- CN107425475A CN107425475A CN201710822157.6A CN201710822157A CN107425475A CN 107425475 A CN107425475 A CN 107425475A CN 201710822157 A CN201710822157 A CN 201710822157A CN 107425475 A CN107425475 A CN 107425475A
- Authority
- CN
- China
- Prior art keywords
- earth wire
- lifter
- overhead
- elevator belt
- aerial
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/16—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with jibs supported by columns, e.g. towers having their lower end mounted for slewing movements
- B66C23/166—Simple cranes with jibs which may be fixed or can slew or luff
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
- B66C23/72—Counterweights or supports for balancing lifting couples
- B66C23/78—Supports, e.g. outriggers, for mobile cranes
Abstract
The present invention relates to overhead transmission line maintenance technique field, particularly to a kind of overhead earth wire lifter and its lifting installation method.The overhead earth wire lifter is made up of electric capstan and foot stool, a kind of overhead earth wire lifter and its lifting installation method are provided, too low for the capstan winch Heave Here of lifting aerial earth wire, lifting is difficult, and overhead earth wire lifter deadweight is larger, the problem of lifting is in place inconvenient, improves winch configurations, optimizes method for improving, solves the difficult problem of current aerial earth wire lifting maintenance, improve the convenience operated on tower, reduce labor intensity, improve the overhaul efficiency of aerial earth wire.
Description
Technical field
The present invention relates to overhead transmission line maintenance technique field, particularly to a kind of overhead earth wire lifter and
It lifts installation method.
Background technology
Aerial earth wire is the device for protecting overhead transmission line to exempt from lightning attack.In order to improve the safety of circuit operation
Property, aerial earth wire is typically all to be erected above protected wire.When there is thundercloud to ground discharge in side on the line, lightning
Passage easily hits aerial earth wire first, lightning current is entered the earth, to protect the normal power transmission of wire.Meanwhile aerial earth wire is also
There is electromagnetic shielding action, when thundercloud is to ground discharge near circuit, it is excessively electric that the caused lightning induction on wire can be reduced
Pressure.Therefore aerial earth wire must firmly be connected with tower grounding device, to ensure reliably lead lightning current after being struck by lightning
Enter the earth.Important transmission line of electricity typically uses two aerial earth wires that protected wire is all placed in its protection domain
It is interior.
Function of the aerial earth wire due to not bearing conveying electric current, so being formed more using steel strand wires.Also some transmission lines of electricity
Using good conductor ground wire, i.e., the aerial earth wire made of aluminium alloy or aluminium Baogang wire.This ground wire electric conductivity is preferable, can be with
Improve multi-line power transmission performance, mitigate the interference to adjacent communication line.
Power transmission line overhead ground wire defect happens occasionally, when stranded needs replacing occurs in aerial earth wire or is inspecting periodically ground
During line wire clamp, workmen needs to lift by crane aerial earth wire, unclamps ground wire wire clamp, is changed or Inspection.Due to shaft tower knot
Structure limits, and lifting by crane the capstan winch of aerial earth wire does not have suitable hanging point, and generally existing Heave Here is too low, lifts by crane the problem of difficult.
China Patent No. is that " 2014103248189 " disclose a kind of " overhead earth wire lifter ", the tray in scheme
Upper setting bobbin, bobbin spanner is connected on bobbin, rope is wrapped on bobbin, the exit connection thread-lifting hook of rope, tray
Upper one end for being flexibly connected shrinking connecting-rod, the other end connection deck of shrinking connecting-rod, deck are provided with governor motion.Tray is
Regular polygon.Bobbin is square shaft.It is flexibly connected between tray and shrinking connecting-rod by bolt and nut.Deck is right-angled U.Adjust
Saving mechanism is:Pad I and pad II is symmetricly set on the inner surface of deck, pad I connection set screws.The program aims to solve the problem that
The artificial line efficiency that carries is low, the problem of potential safety hazard be present.
When overhead earth wire lifter works, more than ten meters of height need to be lifted with insulating cord by staff on tower, be then mounted to
On aerial earth wire support, because line lifter deadweight is larger, whole erection & lift process is also hidden in the presence of surprisingly coming off than relatively time-consuming
Suffer from.
The content of the invention
It is an object of the invention to provide a kind of overhead earth wire lifter and its lifting installation method, for lifting by crane aerial earth wire
Capstan winch Heave Here it is too low, the problem of lifting is difficult, and overhead earth wire lifter deadweight is larger, and lifting is in place inconvenient, improve
Winch configurations, optimize method for improving, solve the difficult problem of current aerial earth wire lifting maintenance, improve the facility operated on tower
Property, reduce labor intensity, improve the overhaul efficiency of aerial earth wire.
To achieve these goals, it is the technical scheme is that such:
A kind of lifting installation method of overhead earth wire lifter, it is dynamic using itself of elevator belt and overhead earth wire lifter
Power, make overhead earth wire lifter along elevator belt automatic lifting to earth wire support, finally overturn in place by operating personnel on tower, will
The overhead earth wire lifter is fixed on earth wire support, and its concrete operation step is as follows:
1) the loop aerial condutor is breaking, operating personnel climb up earth wire support with one end of elevator belt on tower;
2) both ends of the elevator belt are Bifurcation Structure, and operating personnel take the lead jail by two of elevator belt one end respectively on tower
It is connected and is connected on the bolt of earth wire support angle steel both sides;
3) overhead earth wire lifter is moved into ground below aerial earth wire support, the other end of elevator belt is passed through into institute
On the rope sheave for stating the electric capstan that the notch on the foot stool of overhead earth wire lifter is fixed to the overhead earth wire lifter, make institute
State elevator belt and surround the outside of steel wire rope and suspension hook on rope sheave;
4) direct current generator on overhead earth wire lifter is opened, as elevator belt is constantly by rope sheave, aerial earth wire
Line lifter constantly rises along elevator belt, edges down upon aerial earth wire support;
5) when overhead earth wire lifter is risen to below aerial earth wire support termination, direct current generator stops;
6) operating personnel hold the electric capstan on tower, and electric capstan is flipped up pulling, until the notch from
Earth wire support angle steel termination introduces;
7) nut on connecting rod one and connecting rod two is fastened, together with foot stool is tightly attached to aerial earth wire support;
8) direct current generator is reversely rotated, one end of the elevator belt is taken off from the rope sheave, you can on operation rope sheave
Suspension hook, carry out upkeep operation;
9) after aerial earth wire service work terminates, the other end of elevator belt is fixed on rope sheave again, and opened straight
Stream motor is by the elevator belt on the rope sheave;
10) nut on the connecting rod one and the connecting rod two is unclamped, shifts the electric capstan onto aerial earth wire support
End, until electric capstan and the disengaging of aerial earth wire support, suspend in midair on elevator belt;
11) direct current generator is reversely rotated, the electric capstan slowly drops down onto ground;
12) operating personnel pull down one end of elevator belt on tower, under throwing;
13) end of job.
The electric capstan, including capstan winch seat, rope sheave, steel wire rope, suspension hook, axle one and direct current generator, the axle one are placed in
In the endoporus of rope sheave, the both ends of axle one are connected with capstan winch seat respectively, it is characterised in that the side connection worm gear of the rope sheave,
The worm screw being meshed with the worm gear is on axle two, one end connection umbrella tooth one of axle two, the umbrella tooth engaged with umbrella tooth one two
In on axle three, one end of the axle three is provided with direct current generator.
The foot stool includes upper bearing, leg one, leg two, end plate one, end plate two, connecting rod one and connecting rod two, the upper bearing
The same side end of leg one and leg two is connected to, the end plate one is connected to the end side of leg one, and the end plate two is connected to
The end side of leg two, the both ends of the connecting rod one are bolted end plate one and end plate two respectively, the connecting rod two
Both ends connect end plate one and end plate two by bolt and nut respectively, surrounded between the leg one, leg two and connecting rod one, connecting rod two with
The notch of aerial earth wire support angle steel form fit.
The leg one and leg two are 90 ° of made buckling structures of square steel tube, and support bar is provided with 90 ° of flexings.
After the notch and aerial earth wire support Bolted angle connection, the rope sheave center be higher by notch base H for 350~
550mm。
Compared with prior art, the beneficial effects of the invention are as follows:
1) conduct oneself with dignity for electric capstan larger, lift the problem of in place inconvenient, by optimizing method for improving, solve at present
The difficult problem of aerial earth wire lifting maintenance, improves the convenience operated on tower.
2) turbine and worm decelerator is used, simple in construction, compact in design, stable performance, is entirely capable of meeting aerial earth wire
Carry line operation require, it is easy to operate, it is time saving and energy saving.
3) lifting point height is effectively increased, grasps the people of the tower operator one as hanging point by aerial earth wire support
Work can complete aerial earth wire lifting work, reduce labor intensity, improve job safety coefficient and efficiency.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing
There is the required accompanying drawing used in technology description to be briefly described, it should be apparent that, drawings in the following description are only this
Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can be with
Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 is overhead earth wire lifter example structure schematic diagram of the present invention;
Fig. 2 is Fig. 1 A direction views;
Fig. 3 is aerial earth wire cable clamp structure schematic diagram;
Fig. 4 is overhead earth wire lifter embodiment automatic lifting position schematic diagram of the present invention;
Fig. 5 is elevator belt embodiment end structure schematic diagram of the present invention.
In figure:1- capstan winch seats, 2- rope sheaves, 3- steel wire ropes, 4- suspension hooks, 5- axles one, 6- aerial earth wires, 7- worm gears, 8- worm screws,
9- axles two, 10- umbrella tooths one, 11- umbrella tooths two, 12- axles three, 13- foot stools, the upper bearings of 14-, 15- bolts, 16- nuts, 17- notches,
18- strengthening connection bodies, 19- support bars, 20- aerial earth wire support angle steel, 21- direct current generators, 22- battery cases, 23- control box,
24- remote controllers, 25- aerial earth wire wire clamps, 26- elevator belts, 27- overhead earth wire lifters.
Embodiment
The embodiment of the present invention is described further below in conjunction with the accompanying drawings:
See Fig. 1, be overhead earth wire lifter example structure schematic diagram of the present invention, the overhead earth wire lifter is by electric mincing
Disk and foot stool composition, electric capstan structure include capstan winch seat 1, rope sheave 2, steel wire rope 3, suspension hook 4, axle 1 and direct current generator 21,
Axle 1 is placed in the endoporus of rope sheave 2, and the both ends of axle 1 are connected with capstan winch seat 1 respectively, the side connection worm gear 7 of rope sheave 2, with
The worm screw 8 that worm gear is meshed is on axle 29, one end connection umbrella tooth 1 of axle two, the umbrella tooth engaged with umbrella tooth one 2 11
In on axle 3 12, one end of axle three is provided with direct current generator 21;
The bottom of capstan winch seat 1 connects foot stool 13, and foot stool includes upper bearing 14, leg 1, leg 2 132, end plate 1, end plate
2 142, connecting rod 1 and connecting rod 2 152, upper bearing 14 are connected to the same side end of leg 1 and leg 2 132, end plate 1
The end side of leg 1 is connected to, end plate 2 142 is connected to the end side of leg 2 132, the both ends of connecting rod 1
End plate 1 is connected by bolt 15 and nut 16 respectively and end plate 2 142, the both ends of connecting rod 2 152 pass through bolt 15 respectively
End plate 1 and end plate 2 142 are connected with nut 16, is enclosed between leg 1, leg 2 132 and connecting rod 1 and connecting rod 2 152
Into the notch 17 with aerial earth wire support angle steel form fit.
Strengthening connection body 18 is provided between leg 1 and leg 2 132.Leg 1 and leg 2 132 are that square steel tube is made
90 ° of buckling structures, 90 ° of flexings sentence Type of Welding connection support bar 19.Strengthening connection body 18 and support bar 19 can improve leg one
131 and the structural strength and rigidity of leg 2 132, ensure that leg 1 and leg 2 132 are indeformable in stress.
Direct current generator 21 uses lithium battery power supply, and battery case 22 is located at the dorsal part of the upper bearing 14 of foot stool.The direct current generator
Equipped with control box 23, control box, which is provided with, to be risen, declines, stop button, and GSM/GPRS wireless communication modules are provided with control box
PT105, wireless communication module PT105 are communicated with remote controller 24, and remote controller 24 can be operated by ground staff.
See Fig. 2, Fig. 3, during using the overhead earth wire lifter, after notch 17 is connected with aerial earth wire support angle steel 20, rope
It is 350~550mm to take turns 2 centers and be higher by notch base H.Notch 17 can translate along aerial earth wire support angle steel 20, until suspension hook position
Above aerial earth wire wire clamp 25, you can hook aerial earth wire 6 and carry out proposing line operation.
See Fig. 4, the lifting installation method of overhead earth wire lifter of the present invention is exactly to be carried using elevator belt 26 and aerial earth wire
The self power of line device 27, by overhead earth wire lifter along elevator belt automatic lifting to earth wire support 20, finally by being grasped on tower
It is in place to make personnel's upset, overhead earth wire lifter is fixed on earth wire support, you can proceeds by and proposes line operation, it is specifically grasped
It is as follows to make step:
1) the loop aerial condutor is breaking, operating personnel climb up earth wire support with one end of elevator belt on tower;
2) Fig. 5 is seen, the both ends of elevator belt are Bifurcation Structure, and operating personnel are respectively by two bands of the one end of elevator belt 26 on tower
Head is securely attached on the bolt of the both sides of earth wire support angle steel 20;
3) overhead earth wire lifter 27 is moved to below aerial earth wire support, the other end of elevator belt is passed through on its foot stool
Notch be fixed to electric capstan rope sheave on, the other end of elevator belt is pinned with bolt, and now elevator belt surrounds on rope sheave
The outside of steel wire rope and suspension hook;
4) direct current generator on overhead earth wire lifter is opened, as elevator belt is constantly by rope sheave, aerial earth wire
Line lifter 27 constantly rises along elevator belt, edges down upon aerial earth wire support;
5) when overhead earth wire lifter is risen to below aerial earth wire support termination, direct current generator stops;
6) operating personnel hold overhead earth wire lifter on tower, overhead earth wire lifter are flipped up pulling, Zhi Daoqi
Notch on foot stool introduces from earth wire support angle steel termination;
7) nut on connecting rod one and connecting rod two is fastened, together with foot stool is tightly attached to aerial earth wire support;
8) direct current generator is reversely rotated, one end of elevator belt is taken off from rope sheave, you can the suspension hook on control rope sheave is opened
Beginning proposes line operation, carries out upkeep operation;
9) after aerial earth wire service work terminates, the other end of elevator belt is fixed on rope sheave again, and opened straight
Stream motor is by elevator belt on rope sheave;
10) nut on connecting rod one and connecting rod two is unclamped, shifts overhead earth wire lifter 27 onto aerial earth wire bracket end,
Until overhead earth wire lifter and the disengaging of aerial earth wire support, suspend in midair on elevator belt;
11) direct current generator is reversely rotated, overhead earth wire lifter slowly drops down onto ground;
12) operating personnel pull down one end of elevator belt on tower, under throwing;
13) end of job.
Above example is only the specific reality to describe the purpose of the present invention in detail, technical scheme and beneficial effect are chosen
Example, but protection scope of the present invention is should in no way limit, all kinds on the premise of without prejudice to the spirit and principles in the present invention, made
Kind modification, equivalent substitution and improvement, all should fall under the scope of the present invention.
Claims (5)
1. the lifting installation method of a kind of overhead earth wire lifter, it is characterised in that utilize elevator belt and overhead earth wire lifter
Self power, overhead earth wire lifter is finally turned over along elevator belt automatic lifting to earth wire support by operating personnel on tower
Turn in place, the overhead earth wire lifter is fixed on earth wire support, its concrete operation step is as follows:
1) the loop aerial condutor is breaking, operating personnel climb up earth wire support with one end of elevator belt on tower;
2) both ends of the elevator belt are Bifurcation Structure, and two of elevator belt one end are taken the lead firmly to connect by operating personnel respectively on tower
It is connected on the bolt of earth wire support angle steel both sides;
3) overhead earth wire lifter is moved into ground below aerial earth wire support, the other end of elevator belt is passed through into the frame
On the rope sheave for the electric capstan that notch on the foot stool of vacant lot line line lifter is fixed to the overhead earth wire lifter, make described carry
Rise band and surround the outside of steel wire rope and suspension hook on rope sheave;
4) direct current generator on overhead earth wire lifter is opened, as elevator belt is constantly by rope sheave, aerial earth wire carries line
Device constantly rises along elevator belt, edges down upon aerial earth wire support;
5) when overhead earth wire lifter is risen to below aerial earth wire support termination, direct current generator stops;
6) operating personnel hold the electric capstan on tower, and electric capstan is flipped up pulling, until the notch is from ground wire
Support angle steel termination introduces;
7) nut on connecting rod one and connecting rod two is fastened, together with foot stool is tightly attached to aerial earth wire support;
8) direct current generator is reversely rotated, one end of the elevator belt is taken off from the rope sheave, you can hanging on operation rope sheave
Hook, carry out upkeep operation;
9) after aerial earth wire service work terminates, the other end of elevator belt is fixed on rope sheave again, and open direct current
Machine is by the elevator belt on the rope sheave;
10) nut on the connecting rod one and the connecting rod two is unclamped, shifts the electric capstan onto aerial earth wire bracket end,
Until electric capstan and the disengaging of aerial earth wire support, suspend in midair on elevator belt;
11) direct current generator is reversely rotated, the electric capstan slowly drops down onto ground;
12) operating personnel pull down one end of elevator belt on tower, under throwing;
13) end of job.
2. the lifting installation method of a kind of overhead earth wire lifter according to claim 1, it is characterised in that described aerial
Ground wire line lifter includes electric capstan and foot stool, the electric capstan, including capstan winch seat, rope sheave, steel wire rope, suspension hook, the and of axle one
Direct current generator, the axle one are placed in the endoporus of rope sheave, and the both ends of axle one are connected with capstan winch seat respectively, the side of the rope sheave
Worm gear is connected, the worm screw being meshed with the worm gear one end connection umbrella tooth one of axle two, engages on axle two with umbrella tooth one
Umbrella tooth two is located on axle three, and one end of the axle three is provided with direct current generator.
A kind of 3. lifting installation method of overhead earth wire lifter according to claim 2, it is characterised in that the foot stool
Including upper bearing, leg one, leg two, end plate one, end plate two, connecting rod one and connecting rod two, the upper bearing is connected to leg one and leg two
Same side end, the end plate one is connected to the end side of leg one, and the end plate two is connected to the end side of leg two,
The both ends of the connecting rod one are bolted end plate one and end plate two respectively, and the both ends of the connecting rod two pass through bolt spiral shell respectively
Mother's connection end plate one and end plate two, are surrounded and aerial earth wire support angle steel shape between the leg one, leg two and connecting rod one, connecting rod two
The notch of shape matching.
A kind of 4. lifting installation method of overhead earth wire lifter according to claim 3, it is characterised in that the leg one
It is 90 ° of made buckling structures of square steel tube with leg two, support bar is provided with 90 ° of flexings.
A kind of 5. lifting installation method of overhead earth wire lifter according to claim 1, it is characterised in that the notch
After aerial earth wire support Bolted angle connection, it is 350~550mm that the rope sheave center, which is higher by notch base H,.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710822157.6A CN107425475B (en) | 2017-09-13 | 2017-09-13 | Overhead ground wire lifter and lifting in-place method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710822157.6A CN107425475B (en) | 2017-09-13 | 2017-09-13 | Overhead ground wire lifter and lifting in-place method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107425475A true CN107425475A (en) | 2017-12-01 |
CN107425475B CN107425475B (en) | 2023-04-07 |
Family
ID=60433266
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710822157.6A Active CN107425475B (en) | 2017-09-13 | 2017-09-13 | Overhead ground wire lifter and lifting in-place method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107425475B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108383009A (en) * | 2018-03-08 | 2018-08-10 | 辽宁工业大学 | A kind of architectural electricity construction lifting gear |
CN110867767A (en) * | 2019-10-22 | 2020-03-06 | 云南电网有限责任公司曲靖供电局 | Auxiliary device for replacing 500kV heavy-load linear insulator string in electrified manner |
CN112834537A (en) * | 2021-01-29 | 2021-05-25 | 四川赛康智能科技股份有限公司 | X-ray live detection method based on ground potential power transmission line |
CN113612160A (en) * | 2021-09-10 | 2021-11-05 | 亿嘉和科技股份有限公司 | Winch working tool for bypass cable lap joint and operation method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102237655A (en) * | 2011-07-05 | 2011-11-09 | 河南省电力公司洛阳供电公司 | Method and tool for lifting overhead ground wire |
CN202183573U (en) * | 2011-07-05 | 2012-04-04 | 河南省电力公司洛阳供电公司 | Rocker type two-point lifting tool of overhead ground wire |
CN104064996A (en) * | 2014-07-09 | 2014-09-24 | 国家电网公司 | Lifting device for overhead ground wires |
CN104953507A (en) * | 2015-06-30 | 2015-09-30 | 国网山东招远市供电公司 | Device and method for lifting wire during distribution line construction |
CN207381860U (en) * | 2017-09-13 | 2018-05-18 | 国网辽宁省电力有限公司鞍山供电公司 | A kind of overhead earth wire lifter |
-
2017
- 2017-09-13 CN CN201710822157.6A patent/CN107425475B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102237655A (en) * | 2011-07-05 | 2011-11-09 | 河南省电力公司洛阳供电公司 | Method and tool for lifting overhead ground wire |
CN202183573U (en) * | 2011-07-05 | 2012-04-04 | 河南省电力公司洛阳供电公司 | Rocker type two-point lifting tool of overhead ground wire |
CN104064996A (en) * | 2014-07-09 | 2014-09-24 | 国家电网公司 | Lifting device for overhead ground wires |
CN104953507A (en) * | 2015-06-30 | 2015-09-30 | 国网山东招远市供电公司 | Device and method for lifting wire during distribution line construction |
CN207381860U (en) * | 2017-09-13 | 2018-05-18 | 国网辽宁省电力有限公司鞍山供电公司 | A kind of overhead earth wire lifter |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108383009A (en) * | 2018-03-08 | 2018-08-10 | 辽宁工业大学 | A kind of architectural electricity construction lifting gear |
CN110867767A (en) * | 2019-10-22 | 2020-03-06 | 云南电网有限责任公司曲靖供电局 | Auxiliary device for replacing 500kV heavy-load linear insulator string in electrified manner |
CN112834537A (en) * | 2021-01-29 | 2021-05-25 | 四川赛康智能科技股份有限公司 | X-ray live detection method based on ground potential power transmission line |
CN112834537B (en) * | 2021-01-29 | 2024-03-22 | 四川赛康智能科技股份有限公司 | X-ray live detection method based on ground potential power transmission line |
CN113612160A (en) * | 2021-09-10 | 2021-11-05 | 亿嘉和科技股份有限公司 | Winch working tool for bypass cable lap joint and operation method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN107425475B (en) | 2023-04-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107425475A (en) | A kind of overhead earth wire lifter and its lifting installation method | |
CN204760890U (en) | Wire hoisting device in distribution lines construction | |
CN104953507A (en) | Device and method for lifting wire during distribution line construction | |
CN105896379B (en) | For the live working platform of overhead transmission line | |
CN105058052B (en) | A kind of 3MW wind power generating sets installation method | |
CN103939299B (en) | The split type mounting process of a kind of offshore wind turbine | |
CN105162039A (en) | Portable grounding wire transmitter and using method | |
CN206502544U (en) | Bucket type mixing plant duplex type sister block fall arrest lifting device | |
CN104538887B (en) | A kind of lightning conducter lifts converter | |
CN105932601B (en) | Disconnected strand of overhead grounding wire method for repairing and mending | |
CN207381860U (en) | A kind of overhead earth wire lifter | |
CN103738861B (en) | A kind of ultra-high voltage transformer station type column of steel pipe integral hoisting method | |
CN203278097U (en) | Electric pole cross arm erecting device | |
CN204752090U (en) | Motor -driven elevating gear of pole | |
CN203720636U (en) | Novel transformer substation camera operation maintenance protecting device | |
CN103010965A (en) | Special tool of 110kVGW4-type for hoisting switch blades and porcelain bottles | |
CN203289011U (en) | Tension cross arm hoisting device | |
CN202063655U (en) | Anti-tilting safe device of tower type crane | |
CN108466938A (en) | A kind of transformer on-load voltage regulating tap switch boom hoisting | |
CN201285999Y (en) | Soft ladder for high voltage line maintenance | |
CN208401377U (en) | A kind of inspection platform for power station high voltage switchyard | |
CN2401531Y (en) | Lifting/lowering cradle for wind electricity generator | |
CN208632051U (en) | A kind of hanging basket for the maintenance of high tower lamp | |
CN108502700B (en) | Lifting appliance for cabin of wind driven generator | |
CN207347061U (en) | A kind of mechanical whole freight weight limit power-off protection apparatus and its ground jack of application |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |