CN107359587A - The non-reliability earthed system self-adaption route selection leakage protection system of three-phase and method - Google Patents
The non-reliability earthed system self-adaption route selection leakage protection system of three-phase and method Download PDFInfo
- Publication number
- CN107359587A CN107359587A CN201710659186.5A CN201710659186A CN107359587A CN 107359587 A CN107359587 A CN 107359587A CN 201710659186 A CN201710659186 A CN 201710659186A CN 107359587 A CN107359587 A CN 107359587A
- Authority
- CN
- China
- Prior art keywords
- phase
- circuit
- earth leakage
- self
- zero
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H3/00—Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection
- H02H3/006—Calibration or setting of parameters
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R19/00—Arrangements for measuring currents or voltages or for indicating presence or sign thereof
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/50—Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
- G01R31/58—Testing of lines, cables or conductors
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H3/00—Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection
- H02H3/26—Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection responsive to difference between voltages or between currents; responsive to phase angle between voltages or between currents
- H02H3/32—Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection responsive to difference between voltages or between currents; responsive to phase angle between voltages or between currents involving comparison of the voltage or current values at corresponding points in different conductors of a single system, e.g. of currents in go and return conductors
Abstract
The present invention relates to a kind of non-reliability earthed system self-adaption route selection leakage protection system of three-phase and method; on the basis of the residual current protective unit detected based on power direction; add self-adaptive features collecting unit; when electric network composition changes; electric leakage characteristic parameter is captured by self-adaptive features collecting unit and adjustment circuit parameter is to adapt to the residual current protective unit; solve when network system structure changes, the problem of failure based on the earth leakage protective that power direction detects.
Description
Technical field
The present invention relates to earth leakage protective field, more particularly to a kind of non-reliability earthed system self-adaption route selection electric leakage of three-phase
Protect system and method.
Background technology
The non-reliable ground system of three-phase is used for industrial and mining enterprises, and these units are high to electricity consumption reliability requirement, and it is general this
The production overall situation of a little enterprises is complicated, and more or less presence is inflammable, explosion hazard gases or various dust are, it is necessary to there may be put
Electric spark or the leak current fault of critical human life safety use necessary safety measure, should be timely once leak current fault occurs
Fault branch is cut off, does not make failure propagation.The electrical leakage detecting method that the non-reliable ground system of three-phase uses at present has:Additional direct current
Method, residual voltage method, zero sequence power direction method etc..Wherein, if realizing earth leakage protective by detecting residual voltage size, act
Resistance value is unstable.Act selective, but act if realizing earth leakage protective by detecting zero-sequence current size, during single-phase earth leakage
Resistance value is unstable, especially when grid branch is less, is also easy to produce malfunction;If judge to leak electricity by zero sequence power direction information
Fault branch, then after carrying out secondary judgement by branch road zero-sequence current threshold value of leaking electricity, leak current fault branch road can be judged exactly,
Therefore in practice, zero sequence power direction method is advantageously.Zero sequence power direction method combines zero-sequence voltage protection, zero-sequence current
Protection and the principle of zero-sequence current direction protection, power supply system is not judged merely with the amplitude size of residual voltage and zero-sequence current
Electric leakage whether occurs in system and which bar branch road leaks electricity, while also uses the phase of each branch road residual voltage and zero-sequence current
Relation judges branch road, has so reached good selective purpose, and and can well prevent mistake using triple judgements
Action.
With the development of microcontroller technology, currently there is some protection control circuits based on microcontroller, but work
The production environment of ore deposit enterprise is miscellaneous, live power network insulation against ground resistance, distribution capacity etc. electronic component Parameters variation it is larger,
These earth leakage protective device effects based on microcontroller are simultaneously unstable.Especially in the presence of compensation inductance or electric capacity three-phase it is non-can
By in earthed system, once electric network composition changes in network system, there is situations such as back-off, undercompensation, then based on micro-
Controller technology, power direction detection leakage protection system will fail.
The content of the invention
It is an object of the invention to provide a kind of non-reliability earthed system self-adaption route selection leakage protection system of three-phase and
Method, solve when network system structure changes, the problem of failure based on the earth leakage protective that power direction detects.
In order to solve the above problems, the invention provides a kind of non-reliability earthed system self-adaption route selection electric leakage of three-phase to protect
Protecting system, including the residual current protective unit detected based on power direction, in addition to self-adaptive features collecting unit, it is described adaptive
Collection apparatus unit is used for leakage analog, to capture electric leakage feature, and passes through adjustment circuit parameter adaptation residual current protective unit, institute
Stating self-adaptive features collecting unit includes:Collection apparatus primary circuit and control unit, wherein, the collection apparatus primary circuit bag
Include two single-phase earth leakage analog circuits for connecting not isopen;The control unit includes receiving and handles gathered data and adjust electricity
The master controller of road parameter, two hysteresis loop comparator, precision rectifer and the LPFs for corresponding to single-phase earth leakage analog circuit
Device.
Further, the collection apparatus primary circuit includes two single-phase earth leakage analog circuits, i.e. the first single-phase earth leakage
Analog circuit and the second single-phase earth leakage analog circuit, the first single-phase earth leakage analog circuit include resistance R in parallel1And electric capacity
C1, and it is configured with the switch S of control circuit break-make1, the first single-phase earth leakage analog circuit one end ground connection;Described second is single-phase
Leakage analog circuit includes resistance R in parallel2With electric capacity C2, and it is configured with the switch S of control circuit break-make2, described second is single-phase
Leakage analog circuit on one side is grounded;Wherein, S is switched1And S2Opening and closing are controlled by control unit.
Further, the resistance R1=20K, the electric capacity C1=1nF, the resistance R2Value is in resistance R1Three
/ between half, the electric capacity C2Value is in electric capacity C11/3rd and half between.
Further, the master controller includes capture input module, phase shifting control module, A/D modular converters, man-machine
Interface, communication interface and experiment sampling control module, wherein the capture input module is connected by hysteresis loop comparator respectively
Single-phase earth leakage analog circuit, for depositing the circuit parameter received;The phase shifting control module is used for adjustment phase place, the people
Machine interface is used to connect a terminal operating system, convenient to pass through main controller controls collection apparatus primary circuit.
The application further relates to a kind of non-reliability earthed system self-adaption route selection earth leakage protecting method of three-phase, based on power
On the basis of the residual current protective unit of angle detecting, self-adaptive features collecting unit is added, when electric network composition changes,
Electric leakage characteristic parameter is captured by self-adaptive features collecting unit and adjustment circuit parameter is to adapt to the residual current protective unit;Institute
State residual voltage phase and zero-sequence current phase before self-adaptive features collecting unit obtains phase shift by simulating leak current fault
Parameter, phase-shift circuit parameter is then adjusted, makes the residual voltage after phase shift and the same phase of zero-sequence current, to the zero-sequence current before phase shift
Vector sum, and the spy using the electric signal after gained vector sum progress precision rectifer as route selection are asked with the residual voltage after phase shift
Value indicative.
Further, the self-adaptive features collecting unit includes collection apparatus primary circuit, control unit and terminal behaviour
Make system.The collection apparatus primary circuit includes the first single-phase earth leakage analog circuit and the second single-phase earth leakage analog circuit, institute
Stating the first single-phase earth leakage analog circuit includes resistance R in parallel1With electric capacity C1, and it is configured with the switch S of control circuit break-make1, institute
State first single-phase earth leakage analog circuit one end ground connection;The second single-phase earth leakage analog circuit includes resistance R in parallel2And electric capacity
C2, and it is configured with the switch S of control circuit break-make2, the second single-phase earth leakage analog circuit one end ground connection;Wherein, S is switched1With
S2Opening and closing are controlled by control unit.The control unit include receive and processing gathered data and adjustment circuit parameter master controller,
Hysteresis loop comparator, precision rectifer and the low pass filter of two corresponding single-phase earth leakage analog circuits, wherein, the main control
Device include two be used for deposit receive circuit parameter capture input modules, the phase shifting control module for adjustment phase place,
A/D modular converters, man-machine interface, communication interface and experiment sampling control module, wherein capture input module is caught including first
Input module and the second capture input module are obtained, is respectively used to deposit residual voltage and zero-sequence current.The terminal operating system
The man-machine interface connection master controller is connected through, and passes through main controller controls collection apparatus primary circuit, the terminal
Operating system is provided with the electric leakage parameter that the residual current protective unit is obtained by collection apparatus primary circuit and control unit
The flow of operation.
Further, when being tested self-adaptive features collecting unit to obtain electric leakage characteristic parameter, terminal behaviour
The operating process for making system comprises the following steps:
1) electric leakage signal collection or experimental order are inputted;
2) the switch S in the first single-phase earth leakage analog circuit is controlled1Closure;
3) residual voltage A is captured1Value is stored in the first capture input module, if time-out will move out, terminal operating system
User trial failure is prompted, checks circuit, if it is successful, preparing capture zero-sequence current B1;
4) zero-sequence current B is captured1Value is stored in the second capture input module, if time-out will move out, terminal operating system
User trial failure is prompted, checks circuit;
5) residual voltage A is calculated1With zero-sequence current B1Phase difference ψ1;
6) phase-shift circuit parameter is adjusted, the residual voltage after phase shift is moved and zero-sequence current B1Same phase, after gathering phase shift
Residual voltage;
7) the A/D modular converters of master controller are started to the zero-sequence current B before phase shift1With the residual voltage after phase shift to
Amount and SaCarry out 64 conversions;
8) leak(age) test switch S is cut off1;
9) digital filtering processing is carried out to the sampled value of gained in step 7, and calculates arithmetic mean of instantaneous value E1;
10) E is stored1With phasor difference ψ1Information;
11) the switch S in the second single-phase earth leakage analog circuit is controlled2Closure;
12) residual voltage A is captured2Value is stored in the first capture input module, if time-out will move out, prompts user trial
Failure, check circuit;If it is successful, prepare capture zero-sequence current B2;
13) zero-sequence current B is captured2Value is stored in the second capture input module, if time-out will move out, prompts user trial
Failure, check circuit;
14) capture A is calculated2With B2Phase difference ψ2;
15) phase-shift circuit parameter is adjusted, makes the residual voltage shifting after phase shift and zero-sequence current in the second leakage analog circuit
Same phase, gather the residual voltage after phase shift;
16) the A/D modular converters of master controller are started to the residual voltage after phase shift in the second leakage analog circuit and shifting
The zero-sequence current B of phase front2Vector sum SbCarry out 64 conversions;
17) leak(age) test switch S is cut off2;
18) digital filtering processing is carried out to the sampled value of gained in step 15, and calculates arithmetic mean of instantaneous value E2;
If 19) 0.85 ψ1<ψ2<1.1ψ1,E2>0.9E1Then think adaptive success;
20) the adaptive success of display.
Compared with prior art, there is following technique effect in the present invention:
The present invention provides a kind of non-reliability earthed system self-adaption route selection leakage protection system of three-phase, when electric network composition is sent out
During raw change, self-adaptive features collecting unit capture electric leakage characteristic value, so as to adapt to residual current protective unit, earth leakage protective is avoided
There is overcompensation or under-compensated situation in unit.
The present invention also provides a kind of three-phase non-reliability earthed system self-adaption route selection earth leakage protecting method, passes through artificial mould
Intend leak current fault capture electric leakage characteristic value, so as to realize the accurate route selection of residual current protective unit.
Brief description of the drawings
Fig. 1 is the collection apparatus primary circuit figure of the present invention;
Fig. 2 is the electric leakage signal handling principle block diagram of the adaptive collecting unit of the present invention;
Fig. 3 is the algorithm pattern of the adaptive collecting unit experiment of the present invention.
Embodiment
Below in conjunction with accompanying drawing, lift a specific embodiment and described in detail.
As depicted in figs. 1 and 2, the invention provides a kind of non-reliability earthed system self-adaption route selection earth leakage protective of three-phase
System, including (residual current protective unit is existing mature technology to the residual current protective unit detected based on power direction, therefore is not gone to live in the household of one's in-laws on getting married herein
State) and self-adaptive features collecting unit.
Self-adaptive features collecting unit is used for leakage analog, to capture electric leakage feature, and passes through adjustment circuit parameter adaptation
Residual current protective unit, so that it is guaranteed that the accurate route selection of residual current protective unit.Self-adaptive features collecting unit includes collection apparatus once
Circuit, control unit and PC.As Fig. 1 be characterized collection primary circuit circuit diagram, collection apparatus primary circuit be used for simulate leak
Electric fault, to capture the basic parameters such as residual voltage phase, zero-sequence current phase.Collection apparatus primary circuit includes being connected to not
The the first single-phase earth leakage analog circuit and the second single-phase earth leakage analog circuit of isopen.First single-phase earth leakage analog circuit is included simultaneously
The resistance R of connection1With electric capacity C1, and it is configured with the switch S of control circuit break-make1, first single-phase earth leakage analog circuit one end ground connection;
Second single-phase earth leakage analog circuit includes resistance R in parallel2With electric capacity C2, and it is configured with the switch S of control circuit break-make2, second
Single-phase earth leakage analog circuit one end is grounded.The value of resistance and electric capacity and the tolerable single-phase Leaked Current of Line to Ground resistance value of industry spot
Relevant, the application selects C1=20K, C1=1nF, resistance R2Value is in resistance R1Three/with between half, it is described
Electric capacity C2Value is in electric capacity C11/3rd and half between.
Control unit include master controller, the hysteresis loop comparator of two corresponding single-phase earth leakage analog circuits, precision rectifer with
And low pass filter, wherein, master controller can realize controlling feature collection primary circuit, receive gathered data, processing data with
And adjustment circuit parameter, connection PC, controlling switch S2With switch S2, the function such as communication, including storage gathered data first catches
Obtain input module and the second capture input module, the phase shifting control module of adjustment phase place, A/D modular converters, man-machine interface, communication
Interface and experiment sampling control module.Wherein, man-machine interface is used to connect PC, is easy to manual control collection apparatus once electric
Road;Capture input module has two, for receiving the collection signal of primary circuit;First capture input module is used to catch zero sequence
Voltage, the second capture input module are used to capture zero-sequence current.
PC connects master controller and passes through main controller controls collection apparatus primary circuit.PC, which is provided with, passes through feature
Primary circuit and control unit are gathered to obtain the operating process of the electric leakage parameter of the residual current protective unit.
When electric network composition changes, self-adaptive features collecting unit capture electric leakage characteristic parameter, self-adaptive features are adopted
The operation principle for collecting unit is as shown in Figure 2.Closure switch S1Or switch S2, gather residual voltage and carry out digital filtering and put
Big processing, is then deposited in the first capture input module through a hysteresis loop comparator;Zero-sequence current is gathered again and carries out numeral
Filtering and enhanced processing, are then deposited in the second capture input module through another hysteresis loop comparator;According to the zero sequence of collection
Its phase difference can be calculated in voltage and zero-sequence current, and the scope of controllable phase shift is judged according to the phase difference, and passes through main control
The phase shifting control module of device carries out phase shift so that the same phase of residual voltage and zero-sequence current after phase shift;To the electric current before phase shift and
Voltage after phase shift seeks vector sum, carries out precision rectifer and low pass filter processing successively to gained vector sum, then passes through
The A/D modular converters of master controller carry out 64 conversions.
The non-reliability earthed system self-adaption route selection leakage protection system of three-phase provided by the invention, when electric network composition occurs
During change, self-adaptive features collecting unit capture electric leakage characteristic value, so as to adapt to residual current protective unit, earth leakage protective list is avoided
There is overcompensation or under-compensated situation in member.
Present invention also provides a kind of non-reliability earthed system self-adaption route selection earth leakage protecting method of three-phase, its department of physics
System is based on the above-mentioned non-reliability earthed system self-adaption route selection leakage protection system of three-phase.This method is based on power side
To on the basis of the residual current protective unit of detection, self-adaptive features collecting unit is added, when electric network composition changes, is led to
Cross self-adaptive features collecting unit capture electric leakage characteristic parameter and adjustment circuit parameter is to adapt to residual current protective unit.It is adaptive special
The parameter that collecting unit obtains residual voltage phase and zero-sequence current phase before phase shift according to simulation leak current fault is levied, is then adjusted
Whole phase-shift circuit parameter, make the residual voltage after phase shift equal with zero-sequence current, after the zero-sequence current before phase shift and phase shift
Residual voltage asks vector sum, and the characteristic value using the electric signal after gained vector sum progress precision rectifer as route selection, entirely
Electric leakage signal is gathered or experiment process is operated via PC and completed, as shown in figure 3, specific operating procedure is as follows:
1) electric leakage signal collection or experimental order are inputted;
2) the switch S in the first single-phase earth leakage analog circuit is controlled1Closure;
3) residual voltage A is captured1Value is stored in the first capture input module, if time-out will move out, terminal operating system
User trial failure is prompted, checks circuit, if it is successful, preparing capture zero-sequence current B1;
4) zero-sequence current B is captured1Value is stored in the second capture input module, if time-out will move out, terminal operating system
User trial failure is prompted, checks circuit;
5) residual voltage A is calculated1With zero-sequence current B1Phase difference ψ1;
6) phase-shift circuit parameter is adjusted, the residual voltage after phase shift is moved and zero-sequence current B1Same phase, after gathering phase shift
Residual voltage;
7) the A/D modular converters of master controller are started to the zero-sequence current B before phase shift1With the residual voltage after phase shift to
Amount and SaCarry out 64 conversions;
8) leak(age) test switch S is cut off1;
9) digital filtering processing is carried out to the sampled value of gained in step 7, and calculates arithmetic mean of instantaneous value E1;
10) E is stored1With phasor difference ψ1Information;
11) the switch S in the second single-phase earth leakage analog circuit is controlled2Closure;
12) residual voltage A is captured2Value is stored in the first capture input module, if time-out will move out, prompts user trial
Failure, check circuit;If it is successful, prepare capture zero-sequence current B2;
13) zero-sequence current B is captured2Value is stored in the second capture input module, if time-out will move out, prompts user trial
Failure, check circuit;
14) capture A is calculated2With B2Phase difference ψ2;
15) phase-shift circuit parameter is adjusted, makes the residual voltage shifting after phase shift and zero-sequence current in the second leakage analog circuit
Same phase, gather the residual voltage after phase shift;
16) the A/D modular converters of master controller are started to the residual voltage after phase shift in the second leakage analog circuit and shifting
The zero-sequence current B of phase front2Vector sum SbCarry out 64 conversions;
17) leak(age) test switch S is cut off2;
18) digital filtering processing is carried out to the sampled value of gained in step 15, and calculates arithmetic mean of instantaneous value E2;
If 19) 0.85 ψ1<ψ2<1.1ψ1,E2>0.9E1Then think adaptive success;
20) the adaptive success of display.
The non-reliability earthed system self-adaption route selection earth leakage protecting method of three-phase provided by the invention, by artificially simulating Lou
Electric fault capture electric leakage characteristic value, realizes the accurate route selection of residual current protective unit.
Disclosed above is only the specific embodiment of the application, but the application is not limited to this, any this area
Technical staff can think change, should all fall in the protection domain of the application.
Claims (7)
1. a kind of non-reliability earthed system self-adaption route selection leakage protection system of three-phase, including the leakage detected based on power direction
Electric protection unit, it is characterised in that also including self-adaptive features collecting unit,
The self-adaptive features collecting unit is used for leakage analog, to capture electric leakage feature, and passes through adjustment circuit parameter adaptation
Residual current protective unit, the self-adaptive features collecting unit include:
Collection apparatus primary circuit, the collection apparatus primary circuit include two single-phase earth leakage for connecting not isopen simulation electricity
Road;
Control unit, the control unit includes receiving and the master control group master controller of processing gathered data and adjustment circuit parameter, two
Hysteresis loop comparator, precision rectifer and the low pass filter of individual corresponding single-phase earth leakage analog circuit.
2. the non-reliability earthed system self-adaption route selection leakage protection system of three-phase as claimed in claim 1, it is characterised in that
The collection apparatus primary circuit includes:
First single-phase earth leakage analog circuit, the first single-phase earth leakage analog circuit include resistance R in parallel1With electric capacity C1, and match somebody with somebody
It is equipped with the switch S of control circuit break-make1, the first single-phase earth leakage analog circuit one end ground connection;
Second single-phase earth leakage analog circuit, the second single-phase earth leakage analog circuit include resistance R in parallel2With electric capacity C2, and match somebody with somebody
It is equipped with the switch S of control circuit break-make2, the second single-phase earth leakage analog circuit one end ground connection;
Wherein, S is switched1And S2Opening and closing are controlled by control unit.
3. the non-reliability earthed system self-adaption route selection leakage protection system of three-phase as claimed in claim 2, it is characterised in that
The resistance R1=20K, the electric capacity C1=1nF,
The resistance R2Value is in resistance R1Three/with between half, the electric capacity C2Value is in electric capacity C1Three points
One of between half.
4. the non-reliability earthed system self-adaption route selection leakage protection system of three-phase as claimed in claim 2, it is characterised in that
The master controller includes:
Input module is captured, the capture input module connects single-phase earth leakage analog circuit by hysteresis loop comparator respectively, is used for
Deposit the circuit parameter received;
Phase shifting control module, for adjustment phase place;
A/D modular converters;
Man-machine interface;
Communication interface;
Test sampling control module.
5. a kind of non-reliability earthed system self-adaption route selection earth leakage protecting method of three-phase, it is characterised in that based on power side
To on the basis of the residual current protective unit of detection, self-adaptive features collecting unit is added, when electric network composition changes, is led to
Cross self-adaptive features collecting unit capture electric leakage characteristic parameter and adjustment circuit parameter be to adapt to the residual current protective unit,
The self-adaptive features collecting unit obtains residual voltage phase and zero-sequence current before phase shift by simulating leak current fault
The parameter of phase, phase-shift circuit parameter is then adjusted, makes the residual voltage after phase shift and the same phase of zero-sequence current, to zero before phase shift
Residual voltage after sequence electric current and phase shift seeks vector sum, and using the electric signal after gained vector sum progress precision rectifying as route selection
Characteristic value.
6. the non-reliability earthed system self-adaption route selection earth leakage protecting method of three-phase as claimed in claim 5, it is characterised in that
The self-adaptive features collecting unit includes:
Collection apparatus primary circuit, the collection apparatus primary circuit include two single-phase earth leakage analog circuits, i.e., first is single-phase
Leakage analog circuit and the second single-phase earth leakage analog circuit;The first single-phase earth leakage analog circuit includes resistance R in parallel1With
Electric capacity C1, and it is configured with the switch S of control circuit break-make1, the first single-phase earth leakage analog circuit one end ground connection;Described second
Single-phase earth leakage analog circuit includes resistance R in parallel2With electric capacity C2, and it is configured with the switch S of control circuit break-make2, described second
Single-phase earth leakage analog circuit one end is grounded;Wherein, S is switched1And S2Opening and closing are controlled by a control unit;
The control unit includes receiving and the master controller of processing gathered data and adjustable circuit parameter, two single-phase leakages of correspondence
The hysteresis loop comparator of electrical analogue circuit and the accurate reorganizer that master controller is connected by a low pass filter;Wherein, it is described
Master controller includes two and is used to deposit the capture input module of the circuit parameter received, the phase shifting control for adjustment phase place
Module, A/D modular converters, man-machine interface, communication interface and experiment sampling control module, wherein capture input module includes the
One capture input module and the second capture input module;
Terminal operating system, the terminal operating system connects master controller by the man-machine interface, and passes through master controller
Controlling feature gathers primary circuit, and the terminal operating system is provided with obtains institute by collection apparatus primary circuit and control unit
State the operating process of the electric leakage parameter of residual current protective unit.
7. the non-reliability earthed system self-adaption route selection earth leakage protecting method of three-phase described in claim 6, it is characterised in that
Self-adaptive features collecting unit is tested when leaking electricity characteristic parameter to obtain, the operating process of terminal operating system include with
Lower step:
1) electric leakage signal collection or experimental order are inputted;
2) the switch S in the first single-phase earth leakage analog circuit is controlled1Closure;
3) residual voltage A is captured1Value is stored in the first capture input module, if time-out will move out, terminal operating system prompting is used
Family test failure, circuit is checked, if it is successful, preparing capture zero-sequence current B1;
4) zero-sequence current B is captured1Value is stored in the second capture input module, if time-out will move out, terminal operating system prompting is used
Family test failure, check circuit;
5) residual voltage A is calculated1With zero-sequence current B1Phase difference ψ1;
6) phase-shift circuit parameter is adjusted, the residual voltage after phase shift is moved with the same phase of zero-sequence current, the zero sequence electricity after collection phase shift
Pressure;
7) the A/D modular converters of master controller are started to the zero-sequence current B before phase shift1With the vector sum of the residual voltage after phase shift
SaCarry out 64 conversions;
8) leak(age) test switch S is cut off1;
9) to carrying out digital filtering processing to the sampled value of gained in step 7, and arithmetic mean of instantaneous value E is calculated1;
10) E is stored1With phasor difference ψ1Information;
11) the switch S in the second single-phase earth leakage analog circuit is controlled2Closure;
12) residual voltage A is captured2Value is stored in the first capture input module, if time-out will move out, prompts user trial failure,
Check circuit;If it is successful, prepare capture zero-sequence current B2;
13) zero sequence electric power B is captured2Value is stored in the second capture input module, if time-out will move out, prompts user trial failure,
Check circuit;
14) capture A is calculated2With B2Phase difference ψ2;
15) phase-shift circuit parameter is adjusted, makes the residual voltage shifting after phase shift and the same phase of zero-sequence current in the second leakage analog circuit,
Gather the residual voltage after phase shift;
16) before the A/D modular converters of startup master controller are to the residual voltage after phase shift in the second leakage analog circuit and phase shift
Zero-sequence current B2Vector sum SbCarry out 64 conversions;
17) leak(age) test switch S is cut off2;
18) digital filtering processing is carried out to the sampled value of gained in step 16, and calculates arithmetic mean of instantaneous value E2;
If 19) 0.85 ψ1<ψ2<1.1ψ1,E2>0.9E1Then think adaptive success;
20) the adaptive success of display.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710659186.5A CN107359587B (en) | 2017-08-04 | 2017-08-04 | The non-reliability earthed system self-adaption route selection leakage protection system of three-phase and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710659186.5A CN107359587B (en) | 2017-08-04 | 2017-08-04 | The non-reliability earthed system self-adaption route selection leakage protection system of three-phase and method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107359587A true CN107359587A (en) | 2017-11-17 |
CN107359587B CN107359587B (en) | 2019-04-30 |
Family
ID=60288160
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710659186.5A Active CN107359587B (en) | 2017-08-04 | 2017-08-04 | The non-reliability earthed system self-adaption route selection leakage protection system of three-phase and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107359587B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111585244A (en) * | 2020-05-26 | 2020-08-25 | 芯海科技(深圳)股份有限公司 | Leakage protection circuit, integrated circuit, electronic device, and method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2063309U (en) * | 1990-03-12 | 1990-10-03 | 郑秉阳 | Multifunction protector for high-voltage electric leakage |
US6025980A (en) * | 1998-08-10 | 2000-02-15 | General Electric Company | Earth leakage protective relay |
CN101026295A (en) * | 2006-12-21 | 2007-08-29 | 王小华 | Non-grounding neutral point system low-voltage leakage protection method and its equipment |
CN202940556U (en) * | 2012-09-04 | 2013-05-15 | 北京矿能科技有限公司 | Mining explosion-proof type low-voltage power grid multi-level electric leakage protector |
CN204167872U (en) * | 2014-11-25 | 2015-02-18 | 山西潞安环保能源开发股份有限公司常村煤矿 | Underground coal mine electrical network selective earth leakage protection checkout gear |
CN104934925A (en) * | 2015-06-01 | 2015-09-23 | 沈阳基辅新能源科技发展有限公司 | Selective electric leakage protection system for low-voltage power grid of underground coal mine |
-
2017
- 2017-08-04 CN CN201710659186.5A patent/CN107359587B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2063309U (en) * | 1990-03-12 | 1990-10-03 | 郑秉阳 | Multifunction protector for high-voltage electric leakage |
US6025980A (en) * | 1998-08-10 | 2000-02-15 | General Electric Company | Earth leakage protective relay |
CN101026295A (en) * | 2006-12-21 | 2007-08-29 | 王小华 | Non-grounding neutral point system low-voltage leakage protection method and its equipment |
CN202940556U (en) * | 2012-09-04 | 2013-05-15 | 北京矿能科技有限公司 | Mining explosion-proof type low-voltage power grid multi-level electric leakage protector |
CN204167872U (en) * | 2014-11-25 | 2015-02-18 | 山西潞安环保能源开发股份有限公司常村煤矿 | Underground coal mine electrical network selective earth leakage protection checkout gear |
CN104934925A (en) * | 2015-06-01 | 2015-09-23 | 沈阳基辅新能源科技发展有限公司 | Selective electric leakage protection system for low-voltage power grid of underground coal mine |
Non-Patent Citations (1)
Title |
---|
王其军: "基于零序功率方向原理的矿井漏电保护装置设计", 《煤炭科学技术》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111585244A (en) * | 2020-05-26 | 2020-08-25 | 芯海科技(深圳)股份有限公司 | Leakage protection circuit, integrated circuit, electronic device, and method |
CN111585244B (en) * | 2020-05-26 | 2022-09-16 | 芯海科技(深圳)股份有限公司 | Leakage protection circuit, integrated circuit, electronic device, and method |
Also Published As
Publication number | Publication date |
---|---|
CN107359587B (en) | 2019-04-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105610147B (en) | A kind of distribution network ground fault arc extinction method based on three-phase cascaded H-bridges current transformer | |
CN104218563B (en) | The distribution network failure arc extinguishing method that a kind of neutral point is grounded through Multilevel Inverters | |
Zhalefar et al. | A high-speed adaptive single-phase reclosing technique based on local voltage phasors | |
CN108776284B (en) | Single-phase earth fault protection method for small-resistance earth system | |
CN106556759B (en) | A kind of power distribution automation apparatus debugging method and debugging system | |
CN106872852A (en) | The multiple fault type diagnostic method of power distribution network single-phase disconnection ground connection based on residual voltage | |
CN103718055A (en) | Systems and apparatus for fault detection in dc power sources using ac residual current detection | |
CN106656021A (en) | Anti-PID (Potential Induced Degradation) combiner box system and realization method thereof | |
CN102354203B (en) | Combined test method of dynamic simulation device and engineering control system | |
CN110488155A (en) | A kind of fault line selection method for single-phase-to-ground fault applied to flexible ground system | |
CN106646130B (en) | A kind of active distribution network Fault Locating Method compared based on current polarity and system | |
CN105322528A (en) | Injection current two-point calculation method during small-current grounding fault active arc extinguishing | |
CN107329044A (en) | A kind of wire selection method for power distribution network single phase earthing failure based on electric arc transient state component | |
CN206100017U (en) | Electric automobile fills electric pile communication protocol detection device | |
CN112769115A (en) | Self-adaptive active full-compensation control method for grounding residual current | |
CN111103484A (en) | Island detection method, device and system based on hybrid power feedback disturbance | |
CN106329509B (en) | The small current earthing wire-selecting of neutral point of electric network isolated neutral system protects system | |
CN110261723B (en) | Low-current grounding line selection method based on coefficient of variation and high-order cumulant | |
CN111551823A (en) | Power distribution network fault line selection method and system based on angle similarity | |
CN107359587A (en) | The non-reliability earthed system self-adaption route selection leakage protection system of three-phase and method | |
CN104793109B (en) | Turn-adjusting arc-extinguishing winding simulation system and method | |
CN107831378B (en) | Device and method for detecting compensation effect of arc suppression coil | |
CN204375298U (en) | Demarcation switch Simulated training device | |
CN109490805A (en) | A kind of portable fault detector detection device | |
CN101852844A (en) | Data calibration device of AC sampling and measuring device and method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20201109 Address after: 315000 Buzheng East Road 128, Wang Chun Industrial Park, Haishu District, Ningbo, Zhejiang. Patentee after: Ningbo Deqiao Electronic Technology Co., Ltd Address before: 221000 Shanghai Road, Copper Mt. District, Jiangsu, No. 101, No. Patentee before: Jiangsu Normal University |
|
TR01 | Transfer of patent right |