CN107368909A
CN107368909A CN201610314975.0A CN201610314975A CN107368909A CN 107368909 A CN107368909 A CN 107368909A CN 201610314975 A CN201610314975 A CN 201610314975A CN 107368909 A CN107368909 A CN 107368909A
Authority
CN
China
Prior art keywords
cable
line
dosage
race
laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610314975.0A
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chou Haifeng
Zhang Decao
Original Assignee
Chou Haifeng
Zhang Decao
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chou Haifeng, Zhang Decao filed Critical Chou Haifeng
Priority to CN201610314975.0A priority Critical patent/CN107368909A/en
Publication of CN107368909A publication Critical patent/CN107368909A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

One kind solves cable using BIM technology(Line)Laying optimization and the method for dosage statistics are made a summary:Solves cable using BIM technology the invention discloses one kind(Line)Laying optimization and the method for dosage statistics, comprise the following steps:Step 1, the foundation of model, it is threedimensional model by Structures CAD conversion of drawings;Step 2, cable testing bridge, cable(Line), conduit, electrically related component Data Enter;Step 3, cable testing bridge race, distribution box race, power distribution cabinet race, conduit race, the ID of electric related component are obtained in BIM related softwares;Step 4, according to starting point, cable testing bridge, conduit path automatic laying cable(Line);Step 5, cable is calculated(Line)Dosage.It is an advantage of the invention that:Accurate statistics that is directly perceived and quickly improving cable dosage, and quickly calculating, preferably cable trace and logical relation, amendment crane span structure are laid, and instruct procurement staff to save material expense, the cabling that guiding construction personnel specification is quick, scientific and reasonable.

Description

One kind is used BIM Technology solves cable(Line)The method that laying calculates with dosage
Technical field
The present invention relates to a kind of architectural design and construction method, is that one kind BIM technology solves cable(Line)The method that laying calculates with dosage.
Background technology
The laying optimization and the accurate statistical analysis of dosage of cable are the indispensable parts of construction project.Various problems can be run into the installation implementation process of reality, cause larger loss.At present BIM technology in cable calculation amount also without well utilization, it is necessary to establish the correlating method supporting with actual cable.
The content of the invention
The present invention provides one kind and quickly solves cable with BIM technology to the deficiencies in the prior art(Line)The method that laying optimization accurately calculates with dosage.
The a kind of of the present invention solves cable with BIM technology(Line)The method that laying optimization accurately calculates with dosage, comprises the following steps:
Step 1, the foundation of model, it is threedimensional model by Structures CAD conversion of drawings;
Step 2, cable testing bridge, cable(Line)Laying, electrically conduit, related component Data Enter;
Step 3, cable testing bridge race, distribution box race, power distribution cabinet race, conduit race, the ID of electric related component are obtained in BIM correlation t softwares;
Step 4, according to the path automatic laying cable of cable testing bridge(Line), user's selection starting point(Power distribution cabinet), some crane span structure and pipe arrangement and terminal(Power distribution cabinet or loop terminal)System automatically forms optimal cable run figure after setting the rule of the model of cable manually according to the rule of cable distribution or user according to the path that user chooses, and directly calculate the cable theory dosage in the loop, in laid processes, dark pipe arrangement is marked, while irrational place progress re-optimization is laid to the crane span structure of discovery;
Step 5, cable is calculated(Line)Dosage, including the specification of various model cables, model, length, weight, estimate that loss, cable both ends are reserved etc., and when user changes or adjusts circuit assemblies, loop parameters update or manually adjusted by user therewith.
The cable(Line)Laying includes power distribution cabinet, distribution box, crane span structure, conduit, cable duct, cable and loop terminal.
Beneficial effects of the present invention:(1)Intuitively, fast, improve operating efficiency;(2)Secondary development is carried out on the basis of BIM technology, can quickly find the logical path of cable laying automatically, amendment crane span structure is laid, and automatic computing dosage, reduces the loss in work progress.
Embodiment
The invention will be further described below.
The a kind of of the present invention solves cable with BIM technology(Line)The method that laying optimization accurately calculates with dosage, comprises the following steps:
Step 1, the foundation of model, it is threedimensional model by Structures CAD conversion of drawings;
Step 2, cable testing bridge, cable(Line)Laying, electrically conduit, related component Data Enter;
Step 3, cable testing bridge race, distribution box race, power distribution cabinet race, conduit race, the ID of electric related component are obtained in BIM related softwares;
Step 4, according to the path automatic laying cable of cable testing bridge(Line), user's selection starting point(Power distribution cabinet), some crane span structure and pipe arrangement and terminal(Power distribution cabinet or loop terminal)System automatically forms optimal cable run figure after setting the rule of the model of cable manually according to the rule of cable distribution or user according to the path that user chooses, and directly calculate the cable theory dosage in the loop, in laid processes, dark pipe arrangement is marked, while irrational place progress re-optimization is laid to the crane span structure of discovery;
Step 5, cable is calculated(Line)Dosage, including the specification of various model cables, model, length, weight, estimate that loss, cable both ends are reserved etc., and when user changes or adjusts circuit assemblies, loop parameters update or manually adjusted by user therewith.
The cable(Line)Laying includes power distribution cabinet, distribution box, crane span structure, conduit, cable duct, cable and loop terminal.
Beneficial effects of the present invention:(1)Intuitively, fast, improve operating efficiency;(2)Secondary development is carried out on the basis of BIM technology, can quickly find cable automatically(Line)The logical path most preferably laid, amendment crane span structure are laid, and automatic computing dosage, reduce the loss in work progress.

Claims (2)

1. solves cable with BIM technology in one kind(Line)The method that laying calculates with dosage, it is characterised in that comprise the following steps:
Step 1, the foundation of model, it is threedimensional model by Structures CAD conversion of drawings;
Step 2, cable testing bridge, cabling(Line), conduit, electrically related component Data Enter;
Step 3, cable testing bridge race, distribution box race, power distribution cabinet race, conduit race, the ID of electric related component are obtained in BIM related softwares;
Step 4, according to starting point, cable testing bridge, conduit path automatic laying cable(Line);User chooses starting point(Power distribution cabinet), some crane span structure and pipe arrangement and terminal(Power distribution cabinet or loop terminal)System automatically forms cable and most preferably lays path profile after setting the rule of the model of cable manually according to the rule of cable distribution or user according to the path that user chooses, and directly calculate the cable theory dosage in the loop, in laid processes, dark pipe arrangement is marked, while irrational place progress re-optimization is laid to the crane span structure of discovery;
Step 5, cable is calculated(Line)Dosage, including the specification of various model cables, model, length, weight, estimate that loss, cable both ends are reserved etc., and when user changes or adjusts circuit assemblies, loop parameters update or manually adjusted by user therewith.
A kind of 2. BIM technology solution cable according to claim 1(Line)The method that laying calculates with dosage, it is characterised in that the cable laying includes power distribution cabinet, distribution box, crane span structure, conduit, cable duct, cable and loop terminal.
CN201610314975.0A 2016-05-13 2016-05-13 It is a kind of to solve cable with BIM technology(Line)The method that laying calculates with dosage Pending CN107368909A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610314975.0A CN107368909A (en) 2016-05-13 2016-05-13 It is a kind of to solve cable with BIM technology(Line)The method that laying calculates with dosage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610314975.0A CN107368909A (en) 2016-05-13 2016-05-13 It is a kind of to solve cable with BIM technology(Line)The method that laying calculates with dosage

Publications (1)

Publication Number Publication Date
CN107368909A true CN107368909A (en) 2017-11-21

Family

ID=60304660

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610314975.0A Pending CN107368909A (en) 2016-05-13 2016-05-13 It is a kind of to solve cable with BIM technology(Line)The method that laying calculates with dosage

Country Status (1)

Country Link
CN (1) CN107368909A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109033631A (en) * 2018-07-25 2018-12-18 中国长江电力股份有限公司 A kind of power station optical cable or cable routing three-dimensional display method based on design information
CN109244933A (en) * 2018-11-12 2019-01-18 中国十七冶集团有限公司 A method of the installation of electric substation's cable is solved based on BIM technology
CN109284534A (en) * 2018-08-10 2019-01-29 五冶集团上海有限公司 A kind of method and system that the cable dosage information based on BIM technology accurately counts
CN109472044A (en) * 2018-09-18 2019-03-15 上海斯涵福信息科技有限公司 A kind of cable calculation amount method, system and medium based on BIM
CN109766601A (en) * 2018-12-26 2019-05-17 中冶京诚工程技术有限公司 Electric piping computer-assisted mapping method and device
CN110096782A (en) * 2019-04-24 2019-08-06 中国石油天然气集团有限公司 A kind of oil-gas pipeline engineering power cable minute design method
CN112733234A (en) * 2021-01-08 2021-04-30 珠海新势力创建筑设计有限公司 Three-dimensional bridge automatic calculation and generation device based on cable information transmission
CN112883452A (en) * 2019-11-29 2021-06-01 北京博超时代软件有限公司 Method, device and equipment for generating lighting design protection tube and storage medium
CN113113875A (en) * 2021-04-22 2021-07-13 湖南浩宇建设有限公司 Novel building ground electricity cable rack installation method
US11120171B2 (en) 2019-09-13 2021-09-14 Mccormick Systems Llc. System and method for construction cost estimation for non-computer aided design (CAD) files
CN113742832A (en) * 2021-09-17 2021-12-03 中建八局第二建设有限公司 Cable construction control method based on BIM depth plan

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070038415A1 (en) * 2005-08-15 2007-02-15 Kabushiki Kaisha Toshiba Cable quantity totalizing device, cable quantity totalizing method and cable quantity totalizing program
CN102495930A (en) * 2011-12-12 2012-06-13 河北省电力勘测设计研究院 Automatic generation method of cable bridge
CN104361185A (en) * 2014-11-21 2015-02-18 南京航空航天大学 Wire distribution space automatic generating method for cable virtual design
CN105005676A (en) * 2015-08-13 2015-10-28 国网上海市电力公司 Three-dimension design method based on cable engineering information model
CN105005659A (en) * 2015-07-16 2015-10-28 中国能源建设集团广东省电力设计研究院有限公司 Cable laying method and system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070038415A1 (en) * 2005-08-15 2007-02-15 Kabushiki Kaisha Toshiba Cable quantity totalizing device, cable quantity totalizing method and cable quantity totalizing program
CN102495930A (en) * 2011-12-12 2012-06-13 河北省电力勘测设计研究院 Automatic generation method of cable bridge
CN104361185A (en) * 2014-11-21 2015-02-18 南京航空航天大学 Wire distribution space automatic generating method for cable virtual design
CN105005659A (en) * 2015-07-16 2015-10-28 中国能源建设集团广东省电力设计研究院有限公司 Cable laying method and system
CN105005676A (en) * 2015-08-13 2015-10-28 国网上海市电力公司 Three-dimension design method based on cable engineering information model

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘东 等: "BRCM软件在选煤厂电缆敷设中的应用", 《中州煤炭》 *
解莎莎 等: "基于 BIM 技术的 BRCM 三维电缆敷设软件在营口五矿600m2烧结工程中的应用", 《施工技术》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109033631A (en) * 2018-07-25 2018-12-18 中国长江电力股份有限公司 A kind of power station optical cable or cable routing three-dimensional display method based on design information
CN109284534A (en) * 2018-08-10 2019-01-29 五冶集团上海有限公司 A kind of method and system that the cable dosage information based on BIM technology accurately counts
CN109472044A (en) * 2018-09-18 2019-03-15 上海斯涵福信息科技有限公司 A kind of cable calculation amount method, system and medium based on BIM
CN109472044B (en) * 2018-09-18 2022-12-02 上海斯涵福信息科技有限公司 Cable calculation method, system and medium based on BIM
CN109244933A (en) * 2018-11-12 2019-01-18 中国十七冶集团有限公司 A method of the installation of electric substation's cable is solved based on BIM technology
CN109766601A (en) * 2018-12-26 2019-05-17 中冶京诚工程技术有限公司 Electric piping computer-assisted mapping method and device
CN110096782A (en) * 2019-04-24 2019-08-06 中国石油天然气集团有限公司 A kind of oil-gas pipeline engineering power cable minute design method
US11120171B2 (en) 2019-09-13 2021-09-14 Mccormick Systems Llc. System and method for construction cost estimation for non-computer aided design (CAD) files
CN112883452A (en) * 2019-11-29 2021-06-01 北京博超时代软件有限公司 Method, device and equipment for generating lighting design protection tube and storage medium
CN112883452B (en) * 2019-11-29 2024-02-20 北京博超时代软件有限公司 Lighting design protection tube generation method, device, equipment and storage medium
CN112733234A (en) * 2021-01-08 2021-04-30 珠海新势力创建筑设计有限公司 Three-dimensional bridge automatic calculation and generation device based on cable information transmission
CN112733234B (en) * 2021-01-08 2024-03-19 珠海新势力创建筑设计有限公司 Device for automatically calculating and generating three-dimensional bridge based on cable information transmission
CN113113875A (en) * 2021-04-22 2021-07-13 湖南浩宇建设有限公司 Novel building ground electricity cable rack installation method
CN113742832A (en) * 2021-09-17 2021-12-03 中建八局第二建设有限公司 Cable construction control method based on BIM depth plan

Similar Documents

Publication Publication Date Title
CN107368909A (en) It is a kind of to solve cable with BIM technology(Line)The method that laying calculates with dosage
CN103066698B (en) Implement method for automatic generation of visible power grid trend chart in dispatching system
CN110401145B (en) Cable laying method
CN103020335A (en) Method for automatically converting distribution network geographic wiring diagram into region orthogonal diagram
CN109214684A (en) A kind of distribution line theory wire loss on-line calculation method
CN105305438B (en) New energy power station model verification method based on impedance and controlled AC voltage source
CN105811452A (en) Power distribution network distributed photovoltaic limit permeability analysis method and device
CN102436534A (en) Simulating method for electric power system
CN112287540B (en) Electromagnetic transient joint simulation method for accessing wind power plant to power grid
CN103488837B (en) A kind of Net Frame of Electric Network figure autoplacement method based on plant stand geography information
CN110299713A (en) A kind of tractive power supply system imbalance of three-phase voltage compensation method counted and wind power plant influences
CN105335581A (en) Optimization method of airplane wiring harness mass distribution data
CN105184508A (en) Harmonic measuring point optimal allocation method for distribution network
CN110705739B (en) New energy power station power generation plan making method and system
CN106026178B (en) A kind of more distributed generation resources self-discipline electricity-generating control methods in region and device
CN108108888A (en) The active command cooperative control method and device of wind-power electricity generation and photovoltaic generation
CN103401247A (en) Optimization method for realizing automatic generation control (AGC) and automatic voltage control (AVC) in monitoring system of boosting station of power plant
CN106013798A (en) Marker bed construction method based on building information modeling (BIM)
CN103543509B (en) The method and system of laying optical cable in intelligent substation
CN106169089A (en) A kind of progress monitoring method of cable construction
CN109038640A (en) A kind of UPFC series side inverter constant volume method based on Phasor graphical method
CN206820366U (en) Secondary cable lays servicing unit
CN109474027A (en) A kind of droop control method, device and current transformer
CN106339513A (en) Method drafting distribution network rack graph according to GIS platform and PMS system machine account data
CN203930498U (en) Alternating current-direct current complex large power grid frequency control closed loop test system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171121

WD01 Invention patent application deemed withdrawn after publication