CN107356838A - A kind of power distribution automation main station system failure processing function method of testing - Google Patents

A kind of power distribution automation main station system failure processing function method of testing Download PDF

Info

Publication number
CN107356838A
CN107356838A CN201610306018.3A CN201610306018A CN107356838A CN 107356838 A CN107356838 A CN 107356838A CN 201610306018 A CN201610306018 A CN 201610306018A CN 107356838 A CN107356838 A CN 107356838A
Authority
CN
China
Prior art keywords
network
power supply
tested
failure
supply area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610306018.3A
Other languages
Chinese (zh)
Other versions
CN107356838B (en
Inventor
范闻博
梁英
关石磊
白雪峰
唐可新
张新
李东良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
State Grid Shanghai Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
State Grid Shanghai Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, China Electric Power Research Institute Co Ltd CEPRI, State Grid Shanghai Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610306018.3A priority Critical patent/CN107356838B/en
Publication of CN107356838A publication Critical patent/CN107356838A/en
Application granted granted Critical
Publication of CN107356838B publication Critical patent/CN107356838B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/08Locating faults in cables, transmission lines, or networks
    • G01R31/081Locating faults in cables, transmission lines, or networks according to type of conductors
    • G01R31/086Locating faults in cables, transmission lines, or networks according to type of conductors in power transmission or distribution networks, i.e. with interconnected conductors
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The present invention provides a kind of power distribution automation main station system failure processing function method of testing, and methods described comprises the following steps:(1) power distribution network power supply area type is determined according to tested main station system, selects suitable power distribution network wiring construction;(2) distribution network model is established;(3) according to system control model, corresponding grid structure and fault scenes are designed;(4) test cases is generated, and carries out serializing test;(5) test report is generated.All kinds of distribution networks are carried out induction-arrangement by the present invention according to five class power supply areas, and are increased newly and devised typical wiring network structure, are added more active interference failures, test cases is had flexibility and scalability.

