CN107378295A - The application method of large diameter pipe pipe fitting method, installation equipment and equipment in pipe well - Google Patents
The application method of large diameter pipe pipe fitting method, installation equipment and equipment in pipe well Download PDFInfo
- Publication number
- CN107378295A CN107378295A CN201710820509.4A CN201710820509A CN107378295A CN 107378295 A CN107378295 A CN 107378295A CN 201710820509 A CN201710820509 A CN 201710820509A CN 107378295 A CN107378295 A CN 107378295A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- pipe
- pipe well
- well
- welding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K31/00—Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
- B23K31/02—Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K37/00—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K37/00—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
- B23K37/04—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work
- B23K37/053—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work aligning cylindrical work; Clamping devices therefor
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K2101/00—Articles made by soldering, welding or cutting
- B23K2101/04—Tubular or hollow articles
- B23K2101/06—Tubes
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Optics & Photonics (AREA)
- Butt Welding And Welding Of Specific Article (AREA)
Abstract
The present invention provides large diameter pipe pipe fitting method in a kind of pipe well, and first pipeline oblique traction is transported into pipe well, overlays second pipe diameter is relative on first pipeline, synchronously carries out seam welds during rotating pipe;To realize that the method also provides a kind of equipment, including the electric lifting device and raising cord for being installed on the rotating base of pipe well bottom, being installed at the top of pipe well, it is additionally provided with the rotating ring being installed among management for reducing frictional force;The application method of this equipment is:Rotating base, motor hoist are first arranged on corresponding positions, then pipe well is entered from first floor oblique traction pipeline with raising cord, pipeline is sitting on rotating base, second pipeline is drawn into pipe well again, overlay on first pipeline, welding gun is set, is rotated with rotating base using pipeline, while the seam of two pipelines is welded, the present invention is simple in construction, without cutting pipeline, welding job amount, weld seam welding dead angle are reduced.
Description
Technical field
The invention belongs to high-rise building technical field of pipeline construction.
Background technology
Area of the high-rise building as personnel's highly dense, it is necessary to lift convenient bar for the normal work of these personnel
Part, improve the comfort level of the working environment of the people.These conditions greatly have to be by being arranged on all kinds of in floor
For pipeline come what is realized, these pipelines include air-conditioning duct, feedwater, drainage pipeline, gas piping, intermediate water pipeline, hot water pipeline.And
Each layer pipeline is generally by one system for being capable of continuous service of formation for setting different standpipes to be tied in pipe well
's.
Pipe well is connected with elevator, and pipe well space is small, generally reinforced concrete structure.Pipe diameter is big in pipe well, pipe
Road is more.When pipe well internal riser is installed, tower crane has been removed, and when transporting pipe using plug-in elevator, is had the following disadvantages:1) because of elevator chi
Very little limitation needs to cut off homogeneous tube, it may appear that increase weld bond quantity, increase weld job the problem of.2) pipe well space is small, pipeline
It is numerous, the problem of causing the respective regions of pipe joint not weld.
The content of the invention
Pipe cutting segment number is more, pipe joint has asking for welding dead angle existing to solve in the prior art by the present invention
Topic.
The present invention is that the solve the above problems technical scheme of offer is:
Large diameter pipe pipe fitting method in a kind of pipe well, its step are:
1) first pipeline is transported into pipe well from one layer of ground oblique traction, is erected at pipe well bottom;
2) second pipeline is transported into pipe well for one layer from ground, second pipe diameter overlays first pipeline to bore
On;
3) from pipe well entrance side setting welding gun, welding gun align with tube seam a bit, rotating pipe carries out pipeline butt weldering
Connect;
4) pipeline is transported into pipe well successively by above-mentioned steps, and bore counterpart footpath stacks and is sitting on a pipeline, rotation
Pipeline simultaneously carries out synchronous welding.
5) finally, the pipeline for welding completion is done fixed in well.
This method pipeline all by ground one layer be transported into pipe well, reduce the work of a large amount of pipeline partite transports, pipeline is oblique from building
Enter pipe well in layer, obtain bigger apron space, it is not necessary to cut pipeline, reduce the welding job amount in pipe well.Welding
Pipeline while rotating pipe, realize the complete solder of pipeline joint-seam.
Large-diameter pipeline installs equipment in a kind of pipe well, includes and is installed on the rotating base of pipe well bottom, is installed on pipe
Well head rail, the electric lifting device and raising cord being installed on guide rail, the rotating base include bottom plate, and bottom plate is provided with
Roller groove, the roller group of radial arrangement is installed in roller groove;Cover plate is placed with roller group, cover plate is provided with and its affixed one
Instrumentation tubes, be connected with torsion gear in instrumentation tubes;Bottom plate upper idler wheel channel side is provided with motor, and motor is provided with travelling gear,
Travelling gear engages with reversing gear.
As the improvement of the said equipment, the rotating ring being sleeved in the middle part of pipeline is also add, the rotating ring includes sleeve pipe,
Axially arranged some rollers are installed on the inside of sleeve pipe.
The device structure is simple, and operation consumption is small, and use cost is low, pipeline oblique traction can be reduced into pipe cutting section
Number, reduce workload.Tunnel synchronization rotates while realizing pipeline welding, makes welding without dead angle.
The specifically used method of above-mentioned installation equipment:
1st, rotating base is installed two layers located underground of pipe well bottom, and debugs and finish, installed at the top of pipe well electronic
Raising cord on lifting device and electric lifting device;
2nd, pipe well is transported from the first floor with first pipeline of raising cord oblique traction, is sitting in the instrumentation tubes of rotating base and welds
Connect firmly;
3rd, second pipeline is transported into pipe well from the first floor, second pipe diameter is overlayed to bore on first pipeline;
4th, from pipe well entrance side setting welding gun, welding gun align with tube seam a bit, rotating pipe carries out pipeline butt weldering
Connect;
5th, untill carrying out the top layer for being soldered to building of other pipelines by above-mentioned 2 to 4 step flow;
6th, the pipeline for welding completion is done fixed in well.
Further, when pipeline welding to high level, rotating ring is installed on pipeline every three layers.
Synchronous rotary pipeline when this application method realizes pipeline welding, pipeline joint-seam is set to be welded with complete solder without dead
Angle, improve pipeline welding speed.The delivery mode of pipeline described in this method is quick, and implementation cost is low.
Brief description of the drawings
Fig. 1 is that pipeline is towed view;
Fig. 2 is that first lifting pipeline enters pipe well state diagram;
Fig. 3 is that first pipeline is sitting in the upper figure of rotating base;
Fig. 4 is to lift into second piping drawing;
Fig. 5 is installation rotating ring state diagram;
Fig. 6 is track installation figure;
Fig. 7 is rotary base structure figure;
Fig. 8 is a-a line upper section structure charts in Fig. 7;
Fig. 9 is b-b line upper section structure charts in Fig. 7;
Figure 10 is rings configuration figure.
In figure:Track 1, electric lifting device 2, raising cord 3, rotating base 4, rotating ring 5, bottom plate 41, roller groove 42, rolling
Wheel group 43, cover plate 44, reverse gear 45, instrumentation tubes 46, motor 47, travelling gear 48, sleeve pipe 51, roller 52.
Embodiment
Pipeline construction has directly to lift long tube at the top of piping shaft and is sent into well in the prior art, but required lifting is set
Standby big, implementation cost is very high.And when pipe well internal riser is installed such as tower crane has been removed, then transport and manage using plug-in elevator, it is high
Building is built typically per floor FFL between 3-4.5 rice, including basement, and elevator size is corresponding to per layer height, because of elevator
Size limitation needs to cut off homogeneous tube.Existing pipeline be generally it is six meters long, pipe cutting per segment length be 3 meters, it is necessary to by this
A little pipelines deliver to each floor respectively could prepare to weld, and transport amount is big.Because the duct section after cutting is more, Welder in well
Make quite heavy, and space is small in pipe well, pipeline is more, welds narrow conduit welding under space and welding dead angle be present.
The present invention is intended to provide a kind of reduce transport, reduce weld job, the scheme of complete solder.There is provided for this present invention
Large diameter pipe pipe fitting method in a kind of pipe well, its step are:
1) first pipeline is transported into pipe well from one layer of ground (the also referred to as first floor) oblique traction, is erected at pipe well bottom.
2) second pipeline is transported into pipe well from one layer of ground oblique traction, second pipe diameter overlays to bore
On a piece pipeline.
3) from pipe well entrance side setting welding gun, welding gun align with tube seam a bit, rotating pipe carries out pipeline butt weldering
Connect.
4) pipeline is transported into pipe well successively by above-mentioned steps, and bore counterpart footpath stacks and is sitting on a pipeline, rotation
Pipeline simultaneously carries out synchronous welding.
5) finally, the pipeline for welding completion is done fixed in well.
The mentality of designing of this method is:By whole pipelines successively from the first floor, i.e. pipe well is transported on one layer of ground, with small-sized lifting
Be lifted into relevant position after equipment oblique traction to pipe well, because oblique space is big, can for 6 meters of homogeneous tube pipeline by,
Pipeline hop count is reduced, reduces the workload of welding;And rifle is welded in welding can not cause to weld dead angle around management movement, we
Devising corresponding construction makes pipeline rotate the position for deacclimatizing welding gun, makes interface week circle complete solder.
To realize the above method, the present invention provides large-diameter pipeline installation equipment in a kind of pipe well, includes and be installed on pipe
Raising cord 3 on the rotating base 4 of bottom, the electric lifting device 2 being installed at the top of pipe well and electric lifting device, institute
State rotating base 4 and be provided with roller groove 42 including bottom plate 41, bottom plate 41, the roller group of radial arrangement is installed in roller groove 42
43;Cover plate 44 is placed with roller group 43, with being connected with torsion gear in the affixed integral instrumentation tubes 46 of cover plate 44, instrumentation tubes 46
45;The side of 41 upper idler wheel channel of bottom plate 42 is provided with motor 47, and the top of motor 47 is provided with travelling gear 48, and travelling gear 48 is with reversing tooth
The engagement of wheel 45.
As the improvement of the said equipment, the rotating ring 5 being sleeved in the middle part of pipeline is also add, the rotating ring 5 includes set
Pipe 51, the inner side of sleeve pipe 51 are provided with axially arranged some rollers 52.
The specifically used method of this equipment is:
1) rotating base is installed two layers located underground of pipe well bottom, and debugs and finish, installed at the top of pipe well electronic
Raising cord on lifting device and electric lifting device.
2) pipe well is transported from the first floor with first pipeline of raising cord oblique traction, is sitting in the instrumentation tubes of rotating base and welds
Connect firmly.
3) second pipeline is transported into pipe well from the first floor, second pipe diameter is overlayed to bore on first pipeline.
4) from pipe well entrance side setting welding gun, welding gun align with tube seam a bit, rotating pipe carries out pipeline butt weldering
Connect.
5) untill carrying out the top layer for being soldered to building of other pipelines by above-mentioned 2 to 4 step flow.
6) pipeline for welding completion is done fixed in well.
Because pipe well is not only high but also long in high building, when pipeline welding to high level, can with installation rotating ring temporarily on pipeline, one
The stable pipeline of aspect, on the one hand reduces rotation friction.Rotating ring is installed on pipeline every three layers, until the pipeline all welds
Removed after mouth welding.
Because the duct length in pipe well is typically up to more than 30m, ensure that the perpendicularity of pipeline must be by design requirement pipe
Road support is installed in place.
This equipment is relatively specific for tower crane and removed, after pipe well has bound.Electric lifting device 2 is installed on pipe well roof
Guide rail 1.The track 1 is made up of I-steel.Track 1 can be directly anchored on pipe well roof, and one end is fixed on pipe well side wall
On, the curved other end that turn 90 degrees stretches out pipe well side port.Such structure can make the Hoisting Position of lifting device cover pipe well comprehensively.
After this method, pipeline directly can enter in pipe well from the first floor, and the problem of avoiding Pipe Cutting, it is unnecessary to reduce
Welding job amount, improve operating efficiency.Welding dead angle is eliminated by the method for rotating pipe simultaneously, improves welding speed
Degree and quality.
Claims (6)
1. large diameter pipe pipe fitting method in a kind of pipe well, its step are:
1) first pipeline is transported into pipe well from one layer of ground oblique traction, is erected at pipe well bottom;
2) second pipeline is transported into pipe well for one layer from ground, second pipe diameter is overlayed to bore on first pipeline;
3) from pipe well entrance side setting welding gun, welding gun align with tube seam a bit, rotating pipe carries out butt welding of pipelines;
4) pipeline is transported into pipe well successively by above-mentioned steps, and bore counterpart footpath stacks and is sitting on a pipeline, rotating pipe
And carry out synchronous welding.
5) finally, the pipeline for welding completion is done fixed in well.
2. large-diameter pipeline installs equipment in a kind of pipe well, it is characterized in that:Include the rotating base for being installed on pipe well bottom, peace
Loaded on pipe well head rail, the electric lifting device and raising cord that are installed on guide rail, the rotating base includes bottom plate, bottom plate
Roller groove is provided with, the roller group of radial arrangement is installed in roller groove;Cover plate is placed with roller group, cover plate is provided with and it
Affixed integral instrumentation tubes, torsion gear is connected with instrumentation tubes;Bottom plate upper idler wheel channel side is provided with motor, and motor, which is provided with, to be passed
Moving gear, travelling gear engage with reversing gear.
3. large-diameter pipeline installs equipment in pipe well as claimed in claim 2, it is characterized in that:It is additionally provided with and is sleeved in the middle part of pipeline
Rotating ring, rotating ring include sleeve pipe, axially arranged some rollers are provided with the inside of sleeve pipe.
4. large-diameter pipeline installs equipment in pipe well as claimed in claim 2, it is characterized in that:Guide rail one end is fixed on pipe well side wall
On, the curved other end that turn 90 degrees stretches out pipe well side port.
5. the application method of large-diameter pipeline installation equipment in pipe well:
1) rotating base is installed two layers located underground of pipe well bottom, and debugs and finish, electronic lifting is installed at the top of pipe well
Raising cord on device and electric lifting device;
2) pipe well is transported from the first floor with first pipeline of raising cord oblique traction, is sitting in the instrumentation tubes of rotating base and welds jail
Gu;
3) second pipeline is transported into pipe well from the first floor, second pipe diameter is overlayed to bore on first pipeline;
4) from pipe well entrance side setting welding gun, welding gun align with tube seam a bit, rotating pipe carries out butt welding of pipelines;
5) untill carrying out the top layer for being soldered to building of other pipelines by above-mentioned 2 to 4 step flow;
6) pipeline for welding completion is done fixed in well.
6. in pipe well as claimed in claim 5 large-diameter pipeline installation equipment application method, it is characterized in that, when pipeline welding extremely
When high-rise, rotating ring is installed on pipeline every three layers.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710820509.4A CN107378295B (en) | 2017-09-13 | 2017-09-13 | Large-diameter pipeline installs equipment in pipe well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710820509.4A CN107378295B (en) | 2017-09-13 | 2017-09-13 | Large-diameter pipeline installs equipment in pipe well |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107378295A true CN107378295A (en) | 2017-11-24 |
CN107378295B CN107378295B (en) | 2019-09-10 |
Family
ID=60351222
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710820509.4A Active CN107378295B (en) | 2017-09-13 | 2017-09-13 | Large-diameter pipeline installs equipment in pipe well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107378295B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109967959A (en) * | 2019-04-15 | 2019-07-05 | 中建二局安装工程有限公司 | A kind of standpipe well vertical pipe automatically delivers welding rotating device and its application method |
CN110107737A (en) * | 2019-05-10 | 2019-08-09 | 中国建筑第八工程局有限公司 | The pipe installation method and its mounting device for the pipe well being connected to basement |
CN111331283A (en) * | 2019-11-20 | 2020-06-26 | 中国铁建重工集团股份有限公司 | Welding platform |
CN113251210A (en) * | 2021-05-13 | 2021-08-13 | 山西四建集团有限公司 | Inverted installation construction method for riser of super high-rise tubular well |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101798869A (en) * | 2009-12-29 | 2010-08-11 | 广东省工业设备安装公司 | Method for automatically centering and inversely installing vertical shaft pipelines |
KR20110093481A (en) * | 2010-02-12 | 2011-08-18 | 삼성중공업 주식회사 | Block pipe of a vessel connecting method |
CN102734565A (en) * | 2012-07-17 | 2012-10-17 | 江苏江中集团有限公司 | Slideable annular tray bracket mounting structure of large-diameter stand pipe |
CN103243926A (en) * | 2013-05-13 | 2013-08-14 | 中建五局第三建设有限公司 | Construction method for hoisting engineering tube well stand pipe of high-rise building |
CN203374992U (en) * | 2013-06-24 | 2014-01-01 | 中国十七冶集团有限公司 | Fixing device for pipeline penetrating through floor |
KR20140099080A (en) * | 2013-02-01 | 2014-08-11 | 주식회사 연합 | Welding equipment |
CN204430531U (en) * | 2014-12-24 | 2015-07-01 | 重庆百齐居建材有限公司 | Structural fire protection pipeline welding device |
CN105864641A (en) * | 2016-06-16 | 2016-08-17 | 西南石油大学 | Middle-high pressure natural gas pipeline emergency bleeding device |
-
2017
- 2017-09-13 CN CN201710820509.4A patent/CN107378295B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101798869A (en) * | 2009-12-29 | 2010-08-11 | 广东省工业设备安装公司 | Method for automatically centering and inversely installing vertical shaft pipelines |
KR20110093481A (en) * | 2010-02-12 | 2011-08-18 | 삼성중공업 주식회사 | Block pipe of a vessel connecting method |
CN102734565A (en) * | 2012-07-17 | 2012-10-17 | 江苏江中集团有限公司 | Slideable annular tray bracket mounting structure of large-diameter stand pipe |
KR20140099080A (en) * | 2013-02-01 | 2014-08-11 | 주식회사 연합 | Welding equipment |
CN103243926A (en) * | 2013-05-13 | 2013-08-14 | 中建五局第三建设有限公司 | Construction method for hoisting engineering tube well stand pipe of high-rise building |
CN203374992U (en) * | 2013-06-24 | 2014-01-01 | 中国十七冶集团有限公司 | Fixing device for pipeline penetrating through floor |
CN204430531U (en) * | 2014-12-24 | 2015-07-01 | 重庆百齐居建材有限公司 | Structural fire protection pipeline welding device |
CN105864641A (en) * | 2016-06-16 | 2016-08-17 | 西南石油大学 | Middle-high pressure natural gas pipeline emergency bleeding device |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109967959A (en) * | 2019-04-15 | 2019-07-05 | 中建二局安装工程有限公司 | A kind of standpipe well vertical pipe automatically delivers welding rotating device and its application method |
CN110107737A (en) * | 2019-05-10 | 2019-08-09 | 中国建筑第八工程局有限公司 | The pipe installation method and its mounting device for the pipe well being connected to basement |
CN110107737B (en) * | 2019-05-10 | 2021-11-09 | 中国建筑第八工程局有限公司 | Pipeline installation method and device for pipe well communicated with basement |
CN111331283A (en) * | 2019-11-20 | 2020-06-26 | 中国铁建重工集团股份有限公司 | Welding platform |
CN113251210A (en) * | 2021-05-13 | 2021-08-13 | 山西四建集团有限公司 | Inverted installation construction method for riser of super high-rise tubular well |
Also Published As
Publication number | Publication date |
---|---|
CN107378295B (en) | 2019-09-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107378295A (en) | The application method of large diameter pipe pipe fitting method, installation equipment and equipment in pipe well | |
RU2516667C2 (en) | Device and system of pipeline installation | |
CN108149929B (en) | Crawler-type floor concrete distribution system and construction method thereof | |
CN100564791C (en) | The drilling machine shaft frame two-layer platform mechanical arm grasping drill pipe device | |
CN107100633B (en) | Small-diameter slurry shield pipe changing device | |
CN107553687B (en) | The house 3D printer | |
CN110985036B (en) | Slurry shield slurry pipeline extension device and extension method | |
CN107956478A (en) | For earth pressure balanced shield, EPBS or jacking construction excavation device and go out indigenous method | |
CN111794754A (en) | Pipe piece assembled derrick and construction method thereof | |
CN106181142A (en) | Steel-pipe welding device | |
CN113216973B (en) | From top pushing-type shaft heading equipment down | |
CN101660630A (en) | Method for mounting large-diameter pipeline in confined space | |
CN210239692U (en) | Rotary material distribution device for tunnel secondary lining | |
CN107387872A (en) | The tube coupling shield compatible apparatus of push pipe half and its coupling method | |
CN110107737A (en) | The pipe installation method and its mounting device for the pipe well being connected to basement | |
CN209688304U (en) | A kind of pipeline work face converter | |
CN211053008U (en) | Displacement device for assembling and lengthening water-proof sleeve | |
CN110155821A (en) | A kind of guiding device laying recycling for deep-sea mining vehicle | |
CN209557004U (en) | Small-bore tunnel shield machine | |
CN111473162A (en) | Threading construction method for large-diameter long-pipe-section circulating water pipeline | |
CN105133680B (en) | A kind of narrow wall Seepage hydraulic grab of rotary digging guide rod type | |
CN218063645U (en) | Steel pipe passes through construction equipment in heavy-calibre concrete casing | |
CN217993536U (en) | Drainage pipe network 3D prints construction equipment | |
CN109736822A (en) | The shield method and applied shield machine in 900-2000 millimeters of bore tunnels | |
CN217320172U (en) | Comprehensive emergency rescue equipment suitable for multiple terrains |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |