CN107403277A - A kind of construction project construction project time management method and its management system - Google Patents

A kind of construction project construction project time management method and its management system Download PDF

Info

Publication number
CN107403277A
CN107403277A CN201710649810.3A CN201710649810A CN107403277A CN 107403277 A CN107403277 A CN 107403277A CN 201710649810 A CN201710649810 A CN 201710649810A CN 107403277 A CN107403277 A CN 107403277A
Authority
CN
China
Prior art keywords
construction project
project
construction
time management
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710649810.3A
Other languages
Chinese (zh)
Inventor
蒲兰芝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hefei Zhe Cheng Project Management Co Ltd
Original Assignee
Hefei Zhe Cheng Project Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hefei Zhe Cheng Project Management Co Ltd filed Critical Hefei Zhe Cheng Project Management Co Ltd
Priority to CN201710649810.3A priority Critical patent/CN107403277A/en
Publication of CN107403277A publication Critical patent/CN107403277A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a kind of construction project construction project time management method and its management system, and by adding regular meeting system, construction speed and organization work are periodically discussed, ensures that construction speed situation upgrades in time, avoids omitting;Periodically checked, and be analyzed and summarized, understand schedule deviation, to make amendment in time, holding progress meets plan and arranged, and improves reasonability.

Description

A kind of construction project construction project time management method and its management system
Technical field
The present invention relates to construction project administration field, specifically a kind of construction project construction project time management method and its management System.
Background technology
Project management refers to enable project having with special knowledge, technical ability, tool and method in project activity Limit under resource qualifications, realization or the demand more than setting and desired process.Project management is that some are successfully accomplished A series of whole monitoring of the related activity (for example task) of targets and management and control.This includes planning, schedule and safeguards composition The movable progress of project.
Construction-engineering project management is a key factor in China engineering construction construction, at the same be also one will be fixed Assets investment is converted into the real behave of actual productivity, and project management programs are all must pass through in all engineering constructions, no Then, other work all can not be carried out effectively.Cost, progress, quality three elements are to run through construction overall process in project management Key element, be the key point that can project smoothly complete, can enterprise get a profit.
Progress control is in item construction management, and most crucial content is that the construction quality of project, progress and investment are controlled System.Before the project implementation, it is necessary to formulate the schedule of practicable science in advance.Due to the backwardness of management means, existing entry There is the problems such as responsibility distribution is not in place, supervises not in time in mesh progress control, scientific in accountability, Schedule monitoring etc. Have much room for improvement.
The content of the invention
It is an object of the invention to provide a kind of construction project construction project time management method and its management system, with solution State the problem of being proposed in background technology.
To achieve the above object, the present invention provides following technical scheme:
A kind of construction project construction project time management method, comprises the following steps:
S1, start-up course, the discussion of item manager branch is first passed through, determine aggregate scheduling control plan, then assign project duty Appoint target;
S2, planning process, including technique preparation and tissue prepare, and the technique preparation mainly includes to technical scheme, applied Work technique and specification and the preparation of drawing joint examination, the tissue prepare the mainly foundation including complex and formulate regular meeting system Degree;
S3, implementation process, it is divided into and confides a technological secret and allocate resource, establishment officer and other resources is told somebody what one's real intentions are book according to schedule Content Organizing is implemented;
S4, control process, including:Inspect periodically, compile inspection data, schedule variance amendment and Plan rescheduling, lead to Inspection, the analysis to segmenting project are crossed, analyzes schedule variance and producing cause, and takes regulating measures, corrigendum plan in time, is protected Hold progress;
S5, epilog, including project schedule control are summarized, and complete the contract object with owner's agreement.
As the further scheme of the present invention:In step s3, it is described to confide a technological secret including following aspect:Work is completed in plan Measure, resource, technical specification volume and procedure arrangement table need to be used.
As the further scheme of the present invention:The technical specification volume can also be substituted by job instruction.
As the further scheme of the present invention:In step S2, drawing is made a joint checkup and carried out using expert consulting mode, is at least consulted Three experts are ask, and drawing is examined and given a mark, and enclose comment.
A kind of construction project construction project time management system, including:Data Enter unit, information maintenance unit and report generation Unit, described information typing unit include text information module and image information module, and the text information module is used for typing And the text information of construction speed information is stored, described image information module is used for typing and stores the picture of construction speed information Information;
Described information maintenance unit includes verification module and analysis module, and the verification module is used for construction speed information Matched, be compared with project baseline file with confiding a technological secret;The analysis module is used for the verification according to verification module As a result analyzed, generation control analysis result.
As the further scheme of the present invention:The report generation unit is used for all subdivision project progress messages and right The control analysis result answered collects and generates report display.
As the further scheme of the present invention:The project baseline file can be project schedule control planning chart.
Compared with prior art, the beneficial effects of the invention are as follows:
1st, by adding regular meeting system, construction speed and organization work are periodically discussed, ensure construction speed situation in time more Newly, avoid omitting;
2nd, periodically checked, and be analyzed and summarized, understand schedule deviation, to make amendment in time, kept Progress meets plan and arranged, and improves reasonability.
Brief description of the drawings
Fig. 1 is a kind of schematic flow sheet of construction project construction project time management method.
Fig. 2 is a kind of principle schematic of construction project construction project time management system.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of creative work is not made Embodiment, belong to the scope of protection of the invention.
Referring to Fig. 1, in the embodiment of the present invention, a kind of construction project construction project time management method, comprise the following steps:
S1, start-up course, the discussion of item manager branch is first passed through, determine aggregate scheduling control plan, then assign project duty Appoint target;
S2, planning process, including technique preparation and tissue prepare, and technique preparation is mainly included to technical scheme, construction work Skill and specification and the preparation of drawing joint examination, tissue prepare the mainly foundation including complex and formulate regular meeting system;
S3, implementation process, it is divided into and confides a technological secret and allocate resource, establishment officer and other resources is told somebody what one's real intentions are book according to schedule Content Organizing is implemented;
S4, control process, including:Inspect periodically, compile inspection data, schedule variance amendment and Plan rescheduling, lead to Inspection, the analysis to segmenting project are crossed, analyzes schedule variance and producing cause, and takes regulating measures, corrigendum plan in time, is protected Hold progress;
S5, epilog, including project schedule control are summarized, and complete the contract object with owner's agreement.
In step s3, confide a technological secret including following aspect:Plan complete workload, need to use resource, technical specification volume and Procedure arrangement table.
Technical specification volume can also be substituted by job instruction.
In step S2, drawing is made a joint checkup and carried out using expert consulting mode, at least seek advice from three experts, and drawing is carried out Examine and give a mark, and enclose comment.
Refering to Fig. 2,
A kind of construction project construction project time management system, including:Data Enter unit 100, information maintenance unit 200 and report Table generation unit 300, Data Enter unit 100 include text information module 101 and image information module 102, text information mould Block 101 is used for typing and stores the text information of construction speed information, image information module 102 be used for typing and storing construct into Spend the pictorial information of information;Information maintenance unit 200 includes verification module 201 and analysis module 202, and verification module 201 is used for Construction speed information is matched, is compared with project baseline file with confiding a technological secret;Analysis module 201 is used for according to core The checked result of module 201 is analyzed, generation control analysis result, to make amendment to plan.
Report generation unit 300 is used to all subdivision project progress messages and corresponding control analysis result are collected and given birth to Into report display.Project baseline file can be project schedule control planning chart.
It is obvious to a person skilled in the art that the invention is not restricted to the details of above-mentioned one exemplary embodiment, Er Qie In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, the scope of the present invention is by appended power Profit requires rather than described above limits, it is intended that all in the implication and scope of the equivalency of claim by falling Change is included in the present invention.Any reference in claim should not be considered as to the involved claim of limitation.
Moreover, it will be appreciated that although the present specification is described in terms of embodiments, not each embodiment is only wrapped Containing an independent technical scheme, this narrating mode of specification is only that those skilled in the art should for clarity Using specification as an entirety, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art It is appreciated that other embodiment.

Claims (7)

  1. A kind of 1. construction project construction project time management method, it is characterised in that comprise the following steps:
    S1, start-up course, the discussion of item manager branch is first passed through, determine aggregate scheduling control plan, then assign program accountability mesh Mark;
    S2, planning process, including technique preparation and tissue prepare, and the technique preparation is mainly included to technical scheme, construction work Skill and specification and the preparation of drawing joint examination, the tissue prepare the mainly foundation including complex and formulate regular meeting system;
    S3, implementation process, it is divided into and confides a technological secret and allocate resource, establishment officer and other resources is told somebody what one's real intentions are the content of book according to schedule Organize and implement;
    S4, control process, including:Inspect periodically, compile inspection data, schedule variance amendment and Plan rescheduling, by right The inspection of subdivision project, analysis, analyze schedule variance and producing cause, and take regulating measures, in time corrigendum plan, keep into Degree;
    S5, epilog, including project schedule control are summarized, and complete the contract object with owner's agreement.
  2. A kind of 2. construction project construction project time management method according to claim 1, it is characterised in that:In step s3, It is described to confide a technological secret including following aspect:Plan completes workload, need to use resource, technical specification volume and procedure arrangement table.
  3. A kind of 3. construction project construction project time management method according to claim 2, it is characterised in that:The technical specification Volume can also be substituted by job instruction.
  4. A kind of 4. construction project construction project time management method according to claim 1, it is characterised in that:It is right in step S2 Drawing joint examination is carried out using expert consulting mode, at least seeks advice from three experts, and drawing is examined and given a mark, and is enclosed and commented Language.
  5. 5. a kind of management system based on construction project construction project time management method as described in claim 1-4 is any, it is special Sign is,
    Including:Data Enter unit 100, information maintenance unit 200 and report generation unit 300, described information typing unit 100 Including text information module 101 and image information module 102, the text information module 101 be used for typing and storing construct into The text information of information is spent, described image information module 102 is used for typing and stores the pictorial information of construction speed information;
    Described information maintenance unit 200 includes verification module 201 and analysis module 202, and the verification module 201 is used for will construction Progress msg is matched, is compared with project baseline file with confiding a technological secret;The analysis module 201 is used for according to verification The checked result of module 201 is analyzed, generation control analysis result.
  6. A kind of 6. construction project construction project time management system according to claim 5, it is characterised in that:The report generation Unit 300 is used to collect all subdivision project progress messages and corresponding control analysis result and generates report display.
  7. A kind of 7. construction project construction project time management system according to claim 5, it is characterised in that:The project is initial Data can be project schedule control planning chart.
CN201710649810.3A 2017-08-02 2017-08-02 A kind of construction project construction project time management method and its management system Pending CN107403277A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710649810.3A CN107403277A (en) 2017-08-02 2017-08-02 A kind of construction project construction project time management method and its management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710649810.3A CN107403277A (en) 2017-08-02 2017-08-02 A kind of construction project construction project time management method and its management system

Publications (1)

Publication Number Publication Date
CN107403277A true CN107403277A (en) 2017-11-28

Family

ID=60402620

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710649810.3A Pending CN107403277A (en) 2017-08-02 2017-08-02 A kind of construction project construction project time management method and its management system

Country Status (1)

Country Link
CN (1) CN107403277A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110852638A (en) * 2019-11-15 2020-02-28 南京慧石建筑科技有限公司 Construction project progress and cost management system
CN116109213A (en) * 2023-04-12 2023-05-12 江西通慧科技集团股份有限公司 Project security inspection method and system applied to construction scene and electronic equipment

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104899799A (en) * 2015-06-30 2015-09-09 江苏冲浪软件科技有限公司 Project management system
CN106897861A (en) * 2017-02-16 2017-06-27 龙岩学院 A kind of project management system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104899799A (en) * 2015-06-30 2015-09-09 江苏冲浪软件科技有限公司 Project management system
CN106897861A (en) * 2017-02-16 2017-06-27 龙岩学院 A kind of project management system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110852638A (en) * 2019-11-15 2020-02-28 南京慧石建筑科技有限公司 Construction project progress and cost management system
CN116109213A (en) * 2023-04-12 2023-05-12 江西通慧科技集团股份有限公司 Project security inspection method and system applied to construction scene and electronic equipment

Similar Documents

Publication Publication Date Title
Aspinwall et al. TPM implementation in large and medium size organisations
Montgomery A modern framework for achieving enterprise excellence
Russell et al. Case studies of the allocation and reduction of time buffer through use of the last planner system
Fleischmann et al. Subject-oriented BPM= socially executable BPM
Lin et al. A reappraisal on advanced planning and scheduling systems
Seidel et al. A framework for analyzing how context influences lean leadership
CN107403277A (en) A kind of construction project construction project time management method and its management system
Tillmann Using the Last Planner System to tackle the social aspects of BIM-enabled MEP coordination
Kabachinski Have you heard of ITIL? It's time you did
Vieira et al. Technologies integration for distributed manufacturing scheduling in a virtual enterprise
Divakar et al. Critical success factors in the real-time monitoring of construction projects
Gufroni Information systems strategic planning at the Siliwangi University Tasikmalaya
Ahmed et al. Integration of Six Sigma and simulations in real production factory to improve performance–a case study analysis
Parchamijalal et al. Claim management office maturity model (CMOMM) in project-oriented organizations in the construction industry
Bocewicz et al. Robust competence allocation for multi-project scheduling
Sousa et al. Applying an enterprise engineering approach to engineering work: a focus on business process modeling
Gustavsson Practices for vertical and horizontal coordination in the Scaled Agile Framework
Van Den Eeckhout et al. Mode generation rules to define activity flexibility for the integrated project staffing problem with discrete time/resource trade-offs
Warid et al. Lean Construction in the UAE: Implementation of Last Planner System®
Kohlgrüber et al. Understanding future skills and enriching the skills debate
Biazzo et al. Virtual visual planning: A methodology to assess digital project management tools
Lau et al. Quality management framework for a virtual enterprise network: a multi‐agent approach
Nolan-McSweeney et al. Engineering the right change culture in a complex (GB) rail industry
Li et al. Metric-based tracking management in software maintenance
Martin et al. Practicalities of participation: Stakeholder involvement in an electronic patient records project

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171128

RJ01 Rejection of invention patent application after publication