CN107387093A - A kind of shallow buried covered excavation system and construction method suitable for soft soil layer - Google Patents

A kind of shallow buried covered excavation system and construction method suitable for soft soil layer Download PDF

Info

Publication number
CN107387093A
CN107387093A CN201710679701.6A CN201710679701A CN107387093A CN 107387093 A CN107387093 A CN 107387093A CN 201710679701 A CN201710679701 A CN 201710679701A CN 107387093 A CN107387093 A CN 107387093A
Authority
CN
China
Prior art keywords
unit
shallow buried
right arm
buried covered
milling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710679701.6A
Other languages
Chinese (zh)
Inventor
张宏
张东
韩竹青
郭峰
卞正涛
游大江
王利民
姜瑞军
田建华
高琨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BCEG Civil Engineering Co Ltd
Original Assignee
BCEG Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BCEG Civil Engineering Co Ltd filed Critical BCEG Civil Engineering Co Ltd
Priority to CN201710679701.6A priority Critical patent/CN107387093A/en
Publication of CN107387093A publication Critical patent/CN107387093A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of shallow buried covered excavation system and construction method suitable for soft soil layer, shallow buried covered excavation system includes fuselage, left arm, right arm, injection unit and the supply unit being arranged on fuselage, the injection unit are arranged on the middle part of fuselage, and the supply unit is in waist;Excavation lift unit is provided with the left arm, Rockbolt element is provided with the right arm and unit is dug in milling, each unit modularization is arranged on the left arm and right arm of fuselage;The shallow buried covered excavation system also includes the unit that is unearthed;Track on the unearthed unit is arranged in main track tunnel, and conveyer belt is arranged in the transverse passage-way vertical with main track tunnel, and electric transporting vehicle is set in orbit, and claw bucket sling is arranged at the port of vertical shaft.Shallow buried covered excavation system and construction method provided by the invention, integrated mechanization environmental protection construction is realized, the efficiency of constructing tunnel is improved, reduces labor intensity, improve the security of construction, greatly improve Tunnel Engineering mechanized construction technical merit.

Description

A kind of shallow buried covered excavation system and construction method suitable for soft soil layer
Technical field
The present invention relates to technical field of tunnel construction, more particularly to a kind of shallow buried covered excavation system suitable for soft soil layer and Construction method.
Background technology
Shallow burial hidden digging is to carry out one kind side of all kinds underground chamber boring construction in the underground nearer apart from earth's surface Method.In the weak surrounding rock stratum of cities and towns, the constructing underground building under the conditions of shallow embedding, premised on transforming geological conditions, with control Ground settlement is attached most importance to, and preliminary bracing means, referred to as shallow burial hidden digging are used as using grid and spray anchor.Shallow buried covered excavation technology Although developing in constantly improve, each construction link is still constructed mainly by manpower, is had the following disadvantages in construction:
(1)Low construction efficiency, average day construction production efficiency is only to realize that tunnel machine is turned into the 8.3% of the shield method of industry.
(2)Artificial to excavate the earthwork using shovel, spade, pick, labor intensity is big;
(3)Operating environment is poor, and dust pollution influences the occupational health of workmen than more serious in hole.
The content of the invention
The purpose of the present invention is to be directed to above-mentioned technical problem, there is provided a kind of shallow buried covered excavation system suitable for soft soil layer And construction method, its is rational in infrastructure, realizes integrated mechanization environmental protection construction, improves the efficiency of constructing tunnel, reduce labor Fatigue resistance, the security of construction is improved, greatly improve Tunnel Engineering mechanized construction technical merit.
Technical scheme
In order to solve the above technical problems, a kind of shallow buried covered excavation system suitable for soft soil layer provided by the invention, including fuselage, Left arm, right arm, injection unit and the supply unit being arranged on fuselage;The injection unit is arranged on the middle part of fuselage, described Supply unit is penetrated by head to afterbody and set in waist, and excavation lift unit, the right arm are provided with the left arm On be provided with Rockbolt element and milling and dig unit, each unit modularization is arranged on the left arm and right arm of fuselage;The shallow buried covered excavation system System also includes the unit that is unearthed;The unearthed unit includes electric transporting vehicle, track, conveyer belt and claw bucket sling, and track is arranged on just In threaded list road, conveyer belt is arranged in the transverse passage-way vertical with main track tunnel, and electric transporting vehicle is set in orbit, and claw bucket sling is set Put at the port of vertical shaft.
Further, the track is additionally arranged in transverse passage-way, and the track in transverse passage-way leads to the track in main track tunnel Cross arc docking;The conveyer belt in track and transverse passage-way in transverse passage-way be arranged in parallel.
Simultaneously present invention also offers a kind of shallow buried covered excavation system construction method suitable for soft soil layer, it is specifically included Following steps:
S1, the hydrogeology and construction space information of job site are investigated, it is corresponding according to investigation information configuration shallow buried covered excavation system The size of each unit module;
S2, shallow buried covered excavation system each unit module is gone into the well, assembled, it is in place in face and carry out the preparation before construction;
S3, start the Rockbolt element on right arm, set advanced tubule;
S4, start the excavation lift unit on left arm, excavate the earthwork of face, the unit Real-Time Transport earthwork of being unearthed;
Unit is dug in S5, the milling started on right arm, is carried out frame trough position milling and is cutd open, the unit Real-Time Transport earthwork of being unearthed;
S6, start the lift unit on left arm, auxiliary installation grid or bow member;
S7, start injection unit, gunite concrete.
Further, in step S3, described the step of setting advanced tubule, is as follows:
S3-1, operating system right arm, right arm slide unit is set to move forward to front end;
S3-2, system right arm is adjusted, align the anchor pole on Rockbolt element accurate;
S3-3, open ductule and set device, conduit is squeezed into desired depth;
S3-4, control ductule set the retrogressing of device, reset system right arm.
Further, in step S4, it is described excavate face the earthwork the step of be:
S4-1, operating system left arm, excavation lift unit is set to adjust to correct position;
S4-2, operation excavate lift unit and carry out excavation operation, and control digging shovel is vertical with tunnel-side, excavates side wall frame trough;
S4-3, operation of slagging tap is carried out when excavating operation.
Further, in step S5, the step of frame trough position milling is cutd open, is:
S5-1, operates right arm, and cell position and angle are dug in regulation milling;
S5-2, open milling and dig finite element rotation controlling switch, carry out milling and dig operation;
S5-3, milling are dug after the completion of operation, and right arm resets;
Frame trough position is dug in S5-4, manual amendment milling.
Further, the step of unearthed unit Real-Time Transport earthwork is as follows:
Dregs is delivered to mechanical afterbody electric transporting vehicle by S6-1, mechanical supply unit band;
S6-2, electric transporting vehicle load dregs;
S6-3, electric transporting vehicle are transported in transverse passage-way by track;
S6-4, electric transporting vehicle topple over dregs to conveyer belt, and dregs is transported in vertical shaft by conveyer belt;
Dregs in vertical shaft is promoted to ground by S6-5, claw bucket sling.
Further, it is as follows the step of the gunite concrete in step S7:
S7-1, starts injection unit, and trial operation checks the air-tightness of injection unit;
S7-2, clean by spray plane, the concrete to stir is poured into injection unit;
S7-3, gunite concrete, makes concrete reach setting thickness from top to bottom.
Beneficial effect of the present invention:
A kind of shallow buried covered excavation system and construction method suitable for soft soil layer provided by the invention, its is rational in infrastructure, realizes Integrated mechanization environmental protection construction, improves the efficiency of constructing tunnel, reduces labor intensity, improve the security of construction, greatly Width improves Tunnel Engineering mechanized construction technical merit.
Brief description of the drawings
By the detailed description made in conjunction with the following drawings, above-mentioned advantage of the invention will be apparent and be easier reason Solution, these accompanying drawings are simply schematical, are not intended to limit the present invention, wherein:
Fig. 1 is shallow buried covered excavation system of the present invention(Be free of out figure unit)Structural representation;
Fig. 2 is the structural representation of the unit that is unearthed of shallow buried covered excavation system of the present invention;
Fig. 3 is the Dryopteris sublaetaChing et Hsu method flow diagram of the present invention suitable for soft soil layer;
Fig. 4 is the flow chart for setting advanced tubule of the present invention;
Fig. 5 is the flow chart of the earthwork of the excavation face of the present invention;
Fig. 6 is the flow chart that the frame trough position milling of the present invention is cutd open;
Fig. 7 is the flow chart of the unit Real-Time Transport earthwork of being unearthed of the present invention;
Fig. 8 is the flow chart of the gunite concrete of the present invention.
In accompanying drawing, the part representated by each label is as follows:
1. left arm;2. right arm;3. injection unit;4. excavate lift unit;5. Rockbolt element;6. unit is dug in milling;7. be unearthed unit; 8. electric transporting vehicle;9. track;10. conveyer belt;11. claw bucket sling;12. main track tunnel;13. transverse passage-way;14. vertical shaft;15. conveying Unit(Including conveyer belt and shovel board);16. shovel board;17. conveyer belt.
Embodiment
Fig. 1 to Fig. 8 is of the present invention a kind of suitable for the shallow buried covered excavation system of soft soil layer and the correlation of construction method Schematic diagram.With reference to specific embodiments and the drawings, the present invention is described in detail.
The embodiment recorded herein is specific embodiment of the invention, for illustrating the design of the present invention, It is explanatory and exemplary, should not be construed as the limitation to embodiment of the present invention and the scope of the invention.Except what is recorded herein Outside embodiment, those skilled in the art can also be based on the application claims and specification disclosure of that using aobvious and The other technical schemes being clear to, these technical schemes include any obvious using making for the embodiment to recording herein The technical scheme of substitutions and modifications.
The accompanying drawing of this specification is schematic diagram, aids in illustrating the design of the present invention, it is schematically indicated the shape of each several part And its correlation.It note that for the ease of clearly showing the structure of each part of the embodiment of the present invention, between each accompanying drawing Do not drawn according to identical ratio.Identical reference marker is used to represent identical part.
A kind of structural representation of shallow buried covered excavation system suitable for soft soil layer of the present invention, as shown in Figure 1(It is unearthed Unit is not shown), including fuselage, the left arm 1 and right arm 2 and injection unit 3 and supply unit 15 being arranged on fuselage, its feature It is, the injection unit 3 is arranged on the middle part of fuselage, and the supply unit 15 is penetrated by head to afterbody in waist Set, be provided with the left arm 1 and excavate lift unit 4, Rockbolt element 5 is provided with the right arm 2 and unit 6 is dug in milling, respectively Unit-modularized left arm 1 and right arm 2 installed in fuselage.
The shallow buried covered excavation system also includes the unit 7 that is unearthed, and Fig. 2 is the unit that is unearthed of shallow buried covered excavation system of the present invention Structural representation, it includes electric transporting vehicle 8, track 9, conveyer belt 10 and claw bucket sling 11, and track 9 is arranged on main track tunnel 12 Interior, conveyer belt 10 is arranged in the transverse passage-way 13 vertical with main track tunnel 12, and electric transporting vehicle 8 is arranged on track 9, claw bucket sling 11 are arranged at the port of vertical shaft 14.
The track 9 is additionally arranged in transverse passage-way 13, and the track 9 in transverse passage-way 13 and the track 9 in main track tunnel 12 are logical Cross arc docking;Track 9 in transverse passage-way 13 be arranged in parallel with the conveyer belt 10 in transverse passage-way 13.
Present invention also provides a kind of shallow buried covered excavation system construction method suitable for soft soil layer, such as its flow chart, Fig. 3 Shown, it specifically includes following steps:
S1, the hydrogeology and construction space information of job site are investigated, it is corresponding according to investigation information configuration shallow buried covered excavation system The size of each unit module;
Specifically, Construction in Preparatory Stage, drawing should be sufficiently familiar with, grasps design idea with requiring;Before construction, the hydrology should be checked Matter data, underground utilities, building etc. in the range of place are checked, and formulate corresponding safeguard measure;Construction stage, should be according to setting Count file and existing monitoring code requirement carries out construction monitoring, and feedback monitoring data in time, accomplish information-aided construction conscientiously;Machine Tool lectotype selection, site acceptance should meet the relevant regulations of this engineering method;Tunnel structure section, which need to adjust, meets mechanical arrangement and week Side job space safety requirements, inverted arch preferably select flat form.
The appearance and size and weight reasonable selection that workmen should equip according to site condition, shallow buried covered excavation have been lifted and reseted It is standby;Hold facility place should meet the needs of lectotype selection, and equipment hoisting area occupied of going into the well is preferably greater than 15m × 8m, and ground is held Carry Etech and be more than 2t/m2
S2, shallow buried covered excavation system each unit module is gone into the well, assembled, it is in place in face and carry out the beam worker before construction Make;
Specifically, the requirement of transition job instruction is equipped according to shallow buried covered excavation, carry out shallow buried covered excavation equipment goes into the well and assemble work Make, complete assembling and check and accept;Equipment should carry out safe practice to job site personnel using unit and tell somebody what one's real intentions are, and to equipment operation, safeguard Maintenance, maintenance personal carry out safety education;Equipment handling should formulate special scheme before going into the well, after report management examination & approval can handling, The crane capacity of lifting appliance should meet requirement by checking computations, and hoisting and hanging operation work in every should meet that safe practice is advised Range request;Vertical shaft headroom size is no less than 5m × 4m(Transverse passage-way ingate is arranged at short side), and should not in the range of this Any type of inner support be present, to ensure Clearance requirement that equipment is gone into the well.
S3, start the Rockbolt element 5 on right arm 2, set advanced tubule;
In this step, the flow chart for setting advanced tubule, as shown in figure 4, it specifically includes following steps:
S3-1, operating system right arm 2, right arm slide unit is set to move forward to front end;
S3-2, adjustment system right arm 2, align the anchor pole on Rockbolt element 5 accurate;
S3-3, open ductule and set device, conduit is squeezed into desired depth;
S3-4, control ductule set the retrogressing of device, reset system right arm 2.
It should be made hole position according to design requirement and wall rock condition, make a mark before drilling;Shallow buried covered excavation equipment slide unit moves Dynamic, right arm strenuous vibration and when rocking, forbids bore operation;After right arm is moved to specified location nearby, it should ensure that right arm is slow Smoothly move to bore position;Rockbolt element rotating speed is preferably reduced after drilling in place, steady retreat withdraws from operation hole;Bore operation During should be provided with special messenger and command, commanding need to shut down in advance as that need to approach inspection.Not handy hand examination during bore operation Hold drilling rod;Auxiliary impact mode can be taken by being obstructed such as drilling, such as can not still be solved, and should be shut down to search reason and take and accordingly be arranged Apply;When installing ductule, rig must be in stopped status, and ductule is screwed in into drill bushing;When right arm works, car body should approach leave from office Rank;Slide unit should be moved to forefront, fixed with taper bearing pin;In operation process, pipeline must not be squeezed in core by mechanical arm On cubsoil or hole wall.It should be noted that protection fluid pressure line, avoids it from being squeezed damage;After ductule is set, anchor pole is inverted Unit separates ductule and Rockbolt element;For silt, silty clay stratum, static pressure type Rockbolt element can be used to carry out small lead Pipe is set;Set vibration rotation type Rockbolt element can be used to carry out ductule containing cobble, rubble stratum;Should according to " first vault, The method progress ductule of both sides afterwards " sets construction, and every conduit must carry out slip casting operation in time after the completion of setting.
S4, start the excavation lift unit 4 on left arm 1, excavate the earthwork of face, the Real-Time Transport earthwork of unit 7 of being unearthed;
In this step, the flow chart of the earthwork for excavating face, as shown in figure 5, it specifically includes following steps:
S4-1, operating system left arm 1, excavation lift unit 4 is set to adjust to correct position;
S4-2, operation excavate lift unit and carry out excavation operation, and control digging shovel is vertical with tunnel-side, excavates side wall frame trough;
S4-3, operation of slagging tap is carried out when excavating operation.
Benching tunnelling method should take into full account operating condition of geology, excavated section span and plant equipment etc., step when constructing Length should meet design requirement or arrangement and method for construction;Earth excavation order should be from top to bottom, should first be excavated at vault middle part, after open Dig both sides;Both sides should be first excavated at inverted arch, it is rear to excavate middle part;Top bar is excavated when annular stays the construction of core local method, clay silt Stratum preferably uses milling to dig unit cutting soil;Extra-fine sand and sandy gravel preferably use hand excavation, and left arm auxiliary is unearthed;Excavate core It should ensure that Core Soil is regular when native, counter-slope must not occur;Break down or have abnormal sound, should parking checking, and cutting off immediately General supply;Answered when running into compared with ratchel or barrier it is to be cleaned after can excavate, not handy excavation lift unit is broken or with singly Stone is dug by force on side;It must be cut the earth again after complete machine comes to a complete stop during operation, excavation lift unit must not rise and fall too quickly;Lifted using excavation When unit excavates side wall frame trough and inverted arch frame trough, forbid to collide just branch tunnel wall;Extra-fine sand and sand-pebble layer are being opened When digging down step, stepped locations are settable to unload power groove, reduces soil body slump risk, and unload and stayed between power groove and top bar Core Soil The passage that personnel pass through should be met by putting width.
Unit 6 is dug in S5, the milling started on right arm 2, is carried out frame trough position milling and is cutd open, the Real-Time Transport earthwork of unit 7 of being unearthed.
In this step, the flow chart that frame trough position milling is cutd open, as shown in fig. 6, it specifically includes following steps:
S5-1, operates right arm 2, and cell position and angle are dug in regulation milling;
S5-2, open milling and dig finite element rotation controlling switch, carry out milling and dig operation;
S5-3, milling are dug after the completion of operation, and right arm 2 resets;
Frame trough position is dug in S5-4, manual amendment milling.
Unit is dug in mobile milling should be at the uniform velocity steady, ensures face stabilizer and avoids backbreaking;Milling dig cell operation when, support with Angle between right arm should be maintained at 0 ° ~ 90 °, forbid working under 180 ° of states;Milling, which is dug in operation process, must not damage core Cubsoil profile and size.
The flow chart of the Real-Time Transport earthwork of unearthed unit 7, as shown in fig. 7, it specifically includes following steps:
Dregs is delivered to mechanical afterbody electric transporting vehicle by S6-1, mechanical supply unit 15.
S6-2, electric transporting vehicle 8 load dregs;
S6-3, electric transporting vehicle 8 are transported in transverse passage-way 13 by track 9;
S6-4, electric transporting vehicle 8 topple over dregs to conveyer belt 10, and dregs is transported in vertical shaft 14 by conveyer belt 10;
Dregs in vertical shaft 14 is promoted to ground by S6-5, claw bucket sling 11.
Finally the dregs for being promoted to ground is transported outward and appeared on the scene.
The opening and closing left and right frame of the shovel board 16 of supply unit 15 should be able to left and right folding, driver should be noted that nurse during conveying, , should be according to the reasonable feeding of the working condition of supply unit 15 during usage mining 4 feeding of lift unit, unsuitable windrow is excessive.Conveying is single First 15 conveyer belt control devices should be able to realize positive and negative rotating function, the situation of getting stuck such as occur, can push ahead conveying handle, reversely rotation Transfer material motor;Then conveying handle is pulled back again.After releasing gets stuck, continue normal conveying;It can not be solved by repeatedly trial During except getting stuck, carry out inspection and maintenance should be shut down.When there is buildup in the bottom of shovel board 16, should by lifting, decline shovel board 16 and Shi Qingli buildups.Lift unit is excavated to forbid directly to hit opening and closing left and right frame and conveying trough.
S6, start the excavation lift unit 4 on left arm 1, auxiliary installation grid or bow member;
Specifically, first, grid does the flat processing of rammer, boarding cushion block for pin;Then, operation left arm joystick falls scraper bowl To proper height, frock is arranged on left arm fixed position;Then, bow member or grid are arranged on special tooling and fix tightly Gu;Then, operate left arm and bow member or grid are transported to riding position, manually installed fixed bow member or grid, operate left arm control Handle processed withdraws scraper bowl.
Grid arch springing should be squeezed into lock pin anchor tube by design requirement or be leveled up on the solid soil body;Grid/bow member should be in tunnel Road is set up in time after excavating, and steelframe sole void slag and debris should be removed before installation;Lock pin anchor tube, which sets angle and should met, to be set Count documentation requirements;Shaped steel arch, reinforcing bar grid and wall answer wedging, and every reinforcing bar grid node and adjacent grid must longitudinally divide It is not connected firmly, I-steel bow member can use Push-fit to install;The position of grid installation, joint connection, longitudinally connected muscle are answered Meet design requirement;Each section grid, connecting plate should be closely connected, and longitudinally connected muscle spacing should meet design requirement;Bar-mat reinforcement should be with tunnel Road section configuration is adapted, and is coupled with steelframe etc. firm;The grid spacing of bar-mat reinforcement should meet design requirement, and bar-mat reinforcement should be with Grid is connected firmly.
S7, start injection unit 3, gunite concrete.
In this step, the flow chart of the gunite concrete, as shown in figure 8, it specifically includes following steps:
S7-1, starts injection unit 3, and trial operation checks the air-tightness of injection unit 3;
S7-2, clean by spray plane, the concrete to stir is poured into injection unit 3;
S7-3, gunite concrete, makes concrete reach setting thickness from top to bottom.
Specifically, gunite concrete should mix accelerator, and raw material should meet the requirements, and forbidding to select has alkali active aggregate; Place cleaning is answered before gunite concrete, checks and excavates size, descum and deposit;It should conserve, support after gunite concrete 2h Protect the time should not be less than 14 days, when temperature be less than+5 DEG C, must not wet curing;Construction of shotcrete area temperature and compound enter Must not be less than by entering spraying machine temperature by+5 DEG C, and gunite concrete must not endure cold when being less than the 40% of design strength;Whitewashing personnel are necessary Protective articles is equipped with, other staff should be away from spray operation face;The spray regime of gunite concrete should be according to engineering geology and water The conditions such as literary geology, emitted dose determine;Gunite concrete is completed, and should lay measuring point in time, and obtains data, analysis branch at initial stage The situation of change of shield, so as to guiding construction;During gunite concrete, nozzle with being kept vertical substantially by spray plane, distance 0.6m~ 1.0m, each jet thickness 8cm~10cm;Grid, bar-mat reinforcement should be covered all by gunite concrete, and protective layer thickness should meet Design drawing requirement;When using crawler type shallow buried covered excavation equipment, inverted arch gunite concrete protective layer thickness preferably suitably thickens.
The shortcomings that compared to prior art and deficiency, a kind of shallow buried covered excavation system suitable for soft soil layer provided by the invention System and construction method, its is rational in infrastructure, realizes integrated mechanization environmental protection construction, improves the efficiency of constructing tunnel, reduce Labor intensity, the security of construction is improved, greatly improve Tunnel Engineering mechanized construction technical merit.
The present invention is not limited to the above-described embodiments, and anyone can draw other various forms under the enlightenment of the present invention Product, it is every that there is technical side identical or similar to the present application however, make any change in its shape or structure Case, it is within the scope of the present invention.

Claims (8)

1. a kind of shallow buried covered excavation system suitable for soft soil layer, including fuselage, the left arm being arranged on fuselage(1), right arm (2), injection unit(3)And supply unit(15), it is characterised in that the injection unit(3)The middle part of fuselage is arranged on, it is described Supply unit(15)In waist, penetrated and set by head to afterbody;The left arm(1)On be provided with excavation lift unit (4), the right arm(2)On be provided with Rockbolt element(5)And unit is dug in milling(6), left arm of each unit modularization installed in fuselage (1)And right arm(2);The shallow buried covered excavation system also includes the unit that is unearthed(7);The unearthed unit(7)Including electric transporting vehicle (8), track(9), conveyer belt(10)And claw bucket sling(11), track(9)It is arranged on main track tunnel(12)It is interior, conveyer belt(10)Set With main track tunnel(12)Vertical transverse passage-way(13)It is interior, electric transporting vehicle(8)It is arranged on track(9)On, claw bucket sling(11)If Put in vertical shaft(14)Port at.
2. it is applied to the shallow buried covered excavation system of soft soil layer according to claim 1, it is characterised in that the track(9)Also It is arranged on transverse passage-way(13)It is interior, transverse passage-way(13)Interior track(9)With main track tunnel(12)Interior track(9)Pass through arc pair Connect;Transverse passage-way(13)Interior track(9)With transverse passage-way(13)Interior conveyer belt(10)It is arranged in parallel.
A kind of 3. shallow buried covered excavation system construction method suitable for soft soil layer, it is characterised in that comprise the following steps:
S1, the hydrogeology and construction space information of job site are investigated, it is corresponding according to investigation information configuration shallow buried covered excavation system The size of each unit module;
S2, shallow buried covered excavation system each unit module is gone into the well, assembled, it is in place in face and carry out the preparation before construction;
S3, start right arm(2)On Rockbolt element(5), set advanced tubule;
S4, start left arm(1)On excavation lift unit(4), the earthwork of face is excavated, be unearthed unit(7)Real-Time Transport soil Side;
S5, start right arm(2)On milling dig unit(6), carry out frame trough position milling and cut open, be unearthed unit(7)The Real-Time Transport earthwork;
S6, start left arm(1)On excavation lift unit(4), aid in installation grid or bow member;
S7, start injection unit(3), gunite concrete.
4. it is applied to the shallow buried covered excavation system construction method of soft soil layer according to claim 3, it is characterised in that step S3 In, described the step of setting advanced tubule, is as follows:
S3-1, operating system right arm(2), right arm slide unit is moved forward to front end;
S3-2, adjust system right arm(2), make Rockbolt element(5)On anchor pole contraposition it is accurate;
S3-3, open advanced tubule and set device, conduit is squeezed into projected depth;
S3-4, control advanced tubule set the retrogressing of device, reset system right arm(2).
5. it is applied to the shallow buried covered excavation system construction method of soft soil layer according to claim 3, it is characterised in that step S4 In, it is described excavate face the earthwork the step of be:
S4-1, operating system left arm(1), make excavation lift unit(4)Adjust to correct position;
Lift unit is excavated in S4-2, operation(4)Excavation operation is carried out, control, which is dug, shovels, excavation side wall grid vertical with tunnel-side Groove;
S4-3, operation of slagging tap is carried out when excavating operation.
6. it is applied to the shallow buried covered excavation system construction method of soft soil layer according to claim 3, it is characterised in that step S5 In, the step of frame trough position milling is cutd open is:
S5-1, operate right arm(2), regulation milling digging unit(6)Position and angle;
S5-2, open milling and dig unit(6)Rotary control switch, carry out milling and dig operation;
S5-3, milling are dug after the completion of operation, right arm(2)Reset;
Frame trough position is dug in S5-4, manual amendment milling.
7. according to claim 3 be applied to soft soil layer shallow buried covered excavation system construction method, it is characterised in that it is described go out Native unit(7)The step of Real-Time Transport earthwork, is as follows:
S6-1, mechanical supply unit(15)Dregs is delivered to mechanical afterbody electric transporting vehicle(8);
S6-2, electric transporting vehicle(8)Load dregs;
S6-3, electric transporting vehicle(8)Pass through track(9)It is transported to transverse passage-way(13)It is interior;
S6-4, electric transporting vehicle(8)Dregs is toppled over to conveyer belt(10)On, conveyer belt(10)Dregs is transported to vertical shaft(14) It is interior;
S6-5, claw bucket sling(11)By vertical shaft(14)Interior dregs is promoted to ground.
8. it is applied to the shallow buried covered excavation system construction method of soft soil layer according to claim 3, it is characterised in that step S7 In, it is as follows the step of the gunite concrete:
S7-1, start injection unit(3), trial operation inspection injection unit(3)Air-tightness;
S7-2, clean by spray plane, the concrete to stir is poured into injection unit(3);
S7-3, gunite concrete, makes concrete reach design thickness from top to bottom.
CN201710679701.6A 2017-08-10 2017-08-10 A kind of shallow buried covered excavation system and construction method suitable for soft soil layer Pending CN107387093A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710679701.6A CN107387093A (en) 2017-08-10 2017-08-10 A kind of shallow buried covered excavation system and construction method suitable for soft soil layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710679701.6A CN107387093A (en) 2017-08-10 2017-08-10 A kind of shallow buried covered excavation system and construction method suitable for soft soil layer

Publications (1)

Publication Number Publication Date
CN107387093A true CN107387093A (en) 2017-11-24

Family

ID=60355320

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710679701.6A Pending CN107387093A (en) 2017-08-10 2017-08-10 A kind of shallow buried covered excavation system and construction method suitable for soft soil layer

Country Status (1)

Country Link
CN (1) CN107387093A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107893661A (en) * 2017-12-15 2018-04-10 成都格机械有限公司 Tunnel piercing chassis
CN108678753A (en) * 2018-03-29 2018-10-19 中交路桥北方工程有限公司 Reverse-slope tunnel construction method
CN110529121A (en) * 2019-09-05 2019-12-03 北京建工土木工程有限公司 A kind of water rich strata metro built by mining method mechanized construction method
CN110966016A (en) * 2019-12-30 2020-04-07 中铁隧道局集团有限公司 TBM host machine belt conveyor
CN113446009A (en) * 2021-06-01 2021-09-28 北京市政建设集团有限责任公司 Intelligent shallow-buried underground excavation operation method and equipment and storage medium
CN113684875A (en) * 2021-07-08 2021-11-23 浙江中瑞建筑工程有限公司 Construction process for ultra-wide deep foundation pit in soft soil stratum

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1494762A (en) * 1974-10-05 1977-12-14 Eickhoff Geb Tunnelling machines
US5050934A (en) * 1989-05-17 1991-09-24 Voest-Alpine Zeltweg Gesellschaft M.B.H. Shearing machine with roof-bolt drilling and setting devices
CN202500166U (en) * 2012-02-16 2012-10-24 徐州徐工铁路装备有限公司 Tunnel loading machine
CN105625487A (en) * 2014-10-31 2016-06-01 徐州徐工铁路装备有限公司 Underground tunnel digging equipment
CN106089230A (en) * 2016-07-23 2016-11-09 车新宁 The deslagging device of a kind of subway work and method thereof
CN106194171A (en) * 2016-08-11 2016-12-07 安徽宏昌机电装备制造有限公司 A kind of adaptivity digging all-in-one
CN207315380U (en) * 2017-08-10 2018-05-04 北京建工土木工程有限公司 A kind of shallow buried covered excavation system suitable for soft soil layer

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1494762A (en) * 1974-10-05 1977-12-14 Eickhoff Geb Tunnelling machines
US5050934A (en) * 1989-05-17 1991-09-24 Voest-Alpine Zeltweg Gesellschaft M.B.H. Shearing machine with roof-bolt drilling and setting devices
CN202500166U (en) * 2012-02-16 2012-10-24 徐州徐工铁路装备有限公司 Tunnel loading machine
CN105625487A (en) * 2014-10-31 2016-06-01 徐州徐工铁路装备有限公司 Underground tunnel digging equipment
CN106089230A (en) * 2016-07-23 2016-11-09 车新宁 The deslagging device of a kind of subway work and method thereof
CN106194171A (en) * 2016-08-11 2016-12-07 安徽宏昌机电装备制造有限公司 A kind of adaptivity digging all-in-one
CN207315380U (en) * 2017-08-10 2018-05-04 北京建工土木工程有限公司 A kind of shallow buried covered excavation system suitable for soft soil layer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
港口教材编写组, 北京:人民交通出版社 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107893661A (en) * 2017-12-15 2018-04-10 成都格机械有限公司 Tunnel piercing chassis
CN108678753A (en) * 2018-03-29 2018-10-19 中交路桥北方工程有限公司 Reverse-slope tunnel construction method
CN108678753B (en) * 2018-03-29 2019-11-08 中交路桥北方工程有限公司 Reverse-slope tunnel construction method
CN110529121A (en) * 2019-09-05 2019-12-03 北京建工土木工程有限公司 A kind of water rich strata metro built by mining method mechanized construction method
CN110966016A (en) * 2019-12-30 2020-04-07 中铁隧道局集团有限公司 TBM host machine belt conveyor
CN113446009A (en) * 2021-06-01 2021-09-28 北京市政建设集团有限责任公司 Intelligent shallow-buried underground excavation operation method and equipment and storage medium
CN113446009B (en) * 2021-06-01 2023-06-27 北京市政建设集团有限责任公司 Intelligent shallow buried underground excavation operation method, equipment and storage medium
CN113684875A (en) * 2021-07-08 2021-11-23 浙江中瑞建筑工程有限公司 Construction process for ultra-wide deep foundation pit in soft soil stratum
CN113684875B (en) * 2021-07-08 2022-08-23 浙江中瑞建筑工程有限公司 Soft soil stratum ultra-wide deep foundation pit construction process

Similar Documents

Publication Publication Date Title
CN107387093A (en) A kind of shallow buried covered excavation system and construction method suitable for soft soil layer
CN109723065B (en) Reinforcing device and deep foundation pit local freezing reinforcing construction method in water-rich gravel stratum
CN106369223B (en) A kind of silt stratum pipe jacking construction method
CN106402490B (en) Silt stratum push pipe jacking construction method based on steel bushing head tool pipe
CN109296378B (en) Down-the-hole drill matched breaking hammer tunneling and excavating construction method
CN111236957B (en) Mechanical pipe jacking construction process
CN103835661B (en) A kind of local excavation pre support mine shaft rising boring technique
CN107060796A (en) One kind uses Slurry Balanced Pipe Jacking Construction technique
CN104533449B (en) A kind of tunnel excavation stand and apply the adit construction method of this stand
CN104831733A (en) Arch bridge abutment tunnel type large-angle inclined pile construction method
CN107130964A (en) Small-sized tunnel mud stone excavation construction method
CN111455977A (en) Underground continuous wall construction method
CN109356593A (en) A kind of headrace tunnel excavation construction method
CN109339096A (en) A kind of construction integrated constructing device of pipe gallery open cut precast assembly and its construction method
CN204533812U (en) A kind of slurry-water balance type jacking construction system
CN113931637A (en) Shallow-buried water-rich softer rock tunnel construction method
CN207315380U (en) A kind of shallow buried covered excavation system suitable for soft soil layer
CN204099720U (en) The protective housing that under soil stone combination geological condition, artificial pipe jacking construction method is used
CN112112657B (en) New construction method for digging and building inclined shaft of coal mine
CN101994314A (en) Longhole rectangular terraced antiskid pile jump-preventing excavating construction
CN109630123A (en) Deep shaft rock ripper
CN110529120B (en) Construction method for removing invasion limiting structure by chiseling VI-level surrounding rock shallow-buried underground excavation loess tunnel
CN109113092A (en) Construction method is protected in underground large-diameter pipeline original position water flowing
CN205742318U (en) A kind of milling digging machine of automatic material-absorbing
CN208431000U (en) Deep shaft rock ripper

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171124

RJ01 Rejection of invention patent application after publication