CN107381322A - A kind of satellite fairing assembly hanging basket - Google Patents

A kind of satellite fairing assembly hanging basket Download PDF

Info

Publication number
CN107381322A
CN107381322A CN201710557263.6A CN201710557263A CN107381322A CN 107381322 A CN107381322 A CN 107381322A CN 201710557263 A CN201710557263 A CN 201710557263A CN 107381322 A CN107381322 A CN 107381322A
Authority
CN
China
Prior art keywords
semi
ring frame
abutted flange
hanger
hanging basket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710557263.6A
Other languages
Chinese (zh)
Inventor
贾海龙
何利
郭巍
刘聪聪
于军
王南
张国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Academy of Launch Vehicle Technology CALT
Beijing Institute of Space Launch Technology
Original Assignee
China Academy of Launch Vehicle Technology CALT
Beijing Institute of Space Launch Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Academy of Launch Vehicle Technology CALT, Beijing Institute of Space Launch Technology filed Critical China Academy of Launch Vehicle Technology CALT
Priority to CN201710557263.6A priority Critical patent/CN107381322A/en
Publication of CN107381322A publication Critical patent/CN107381322A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

The present invention relates to a kind of satellite fairing assembly hanging basket, including the first half baskets that are oppositely arranged and are symmetric and the second half baskets, the first half baskets include semi-ring frame on concentric first time semi-ring frame and first, and semi-ring frame is fixedly connected by circumferentially spaced multiple first tie-beams on first time semi-ring frame and first;The second half baskets include semi-ring frame on concentric second time semi-ring frame and second, and semi-ring frame is fixedly connected by circumferentially spaced multiple second tie-beams on second time semi-ring frame and second;It is equipped with the carrying beam assembly for connecting satellite fairing assembly on first time semi-ring frame and second time semi-ring frame, hanger is equipped with semi-ring frame on semi-ring frame and second on first.It has the advantages of simple in construction, easy to use, adjustment is convenient, connection is reliable, practical, and the fast and reliable connection with satellite fairing assembly can be achieved, and improves the stability and security of lifting.

Description

A kind of satellite fairing assembly hanging basket
Technical field
The present invention relates to a kind of suspender, and in particular to a kind of hanging basket for being used to lift satellite fairing assembly, belongs to and defends Star lift-off technology field.
Background technology
In space industry, assembling of the satellite at launching site usually requires to be lifted.For satellite fairing assembly Speech, because shape of product is special, is relatively large in diameter, and tie point is more, and the operation convenience and connection reliability to suspender all carry More strict requirements are gone out.Existing suspender often reaches above-mentioned requirement, is mainly manifested in cumbersome, adjustment not Just it is unreliable etc., to connect, and can not ensure the stability and security of the lifting of satellite fairing assembly.
The content of the invention
It is an object of the invention to provide a kind of satellite fairing assembly hanging basket, and it has simple in construction, easy to use, tune The advantages of whole convenient, connection is reliable, practical, the fast and reliable connection with satellite fairing assembly can be achieved, improve The stability and security of lifting.
To solve suspender of the prior art its existing cumbersome, adjustment inconvenience, connection is insecure states problem, this A kind of satellite fairing assembly hanging basket provided is provided, including the first half baskets that are oppositely arranged and are symmetric and the second half Basket, the first half basket include semi-ring frame on concentric first time semi-ring frame and first, semi-ring on first time semi-ring frame and first Frame is fixedly connected by circumferentially spaced multiple first tie-beams;The second half basket includes second time concentric semi-ring Semi-ring frame on frame and second, semi-ring frame passes through circumferentially spaced multiple second tie-beams on second time semi-ring frame and second It is fixedly connected;The carrying for connecting satellite fairing assembly is equipped with first time semi-ring frame and second time semi-ring frame Beam assembly, hanger is equipped with semi-ring frame on semi-ring frame and second on described first.
Further, a kind of satellite fairing assembly hanging basket of the present invention, wherein, the upper and lower side of the first half basket both sides Be correspondingly provided with the first abutted flange and the second abutted flange, the upper and lower sides of the second half basket both sides be correspondingly provided with the 3rd abutted flange and 4th abutted flange;When the first half baskets and the second half basket docking, first abutted flange and the second abutted flange are corresponding with the Three abutted flanges and the 4th abutted flange are fixedly connected by connecting bolt.
Further, a kind of satellite fairing assembly hanging basket of the present invention, wherein, first abutted flange and the 3rd pair Offer the first horizontal locating slot and the second vertical locating slot on the interface of acting flange, first locating slot and the Two locating slots are semi-cylindrical, right in the first abutted flange or the first locating slot and the second locating slot on the 3rd abutted flange The first locating dowel and the second locating dowel should be embedded with.
Further, a kind of satellite fairing assembly hanging basket of the present invention, wherein, second abutted flange and the 4th pair Offer the 3rd horizontal locating slot and the 4th vertical locating slot on the interface of acting flange, the 3rd locating slot and the Four locating slots are semi-cylindrical, right in the second abutted flange or the 3rd locating slot and the 4th locating slot on the 4th abutted flange The 3rd locating dowel and the 4th locating dowel should be embedded with.
Further, a kind of satellite fairing assembly hanging basket of the present invention, wherein, the carrying beam assembly is held including first Carrier beam component and the second carrying beam assembly, the first carrying beam assembly include the first installation set, the first carrier bar, first wedge Iron, the first end cap and the first tight fixed bolt, first installation set are provided with the first through hole comprising a sloped sidewall and make it solid Due in the first mounting hole that first time semi-ring frame or second time semi-ring frame open up, the first carrier bar from the first installation set first Passed through in through hole, the first drift is placed between the first carrier bar and the sloped sidewall of first through hole, and the first end cap is fixed on first In installation set and the first carrier bar is set to be stretched out from the first end cap, the first tight fixed bolt spinning covers in first end and makes itself and first Drift is relative;The second carrying beam assembly includes the second installation set, two the second carrier bars, two the second drifts, the second ends Lid and two the second tight fixed bolts, second installation set are provided with two the second through holes comprising a sloped sidewall and fix it In the second mounting hole that first time semi-ring frame or second time semi-ring frame open up, two the second carrier bars are corresponding from the second installation set Two the second through holes in pass through, two the second drifts are correspondingly placed in inclination of two the second carrier bars with corresponding second through hole Between side wall, the second end cap is fixed in the second installation set and two the second carrier bars is stretched out from the second end cap, two second Tight fixed bolt spinning is on the second end cap and makes it corresponding relative with two the second drifts.
Further, a kind of satellite fairing assembly hanging basket of the present invention, wherein, under first time semi-ring frame and second The first carrying beam assembly and the second carrying beam assembly on semi-ring frame are respectively provided with two, and make first on both to carry beam assembly It is symmetric with the second carrying beam assembly.
Further, a kind of satellite fairing assembly hanging basket of the present invention, wherein, the hanger includes the first hanger and the Two hangers, the first hanger on first on semi-ring frame and second on semi-ring frame are respectively provided with three and make the first hanger on both be in It is symmetrical;The second hanger on first on semi-ring frame and second on semi-ring frame is respectively provided with two and makes the second hanger on both It is symmetric;Wherein, the first hanger hangs the first half baskets and the second half baskets for sky, and the second hanger is used to lift by crane hanging basket and satellite Radome fairing assembly.
Further, a kind of satellite fairing assembly hanging basket of the present invention, wherein, on described first on semi-ring frame and second The auxiliary connecting hole for connecting satellite fairing assembly is additionally provided with semi-ring frame, aids in that auxiliary connection is installed in connecting hole Bolt.
Further, a kind of satellite fairing assembly hanging basket of the present invention, wherein, on described first on semi-ring frame and second The upper auxiliary connecting hole of semi-ring frame is respectively provided with four and the both sides for making auxiliary connecting hole correspondingly be distributed in the second hanger.
A kind of satellite fairing assembly hanging basket of the present invention compared with prior art, has advantages below:The present invention passes through Relative distribution is set and in symmetrical the first half basket and the second half baskets, allows the first half baskets to include first time concentric semi-ring frame and the Semi-ring frame on one, and semi-ring frame on first time semi-ring frame and first is consolidated by circumferentially spaced multiple first tie-beams Fixed connection;Allow the second half baskets to include semi-ring frame on concentric second time semi-ring frame and second, and make second time semi-ring frame and second Upper semi-ring frame is fixedly connected by circumferentially spaced multiple second tie-beams, and in first time semi-ring frame and the second lower half The carrying beam assembly for connecting satellite fairing assembly is respectively provided with ring frame, the semi-ring frame on semi-ring frame and second on first On be respectively provided with hanger.Thus just constitute it is a kind of it is simple in construction, easy to use, adjustment is convenient, the reliable satellite fairing of connection Assembly hanging basket.In actual applications, the first half baskets and the second half baskets are sling respectively first, are allowed under first time semi-ring frame and second Carrying beam assembly on semi-ring frame is connected with satellite fairing assembly respectively, then allows the first half baskets and the second half basket connections again It is fixed, satellite fairing assembly can be hung finally by the hanger on semi-ring frame on semi-ring frame and second on first Dress.The present invention is advantageous to adjustment tie point position by allowing hanging basket to use to include the split-type structural of the first half baskets and the second half baskets Put, improve the convenience of attended operation, and by allowing satellite fairing to be in hanging basket, ensure that the stability and peace of lifting Quan Xing.
Shown embodiment is made further to a kind of satellite fairing assembly hanging basket of the present invention below in conjunction with the accompanying drawings Describe in detail:
Brief description of the drawings
Fig. 1 is a kind of top view of satellite fairing assembly hanging basket of the present invention;
Fig. 2 is a kind of front view of satellite fairing assembly hanging basket of the present invention;
Fig. 3 be Fig. 2 in A to partial enlarged view;
Fig. 4 is B-B direction view in Fig. 3;
Fig. 5 is that location of C faces enlarged drawing in Fig. 2;
Fig. 6 is E-E direction views in Fig. 5;
Fig. 7 is that enlarged drawing is faced in D positions in Fig. 2;
Fig. 8 is F-F direction views in Fig. 7;
Fig. 9 is a kind of lifting view of satellite fairing assembly hanging basket of the present invention.
Embodiment
Firstly the need of explanation, the noun of locality such as heretofore described front, back, left, right, up, down simply enters with reference to the accompanying drawings Capable description, in order to understand, not to technical scheme and be claimed scope progress limitation.
The embodiment of a kind of satellite fairing assembly hanging basket of the invention as shown in Figures 1 to 9, including set relatively The first half baskets 1 putting and be symmetric and the second half baskets 2.The first half baskets 1 specifically include first time concentric He of semi-ring frame 11 Semi-ring frame 12 on first, allow on first time semi-ring frame 11 and first semi-ring frame 12 to pass through circumferentially spaced multiple first and connect Beam 13 is connect to be fixedly connected.The second half baskets 2 specifically include semi-ring frame 22 on concentric second time semi-ring frame 21 and second, allow under second Semi-ring frame 21 is fixedly connected with semi-ring frame 22 on second by circumferentially spaced multiple second tie-beams 23.Meanwhile The carrying beam assembly for connecting satellite fairing assembly is respectively provided with first time semi-ring frame 11 and second time semi-ring frame 21, On first hanger is respectively provided with semi-ring frame 12 and second on semi-ring frame 22.A kind of structure letter is just constituted by above structure setting Satellite fairing assembly hanging basket single, easy to use, adjustment is convenient, connection is reliable, safe, practical.In reality In, the first half baskets 1 and the second half baskets 2 are sling respectively first, allow on first time semi-ring frame 11 and second time semi-ring frame 21 Carrying beam assembly is connected with satellite fairing assembly respectively, then allows the first half baskets 1 and the second half baskets 2 to be connected again, most Satellite fairing assembly can be lifted by the hanger on semi-ring frame 22 on semi-ring frame 12 and second on first afterwards.This Invention is advantageous to adjustment tie point position by allowing hanging basket to use to include the split-type structural of the first half baskets 1 and the second half baskets 2, The convenience of attended operation is improved, and by allowing satellite fairing to be in hanging basket, ensure that the stability and safety of lifting Property.
As embodiment, upper and lower side of the present invention in the first half both sides of basket 1 has been correspondingly arranged the first abutted flange 14 and second abutted flange 15, the upper and lower side in the second half both sides of basket 2 has been correspondingly arranged the 3rd abutted flange 24 and the 4th docking Flange 25.When the first half baskets 1 and the second half baskets 2 dock, make the first abutted flange 14 and the second abutted flange 15 corresponding with the 3rd Abutted flange 24 is fixedly connected with the 4th abutted flange 25 by connecting bolt.
As prioritization scheme, present embodiment is on the interface of the first abutted flange 14 and the 3rd abutted flange 24 The first horizontal locating slot and the second vertical locating slot are provided with, allows the first locating slot and the second locating slot to use semicircle Cylindricality, and be correspondingly embedded in the first locating slot and the second locating slot on the first abutted flange 14 or the 3rd abutted flange 24 First locating dowel 3 and the second locating dowel 4.This structure setting, it is fixed by first when the first half baskets 1 and the second half baskets 2 dock The position locating dowel 4 of post 3 and second and its corresponding first locating slot and the second locating slot, can be achieved fast positioning, and determine because of first The position locating dowel 4 of post 3 and second relation vertical each other, ensure that the degree of accuracy of positioning.Similarly, present embodiment is second The 3rd horizontal locating slot and the vertical the 4th positioning are provided with the interface of the abutted flange 25 of abutted flange 15 and the 4th Groove, the 3rd locating slot and the 4th locating slot is allowed to use semi-cylindrical, and in the second abutted flange 15 or the 4th abutted flange 25 On the 3rd locating slot and the 4th locating slot in be correspondingly embedded the 3rd locating dowel 5 and the 4th locating dowel 6, it is fixed to further increase The convenience of position and the degree of accuracy.
As further prioritization scheme, present embodiment allows carrying beam assembly to include the first carrying beam assembly 7 and the Two carrying beam assemblies 8, and allow the first carrying beam assembly 7 and the second carrying beam assembly 8 to use two kinds of different structure types.Its In, the first carrying beam assembly 7 specifically includes the first installation set 71, the first carrier bar 72, the first drift 73, the first end cap 74 and the One tight fixed bolt 75.Allow the first installation set 71 that the first through hole comprising a sloped sidewall is set and be secured to first time semi-ring In the first mounting hole that frame 11 or second time semi-ring frame 21 open up, the first carrier bar 72 is allowed from the first through hole of the first installation set 71 In pass through, allow the first drift 73 to be arranged between the first carrier bar 72 and the sloped sidewall of first through hole, make the first end cap 74 solid It is scheduled in the first installation set 71 and the first carrier bar 72 is stretched out from the first end cap 74, allows the spinning of the first tight fixed bolt 75 first On end cap 74 and make it relative with the first drift 73.The second carrying beam assembly 8 is allowed to specifically include the second installation set 81, two second 82, two the second drifts 83 of carrier bar, the second end cap 84 and two the second tight fixed bolts 85, allow the second installation set 81 to set and include Two the second through holes of one sloped sidewall are simultaneously secured to first time semi-ring frame 11 or second time semi-ring frame 21 open up second In mounting hole, allow two the second carrier bars 82 are corresponding to be passed through from two the second through holes of the second installation set 81, allow two second Drift 83 is correspondingly arranged between two the second carrier bars 82 and the sloped sidewall of corresponding second through hole, makes the second end cap 84 solid It is scheduled in the second installation set 81 and two the second carrier bars 82 is stretched out from the second end cap 84, allows two the second tight fixed bolts 85 to revolve On the second end cap 84 and make it corresponding relative with two the second drifts 83.The present invention is held by two kinds of structure types of setting Carrier beam component, allow the first carrying beam assembly 7 that first carrier bar 72 is set, allow the second carrying beam assembly 8 to set two second Carrier bar 82, and by setting link bolt hole and connecting bolt in the first carrier bar 72 and the second carrier bar 82 respectively, can fit Multiple tie points on satellite fairing assembly are answered, ensure that connection, the steadiness of lifting and security.And whole with satellite During flowing the connection of cover assembly, the first carrier bar can be made by unscrewing the first tight fixed bolt 75 and the second tight fixed bolt 85 72 and second carrier bar 82 move radially, and by screwing the corresponding top pressure of the first tight fixed bolt 75 and the second tight fixed bolt 85 the One drift 73 and the second drift 83 can be achieved to fix the purpose of the first carrier bar 72 and the second carrier bar 82, have adjustment just The advantages of victory, positioning precision, reliable connection, effectively increase connection, the convenient, flexible property and operating efficiency of lifting.
As embodiment, the present invention is by allowing first on first time semi-ring frame 11 and second time semi-ring frame 21 to hold Carrier beam component 7 and second carries beam assembly 8 and is respectively provided with two, and makes first on both to carry the carrier bar of beam assembly 7 and second Component 8 is symmetric, and connection, the stationarity of lifting and stress equalization has been effectively ensured.Meanwhile the present invention allows hanger to set First hanger 91 and the second hanger 92, and allow the first hanger 91 and the second hanger 92 to use different structure type.And make The first hanger 91 on one on semi-ring frame 12 and second on semi-ring frame 22 is respectively provided with three and makes the first hanger 91 on both be in It is symmetrical.The second hanger 92 on first on semi-ring frame 12 and second on semi-ring frame 22 is allowed to be respectively provided with two and make on both Second hanger 92 is symmetric.Wherein, the first hanger 91 hangs the first half baskets 1 and the second half baskets 2 for sky, and the second hanger 92 is used In lifting hanging basket and satellite fairing assembly.
Present embodiment is provided with also on first on semi-ring frame 12 and second on semi-ring frame 22 to be used to connect satellite The auxiliary connecting hole of radome fairing assembly, and auxiliary connecting bolt is mounted with connecting hole is aided in, by aiding in connecting bolt It is connected with satellite fairing assembly, can further improve the stability and security of connection and lifting.In actual applications, originally Invention generally allows semi-ring frame 12 on first to be respectively provided with four with the upper auxiliary connecting hole of semi-ring frame 22 on second and connect auxiliary Hole is correspondingly distributed in the both sides of the second hanger 92, and this structure is ensureing on first the intensity of semi-ring frame 22 on semi-ring frame 12 and second While, the steadiness of connection and the harmony of stress can be improved, practicality is stronger.
Above example is only the description carried out to the preferred embodiment of the present invention, and model not is claimed to the present invention Enclose and be defined, on the premise of design spirit of the present invention is not departed from, technology of this area engineers and technicians according to the present invention The various forms of deformations that scheme is made, it all should fall into the protection domain of claims of the present invention determination.

Claims (9)

1. a kind of satellite fairing assembly hanging basket, it is characterised in that including the first half baskets for being oppositely arranged and being symmetric (1) and the second half baskets (2), the first half basket (1) includes semi-ring frame (12) on concentric first time semi-ring frame (11) and first, Semi-ring frame (12) is fixed by circumferentially spaced multiple first tie-beams (13) on first time semi-ring frame (11) and first Connection;The second half basket (2) includes semi-ring frame (22) on concentric second time semi-ring frame (21) and second, second time semi-ring frame (21) it is fixedly connected with semi-ring frame (22) on second by circumferentially spaced multiple second tie-beams (23);Described first The carrying beam assembly for connecting satellite fairing assembly, institute are equipped with lower semi-ring frame (11) and second time semi-ring frame (21) State and be equipped with hanger on semi-ring frame (22) on semi-ring frame (12) and second on first.
2. according to a kind of satellite fairing assembly hanging basket described in claim 1, it is characterised in that the first half basket (1) The upper and lower side of both sides is correspondingly provided with the first abutted flange (14) and the second abutted flange (15), the second half basket (2) both sides up and down End is correspondingly provided with the 3rd abutted flange (24) and the 4th abutted flange (25);When the first half baskets (1) and the second half basket (2) docking, First abutted flange (14) and the second abutted flange (15) correspond to and the 3rd abutted flange (24) and the 4th abutted flange (25) it is fixedly connected by connecting bolt.
3. according to a kind of satellite fairing assembly hanging basket described in claim 2, it is characterised in that first abutted flange (14) the first horizontal locating slot and the second vertical locating slot, institute and on the interface of the 3rd abutted flange (24) are offered State the first locating slot and the second locating slot is semi-cylindrical, on the first abutted flange (14) or the 3rd abutted flange (24) The first locating dowel (3) and the second locating dowel (4) are correspondingly embedded with one locating slot and the second locating slot.
4. according to a kind of satellite fairing assembly hanging basket described in claim 3, it is characterised in that second abutted flange (15) the 3rd horizontal locating slot and the 4th vertical locating slot, institute and on the interface of the 4th abutted flange (25) are offered It is semi-cylindrical to state the 3rd locating slot and the 4th locating slot, and on the second abutted flange (15) or the 4th abutted flange (25) The 3rd locating dowel (5) and the 4th locating dowel (6) are correspondingly embedded with three locating slots and the 4th locating slot.
5. according to a kind of satellite fairing assembly hanging basket described in claim 4, it is characterised in that the carrying beam assembly bag The first carrying beam assembly (7) and the second carrying beam assembly (8) are included, the first carrying beam assembly (7) includes the first installation set (71), the first carrier bar (72), the first drift (73), the first end cap (74) and the first tight fixed bolt (75), first installation Set (71) is provided with the first through hole comprising a sloped sidewall and is secured to first time semi-ring frame (11) or second time semi-ring frame (21) in the first mounting hole opened up, the first carrier bar (72) passes through from the first through hole of the first installation set (71), first wedge Iron (73) is placed in the first carrier bar (72) between the sloped sidewall of first through hole, and the first end cap (74) is fixed on the first installation set (71) on and the first carrier bar (72) is made to be stretched out from the first end cap (74), the first tight fixed bolt (75) spinning is in the first end cap (74) Above and make it relative with the first drift (73);The second carrying beam assembly (8) include the second installation set (81), two second hold Carrier beam (82), two the second drifts (83), the second end cap (84) and two the second tight fixed bolts (85), second installation set (81) two the second through holes comprising a sloped sidewall are provided with and are secured to first time semi-ring frame (11) or second time semi-ring In the second mounting hole that frame (21) opens up, two corresponding two the second through holes from the second installation set (81) of the second carrier bar (82) In pass through, two the second drifts (83) are corresponding be placed in two the second carrier bars (82) and corresponding second through hole sloped sidewall it Between, the second end cap (84) is fixed in the second installation set (81) and two the second carrier bars (82) is stretched from the second end cap (84) Go out, two the second tight fixed bolt (85) spinnings are on the second end cap (84) and it is corresponded to two the second drifts (83) relatively.
6. according to a kind of satellite fairing assembly hanging basket described in claim 5, it is characterised in that first time semi-ring frame (11) the first carrying beam assembly (7) and the second carrying beam assembly (8) and on second time semi-ring frame (21) are respectively provided with two, and make The first carrying beam assembly (7) and the second carrying beam assembly (8) on both are symmetric.
7. according to a kind of satellite fairing assembly hanging basket described in claim 6, it is characterised in that the hanger includes first Hanger (91) and the second hanger (92), the first hanger (91) on first on semi-ring frame (12) and second on semi-ring frame (22) are all provided with Put three and be symmetric the first hanger (91) on both;On first on semi-ring frame (12) and second on semi-ring frame (22) The second hanger (92) be respectively provided with two and be symmetric the second hanger (92) on both;Wherein, the first hanger (91) The first half baskets (1) and the second half baskets (2) are hung for sky, the second hanger (92) is used to lift by crane hanging basket and satellite fairing assembly.
8. according to a kind of satellite fairing assembly hanging basket described in claim 7, it is characterised in that semi-ring frame on described first (12) the auxiliary connecting hole for connecting satellite fairing assembly is additionally provided with and on second on semi-ring frame (22), aids in connecting hole In auxiliary connecting bolt is installed.
9. according to a kind of satellite fairing assembly hanging basket described in claim 8, it is characterised in that semi-ring frame on described first (12) four are respectively provided with the upper auxiliary connecting hole of semi-ring frame (22) on second and makes auxiliary connecting hole is corresponding to be distributed in second and hang The both sides of ear (92).
CN201710557263.6A 2017-07-10 2017-07-10 A kind of satellite fairing assembly hanging basket Pending CN107381322A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710557263.6A CN107381322A (en) 2017-07-10 2017-07-10 A kind of satellite fairing assembly hanging basket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710557263.6A CN107381322A (en) 2017-07-10 2017-07-10 A kind of satellite fairing assembly hanging basket

Publications (1)

Publication Number Publication Date
CN107381322A true CN107381322A (en) 2017-11-24

Family

ID=60333884

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710557263.6A Pending CN107381322A (en) 2017-07-10 2017-07-10 A kind of satellite fairing assembly hanging basket

Country Status (1)

Country Link
CN (1) CN107381322A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3459406A (en) * 1967-09-25 1969-08-05 Harmonic Reed Corp Dome hoist
CN102849612A (en) * 2012-03-31 2013-01-02 航天东方红卫星有限公司 Multi-function combination lifting device for minisatellite
CN103030061A (en) * 2012-12-28 2013-04-10 北京空间飞行器总体设计部 Circular ring lifting tool based on satellite bearing cylinder lifting
CN103062538A (en) * 2012-10-01 2013-04-24 徐州支点机电设备有限公司 Flange with locating function
CN203638954U (en) * 2013-11-04 2014-06-11 北京航天发射技术研究所 Hanger for vertically hoisting fairing
CN104266856B (en) * 2014-09-23 2016-08-31 北京强度环境研究所 Two grades of band cover free boundaries and radome fairing built-in boundary implementation in vibration tower

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3459406A (en) * 1967-09-25 1969-08-05 Harmonic Reed Corp Dome hoist
CN102849612A (en) * 2012-03-31 2013-01-02 航天东方红卫星有限公司 Multi-function combination lifting device for minisatellite
CN103062538A (en) * 2012-10-01 2013-04-24 徐州支点机电设备有限公司 Flange with locating function
CN103030061A (en) * 2012-12-28 2013-04-10 北京空间飞行器总体设计部 Circular ring lifting tool based on satellite bearing cylinder lifting
CN203638954U (en) * 2013-11-04 2014-06-11 北京航天发射技术研究所 Hanger for vertically hoisting fairing
CN104266856B (en) * 2014-09-23 2016-08-31 北京强度环境研究所 Two grades of band cover free boundaries and radome fairing built-in boundary implementation in vibration tower

Similar Documents

Publication Publication Date Title
CN107082354B (en) Self-tipping type transports cage and its construction method
CN205653036U (en) Structure of wireless communication device integration installation
CN103010940B (en) Falling preventing device for lifting hook
CN207614206U (en) A kind of hanging rack for safety belt
CN206720558U (en) A kind of adjustable steel-reinforcement cage hanger
CN107381322A (en) A kind of satellite fairing assembly hanging basket
CN103287964B (en) Folding lifting appliance
CN109958819A (en) A kind of gas pipeline laying method and its supporting structure
CN208479063U (en) A kind of tower crane cable self-locking fixer
CN209493231U (en) Tool is turned in large-size machine general assembly
CN209009975U (en) A kind of self-balancing triangular hanging tool
CN203237915U (en) Folding lifting appliance
CN206915557U (en) A kind of suspending assembly
CN205339897U (en) Aerial -working safety of transformer substation takes linkage
CN204324685U (en) Interim hanger is used in a kind of novel short range lifting
CN204355947U (en) Large-scale without eye plate lifting beam device
CN209430211U (en) One kind hanging mould support device for shield end well to be closed
CN209835621U (en) Improved oil basin structure
CN208792792U (en) Prefabricated components hoisting structure and prefabricated components
CN207158604U (en) A kind of metro bogie boom hoisting
CN203373736U (en) Precast pile hoisting structure
CN201851137U (en) Forepole hoisting ring with movable opening
CN106586822A (en) Lifting tool
CN208489612U (en) A kind of cable testing bridge
CN203878752U (en) Connecting device for large steel beam and connecting plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171124