CN107447990A - A kind of steel beam lifting method of two theodolites Synchronization Control girder steel both ends discrepancy in elevation - Google Patents
A kind of steel beam lifting method of two theodolites Synchronization Control girder steel both ends discrepancy in elevation Download PDFInfo
- Publication number
- CN107447990A CN107447990A CN201610364896.0A CN201610364896A CN107447990A CN 107447990 A CN107447990 A CN 107447990A CN 201610364896 A CN201610364896 A CN 201610364896A CN 107447990 A CN107447990 A CN 107447990A
- Authority
- CN
- China
- Prior art keywords
- girder steel
- steel
- lifting
- elevation
- girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Abstract
A kind of steel beam lifting method of two theodolites Synchronization Control girder steel both ends discrepancy in elevation, uses prypole(4), hoist cable(5)And hoist engine(3)Lift hoisting steel beam, it is characterised in that comprise the following steps:A, girder steel Measurement scales line is preset on girder steel, b, theodolite is set, c, girder steel lifting lifting, d, theodolite monitor in real time and discrepancy in elevation adjustment, it is ensured that the girder steel both ends discrepancy in elevation is no more than 5cm, so as to control the overall horizontal lifting of girder steel, completes steel girder erection.The steel beam lifting method of two theodolite Synchronization Control girder steel both ends discrepancy in elevation of the present invention has the advantages of steel beam lifting apparatus structure is simple, easy to use, and the overall horizontal lifting of stability contorting girder steel lifts and reduces steel beam lifting engineering cost.
Description
Technical field
The present invention relates to a kind of steel beam lifting method, is a kind of two theodolite Synchronization Control girder steel both ends specifically
The steel beam lifting method of the discrepancy in elevation.
Background technology
The lifting mode of domestic steel structure girder is varied, with the continuous development of scientific technology, steel structure girder construction
Also complexity is also more carried out in space, and hanging method difficulty is also increasing, and this brings new challenge to the lifting construction of steel structure girder.
Traditional steel structure girder lifting lifting process is visually observing to command steel structure girder to lift by department rope commanding, but
Often deviation is larger for the girder steel both ends discrepancy in elevation, and steel roof truss is away from lifting ground 20m, and both sides are away from building less than 0.5m, steel roof truss
Long 34m, if whole steel roof truss is lifted using overall, lifting speed, the discrepancy in elevation are controlled by special range sensor, it is required
Cost greatly increases.If using single girder steel is lifted, lifting lifting, girder steel length are controlled by traditional department rope commanding
It is longer, be not easy to command, easily cause girder steel collide neighbour's building.
Therefore known steel beam lifting method there are problems that above-mentioned a variety of inconvenience and.
The content of the invention
The purpose of the present invention, it is to propose a kind of steel of the two safe and reliable theodolite Synchronization Control girder steel both ends discrepancy in elevation
Beam hanging method.
To achieve the above object, technical solution of the invention is:
A kind of steel beam lifting method of two theodolites Synchronization Control girder steel both ends discrepancy in elevation, uses prypole, hoist cable and hoist engine
Lift hoisting steel beam, it is characterised in that comprise the following steps:
A, girder steel Measurement scales line is preset on girder steel
Before girder steel lifting, some obvious measurements are set to carve on the girder steel facade on girder steel both ends and girder steel below each Heave Here
Spend line;
Theodolite is set b,
Theodolite erect-position must is fulfilled for that girder steel lifting process is unobstructed and reflective, and the good sight of Measurement scales line is preset to girder steel
Survey, it is ensured that accurate to the number of degrees of graduation mark;
C, girder steel lifting lifting
In girder steel lifting process, information commander's control hoist engine that department rope commanding provides according to transit survey personnel is lifted
The operating personnel of girder steel, if the girder steel both ends discrepancy in elevation adjusts in time when exceeding prescribed limit value, control girder steel lifting, it is ensured that whole beam
Horizontal lifting;
D, theodolite monitors in real time and the discrepancy in elevation adjusts
In girder steel lifting process, by two theodolites for being arranged at ground to the level measurement scale on the facade of girder steel both ends
Line is observed, if the specific amount of deflection is informed department rope commander people by the graduation mark number of degrees deviation at girder steel both ends more than 5cm, survey crew
Member, department rope commanding command the adjustment of hoist engine operating personnel progress girder steel hoisting depth in time, it is ensured that the girder steel both ends discrepancy in elevation
No more than 5cm, so as to control the overall horizontal lifting of girder steel, steel girder erection is completed.
The steel beam lifting method of two theodolite Synchronization Control girder steel both ends discrepancy in elevation of the present invention can also use following
Technical measures are further realized.
Foregoing method, wherein each Measurement scales line has unified setting specification.
After adopting the above technical scheme, the steel beam lifting side of the two theodolite Synchronization Control girder steel both ends discrepancy in elevation of the present invention
Method has advantages below:
1st, steel beam lifting apparatus structure is simple, easy to use;
2nd, the overall horizontal lifting lifting of stability contorting girder steel, controlling are good;
3rd, considerable economic cost is saved, reduces steel beam lifting engineering cost.
Brief description of the drawings
Fig. 1 is to set Measurement scales line schematic diagram on the girder steel of the embodiment of the present invention;
Fig. 2 is the overall horizontal lifting lifting schematic diagram of the control girder steel of the embodiment of the present invention.
In figure:1 girder steel termination, 2 Measurement scales lines, 3 hoist engines, 4 prypoles, 5 hoist cables, 6 girder steels, 7 theodolites.
Embodiment
With reference to embodiments and its accompanying drawing illustrates further to the present invention.
Embodiment 1
The steel beam lifting method of two theodolite Synchronization Control girder steel both ends discrepancy in elevation of the present invention is suitable for steel beam lifting height not
It is very high(In theodolite visual range), the larger workplace of lifting narrow space, girder steel span.Fuzhou City's track traffic refers to
Wave Center Project.In track traffic command centre of Fuzhou City engineering, it is made up of two 12 floor, 21 floor high building and 5 floor annex, middle tower
Roofing uses steel roof truss form, and Steel Structural Design service life is 100 years, and safety classes of structure is one-level.Steel house
Frame away from lifting ground 20m, the long 34m of steel roof truss, steel house set a roof beam in place both sides away from building less than 0.5m, lift narrow space, steel
Beam lifting Synchronization Control is not in place easily to collide neighbour's building.
The steel beam lifting method of the Synchronization Control girder steel both ends discrepancy in elevation of two theodolites 7 of the present invention, using prypole 4, hangs
Rope 5 and hoist engine 3 lift hoisting steel beam, it is characterised in that comprise the following steps:
A, girder steel Measurement scales line is preset on girder steel
Fig. 1 is to set Measurement scales line schematic diagram on the girder steel of the embodiment of the present invention.Before girder steel 6 is lifted, in the girder steel termination 1 of girder steel two
And some obvious Measurement scales lines 2 are set on the girder steel facade on girder steel below each Heave Here.Each Measurement scales line tool
There is unified setting specification.
Theodolite is set b,
Theodolite erect-position must is fulfilled for that girder steel lifting process is unobstructed and reflective, and the good sight of Measurement scales line is preset to girder steel
Survey, it is ensured that accurate to the number of degrees of graduation mark;
C, girder steel lifting lifting
In girder steel lifting process, information commander's control hoist engine that department rope commanding provides according to transit survey personnel is lifted
The operating personnel of girder steel, if the girder steel both ends discrepancy in elevation adjusts in time when exceeding prescribed limit value, control girder steel lifting, it is ensured that whole beam
Horizontal lifting;
D, theodolite monitors in real time and the discrepancy in elevation adjusts
Fig. 2 is the overall horizontal lifting lifting schematic diagram of the control girder steel of the embodiment of the present invention.In girder steel lifting process, pass through
Two theodolites for being arranged at ground are observed the level measurement graduation mark on the facade of girder steel both ends, if the graduation mark at girder steel both ends
The specific amount of deflection is informed department rope commanding by number of degrees deviation more than 5cm, survey crew, and department rope commanding commands volume in time
Raise the adjustment that machine operating personnel carry out girder steel hoisting depth, it is ensured that the girder steel both ends discrepancy in elevation is no more than 5cm, so as to control girder steel overall
Horizontal lifting, complete steel girder erection.
The present invention has substantive distinguishing features and significant technological progress, of the invention two theodolite Synchronization Control girder steels two
The steel beam lifting method of the discrepancy in elevation is held, by presetting level measurement graduation mark on girder steel, real-time monitored is carried out using theodolite, adjusts
It is whole, finally control the horizontal lifting of girder steel, it is ensured that girder steel is reliably in place, avoids asking for girder steel collision neighbour's building
Topic.
The steel beam lifting method of the two theodolite Synchronization Control girder steel both ends discrepancy in elevation of the present invention is in Fuzhou City's track traffic
Used in command centre's engineering steel beam lifting, in place, method is easy, easy, economy, matter for overall steel beam lifting lifting control
Amount is guaranteed, and whole hoisting process obtains management, owner's accreditation.
Above example is used for illustrative purposes only, rather than limitation of the present invention, the technology people about technical field
Member, without departing from the spirit and scope of the present invention, can also make various conversion or change.Therefore, it is all equivalent
Technical scheme should also belong to scope of the invention, should be limited by each claim.
Claims (2)
1. a kind of steel beam lifting method of two theodolites Synchronization Control girder steel both ends discrepancy in elevation, uses prypole(4), hoist cable(5)
And hoist engine(3)Lift hoisting steel beam, it is characterised in that comprise the following steps:
A, girder steel Measurement scales line is preset on girder steel
Before girder steel lifting, some obvious measurements are set to carve on the girder steel facade on girder steel both ends and girder steel below each Heave Here
Spend line;
Theodolite is set b,
Theodolite erect-position must is fulfilled for that girder steel lifting process is unobstructed and reflective, and the good sight of Measurement scales line is preset to girder steel
Survey, it is ensured that accurate to the number of degrees of graduation mark;
C, girder steel lifting lifting
In girder steel lifting process, information commander's control hoist engine that department rope commanding provides according to transit survey personnel is lifted
The operating personnel of girder steel, if the girder steel both ends discrepancy in elevation adjusts in time when exceeding prescribed limit value, control girder steel lifting, it is ensured that whole beam
Horizontal lifting;
D, theodolite monitors in real time and the discrepancy in elevation adjusts
In girder steel lifting process, by two theodolites for being arranged at ground to the level measurement scale on the facade of girder steel both ends
Line is observed, if the specific amount of deflection is informed department rope commander people by the graduation mark number of degrees deviation at girder steel both ends more than 5cm, survey crew
Member, department rope commanding command the adjustment of hoist engine operating personnel progress girder steel hoisting depth in time, it is ensured that the girder steel both ends discrepancy in elevation
No more than 5cm, so as to control the overall horizontal lifting of girder steel, steel girder erection is completed.
2. the steel beam lifting method of two theodolites Synchronization Control girder steel both ends as claimed in claim 1 discrepancy in elevation, its feature exist
In each Measurement scales line has unified setting specification.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610364896.0A CN107447990B (en) | 2016-05-30 | 2016-05-30 | A kind of steel beam lifting method of two theodolites synchronously control girder steel both ends height difference |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610364896.0A CN107447990B (en) | 2016-05-30 | 2016-05-30 | A kind of steel beam lifting method of two theodolites synchronously control girder steel both ends height difference |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107447990A true CN107447990A (en) | 2017-12-08 |
CN107447990B CN107447990B (en) | 2019-06-14 |
Family
ID=60484618
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610364896.0A Active CN107447990B (en) | 2016-05-30 | 2016-05-30 | A kind of steel beam lifting method of two theodolites synchronously control girder steel both ends height difference |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107447990B (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102400559A (en) * | 2010-09-13 | 2012-04-04 | 五冶集团上海有限公司 | Steel column correction method in assembly of main body frame steel structure in benzene hydrogenation engineering |
CN102888998A (en) * | 2012-04-19 | 2013-01-23 | 中国建筑第四工程局有限公司 | Method and structure for lifting supporting steel column |
CN203891486U (en) * | 2014-06-04 | 2014-10-22 | 青岛东方铁塔股份有限公司 | Rapidly-positioning device for angle iron at end of angle beam |
CN104420694A (en) * | 2013-08-21 | 2015-03-18 | 五冶集团上海有限公司 | General mounting method for benzene hydrogenation engineering tower equipment |
CN105003080A (en) * | 2015-05-06 | 2015-10-28 | 上海绿地建设(集团)有限公司 | Construction technique of sector steel-structured building |
-
2016
- 2016-05-30 CN CN201610364896.0A patent/CN107447990B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102400559A (en) * | 2010-09-13 | 2012-04-04 | 五冶集团上海有限公司 | Steel column correction method in assembly of main body frame steel structure in benzene hydrogenation engineering |
CN102888998A (en) * | 2012-04-19 | 2013-01-23 | 中国建筑第四工程局有限公司 | Method and structure for lifting supporting steel column |
CN104420694A (en) * | 2013-08-21 | 2015-03-18 | 五冶集团上海有限公司 | General mounting method for benzene hydrogenation engineering tower equipment |
CN203891486U (en) * | 2014-06-04 | 2014-10-22 | 青岛东方铁塔股份有限公司 | Rapidly-positioning device for angle iron at end of angle beam |
CN105003080A (en) * | 2015-05-06 | 2015-10-28 | 上海绿地建设(集团)有限公司 | Construction technique of sector steel-structured building |
Also Published As
Publication number | Publication date |
---|---|
CN107447990B (en) | 2019-06-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106703416B (en) | Steel roof truss dead man hanging method in small space | |
CN103291076B (en) | Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame | |
CN103225408B (en) | Construction method for long-span net rack multiple-mast independent type integral lifting | |
CN106193618B (en) | A kind of aerial steel structure truss construction of Long span | |
CN104695337B (en) | Self-lifting sliding and turnover construction system and construction method | |
CN201351084Y (en) | Dual-machine load walking type hydraulic numerical control cross cable crane | |
CN101537976B (en) | Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof | |
CN104060835B (en) | Lifting-sliding construction method for single plane truss | |
CN203296361U (en) | Long-span steel structure cross assembling hoisting platform | |
CN201376848Y (en) | Large-scale double-tower automatic-elevation hoisting equipment | |
CN106223623B (en) | Steel construction box arched roof truss installation method | |
CN104060840A (en) | Construction method for lifting large-span dome net rack by using bolt sphere truss lifter | |
CN202530769U (en) | Large span steel structure high-altitude subsection hoisting support system | |
CN108049666B (en) | A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction | |
CN105484502A (en) | Combination installation method for steel structure roofing purlins and support bars of industrial factory building | |
CN103912128A (en) | Construction method of high-altitude one-piece steel truss | |
CN113638853A (en) | Monitoring system for lifting process of self-lifting type wind power tower cylinder | |
CN105155418A (en) | Construction method for bridge horizontal movement | |
CN103434933A (en) | Large member hoisting in-position device and in-position method | |
CN104404888A (en) | Large hoisting system allowing gradient to be adjusted in air and application | |
CN107447990A (en) | A kind of steel beam lifting method of two theodolites Synchronization Control girder steel both ends discrepancy in elevation | |
CN104060838B (en) | A kind of vestibule divides into groups aerial group to Method for Installation | |
CN105625732A (en) | Supporting-free construction method of ultrahigh overhung steel-structure truss | |
CN205575534U (en) | Lattice formula groined type support body lifting means | |
CN202449757U (en) | Motor-driven single-beam suspending crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |