CN107339069A - A kind of boring method of machine drilling stake - Google Patents

A kind of boring method of machine drilling stake Download PDF

Info

Publication number
CN107339069A
CN107339069A CN201710479041.7A CN201710479041A CN107339069A CN 107339069 A CN107339069 A CN 107339069A CN 201710479041 A CN201710479041 A CN 201710479041A CN 107339069 A CN107339069 A CN 107339069A
Authority
CN
China
Prior art keywords
diameter
stake
bit
pore
drill bit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710479041.7A
Other languages
Chinese (zh)
Inventor
于安文
谢建民
张永朋
张凯
陈柏光
周林刚
吴鸿胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
5TH CONSTRUCTION Co Ltd OF CHINA 15TH CORPERATION
China Railway 15th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Original Assignee
5TH CONSTRUCTION Co Ltd OF CHINA 15TH CORPERATION
China Railway 15th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 5TH CONSTRUCTION Co Ltd OF CHINA 15TH CORPERATION, China Railway 15th Bureau Group Co Ltd filed Critical 5TH CONSTRUCTION Co Ltd OF CHINA 15TH CORPERATION
Priority to CN201710479041.7A priority Critical patent/CN107339069A/en
Publication of CN107339069A publication Critical patent/CN107339069A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/28Enlarging drilled holes, e.g. by counterboring

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a kind of boring method of machine drilling stake, belong to civil construction piling technology field.Including:The first step, the drill bit of at least three kinds sizes is chosen according to the stake holes diameter of practice of construction;Second step, pile place is drilled successively according to the order of bit diameter from small to large, and drilling depth is the hole depth of actual design every time, until the diameter of pore-forming is identical with actual design stake holes diameter.The pore-forming resistance in work progress can be reduced.

Description

A kind of boring method of machine drilling stake
Technical field
The present invention relates to civil construction piling technology field, more particularly to a kind of boring method of machine drilling stake.
Background technology
Application No. 201510485561.X patent of invention, disclose a kind of drilling construction side of three-stage club-footed pile Method.
Civil construction be unable to do without pile foundation, and earthward lower drilling is needed before forming pile foundation.Existing boring method is three Segmentation play, i.e., hole is divided into three sections along its length and carries out drilling construction respectively.
But when being more than 1.5 meters of timber pile footpath to stake footpath, such as:
Stake footpath Φ 2.2m, designing pile length 98m pile foundation, its actual hole depth is 108m.
In punching to 90m position, dash forward and meet compared with hard formation, impact drill due in hole slip consistency it is big, chopping bit is under The resistance run into during pendant impact reduces kinetic energy, occurs inhaling and bores phenomenon, easily bit freezing.Time-parallel strata is to impact drill rebound effect Strengthen, impact drill drilling depth effect has been had a greatly reduced quality, and drilling depth is very slow.
Finally, the hole depth that impact drill is replaced with to this last 18m of clean-out machine solution is taken at scene.
But this method pore-forming, it is necessary in boring procedure backfill after continue to drill, add construction duration.Because The stake holes of 108 meters of depths, need to pour as early as possible after pore-forming.Otherwise, as the increase of engineering time, the risk of collapse hole can increase.Ten thousand One there is collapse hole, and intractability can be increasing, and working sources and fund input also can be more, cause unnecessary waste.
The content of the invention
It is an object of the invention to provide a kind of boring method of machine drilling stake, reduces the pore-forming resistance in work progress Power.
The present invention above-mentioned technical purpose technical scheme is that:
A kind of boring method of machine drilling stake,
The first step, the drill bit of at least three kinds sizes is chosen according to the stake holes diameter of practice of construction;
Second step, pile place is drilled successively according to the order of bit diameter from small to large, and drilling depth is every time The hole depth of actual design, until the diameter of pore-forming is identical with actual design stake holes diameter.
By using above-mentioned technical proposal, the depth for needing pore-forming is first drilled into less than the drill bit of drilling diameter with diameter dimension Degree.Smaller due to boring footpath, pore-forming resistance diminishes in boring procedure, runs into harder rock stratum and is more easy to punch, runs into sticky mud Caused resistance is small, is not susceptible to inhale and bores phenomenon.Then reaming, each reaming are carried out using the bigger drill bit of diameter again When be both less than the resistance of one-step pore-creating in face of resistance caused by drill bit.So drilling depth progress is accelerated, and in this method In without carrying out backfill processing to stake holes, the pore-forming duration is substantially reduced, so as to reduce the risk that pore-forming caves in.
Further set:When choosing bit diameter size, the minimum bit diameter of selection is no more than 1.5 meters.
By using above-mentioned technical proposal, according to practical construction experience, when stake holes diameter is less than 1.5 meters, it is not susceptible to The phenomenon that drill bit drops, so the bit diameter of drilling is no more than 1.5 meters for the first time.
Further set:It is no more than 0.5 meter per the adjacent bit diameter difference to drill twice.
Because follow-up drill process, constructed on the basis of previous step pore-forming by using above-mentioned technical proposal, And drill bit and contact area of ground are bigger, then pore-forming resistance is bigger.So in this programme between every adjacent drill bit to drill twice Difference is no more than 0.5 meter, and the pore-forming resistance in subsequent step is reduced, penetration rate during so as to accelerate drilling.
In summary, the invention has the advantages that:
1st, because in boring procedure, bit diameter is smaller, and resistance is smaller caused by pore-forming, more the geology easily against complexity Situation is drilled.And now the penetration rate of pore-forming is fast, it is more easy to be drilled into designed elevation.
2nd, in follow-up reaming, bit size becomes big, but the real contact area between ground diminishes, pore-forming resistance Power diminishes, and runs into harder rock stratum and is not susceptible to inhale brill phenomenon.So that drill bit is not easy to drop, without time-consuming salvaging, so as to shorten Duration, and reduce the risk that pore-forming caves in.
Brief description of the drawings
Fig. 1 is the drill bit FEM model for representing Φ 1.5m;
Fig. 2 is the force analysis of drill bit when the FEM model based on Fig. 1 carries out simulating actual probing.
Embodiment
The present invention is described in further detail below in conjunction with accompanying drawing.
Embodiment 1:
Stake footpath Φ 2.2m, designing pile length 98m pile foundation, its actual hole depth is 108m.
The first step, first it is drilled into design stake bottom absolute altitude with Φ 1.5m bradawl;
Second step, the middle drill bit that extraction drilling rod is replaced with Φ 1.8m are drilled into designed elevation;
3rd step, it is replaced with and is drilled into designed elevation with design stake footpath size identical Φ 2.2m big drill bit.
The calculating analysis of first step bit size:
Using GF-400 model clean-out machines, point three steps are excavated, the first stage excavates whether ability directly determines three-step approach It is feasible.Main-shaft torque 42000N.m, first step bit profile diameter 1.5m, therefore be converted into single-point horizontal loading and be: 42000/0.75/1000=56KN.Because geological condition is complicated at drill bit, 4 of simulating contact are also difficult to using theoretical model Blade thin portion stressing conditions, and it is also inaccurate.Therefore can be passed through by the way that drill hole geologic counter-force is put on into drill bit to simulate Bending, shearing, the ratio coefficient of axial action and ultimate load judge reasonability that the drill bit first step is excavated.
With reference to Fig. 1 and Fig. 2, in unit coordinate system z-axis direction, the section calculated using moment M y, cross-section data Czp, Czm Stress, output be absolute value in two values higher value.Maximum is 57.6MPa, less than allowable stress 145MPa, subitem Ratio safety coefficient:145/57.6=2.5.Therefore no matter material or safety coefficient disclosure satisfy that requirement to the drill bit.
Bit force situation analysis table
To sum up, the first step uses diameter 1.5m drill bits, is fully able to meet requirement, fact proved that the first step is excavated also very Smoothly.
Embodiment 2:
Stake footpath Φ 2.4m, designing pile length 104m pile foundation, its actual hole depth is 114m.
The first step, first it is drilled into design stake bottom absolute altitude with Φ 1.4m bradawl;
Second step, the middle drill bit that extraction drilling rod is replaced with Φ 1.8m are drilled into designed elevation;
3rd step, drilling rod takes out and is replaced with Φ 2.1m drill bit be drilled into designed elevation;
4th step, it is replaced with and is drilled into designed elevation with design stake footpath size identical Φ 2.4m big drill bit.
Embodiment 3:
Stake footpath Φ 2.0m, designing pile length 90m pile foundation, its actual hole depth is 100m.
The first step, first it is drilled into design stake bottom absolute altitude with Φ 1.3m bradawl;
Second step, the middle drill bit that extraction drilling rod is replaced with Φ 1.6m are drilled into designed elevation;
3rd step, it is replaced with and is drilled into designed elevation with design stake footpath size identical Φ 2.0m big drill bit.
The above embodiments are only explanation of the invention, and it is not limitation of the present invention, people in the art Member can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but as long as at this All protected in the right of invention by Patent Law.

Claims (3)

  1. A kind of 1. boring method of machine drilling stake, it is characterised in that:
    The first step, the drill bit of at least three kinds sizes is chosen according to the stake holes diameter of practice of construction;
    Second step, pile place is drilled successively according to the order of bit diameter from small to large, and drilling depth is every time The hole depth of actual design, until the diameter of pore-forming is identical with actual design stake holes diameter.
  2. 2. the boring method of machine drilling stake according to claim 1, it is characterised in that:Choosing bit diameter size When, the minimum bit diameter of selection is no more than 1.5 meters.
  3. 3. the boring method of machine drilling stake according to claim 2, it is characterised in that:Per the adjacent drill bit to drill twice Diameter difference is no more than 0.5 meter.
CN201710479041.7A 2017-06-22 2017-06-22 A kind of boring method of machine drilling stake Pending CN107339069A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710479041.7A CN107339069A (en) 2017-06-22 2017-06-22 A kind of boring method of machine drilling stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710479041.7A CN107339069A (en) 2017-06-22 2017-06-22 A kind of boring method of machine drilling stake

Publications (1)

Publication Number Publication Date
CN107339069A true CN107339069A (en) 2017-11-10

Family

ID=60221105

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710479041.7A Pending CN107339069A (en) 2017-06-22 2017-06-22 A kind of boring method of machine drilling stake

Country Status (1)

Country Link
CN (1) CN107339069A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5902939A (en) * 1996-06-04 1999-05-11 U.S. Army Corps Of Engineers As Represented By The Secretary Of The Army Penetrometer sampler system for subsurface spectral analysis of contaminated media
CN103195365A (en) * 2013-03-29 2013-07-10 徐州徐工基础工程机械有限公司 Rotary drilling rig hard rock stratum step drilling construction process
CN104047543A (en) * 2014-05-30 2014-09-17 中铁隧道集团有限公司 Construction method for forming hole by large-diameter bored pile in high-strength rock stratum
CN104074458A (en) * 2014-06-25 2014-10-01 中铁上海工程局集团有限公司 Drilled pile graded casing drilling perforating method
CN106168024A (en) * 2015-05-19 2016-11-30 五冶集团上海有限公司 A drilling construction method is dug in special formation rotation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5902939A (en) * 1996-06-04 1999-05-11 U.S. Army Corps Of Engineers As Represented By The Secretary Of The Army Penetrometer sampler system for subsurface spectral analysis of contaminated media
CN103195365A (en) * 2013-03-29 2013-07-10 徐州徐工基础工程机械有限公司 Rotary drilling rig hard rock stratum step drilling construction process
CN104047543A (en) * 2014-05-30 2014-09-17 中铁隧道集团有限公司 Construction method for forming hole by large-diameter bored pile in high-strength rock stratum
CN104074458A (en) * 2014-06-25 2014-10-01 中铁上海工程局集团有限公司 Drilled pile graded casing drilling perforating method
CN106168024A (en) * 2015-05-19 2016-11-30 五冶集团上海有限公司 A drilling construction method is dug in special formation rotation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杜永昌: "《铁路工程施工装备选型配套手册 (1)》", 28 February 2011, 中国铁道出版社 *

Similar Documents

Publication Publication Date Title
Li et al. Experimental investigation of the influence of confining stress on hard rock fragmentation using a conical pick
CN106529092B (en) Finite element calculation method for shearing deformation force of well drilling casing
Rashidi et al. Performance, simulation and field application modeling of rollercone bits
CN108729924A (en) A kind of urban hard rock tunnel mechanical excavation rapid constructing method
Shaterpour-Mamaghani et al. Some contributions on the estimation of performance and operational parameters of raise borers–A case study in Kure Copper Mine, Turkey
CN106372297A (en) Method for determining safe vertical distance between shield and karst cave in sand karst stratum
Su Performance evaluation of button bits in coal measure rocks by using multiple regression analyses
CN109681180A (en) Coal mine ground vertical well pressure break tight roof controls the strong mine of stope and presses effect pre-evaluation method
CN203584301U (en) Hole guide equipment
Abu Bakar et al. Penetration rate and specific energy prediction of rotary–percussive drills using drill cuttings and engineering properties of selected rock units
CN107339069A (en) A kind of boring method of machine drilling stake
Ramoni et al. TBM drives in squeezing ground–Shield-rock interaction
Paredes et al. Undercutless caving at Newcrest: towards the next generation of cave mining
JP6339425B2 (en) Drilling condition determination method, drilling length calculation method, and geological logging method
CN211819264U (en) Foundation pile drilling and digging sleeve for constructional engineering
CN106761725A (en) A kind of method that the tunnel reasonable hole sealing depth of concordant mash gas pumping drilling is determined based on coal powder quantity of bore
KR102073571B1 (en) Optimal design method of a hydraulic cylinder to support the repulsive force generated by horizontal strikings of the hydraulic breaker and, press-in shear test method for obtaining the coefficient of shear force degradation used in this design method
Gault Measurement of Drilling Properties
CN111396014A (en) Thin interbed reservoir reformation method, device and equipment
Akbarzadeh et al. A Numerical Study of Critical Parameters That Affect Stability of a Cavity Induced by Borehole Mining
CN116104474B (en) Roof cutting pressure relief method based on roof cutting drilling hole edge concentrated stress fracturing principle
CN107561161A (en) A kind of method for early warning of the disconnected release of the old bursting in colliery
Elmo et al. An FEM-DEM numerical approach to simulate secondary fragmentation
JP6724404B2 (en) Rock crack evaluation method, rock evaluation method, and rock crack evaluation apparatus
JP5720967B2 (en) Exploration method of the front ground

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171110