Description

A kind of power distribution automation main station system failure processing function method of testing
Technical field
The present invention relates to a kind of trouble handling function method of testing, and in particular at a kind of power distribution automation main station system failure Manage function test method.
Background technology
Traditional power distribution automation test needs to wait operation Distribution Network Failure, causes defect to be unable to early detection and solution, makes Made slow progress into electrical power distribution automatization system function validity test.Meanwhile existing numerous power distribution automation test systems, One interconnection feeder line can only be tested and emulated, lack the classification analysis to faulty line type, fault scenes pattern Tested with serializing.
When testing power distribution automation trouble handling function, conventional test methodologies are based primarily upon concentration master station mode, lack The weary fault scenes for considering to occur under other control models, it is difficult to which simulation and checking system are in the complicated variation of power distribution network Fault scenes in utility function.
The content of the invention
In order to overcome the above-mentioned deficiencies of the prior art, the present invention provides a kind of power distribution automation main station system failure processing function Method of testing, all kinds of distribution networks are carried out induction-arrangement by the present invention according to five class power supply areas, and are increased newly and devised typical case Wired network structure, more active interference failures are added, make test cases that there is flexibility and scalability.
In order to realize foregoing invention purpose, the present invention adopts the following technical scheme that:
A kind of power distribution automation main station system failure processing function method of testing, methods described comprise the following steps:
(1) power distribution network power supply area type is determined according to tested main station system, selects suitable power distribution network wiring construction;
(2) distribution network model is established;
(3) according to system control model, corresponding grid structure and fault scenes are designed;
(4) test cases is generated, and carries out serializing test;
(5) test report is generated.
Preferably, the step (1) comprises the following steps:
Step 1-1, establishing criteria Q/GDW738 division of the power supply area type, with reference to load density, the important journey of user Degree, electricity consumption level and GDP factors, determine power supply area;
Step 1-2, selection is tested the typical distribution net wiring construction of the power supply area;
If the power supply area is A or A+ classes, select bicyclic liaison net, twinshot network, three dual networks, supply one Standby network, petal-shaped network, the contact of three segmentation three and six electric power networks are tested;
If the power supply area is B classes, two-section two is selected to get in touch with, 4*6 wire meshes, monocyclic contact Single-ring network and son Female ring net is tested;
If the power supply area is C classes, two contacts, three contacts and Single-ring network is selected to be tested;
If the power supply area is D classes, simply connected network is selected to be tested;
If the power supply area is E classes, tree-type or chain type is selected to be tested.
Preferably, the step (2) comprises the following steps:
Step 2-1, configuration device table, for artificial site terminal acquisition;
The 2-2, described device table are sent to main website by gathering switch parameter;
Step 2-3, described main website issues guidance command by logic analysis, is the phantom channel where each switchgear distribution, Select communications parameter and communication type;
Step 2-4, switch parameter and load parameter are configured;
Step 2-5, the typical power distribution network figure of test required for drawing;
Step 2-6, connect database and topology information is generated in database.
Preferably, in the step (3), the following aspects is included according to the design of the fault scenes:
A, abort situation includes backbone and branched line;
B, fault type includes earth fault and two-phase phase fault;
C, active interference factor includes switch failure, switch malfunction, switch time delay response, locking and communication failure;
D, service condition, which is set, includes open loop operation, turns for allowance deficiency, maintenance circuit and extension wire failure be present;
E, multiple failure triggering includes different location and breaks down and multiple failure scene while occur.
Preferably, in the step (3), the system control model includes centralized and distributed;
For the centralized control system, when selecting grid structure, the cable web frame more than number of switches is mainly tested, Including petal-shaped network, more for one for network, monocyclic contact Single-ring network, three dual networks, bicyclic liaison net and twinshot net Network;It is main to consider active interference factor and multiple failure triggering factors in design error failure scene;
For the dcs, when selecting grid structure, selection network is complex, turns more for path Electric network composition, including more segmentation more contact, 4*6 wired networks and six electric power networks;In design error failure scene, mainly Consider that active interference factor and service condition are set.
Preferably, in the step (4), the test cases establishment, the electrical power distribution automatization system control tested with reference to needs Molding formula, corresponding fault scenes case is made, and generate orderly test cases, tested one by one.
Compared with prior art, the beneficial effects of the present invention are:
All kinds of distribution networks are carried out induction-arrangement by the present invention according to five class power supply areas, and are increased newly and devised typical wiring net Network structure, different system operation modes is considered in design error failure scene, add more active interference failures, make survey Examination case has flexibility and scalability, electrical power distribution automatization system fault simulation and processing test is more of practical significance.
Brief description of the drawings
Fig. 1 is a kind of power distribution automation main station system failure processing function method of testing flow chart provided by the invention
Embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings.
As shown in figure 1, a kind of power distribution automation main station system failure processing function method of testing provided by the invention, described Method comprises the following steps:
The tested main station system of step 1, basis determines power distribution network power supply area type, selects suitable power distribution network wiring construction;
Step 1-1, establishing criteria Q/GDW738 division of the power supply area type, with reference to load density, the important journey of user Degree, electricity consumption level and GDP factors, determine power supply area;
Step 1-2, selection is tested the typical distribution net wiring construction of the power supply area;
Step 2, establish distribution network model;
Step 2-1, configuration device table, for artificial site terminal acquisition;
The 2-2, described device table are sent to main website by gathering switch parameter;
Step 2-3, described main website issues guidance command by logic analysis, is the phantom channel where each switchgear distribution, Select communications parameter and communication type;
Step 2-4, switch parameter and load parameter are configured;
Step 2-5, the typical power distribution network figure of test required for drawing;
Step 2-6, connect database and topology information is generated in database.
Step 3, according to system control model, design corresponding grid structure and fault scenes;
A, in terms of grid structure
For centralized FA, test should be focused on when information content is huge, acquisition terminal is various, the collection of system, storage and Disposal ability.Therefore it is main to test the more cable web frame of number of switches when selecting grid structure, such as:It is quincunx Network, supply one for network, simply connected network Single-ring network, three dual networks, dual-ring network, dijection net etc. more.
It is complex from network for distributed FA, turn for the more electric network composition in path, as typical overhead net, More segmentation more contact, 4*6 wired networks, six electric power networks etc..Examination in failure recovery time when, from trouble point away from The rack case of interconnection switch farther out, such as monocyclic cable system, supply one for network, three dual networks, primary and secondary looped network more.
B, in terms of fault scenes
Centralized FA active interferences are considered as such as communication failure, switch malfunction:The identification to exception response of investigation system And fault-tolerant ability;Multiposition simultaneous faults, continuous fault:Investigate collections and processing of the centralized FA to bulk information data Ability.
Distributed FA active interferences are considered as such as communication failure, switch failure, delay response:Investigate each distributed FA The matching problem of system and automatic reclosing;Turn for allowance deficiency:Investigate processing energy of each distributed FA to remote information Power.
Step 4, generation test cases, and carry out serializing test;
Step 5, generation test report.
The feeder network wiring construction design of typical power supply area
With reference to factors such as load density, user's significance level, electricity consumption level, GDP, devise suitable for every kind of service area The typical power network wiring construction in domain, as shown in Table 5-1.Including radial circuit, various typical loop grids, more points The more contacts of section, supply standby, petal-shaped network etc. more, cover all 10kV typical distributions net wiring types, and root substantially Need to be divided into different types of power supply area according to load density, more meet the practical significance of fault simulation and test.
Each power supply area 10kV typical distributions net wiring classification of table 5-1
Typical wiring structure in test cases belongs to the early stage of modeling and the fault scenes emulation of power distribution network typical wiring structure Work, typical wiring structure should include designing suitable for the typical 10kV power distribution networks wiring construction of the class power supply area of power distribution network 5 It is main to include single radiation (radial, chain type, dijection), looped network (bicyclic contact, primary and secondary looped network, three dual networks) electricity more Source contact, the more contacts of more segmentations, n are for typical wiring structure compositions such as a standby, petal-shapeds.
Power distribution automation main station system failure processing test active interference type and Scenario-Based Design
In order to ensure the diversity of test cases, typical fault scene should consider that position, short trouble type occur for failure With test scene etc..Test scene includes switch fault, communication failure, extension wire failure etc..Meanwhile Various faults or several scenes can be allowed in individual test case while occurred, ensure that test cases diversity and Autgmentability.Fault scenes set include setting initial separating brake (i.e. setting interconnection switch position), short trouble type and position, Responsive state, Communication Jamming etc. are switched, the fault scenes of required test can be entered according to the inductive design of fault scenes Row is set.In view of it is existing concentration main station type, distribution and on the spot control etc. a variety of electrical power distribution automatization system construction scales And configuration mode.
In order to increase the comprehensive and depth of test examination, increase active interference factor, typical fault scenes should consider Position that failure occurs, short trouble type, active interference mode, service condition etc..The design of fault scenes is thought Road is as follows:
(1) abort situation selects:Backbone;Branched line;
(2) fault type selects:Earth fault (single-phase, two-phase, three-phase);Two-phase phase fault;
(3) active interference factor:Switch whether tripping;Switch whether malfunction;Switch the response that whether is delayed;Locking;It is logical Whether letter interrupts;
(4) service condition is set:Whether open loop operation;Whether turn for allowance deficiency;With the presence or absence of maintenance circuit;It is standby Line fault;
(5) multiple failure triggers:Break down different location;Multiple failure scene occurs simultaneously.
By taking the monocyclic cable system in C class power supply areas as an example, the test to several fault scenes is illustrated.According to The section of test required for electrical power distribution automatization system, with reference to load density, user's significance level, electricity consumption level, GDP etc. Factor, power supply area where determining itself, selects to test the typical distribution net wiring construction of such power supply area. It is assumed that it is C class power supply areas that surveyed electrical power distribution automatization system, which implements region, wiring construction is cable system, therefore according to table 5-1, It is test object to select Single-ring network.
Monocyclic cable system model is established, after distribution network model is built up, next stage is designed and tested for fault scenes The making of case.The present embodiment chooses wherein three kinds and (is divided to as displaying, i.e. short trouble and turns to supply whether enough two kinds of allowance Situation discussion), short trouble and the simultaneous twin failure scene of tripping.Wherein, on-load switch 1, on-load switch 2, On-load switch 3 and on-load switch 4 pass through digital communication by physical simulation, outlet breaker and other on-load switches Emulation.
(1) the short trouble scene in the case of enough for allowance is turned
Failure occurs between on-load switch 1 and 2, and outlet breaker trips first, and system enters fault isolation stage. Switch 1 trips respectively with switch 2, there is the switch of disconnection on trouble point to the path between the transformer station of both ends.In failure Restoration stage, interconnection switch close a floodgate, and outlet breaker closes a floodgate, and have opening for disconnection on the path of interconnection switch 5 to trouble point 2 are closed, the switch 1 for having disconnection on the path of outlet breaker first to trouble point.Therefore, Fault Isolation and failure are considered Recover two stages, this troubleshooting is successful.
(2) the short trouble scene supplied in the case of allowance deficiency is turned
Present case is identical with previous case, and simply set makes to turn not reaching for allowance to turn for requiring during switch load value. Therefore identical with previous case in the processing procedure of fault isolation stage, i.e. fault isolation stage processing is successful. In the fault recovery stage, due to turning to fail to close a floodgate for allowance deficiency, interconnection switch, only outlet breaker re-closes, and goes out Mouthful breaker first is to the switch 1 for having disconnection on the path of trouble point, therefore the fault recovery stage is also safe and reliable, whole failure Processing procedure is safe and reasonable.
(3) short circuit and switch failure twin failure scene
Under normal operating condition, on-load switch 4 has been set to tripping state.Failure occurs between switch 3 and 4, Switch 3 successfully be detected fault message and trip, but switch 4 due to there is provided tripping, so it keeps "on" position not Action, adjacent interconnection switch 5 is not because switch 4 disconnects normally and keeps gate-dividing state constant, trouble point to both ends There are the switch 3 and switch 5 of disconnection on path between transformer station's power supply.In the fault recovery stage, outlet breaker closes a floodgate, To the switch 3 that disconnects on the path of trouble point be present in outlet breaker first, therefore, fault recovery stage also safe and reasonable.
Finally it should be noted that:The above embodiments are merely illustrative of the technical scheme of the present invention and are not intended to be limiting thereof, although The present invention is described in detail with reference to above-described embodiment, those of ordinary skills in the art should understand that:Still The embodiment of the present invention can be modified or equivalent substitution, and appointing without departing from spirit and scope of the invention What modification or equivalent substitution, it all should cover among scope of the presently claimed invention.

Claims (6)

1. a kind of power distribution automation main station system failure processing function method of testing, it is characterised in that methods described is included such as Lower step:
(1) power distribution network power supply area type is determined according to tested main station system, selects suitable power distribution network wiring construction;
(2) distribution network model is established;
(3) according to system control model, corresponding grid structure and fault scenes are designed;
(4) test cases is generated, and carries out serializing test;
(5) test report is generated.
2. method of testing according to claim 1, it is characterised in that the step (1) comprises the following steps:
Step 1-1, establishing criteria Q/GDW738 division of the power supply area type, with reference to load density, the important journey of user Degree, electricity consumption level and GDP factors, determine power supply area;
Step 1-2, selection is tested the typical distribution net wiring construction of the power supply area;
If the power supply area is A or A+ classes, select bicyclic liaison net, twinshot network, three dual networks, supply one Standby network, petal-shaped network, the contact of three segmentation three and six electric power networks are tested;
If the power supply area is B classes, two-section two is selected to get in touch with, 4*6 wire meshes, monocyclic contact Single-ring network and son Female ring net is tested;
If the power supply area is C classes, two contacts, three contacts and Single-ring network is selected to be tested;
If the power supply area is D classes, simply connected network is selected to be tested;
If the power supply area is E classes, tree-type or chain type is selected to be tested.
3. method of testing according to claim 1, it is characterised in that the step (2) comprises the following steps:
Step 2-1, configuration device table, for artificial site terminal acquisition;
The 2-2, described device table are sent to main website by gathering switch parameter;
Step 2-3, described main website issues guidance command by logic analysis, is the phantom channel where each switchgear distribution, Select communications parameter and communication type;
Step 2-4, switch parameter and load parameter are configured;
Step 2-5, the typical power distribution network figure of test required for drawing;
Step 2-6, connect database and topology information is generated in database.
4. method of testing according to claim 1, it is characterised in that in the step (3), according to the failure The design of scene includes the following aspects:
A, abort situation includes backbone and branched line;
B, fault type includes earth fault and two-phase phase fault;
C, active interference factor includes switch failure, switch malfunction, switch time delay response, locking and communication failure;
D, service condition, which is set, includes open loop operation, turns for allowance deficiency, maintenance circuit and extension wire failure be present;
E, multiple failure triggering includes different location and breaks down and multiple failure scene while occur.
5. method of testing according to claim 4, it is characterised in that in the step (3), the system control Pattern includes centralized and distributed;
For the centralized control system, when selecting grid structure, the cable web frame more than number of switches is mainly tested, Including petal-shaped network, more for one for network, monocyclic contact Single-ring network, three dual networks, bicyclic liaison net and twinshot net Network;It is main to consider active interference factor and multiple failure triggering factors in design error failure scene;
For the dcs, when selecting grid structure, selection network is complex, turns more for path Electric network composition, including more segmentations more contact, 4*6 wired networks and six electric power networks;In design error failure scene, mainly examine Consider active interference factor and service condition is set.
6. method of testing according to claim 1, it is characterised in that in the step (4), the test cases Establishment, the electrical power distribution automatization system control model tested with reference to needs, corresponding fault scenes case is made, and generation has The test cases of sequence, is tested one by one.
CN201610306018.3A 2016-05-10 2016-05-10 Fault processing function test method for power distribution automation master station system Active CN107356838B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610306018.3A CN107356838B (en) 2016-05-10 2016-05-10 Fault processing function test method for power distribution automation master station system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610306018.3A CN107356838B (en) 2016-05-10 2016-05-10 Fault processing function test method for power distribution automation master station system

Publications (2)

Publication Number Publication Date
CN107356838A true CN107356838A (en) 2017-11-17
CN107356838B CN107356838B (en) 2021-01-08

Family

ID=60271167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610306018.3A Active CN107356838B (en) 2016-05-10 2016-05-10 Fault processing function test method for power distribution automation master station system

Country Status (1)

Country Link
CN (1) CN107356838B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108153167A (en) * 2018-02-01 2018-06-12 上海金智晟东电力科技有限公司 It can flexible configurations power distribution network dynamic model experiment platform and its method
CN108710566A (en) * 2018-04-28 2018-10-26 南京国电南自电网自动化有限公司 A kind of distribution scheduling station integration testing framework and method
CN108873735A (en) * 2018-06-29 2018-11-23 许继集团有限公司 A kind of distribution main station system component simulation testing device and method
CN109149771A (en) * 2018-09-11 2019-01-04 国网江苏省电力有限公司泰州供电分公司 A kind of feeder test method based on petal type power grid
CN110414172A (en) * 2019-08-06 2019-11-05 上海金智晟东电力科技有限公司 A kind of dynamic model configuration monitoring management method and system
CN112131096A (en) * 2020-05-07 2020-12-25 北京国网信通埃森哲信息技术有限公司 Automatic generation method and device for ICT system fault analysis and auxiliary study and judgment test cases
CN112465281A (en) * 2019-09-09 2021-03-09 南京南瑞继保电气有限公司 Stability control strategy prejudging method under real-time power system scene
CN114325224A (en) * 2021-12-14 2022-04-12 国网浙江省电力有限公司电力科学研究院 Fault section positioning method based on real-time data of distribution network

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102361346A (en) * 2011-06-23 2012-02-22 陕西电力科学研究院 Master station full-digital scene testing method of power distribution automation system
CN103632203A (en) * 2013-09-23 2014-03-12 国家电网公司 Distribution network power supply area division method based on comprehensive evaluation
CN103632306A (en) * 2013-09-23 2014-03-12 国家电网公司 Distribution network power supply area division method based on clustering analysis
JP5518926B2 (en) * 2012-03-29 2014-06-11 中国電力株式会社 Distribution automation system
CN104700327A (en) * 2015-03-30 2015-06-10 国家电网公司 Method and system for establishing power distribution automation scheme
CN105224779A (en) * 2014-06-23 2016-01-06 国家电网公司 Electrical power distribution network fault location method and device
CN105405334A (en) * 2015-12-11 2016-03-16 贵州电网公司培训与评价中心 Power distribution automation system and simulation method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102361346A (en) * 2011-06-23 2012-02-22 陕西电力科学研究院 Master station full-digital scene testing method of power distribution automation system
JP5518926B2 (en) * 2012-03-29 2014-06-11 中国電力株式会社 Distribution automation system
CN103632203A (en) * 2013-09-23 2014-03-12 国家电网公司 Distribution network power supply area division method based on comprehensive evaluation
CN103632306A (en) * 2013-09-23 2014-03-12 国家电网公司 Distribution network power supply area division method based on clustering analysis
CN105224779A (en) * 2014-06-23 2016-01-06 国家电网公司 Electrical power distribution network fault location method and device
CN104700327A (en) * 2015-03-30 2015-06-10 国家电网公司 Method and system for establishing power distribution automation scheme
CN105405334A (en) * 2015-12-11 2016-03-16 贵州电网公司培训与评价中心 Power distribution automation system and simulation method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
董旭柱: "智能配电网自愈控制技术的内涵及其应用", 《南方电网技术》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108153167A (en) * 2018-02-01 2018-06-12 上海金智晟东电力科技有限公司 It can flexible configurations power distribution network dynamic model experiment platform and its method
CN108710566A (en) * 2018-04-28 2018-10-26 南京国电南自电网自动化有限公司 A kind of distribution scheduling station integration testing framework and method
CN108710566B (en) * 2018-04-28 2021-10-22 南京国电南自电网自动化有限公司 Power distribution dispatching master station integration test system and method
CN108873735A (en) * 2018-06-29 2018-11-23 许继集团有限公司 A kind of distribution main station system component simulation testing device and method
CN108873735B (en) * 2018-06-29 2021-11-19 许继集团有限公司 Power distribution main station system component simulation test device and method
CN109149771A (en) * 2018-09-11 2019-01-04 国网江苏省电力有限公司泰州供电分公司 A kind of feeder test method based on petal type power grid
CN110414172A (en) * 2019-08-06 2019-11-05 上海金智晟东电力科技有限公司 A kind of dynamic model configuration monitoring management method and system
CN112465281A (en) * 2019-09-09 2021-03-09 南京南瑞继保电气有限公司 Stability control strategy prejudging method under real-time power system scene
CN112131096A (en) * 2020-05-07 2020-12-25 北京国网信通埃森哲信息技术有限公司 Automatic generation method and device for ICT system fault analysis and auxiliary study and judgment test cases
CN112131096B (en) * 2020-05-07 2024-05-24 北京国网信通埃森哲信息技术有限公司 ICT system fault analysis and auxiliary research and judgment test case automatic generation method and device
CN114325224A (en) * 2021-12-14 2022-04-12 国网浙江省电力有限公司电力科学研究院 Fault section positioning method based on real-time data of distribution network
CN114325224B (en) * 2021-12-14 2023-09-22 国网浙江省电力有限公司电力科学研究院 Fault interval positioning method based on distribution network real-time data

Also Published As

Publication number Publication date
CN107356838B (en) 2021-01-08

Similar Documents

Publication Publication Date Title
CN107356838A (en) A kind of power distribution automation main station system failure processing function method of testing
CN104113048B (en) A kind of power distribution network intelligent protection system
CN102035202B (en) Network reconfiguration system
CN105140894B (en) A kind of power distribution network differential protecting method based on Phase Difference Principle
CN102411117B (en) Method for positioning short-circuit fault of distribution network based on distributed intelligent multi-calibration
CN101917064B (en) Back-up protection processing method of digital substation transformer based on GOOSE mode
CN105388370B (en) A kind of substation's wall connection latching logic automated closed-loop test method
CN103956717A (en) Self-adaption microgrid overcurrent protection method
CN106527181A (en) Communication network-based distribution automation system simulation test method
CN103022994A (en) Method for achieving fault isolation and recovery of power distribution network with permeability distribution type power supply
CN104283215A (en) Detection and test method and device of intelligent distributed power distribution terminal
CN105548801B (en) Fault Locating Method suitable for power distribution network operation with closed ring
CN107843800A (en) Supply network monitoring method, apparatus and system
CN112421614A (en) Power distribution station self-healing control system and method based on local communication and topology identification
CN110514930A (en) A kind of the detection test method and device of intelligent distributed distribution terminal
CN104485736A (en) Intelligent protection center-based wide-area backup protection system and method
CN113162226A (en) Primary side fault injection FA system level test system and method based on HIL
CN108400586A (en) A kind of distributed fault self-healing method suitable for active power distribution network
CN109617238A (en) A kind of feeder automation remote terminal unit of tape test function
CN111276929B (en) Information recording method for fault expert diagnosis of power system
CN107846015A (en) Intelligent distribution network load transfer optimal route selection method based on peer-to-peer communication
CN110380378A (en) Distributed 10KV power distribution network monitoring and protection system and guard method
CN207232306U (en) A kind of pocket intelligent distribution type feeder automation tests system
CN105337314A (en) Multisource coordination control fault treatment method based on distributed power supply black start technology
AU2018363059B2 (en) Control system for and method of fault location, isolation and supply restoration

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant