CN107401124A - The Bridge Erector of T-shaped beam bridge - Google Patents
The Bridge Erector of T-shaped beam bridge Download PDFInfo
- Publication number
- CN107401124A CN107401124A CN201710835392.7A CN201710835392A CN107401124A CN 107401124 A CN107401124 A CN 107401124A CN 201710835392 A CN201710835392 A CN 201710835392A CN 107401124 A CN107401124 A CN 107401124A
- Authority
- CN
- China
- Prior art keywords
- bridge
- girder
- guide column
- shaped beam
- erector
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/06—Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
Abstract
The present invention relates to T-shaped beam bridge setting up girder technical field, there is provided a kind of Bridge Erector of T-shaped beam bridge.Including girder, girder is provided with the two hanging beam dollies that can be moved along its length, the rear portion of girder is set up in bridge floor by telescopic BB1, the front portion of girder is provided with telescopic frong guide column, frong guide column is set up in by the extension of bottom on the bridge pier at place to be set a roof beam in place, and the front portion of girder is additionally provided with the supporting leg that can be moved along its length;Hanging beam dolly include again moving cart and transverse shifting across beam.The mutual cooperation that this erecting machine is only relied between three supporting legs can complete the overall via of equipment, and simple to operate, step is clear and definite, greatly reduces the equipment via time, improves via efficiency.In addition, by liftable frong guide column and BB1, the overall landing of equipment can be achieved, make to change beam process is not influenceed by natural conditions such as wind-force, will not be made to fall beam to cause a deviation, be improved and change beam efficiency.
Description
Technical field
The present invention relates to the present invention relates to T-shaped beam bridge setting up girder technical field, and in particular to a kind of bridge formation of T-shaped beam bridge
Machine.
Background technology
Construction for simply supported girder bridge on newly built railway line, has had the Bridge Erector of many sizings, has been set by these now
It is standby, it is possible to achieve whole opening prefabricated safety beam, efficient erection, to substantially increase bridge construction speed.But due to existing Bridge Erector
Complete machine height seriously transfinites, therefore, under the conditions of existing line, old beam needs continuous beam after removing up to 8m during construction operation
If the situation of porous new beam, existing Bridge Erector just can not be applicable, a kind of New-Type Bridge Girder Erection Machine structural shape need to be proposed.
The content of the invention
The purpose of the present invention is to propose to it is a kind of can be safe efficient complete the erecting beam construction equipment of whole hole simple supported T-beam.
To achieve the above object, the invention provides a kind of Bridge Erector of T-shaped beam bridge, including girder, set on the girder
There are the two hanging beam dollies that can be moved along its length, the rear portion of the girder is set up in bridge by telescopic BB1
Face, the front portion of the girder are provided with telescopic frong guide column, and the frong guide column is set up in by the extension of bottom and waits the place that sets a roof beam in place
Bridge pier on, the front portion of the girder is additionally provided with the supporting leg that can be moved along its length.
Preferably, the frong guide column and BB1 are telescopic oil cylinder.
Preferably, the bottom of the frong guide column and BB1 is equipped with runners.
Preferably, in addition to two rows of tracks and multiple loop wheel machine sleeper beams, multiple loop wheel machine sleeper beams, which are erected at, changes beam position two
On the T-shaped beam bridge of side, two tracks are respectively erected on multiple loop wheel machine sleeper beams of both sides to be changed of setting a roof beam in place.
Preferably, the both sides of the track are extended at the both ends of multiple loop wheel machine sleeper beams, described leading for supporting
Post and BB1.
Preferably, in addition to two fortune beam dollies, two fortune beam dollies are used to carry out feeding beam to two hanging beam dollies.
Preferably, in addition to two cushion blocks, two cushion block activity mats are located at the lower section of two hanging beam dollies.
Preferably, the lower section of the hanging beam dolly is provided with hoist engine.
From the foregoing, it will be observed that the mutual cooperation that this erecting machine is only relied between three supporting legs can complete the overall via of equipment, behaviour
Make simply, step is clear and definite, greatly reduces the equipment via time, improves via efficiency.In addition, pass through liftable frong guide column
And BB1, the overall landing of equipment can be achieved, make to change beam process is not influenceed by natural conditions such as wind-force, will not make to fall beam to be made
Into deviation, improve and change beam efficiency;Furthermore it is also possible to effectively reduce the lifting altitude of equipment in work progress, realizing is having
Track clearance requirement operating mode under smoothly complete T-shaped beam change beam operation, it is ensured that former line facility is not caused it is any need not
On the premise of influenceing, that completes whole hole simple supported T-beam safe efficiently in " skylight point " changes frame construction.
Brief description of the drawings
Fig. 1 is a kind of stereogram of the Bridge Erector of double-T shaped beam bridge of the embodiment of the present invention;
Fig. 2 is the enlarged drawing at A in Fig. 1;
Fig. 3 is a kind of via state diagram one of the Bridge Erector of T-shaped beam bridge of the embodiment of the present invention;
Fig. 4 is a kind of via state diagram two of the Bridge Erector of T-shaped beam bridge of the embodiment of the present invention;
Fig. 5 is a kind of via state diagram three of the Bridge Erector of T-shaped beam bridge of the embodiment of the present invention;
Fig. 6 is a kind of state diagram one of setting a roof beam in place of the Bridge Erector of T-shaped beam bridge of the embodiment of the present invention;
Fig. 7 is a kind of state diagram two of setting a roof beam in place of the Bridge Erector of T-shaped beam bridge of the embodiment of the present invention;
Fig. 8 is a kind of state diagram three of setting a roof beam in place of the Bridge Erector of T-shaped beam bridge of the embodiment of the present invention.
Reference:
1st, hanging beam dolly;2nd, BB1;3rd, girder;4th, frong guide column;5th, cushion block;6th, extension;7th, supporting leg;8th, bridge pier;9、
Transport beam dolly;10th, wait to set a roof beam in place;11st, lift rope;12nd, moving cart;13rd, across beam;14th, the edge of a wing.
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention
In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is
The part of the embodiment of the present invention, rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill people
The every other embodiment that member is obtained on the premise of creative work is not made, belongs to the scope of protection of the invention.
As shown in figure 1, a kind of T-shaped beam bridge provided in an embodiment of the present invention changes erecting machine, including girder 3, set on girder 3
There are the two hanging beam dollies 1 that can be moved along its length, hanging beam dolly 1 treats the new beam of frame for hanged;The rear portion of girder 3 passes through
Telescopic BB1 2 is set up in bridge floor, and the front portion of girder 3 is provided with telescopic frong guide column 4, and frong guide column 4 is added by bottom
Meropodium 6 is set up on the bridge pier 8 for waiting to set a roof beam in place at 10, and the front portion of girder 3 is additionally provided with the supporting leg 7 that can be moved along its length, preceding
Guide pillar 4 and BB1 2 specifically can use telescopic oil cylinder, girder 3 and two hanging beam dollies 1 is done lifting fortune
It is dynamic, realized with this and treat rising and falling for the new beam of frame.
With reference to shown in figure 3 to Fig. 5, during via, the frong guide column 4 and BB1 2 of Bridge Erector shrink, and two on girder 3 hang
Beam dolly 1, which is supported on, both set a roof beam in place on bridge floor, and bridge floor is left in the bottom of frong guide column 4 and BB1 2, hanging beam dolly 1 drive girder 3 to
Preceding movement, hanging beam dolly 1 pass through the moveable supporting leg 7 of the front end of girder 3 first during driving girder 3 moves forward
It is supported on bridge pier 8, so that the front end of girder 3 obtains temporary support, until frong guide column 4 and BB1 2 are moved respectively to set a roof beam in place
The top of two bridge piers 8 of opening position, frong guide column 4 and BB1 2 stretch out and are supported on two bridges of opening position of setting a roof beam in place still further below
On pier 8, girder 3 is propped up upwards.
With reference to shown in figure 6 to Fig. 8, when setting a roof beam in place, two hanging beam dollies 1 are moved to the rear end of girder 3, coordinate two one by one
Transport beam dolly 9 and carry out feeding beam, two hanging beam dollies 1 will be after the new beam of frame be hoisted to above position of setting a roof beam in place, frong guide column 4 and BB1
2 shrink, and treat that the new beam of frame together falls with girder 3, on final erection to bridge pier 8.
The mutual cooperation that this erecting machine is only relied between three supporting legs 7 can complete the overall via of equipment, simple to operate, step
It is rapid clear and definite, the equipment via time is greatly reduced, improves via efficiency.In addition, pass through liftable frong guide column 4 and BB1
2, the overall landing of equipment can be achieved, make to change beam process is not influenceed by natural conditions such as wind-force, will not make to fall beam to cause a deviation,
Improve and change beam efficiency;Furthermore it is also possible to effectively reduce the lifting altitude of equipment in work progress, realizing is having track clearance
It is required that operating mode under smoothly complete T-shaped beam change beam operation, it is ensured that do not cause any unnecessary influence on former line facility
Under the premise of, that completes whole hole simple supported T-beam safe efficiently in " skylight point " changes frame construction.
In certain embodiments, the bottom of frong guide column 4 and BB1 2 is equipped with runners, and runners can increase frong guide column 4 with after
The support strength and stability of guide pillar 2, and runners cross-sectional area is preferably greater than the cross-sectional area of frong guide column 4 and BB1 2, so
The lifting surface area of support is bigger, and support is more steady.
The system also includes two rows of tracks and multiple loop wheel machine sleeper beams, multiple loop wheel machine sleeper beams are erected at the T for changing beam position both sides
On type beam bridge, two tracks are respectively erected on multiple loop wheel machine sleeper beams of both sides to be changed of setting a roof beam in place, and two tracks are each fortune beam special train
And the dedicated track of fortune beam dolly 9.
Further, the both ends of multiple loop wheel machine sleeper beams extend the both sides of errant, for supporting frong guide column 4 and BB1
2, the material of loop wheel machine sleeper beam is firm, sets steady, to first upside-down mounting gantry, second upside-down mounting gantry and can change erecting machine and is formed surely
Fixed support.
With reference to shown in figure 3 and Fig. 4, originally changing erecting machine preferably also includes two cushion blocks 5, and two activity mats of cushion block 5 are located at two
The lower section of platform hanging beam dolly 1, i.e., in via, when the frong guide column 4 and BB1 2 of Bridge Erector shrink, two on girder 3 are hung
Beam dolly 1 is supported on by a cushion block 5 both set a roof beam in place on bridge floor respectively, and the pad that on the one hand can so increase girder 3 sets height,
On the other hand, during hanging beam dolly 1 drives girder 3 to move forward, when supporting leg 7 is supported on bridge pier 8, now girder
3 is less positioned at the part at the rear of hanging beam dolly 1, and has reached the rear end of girder 3 by the latter hanging beam dolly 1, this
When the dismountable cushion block 5 by the lower section of the latter hanging beam dolly 1, the hanging beam dolly 1 is moved forward along girder 3, and girder 3 then leads to
Cross the support by previous hanging beam dolly 1 and supporting leg 7 and by being continued to move along by the driving of previous hanging beam dolly 1.
In addition, the lower section of hanging beam dolly 1 is preferably also provided with hoist engine, i.e. hanging beam dolly 1 will be treated by the hoist engine of lower section
10 bindings set a roof beam in place thereunder, and during via, the binding that hanging beam dolly 1 can be by the hoist engine of lower section with both having set a roof beam in place
To increase the stability of hanging beam dolly 1.
With reference to shown in Fig. 1 and Fig. 2, the embodiment of the present invention additionally provides a kind of erecting machine that changes of double-T shaped beam bridge, girder 3
Both lateral sides have the edge of a wing 14;Hanging beam dolly 1 includes moving cart 12 and is provided with and master across beam 13, the top of moving cart 12
The driving wheel that the top side on the edge of a wing 14 of the both sides of beam 3 coordinates, the i.e. top of moving cart 12 have two row's driving wheels, and moving cart 12 is led to
Cross the cooperation of two row's driving wheels and 3 liang of side wing edges 14 of girder and hang and be located on girder 3, the driving wheel is used to drive moving cart 12
Moved along the length direction of girder 3;The bottom side of hanging beam dolly 1 is provided with mounting groove, is arranged in mounting groove and passes through across beam 13
Drive mechanism is provided with hoist engine, the lift rope 11 of hoist engine treats frame for binding relative to the transverse shifting of girder 3 across beam 13
New beam or old beam to be replaced, by the contraction of lift rope 11, the new beam of frame or old beam being bundled under girder 3 tightly will be treated
Side, and then by the transverse shifting across beam 13 relative to girder 3, realize that the bias of T-shaped beam is risen and fallen, so as to realize T-shaped beam bridge
The replacing of upstream side and downlink side roof beam structure.
In summary, it is proposed by the present invention change erecting beam construction technology can ensure not cause existing line it is any unnecessary broken
On the premise of bad, frame construction is changed in the whole hole that freely-supported " T " beam on existing line is safely and fast completed in " skylight point ", effectively
Ground solves the problem of current cost height, workload during changing erecting beam construction, long-term closed-loop, is available for road bureau's permanent-way technology
It is equipped with and uses.
Finally it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although
The present invention is described in detail with reference to the foregoing embodiments, it will be understood by those within the art that:It still may be used
To be modified to the technical scheme described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic;
And these modification or replace, do not make appropriate technical solution essence depart from various embodiments of the present invention technical scheme spirit and
Scope.
Claims (8)
1. a kind of Bridge Erector of T-shaped beam bridge, it is characterised in that including girder, the girder is provided with and can transported along its length
Two dynamic hanging beam dollies, the rear portion of the girder are set up in bridge floor by telescopic BB1, and the front portion of the girder is set
There is telescopic frong guide column, the frong guide column is set up in by the extension of bottom on the bridge pier at place to be set a roof beam in place, the girder
Front portion is additionally provided with the supporting leg that can be moved along its length.
2. the Bridge Erector of T-shaped beam bridge according to claim 1, it is characterised in that the frong guide column and BB1 are to stretch
Contracting oil cylinder.
3. the Bridge Erector of T-shaped beam bridge according to claim 2, it is characterised in that the bottom of the frong guide column and BB1
It is equipped with runners.
4. the Bridge Erector of T-shaped beam bridge according to claim 1, it is characterised in that also including two rows of tracks and multiple loop wheel machines
Sleeper beam, multiple loop wheel machine sleeper beams, which are erected at, to be changed on the T-shaped beam bridge of beam position both sides, and two tracks are respectively erected in be changed
Set a roof beam in place on multiple loop wheel machine sleeper beams of both sides.
5. the Bridge Erector of T-shaped beam bridge according to claim 1, it is characterised in that the both ends of multiple loop wheel machine sleeper beams are equal
Extend the both sides of the track, for supporting the frong guide column and BB1.
6. the Bridge Erector of T-shaped beam bridge according to claim 1, it is characterised in that also including two fortune beam dollies, two fortune
Beam dolly is used to carry out feeding beam to two hanging beam dollies.
7. the Bridge Erector of T-shaped beam bridge according to claim 1, it is characterised in that also lived including two cushion blocks, two cushion blocks
Dynamic pad is located at the lower section of two hanging beam dollies.
8. the Bridge Erector of T-shaped beam bridge according to claim 1, it is characterised in that the lower section of the hanging beam dolly is provided with volume
Raise machine.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710835392.7A CN107401124A (en) | 2017-09-15 | 2017-09-15 | The Bridge Erector of T-shaped beam bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710835392.7A CN107401124A (en) | 2017-09-15 | 2017-09-15 | The Bridge Erector of T-shaped beam bridge |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107401124A true CN107401124A (en) | 2017-11-28 |
Family
ID=60388296
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710835392.7A Pending CN107401124A (en) | 2017-09-15 | 2017-09-15 | The Bridge Erector of T-shaped beam bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107401124A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109019332A (en) * | 2018-09-30 | 2018-12-18 | 田间 | A kind of aerial slide device and method of T plate |
CN110606447A (en) * | 2019-10-15 | 2019-12-24 | 合肥正浩机械科技有限公司 | Lifting and carrying device for precast beam of bridge girder erection machine on beam transporting vehicle and working method of lifting and carrying device |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2585888Y (en) * | 2001-06-07 | 2003-11-12 | 中铁三局集团邯郸工程机械制造有限公司 | Walking and telescopic single nose girder bridging machinery |
CN2753788Y (en) * | 2005-01-06 | 2006-01-25 | 北京万桥兴业机械有限公司 | Auxiliary nose-girder type bridging machine |
CN101144259A (en) * | 2007-09-20 | 2008-03-19 | 中铁二局股份有限公司 | Large tonnage whole opening box girder transmitting and construction method |
JP2010047905A (en) * | 2008-08-19 | 2010-03-04 | Ihi Corp | Apparatus and method for cantilever overhanging bridge |
CN101851898A (en) * | 2010-06-09 | 2010-10-06 | 中铁科工集团有限公司 | Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof |
JP2014066007A (en) * | 2012-09-24 | 2014-04-17 | Nexco-East Engineering Co Ltd | Removal method of existent bridge and renewal method of existent bridge |
CN207567670U (en) * | 2017-09-15 | 2018-07-03 | 中铁第五勘察设计院集团有限公司 | The Bridge Erector of T-shaped beam bridge |
-
2017
- 2017-09-15 CN CN201710835392.7A patent/CN107401124A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2585888Y (en) * | 2001-06-07 | 2003-11-12 | 中铁三局集团邯郸工程机械制造有限公司 | Walking and telescopic single nose girder bridging machinery |
CN2753788Y (en) * | 2005-01-06 | 2006-01-25 | 北京万桥兴业机械有限公司 | Auxiliary nose-girder type bridging machine |
CN101144259A (en) * | 2007-09-20 | 2008-03-19 | 中铁二局股份有限公司 | Large tonnage whole opening box girder transmitting and construction method |
JP2010047905A (en) * | 2008-08-19 | 2010-03-04 | Ihi Corp | Apparatus and method for cantilever overhanging bridge |
CN101851898A (en) * | 2010-06-09 | 2010-10-06 | 中铁科工集团有限公司 | Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof |
JP2014066007A (en) * | 2012-09-24 | 2014-04-17 | Nexco-East Engineering Co Ltd | Removal method of existent bridge and renewal method of existent bridge |
CN207567670U (en) * | 2017-09-15 | 2018-07-03 | 中铁第五勘察设计院集团有限公司 | The Bridge Erector of T-shaped beam bridge |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109019332A (en) * | 2018-09-30 | 2018-12-18 | 田间 | A kind of aerial slide device and method of T plate |
CN110606447A (en) * | 2019-10-15 | 2019-12-24 | 合肥正浩机械科技有限公司 | Lifting and carrying device for precast beam of bridge girder erection machine on beam transporting vehicle and working method of lifting and carrying device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201250064Y (en) | Front launching nose type bridge girder erection machine for bridge erection | |
CN107386128A (en) | Double-T shaped beam bridge changes beam construction system | |
CN109763430A (en) | A kind of Bridge Erector that curve via holes are set a roof beam in place and its application method | |
CN207498755U (en) | A kind of traveling trolley adjusted with horizontal extension and vertical supporting | |
CN207567659U (en) | Double-T shaped beam bridge changes beam construction system | |
CN207932932U (en) | A kind of twin beams slope Bridge Erector | |
CN101787678A (en) | Large-span section assembling bridge manufacturing machine and assembling construction process thereof | |
CN107604828A (en) | The Bridge Erector of double-T shaped beam bridge | |
CN110273375B (en) | Bridge erecting machine | |
CN107604825A (en) | The bridging method of T-shaped beam bridge | |
CN106758872A (en) | Wavelike steel webplate SCC engineering methods hang movable hanging basket and the method using its construction with car convolution | |
CN207567670U (en) | The Bridge Erector of T-shaped beam bridge | |
CN110158486B (en) | Bridge girder erection machine for erecting spliced wide beams and construction method | |
CN210561749U (en) | Multi-frame juxtaposed double-cantilever bridge girder erection machine | |
CN107401124A (en) | The Bridge Erector of T-shaped beam bridge | |
CN110205948A (en) | A kind of expanded letter Bridge Erector and its erection method | |
CN106400700A (en) | Double-line cantilever type bridge formation machine | |
CN107311047B (en) | The steel box-girder lift structure and method for improving of large span bondbeam | |
CN204059201U (en) | Bridge Erector | |
CN203866709U (en) | Bridge girder erection machine used for integrally laying steel girders and ballast bed plates | |
CN102071641A (en) | Integral bridge girder erection machine of distributed landing leg type transportation rack of concrete beam packing bridge crane and bridge girder erection engineering method thereof | |
CN112323657A (en) | Integrated prefabricated bridge dismantling machine and prefabricated bridge dismantling method | |
CN204151685U (en) | Rear feeding beam formula steel girder segment cantilever Bridge Erector | |
CN207567672U (en) | T-shaped beam bridge and double-T shaped beam bridge change erecting machine | |
CN207987782U (en) | The Bridge Erector of double-T shaped beam bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |