet head on, top plate and 1511 After skin is along left side permanent support, then side construction is split by the way of the direct cut of cutterhead, every meter of cyclic advance is from when splitting side Point is split side cut face and tiltedly faced directly into one to side end is split.
  3. 3. the construction method that EBZ160 development machines acute angle according to claim 1 is turned, it is characterized in that, the step 6 In, when development machine band two, which transports belt construction, reaches the maximum amplitude of oscillation, machine is moved back, shovel board of development machine front end to 1511 is cut eye and is led cave and opens At doorway, and development machine is adjusted again, make on the left of development machine to carry out the standard before development machine turn construction along left side against 1511 skins Standby work.
  4. 4. the construction method that EBZ160 development machines acute angle according to claim 1 is turned, it is characterized in that, the step 7 In, tunneling machine cutting crown reality bottom, side angle, by controlling cutting arm to extend, lower sleeping, by shovel board of development machine and crawler belt front end Prop up, now the weight of whole development machine is entirely fallen within cutterhead and two crawler belt rear end fulcrums, then by controlling cut Arm turns left to move joystick, its is produced the power to turn left, and because cut crown reality bottom, side junction can not be moved Dynamic, tail is moved to the left against 1511 skins along left side, limitation tail, and the dynamic reaction that now cutting arm turns left is in driving Machine, shovel board of development machine is elapsed to the right to about 20cm finally by reaction force to the right, after at this moment development machine slightly bends to right, It can continue to construct forward along the rectilinear direction after the pendulum machine that turns around for the first time, cut eye when cutterhead cut to 1511 and lead the left side design of cave Behind position, continue to turn around using above-mentioned identical operating method, pendulum machine is constructed.
  5. 5. the construction method that EBZ160 development machines acute angle according to claim 1 is turned, it is characterized in that, the step 8 In, when development machine repeatedly turns around, pendulum machine to the maximum amplitude of oscillation when, remove development machine and the connection bearing pin at two fortune belt tails, dismounting After bearing pin, development machine separates with two fortune belts, is constructed for ease of turning round, and need to transport belt machine end by two with 2 5T chain block Sling to lap position, then by using special suspension chain of 2 40T, two fortune tail hangings are slipped into head to the fortune of development machine one Under hanging nose on, it is ensured that be flexible coupling firm, effective.
  6. 6. the construction method that EBZ160 development machines acute angle according to claim 1 is turned, it is characterized in that, the step 9 In, when development machine and two fortune belt machine ends be changed to be flexible coupling after, development machine can big swing angle continue to construct, when shovel board of development machine abuts In step 5 " construct less than 1511 cut eye lead cave bottom right side corner " when, shovel board of development machine is mobile restricted, it is impossible to is further continued for To 1511 cut eye lead cave it is right side move down, now crouched under cutting head of roadheader to bottom plate, as fulcrum, to pass through operation at the side of shovel board top Cutting arm right turn makes its produce a power to the right, because cutterhead, shovel board pushed up real 1511 cut eye lead the right side of cave can not be again Move right, a reaction force to the left is so just generated to development machine, by operating pendulum machine by force, reach development machine pendulum The purpose of tail, so as to ajust the purpose that development machine reaches turn.
  7. 7. the construction method that EBZ160 development machines acute angle according to claim 1 is turned, it is characterized in that, the step 12 In, when development machine can not continue to construct forward, mark 1511 and cut eye and lead cave construction center line, development machine band two transported along center line direction Machine is moved back to 1511 skins along left side, now removes being flexible coupling for two fortune belt tails, and two fortune belt tails are put by 1511 skins along left side Put, and be fixed on roadway floor, then by development machine reach 1511 cut eye lead cave construction meet head on, development machine with two transport skins A 40T scraper-trough conveyer transshipment is laid between magnetic tape trailer.
  8. 8. the construction method that EBZ160 development machines acute angle according to claim 1 is turned, it is characterized in that, the step 13 In, continue to construct forward by way of development machine rides 40T scraper-trough conveyer transshipments and 1511 cut after eye leads cave 40m, the 40T that dismantles is slipped Head, two sections, remove two fortune belts and be transported to 1511 and cut eye and lead that cave is standby, then by 1511 skins along interior contracting belt tail Drawing, which moves on to 1511, cuts eye and leads and fixed at cave enabling mouth, lays 40T again and slips head, two sections, it is ensured that overlap joint is reasonable, after last development machine To recover two fortune belts, belt transfer is transported using development machine heel two, the mode that two fortune belts ride 40T scraper-trough conveyers is constructed, so far, scene Construction enters normal cyclic, and development machine acute angle turn construction terminates.
CN201710819162.1A 2017-09-12 2017-09-12 The construction method that EBZ160 development machines acute angle is turned Pending CN107461198A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710819162.1A CN107461198A (en) 2017-09-12 2017-09-12 The construction method that EBZ160 development machines acute angle is turned

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710819162.1A CN107461198A (en) 2017-09-12 2017-09-12 The construction method that EBZ160 development machines acute angle is turned

Publications (1)

Publication Number Publication Date
CN107461198A true CN107461198A (en) 2017-12-12

Family

ID=60552282

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710819162.1A Pending CN107461198A (en) 2017-09-12 2017-09-12 The construction method that EBZ160 development machines acute angle is turned

Country Status (1)

Country Link
CN (1) CN107461198A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952751A (en) * 2018-06-28 2018-12-07 山东新阳能源有限公司 Monorail crane locomotive turn round method on the spot
CN110159269A (en) * 2019-04-17 2019-08-23 贵州开磷有限责任公司 A kind of underground winding roadway tunneling construction method
CN110306998A (en) * 2019-06-14 2019-10-08 龙口矿业集团有限公司 A kind of fully-mechanized digging machine turn simultaneous drifting method
CN111691886A (en) * 2020-06-23 2020-09-22 国家能源集团宁夏煤业有限责任公司 Construction method for opening cutting hole by fully-mechanized coal mining machine in fully-mechanized coal mining face
CN111764917A (en) * 2020-06-24 2020-10-13 临沂矿业集团菏泽煤电有限公司 Tunneling construction method for quick door opening roadway of fully-mechanized excavating machine
CN113309535A (en) * 2021-06-21 2021-08-27 中铁工程装备集团有限公司 Combined continuous belt conveyor slag discharging system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3902127A1 (en) * 1989-01-25 1990-07-26 E & Pk Ingbuero Wagon drill with laser-orientated control
CN201003401Y (en) * 2007-01-23 2008-01-09 上海科煤机电有限公司 Articulate folding and rotary cutting arm type cantalever tunnelling machine
CN103899312A (en) * 2012-12-28 2014-07-02 折俊杰 Right angle turn construction method of underwell T-shaped roadway
CN104018845A (en) * 2014-06-12 2014-09-03 中国铁建重工集团有限公司 Method for determining minimum horizontal turning radius of open-type TBM

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3902127A1 (en) * 1989-01-25 1990-07-26 E & Pk Ingbuero Wagon drill with laser-orientated control
CN201003401Y (en) * 2007-01-23 2008-01-09 上海科煤机电有限公司 Articulate folding and rotary cutting arm type cantalever tunnelling machine
CN103899312A (en) * 2012-12-28 2014-07-02 折俊杰 Right angle turn construction method of underwell T-shaped roadway
CN104018845A (en) * 2014-06-12 2014-09-03 中国铁建重工集团有限公司 Method for determining minimum horizontal turning radius of open-type TBM

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
范吉宏、崔红启: "掘进机锐角巷道转弯技术的研究与应用", 《中国煤炭工业》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952751A (en) * 2018-06-28 2018-12-07 山东新阳能源有限公司 Monorail crane locomotive turn round method on the spot
CN108952751B (en) * 2018-06-28 2020-04-24 山东新阳能源有限公司 In-situ turning method for monorail crane
CN110159269A (en) * 2019-04-17 2019-08-23 贵州开磷有限责任公司 A kind of underground winding roadway tunneling construction method
CN110159269B (en) * 2019-04-17 2020-10-30 贵州开磷有限责任公司 Underground bent roadway tunneling construction method
CN110306998A (en) * 2019-06-14 2019-10-08 龙口矿业集团有限公司 A kind of fully-mechanized digging machine turn simultaneous drifting method
CN111691886A (en) * 2020-06-23 2020-09-22 国家能源集团宁夏煤业有限责任公司 Construction method for opening cutting hole by fully-mechanized coal mining machine in fully-mechanized coal mining face
CN111691886B (en) * 2020-06-23 2021-08-31 国家能源集团宁夏煤业有限责任公司 Construction method for opening cutting hole by fully-mechanized coal mining machine in fully-mechanized coal mining face
CN111764917A (en) * 2020-06-24 2020-10-13 临沂矿业集团菏泽煤电有限公司 Tunneling construction method for quick door opening roadway of fully-mechanized excavating machine
CN113309535A (en) * 2021-06-21 2021-08-27 中铁工程装备集团有限公司 Combined continuous belt conveyor slag discharging system
CN113309535B (en) * 2021-06-21 2022-03-22 中铁工程装备集团有限公司 Combined continuous belt conveyor slag discharging system

Similar Documents

Publication Publication Date Title
CN107461198A (en) The construction method that EBZ160 development machines acute angle is turned
CN107060795B (en) A kind of underground mine TBM assembly construction methods
CN104131829B (en) A kind of solid filling coal mining hydraulic supporting building and withdrawing frame method
CN101302931B (en) Method for extracting rim angle coal and re-extracting after warehouse coal extracting
CN206190289U (en) Shape of a hoof shield excavation device in anhydrous weak soil tunnel
AU2019259069C1 (en) Underground space intelligent construction system and method
CN104912557A (en) High-efficiency thin coal seam complete-set coal mining equipment and coal mining method
CN102704927A (en) Comprehensive mechanization stone drift heading machine set
CN105715272A (en) Fully-mechanized caving mining method for lower slice of ultra-thick hard coal
CN104500069A (en) Continuous coal mining machine top-coal mining process for extremely-thick coal seam bound coal
CN102900444A (en) Improved withdrawing technology for hydraulic supports on fully mechanized coal face
CN105003268A (en) Steeply inclined coal seam strike advancing false dipping fully-mechanized coal mining
CN101302933B (en) Method for developing rock lane comprehensive mechanization developing operation
CN104358574A (en) Horizontal room-and-pillar mining method of slightly inclined orebody
CN104405392B (en) Three soft high seam tunnel jackings are kept on file anchor rete cord active support longwall top coal caving method
CN106437734B (en) The shape of a hoof shield excavating device and tunnel excavation method of anhydrous soft soil tunnel
CN101824986A (en) Coal mining process of drilling, loading, conveying and anchoring integral machine
CN101302932A (en) Method for underground chamber digging and laneway opening digging
CN103362511A (en) Steep medium-thickness coal seam stepped coal pillar-free coal mining method
CN102606158A (en) Novel low coal seam coal mine underground mining complete equipment
CN102536312B (en) Anchor rod transloading set
CN202055850U (en) Full mechanized roadway remote end surface protective device
CN205677650U (en) Support automatic moving type continuous digging machine
CN104329117A (en) Installation method of comprehensive mechanized filling, coal mining and open-off cutting equipment
CN102748032B (en) Mechanized rapid construction method for traditional rock drivage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination