CN107338796A CN201710608468.2A CN201710608468A CN107338796A CN 107338796 A CN107338796 A CN 107338796A CN 201710608468 A CN201710608468 A CN 201710608468A CN 107338796 A CN107338796 A CN 107338796A
Authority
CN
China
Prior art keywords
steel sheet
sheet pile
pile supporting
hook
larsen
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710608468.2A
Other languages
Chinese (zh)
Inventor
翁恩豪
黄伟
钟宁
叶日辉
张婉
张政权
刘少华
张薇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Days And Architectural Design Co Ltd
Original Assignee
Zhejiang Days And Architectural Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Days And Architectural Design Co Ltd filed Critical Zhejiang Days And Architectural Design Co Ltd
Priority to CN201710608468.2A priority Critical patent/CN107338796A/en
Publication of CN107338796A publication Critical patent/CN107338796A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • E02D5/08Locking forms; Edge joints; Pile crossings; Branch pieces

Abstract

The invention discloses the steel sheet pile supporting construction and its construction method of a kind of lateral reinforcement strength of band, including for the steel sheet pile supporting outside foundation ditch, multiple auxiliary shoring components are provided with the outside of the steel sheet pile supporting, each described equal one end of auxiliary shoring component is connected with steel sheet pile supporting, and auxiliary shoring component stretches out from steel sheet pile supporting vertical with steel sheet pile supporting one end being connected;By using above-mentioned technical proposal, auxiliary shoring component is set up on the basis of original steel sheet pile supporting, the auxiliary shoring component stretches out backwards to foundation ditch to be connected with the soil layer of foundation ditch outer ring, steel sheet pile supporting and auxiliary shoring component form combination of the soil layer to steel sheet pile supporting pressure outside a resistance foundation ditch, effectively lift foundation ditch integer support intensity.

Description

Steel sheet pile supporting construction and its construction method with lateral reinforcement strength
Technical field
The present invention relates to foundation ditch protection, and in particular to steel sheet pile supporting construction and its construction method with lateral reinforcement strength.
Background technology
Pattern foundation pit supporting structure, it is to ensure the safety of Underground Construction and foundation ditch surrounding enviroment, to foundation pit side-wall and peripheral ring Supporting and retaining system, reinforcing and the safeguard measure that border uses.
Existing traditional foundation pit supporting construction typically can refer to publication No. CN103114599A patent, foundation ditch upper surface Support system is provided with, support system uses steel sheet pile supporting, and support system surrounding is provided with water-stop curtain system, water-stop curtain System is formed using cement injection pile overlap joint, and stull is connected between steel sheet pile.
The foundation pit supporting construction, which generally requires, is internally put into inner support to lift integer support intensity.
The present invention proposes a kind of new scheme to realize.
The content of the invention
In view of the deficienciess of the prior art, it is an object of the invention to provide a kind of steel sheet pile branch of the lateral reinforcement strength of band Protection structure, lift foundation ditch integer support intensity.
To achieve the above object, the invention provides following technical scheme:A kind of steel sheet pile supporting of the lateral reinforcement strength of band Structure, including the steel sheet pile supporting outside foundation ditch, the steel sheet pile supporting outside are provided with multiple auxiliary shoring groups Part, each described equal one end of auxiliary shoring component are connected with steel sheet pile supporting, and auxiliary shoring component connects from steel sheet pile supporting The vertical steel sheet pile supporting in one end connect stretches out.
By using above-mentioned technical proposal, auxiliary shoring component is set up on the basis of original steel sheet pile supporting, the auxiliary Branch protecting assembly stretches out backwards to foundation ditch to be connected with the soil layer of foundation ditch outer ring, and steel sheet pile supporting and auxiliary shoring component form one and supported Combination of the soil layer to steel sheet pile supporting pressure outside anti-foundation ditch, effectively lifts foundation ditch integer support intensity.
It is further arranged to:The steel sheet pile supporting includes multiple first Larsen steel sheet piles, the first Larsen steel sheet pile Hook part one including main part one and positioned at the both ends of main part one, the mouth of hook of the hook part one is towards main part One center line, the first adjacent Larsen steel sheet pile are connected by the hook of hook part one.
It is further arranged to:A connecting hook one is fixed in the side of the main part one;The auxiliary shoring component includes Multiple first Larsen steel sheet piles, the first Larsen steel sheet pile of auxiliary shoring component pass through in hook part one and steel sheet pile supporting first The hook of connecting hook one of Larsen steel plate connects, and the first adjacent Larsen steel sheet pile is connected by the hook of hook part one.
By using above-mentioned technical proposal, the first Larsen steel sheet pile of auxiliary shoring component passes through hook part one and steel sheet pile The hook of connecting hook one of the first Larsen steel plate connects in supporting, fast and easy assembling, without welding.
The further setting of the present invention is:The steel sheet pile supporting includes multiple second Larsen steel sheet piles, the second steel sheet pile Hook part two including main part two and positioned at the both ends of main part two, the mouth of hook of hook part two is at least partly backwards to main body The hook part two of the center line of part two, wherein one end is fixedly connected with a rotating shaft, the hook part two of the other end opens up one and matched somebody with somebody with rotating shaft The axis hole of conjunction, the axis hole side wall set the opening radian of an opening and axis hole to be less than π, and the second adjacent Larsen steel sheet pile passes through Rotating shaft connects with shaft hole matching.
By using above-mentioned technical proposal, it can so facilitate and realize the circular, splicing of profile iron sheet pile supporting, and due to Axis hole and the fit precision of rotating shaft are higher, conveniently realize the positioning of the second Larsen steel sheet pile.
The further setting of the present invention is:A connecting hook two is fixed in the side of the main part two;The auxiliary shoring Component includes multiple second Larsen steel sheet piles, and the second Larsen steel sheet pile of auxiliary shoring component passes through hook part two and connecting hook two Hook connects, and the second adjacent Larsen steel sheet pile is connected by the hook of hook part two.
By using above-mentioned technical proposal, the second Larsen steel sheet pile of auxiliary shoring component passes through hook part two and connecting hook Two hooks connect, fast and easy assembling, without welding.
Second object of the present invention is to provide a kind of construction method of steel sheet pile supporting construction.
A kind of construction method of steel sheet pile supporting construction, comprises the following steps:
1) height of steel sheet pile supporting is determined according to the depth for treating soil layer in excavation pit, the minimum constructive height of steel sheet pile supporting is Its lower end is inserted into soil layer 1~1.5m the distance between to ground;Determined simultaneously according to the sectional dimension of construction frame structure main body Go out the size of steel sheet pile supporting, the size of steel sheet pile supporting be construct frame structure main body every side outer to external expansion 1~ 1.5m;
2) internal layer leading truck and outer layer leading truck, internal layer leading truck and outer layer are installed according to the steel sheet pile supporting size of above-mentioned determination Leading truck is at least combined by multiple guide piles, and internal layer leading truck is located at steel sheet pile supporting inner ring, and outer layer leading truck is located at Steel sheet pile supporting outer ring;
3) a first Larsen steel sheet pile of circle is plugged between internal layer leading truck and outer layer leading truck and forms steel sheet pile supporting;
4)Multigroup locating rack is installed outside steel sheet pile supporting, every group of locating rack is made up of two row's guide piles, two row's guide piles it Between plug one ranked first Larsen steel sheet pile form auxiliary shoring component, the first Larsen steel sheet pile and steel of auxiliary shoring component one end The hook of connecting hook one of the first Larsen steel plate connects in sheet pile supporting, and the vertical steel sheet pile supporting of auxiliary shoring component;
5) above-mentioned leading truck and locating rack are all removed;
Third object of the present invention is to provide a kind of construction method of steel sheet pile supporting construction.
A kind of construction method of steel sheet pile supporting construction, comprises the following steps:
1) height of steel sheet pile supporting is determined according to the depth for treating soil layer in excavation pit, the minimum constructive height of steel sheet pile supporting is Its lower end is inserted into soil layer 0.5~1.5m the distance between to ground;It is simultaneously true according to the sectional dimension of construction frame structure main body Make the size of steel sheet pile supporting, the size of steel sheet pile supporting be construct frame structure main body every side outer to external expansion 1~ 1.5m;
2) one group of leading truck is installed according to the steel sheet pile supporting of above-mentioned determination, this group of leading truck is simply possible to use in one piece of second Larsen steel The installation of sheet pile;
3) first piece of the second Larsen steel sheet pile is squeezed into soil layer to desired depth in leading truck, squeeze into successively afterwards remaining second Larsen steel sheet pile is extremely identical with the depth of first block of the second Larsen steel plate and is enclosed, afterwards first by first piece of the second Larsen steel sheet pile Squeeze into projected depth, then remaining second Larsen steel sheet pile is squeezed into projected depth form steel sheet pile supporting successively, make a reservation for Depth is away from soil layer surface 2-3m;
4)Multiple auxiliary shoring components are installed outside steel sheet pile supporting:It is auxiliary that the second Larsen of polylith steel sheet pile is squeezed into the composition that is connected successively Help branch protecting assembly, the connecting hook of the second Larsen steel sheet pile and the second Larsen steel plate in steel sheet pile supporting of auxiliary shoring component one end Two hooks connect, and the vertical steel sheet pile supporting of auxiliary shoring component;
5) above-mentioned leading truck is removed.
The present invention has advantages below:The steel sheet pile supporting construction of the present invention effectively lifts foundation ditch integer support intensity;Together When can conveniently realize the circular, splicing of profile iron sheet pile supporting.
Brief description of the drawings
Fig. 1 is the first Larsen steel sheet pile A structural representation;
Fig. 2 is the first Larsen steel sheet pile B structural representation;
Fig. 3 is the second Larsen steel sheet pile A structural representation;
Fig. 4 is the second Larsen steel sheet pile B structural representation;
Fig. 5 is the structural representation of embodiment 1;
Fig. 6 is Fig. 5 A portions enlarged drawing;
Fig. 7 is the structural representation of embodiment 2.
Reference:1st, the first Larsen steel sheet pile A;11st, main part one;12nd, hook part one;2nd, the first Larsen steel sheet pile B;21st, connecting hook one;3rd, the second Larsen steel sheet pile A;31st, main part two;32nd, hook part two;33rd, rotating shaft;34th, axis hole;35、 Opening;4th, the second Larsen steel sheet pile B;41st, connecting hook two;5th, foundation ditch;6th, steel sheet pile supporting;7th, auxiliary shoring component.
Embodiment
The present invention will be further described referring to the drawings.
All parts are introduced first choice:
Such as Fig. 1:First Larsen steel sheet pile A1:By the main part 1 to take the shape of the letter U and positioned at the curved of the both ends of main part 1 Hook portion 1, the center line of the mouth of hook of hook part 1 towards main part 1.
Such as Fig. 2:First Larsen steel sheet pile B2:On the basis of the first Larsen steel sheet pile A1, its main part 1 deviates from U A connecting hook 1 is fixed in the side of shape mouth, and the vertical body part 1 of connecting hook 1 stretches out.
Such as Fig. 3:Second Larsen steel sheet pile A3:By the main part 2 31 to take the shape of the letter U and positioned at the both ends of main part 2 31 Hook part 2 32, the mouth of hook of hook part 2 32 is at least partly backwards to the center line of main part 2 31;The wherein hook part of one end 2 32 are fixedly connected with a rotating shaft 33, the hook part 2 32 of the other end opens up an axis hole 34 coordinated with rotating shaft 33, the axis hole 34 Side wall sets π/3 of the radian measure alpha of opening 35=2 of an opening 35 and axis hole 34.
Such as Fig. 4:Second Larsen steel sheet pile B4:On the basis of the first Larsen steel sheet pile A1, its main part 2 31 deviates from U A connecting hook 2 41 is fixed in the side of shape mouth, and the vertical body part 2 31 of connecting hook 2 41 stretches out.
First Larsen steel sheet pile A1 and the first Larsen steel sheet pile B2 is the first Larsen steel sheet pile;Second Larsen steel sheet pile A3 It is the second Larsen steel sheet pile with the second Larsen steel sheet pile B4, is intended merely to facilitate differentiation to do above-mentioned name in the present embodiment.
Embodiment 1:A kind of steel sheet pile supporting construction of the lateral reinforcement strength of band, such as Fig. 5, including steel sheet pile supporting 6 and setting Multiple auxiliary shoring components 7 in the outside of steel sheet pile supporting 6.Such as Fig. 6, its Steel Sheet Pile supporting 6 is by the first Larsen steel sheet pile A1 It is formed by connecting with the first Larsen steel sheet pile B2, specific first Larsen steel sheet pile A1 and the first Larsen steel sheet pile B2 quantity selection root Factually border is it needs to be determined that and arrange.Auxiliary shoring component 7 is formed by connecting by multiple first Larsen steel sheet pile A1, auxiliary shoring component First Larsen steel sheet pile B2 connecting hook 1 connects in the first Larsen steel sheet pile A1 of 7 one end and steel sheet pile supporting 6.
The construction method of embodiment 1 is as follows:A kind of construction method of steel sheet pile supporting construction:Comprise the following steps:
1) height of steel sheet pile supporting 6, the minimum height of steel sheet pile supporting 6 are determined according to the depth for treating soil layer in excavation pit 5 Spend and be inserted into soil layer 1~1.5m the distance between to ground for its lower end;Simultaneously according to the sectional dimension of construction frame structure main body Determine the size of steel sheet pile supporting 6, the size of steel sheet pile supporting 6 be construct frame structure main body every side outer to external expansion 1~1.5m;
2) internal layer leading truck and outer layer leading truck are installed according to the size of steel sheet pile supporting 6 of above-mentioned determination, internal layer leading truck and outer Layer leading truck is at least combined by multiple guide piles, and guide pile is steel-pipe pile, can choose whether positioning as needed Stake is outer to install crossbeam to lift the resistance to overturning of internal layer leading truck and outer layer leading truck, and internal layer leading truck is located at steel sheet pile supporting 6 inner rings, outer layer leading truck are located at the outer ring of steel sheet pile supporting 6;
3) plugged between internal layer leading truck and outer layer leading truck between the first Larsen steel sheet pile of circle A1, the first Larsen steel sheet pile B2 Steel sheet pile supporting 6 is formed every arrangement;
4)Multigroup locating rack is installed outside steel sheet pile supporting 6, every group of locating rack is made up of two row's guide piles, two row's guide piles it Between plug one and ranked first Larsen steel sheet pile A1 and form auxiliary shoring component 7, the first Larsen steel sheet pile of the one end of auxiliary shoring component 7 A1 and the first Larsen steel sheet pile B2 in steel sheet pile supporting 6 hook of connecting hook 1 connects, and the vertical steel sheet pile branch of auxiliary shoring component 7 Shield 6;
5) above-mentioned leading truck and locating rack are all removed.
Embodiment 2:A kind of steel sheet pile supporting construction of the lateral reinforcement strength of band, such as Fig. 7, including steel sheet pile supporting 6 and setting Multiple auxiliary shoring components 7 in the outside of steel sheet pile supporting 6.Its Steel Sheet Pile supporting 6 is by the second Larsen steel sheet pile A3 and second Larsen steel sheet pile B4 is formed by connecting, and specific second Larsen steel sheet pile A3 and the second Larsen steel sheet pile B4 quantity are selected according to reality It needs to be determined that and arrange.Auxiliary shoring component 7 is formed by connecting by multiple second Larsen steel sheet pile A3, the one end of auxiliary shoring component 7 The second Larsen steel sheet pile A3 and steel sheet pile supporting 6 in the second Larsen steel sheet pile B4 connecting hook 2 41 connect.
The construction method of embodiment 2 is as follows:A kind of construction method of steel sheet pile supporting construction:Comprise the following steps:
1) height of steel sheet pile supporting 6, the minimum height of steel sheet pile supporting 6 are determined according to the depth for treating soil layer in excavation pit 5 Spend and be inserted into soil layer 0.5~1.5m the distance between to ground for its lower end;Simultaneously according to the section chi of construction frame structure main body The very little size for determining steel sheet pile supporting 6, the size of steel sheet pile supporting 6 be construct frame structure main body every side outer to extending out Open up 1~1.5m;
2) one group of leading truck is installed according to the steel sheet pile supporting 6 of above-mentioned determination, this group of leading truck is simply possible to use in one piece of second Larsen Steel sheet pile A3 installation;Leading truck is made up of the multiple steel-pipe piles for squeezing into soil layer.
3) first piece of the second Larsen steel sheet pile A3 is squeezed into soil layer to desired depth in leading truck, squeezes into remaining successively afterwards The second Larsen steel sheet pile A3, the second Larsen steel sheet pile B4 to identical and enclosed with first piece of the second Larsen steel plate A3 depth Close, afterwards first squeeze into first piece of the second Larsen steel sheet pile A3 to projected depth in leading truck, then drawn successively by remaining second Gloomy steel sheet pile A3, the second Larsen steel sheet pile B4 are squeezed into projected depth and are formed steel sheet pile supporting 6, and desired depth is away from soil layer surface 2-3m;
4)Multiple auxiliary shoring components 7 are installed outside steel sheet pile supporting 6:Polylith the second Larsen steel sheet pile A3 is squeezed into connected structure successively Into auxiliary shoring component 7, the second Larsen steel sheet pile A3 and the second Larsen steel in steel sheet pile supporting 6 of the one end of auxiliary shoring component 7 The plate B4 hook of connecting hook 2 41 connects, and the vertical steel sheet pile supporting 6 of auxiliary shoring component 7;
5) above-mentioned leading truck is removed.
Certain engineering 1:Carried out in the soil layer that geology bearing capacity is 500kPa.The size of foundation ditch 5 is 12m × 15m, foundation ditch 5 Digging depth is 6m.It is that the method for embodiment 1 is constructed to employ, and is comprised the following steps that:
1) height of Larsen steel sheet pile is determined according to the depth of soil layer in the foundation ditch 5, the first Larsen steel sheet pile A1 and first is drawn Gloomy steel sheet pile B2 height is 8m;The size of steel sheet pile supporting 6 is determined according to the sectional dimension of construction frame structure main body simultaneously Size, the size of steel sheet pile supporting 6 is 13m × 16m;
2) internal layer leading truck is installed according to the size of steel sheet pile supporting 6 of above-mentioned determination and outer layer leading truck, internal layer leading truck is located at The inner ring of steel sheet pile supporting 6, outer layer leading truck are located at the outer ring of steel sheet pile supporting 6;Internal layer leading truck and outer layer leading truck are by more The guide pile that standoff distance is arranged side by side is formed with the crossbeam for being horizontally arranged at the more side external surface upper ends of guide pile one;Inner ring is led It is 1.5m to frame and the distance on construction frame structure body edge edge, wherein guide pile uses steel-pipe pile, and crossbeam uses I-steel;
3) inserting piling one is enclosed by the first Larsen steel sheet pile A1 and the first Larsen steel sheet pile in the soil layer between above-mentioned two circle leading trucks The steel sheet pile supporting 6 that B2 connects and formed;Vibration hammer inserting piling is coordinated using crawler crane;
4)Multigroup locating rack is installed outside steel sheet pile supporting 6, every group of locating rack is made up of two row's guide piles, and guide pile is steel pipe Stake, one is plugged between two row's guide piles and ranked first Larsen steel sheet pile A1 composition auxiliary shorings component 7, auxiliary shoring component 7 one The first Larsen steel sheet pile A1 at end and the first Larsen steel sheet pile B2 in steel sheet pile supporting 6 hook of connecting hook 1 connects, and aids in branch The vertical steel sheet pile supporting 6 of protecting assembly 7;
5) above-mentioned leading truck and locating rack are all removed;
6) soil layer inside steel sheet pile supporting 6 is successively excavated;Said process is repeated until forming foundation ditch 5;
7) one layer of colour bar cloth or geotextiles are laid at the adjacent position in the lower end of steel sheet pile supporting 6 and the bottom surface of foundation ditch 5, then in base Cheat the thick C30 concrete cushions of 5 bottom surface upper, one layer of 30cm;The effect of colour bar cloth or geotextiles be by steel sheet pile supporting 6 with Concrete isolation is sealed, so that future can successfully pull out steel sheet pile supporting 6;Promoted, but should ensure that from one side to another side during back cover Continuously, uninterruptedly, do not stay seam, and disposably complete;
8) template is built on above-mentioned concrete cushion, construction is then carried out and completes construction frame structure main body, afterwards form removal;
9) space constructed in foundation ditch 5 between frame structure main body and steel sheet pile supporting 6 is successively backfilled using graded broken stone or concrete;
The engineering is 26 days in the practice of construction time.Construction period cofferdam (structure of steel sheet pile supporting 6) is firm, through being built around observation The divine force that created the universe and it is both wired do not occur substantially settling, favorably accomplished construction task.
Certain engineering 2:Carried out in the soil layer that geology bearing capacity is 500kPa.The size of foundation ditch 5 is diameter 16m, the digging of foundation ditch 5 Depth is 5.5m.It is that the method for embodiment 2 is constructed to employ, and is comprised the following steps that:
1) height of Larsen steel sheet pile is determined according to the depth of soil layer in the foundation ditch 5, the second Larsen steel sheet pile A3 and second is drawn Gloomy steel sheet pile B4 height is 7m;Determine that the size of steel sheet pile supporting 6 is big according to the sectional dimension of construction frame structure main body simultaneously It is small, the diameter 18m of steel sheet pile supporting 6;
2) one group of leading truck is installed according to the steel sheet pile supporting 6 of above-mentioned determination, this group of leading truck is simply possible to use in one piece of second Larsen Steel sheet pile A3 installation;The guide pile and be horizontally arranged at more guide piles one that leading truck is arranged side by side by more standoff distances The crossbeam of side external surface upper end is formed;Inner ring leading truck and the distance on construction frame structure body edge edge are 1.5m, and wherein guide pile is adopted With steel-pipe pile, crossbeam uses I-steel;
3) first piece of the second Larsen steel sheet pile A3 is squeezed into soil layer to desired depth in leading truck, squeeze into successively afterwards remaining Two Larsen steel sheet pile A3 and the second Larsen steel sheet pile B4 are extremely identical with first piece of the second Larsen steel plate A3 depth and enclosed, it First first piece of the second Larsen steel sheet pile A3 is squeezed into projected depth afterwards, then successively by remaining second Larsen steel sheet pile A3 and second Larsen steel sheet pile B4 is squeezed into projected depth and is formed steel sheet pile supporting 6, and desired depth is away from soil layer surface 2-3m;Using crawler crane Coordinate vibration hammer inserting piling;
4)Multigroup locating rack is installed outside steel sheet pile supporting 6, every group of locating rack is made up of two row's guide piles, and guide pile is steel pipe Stake, one is plugged between two row's guide piles and ranked second Larsen steel sheet pile A3 composition auxiliary shorings component 7, auxiliary shoring component 7 one The second Larsen steel sheet pile A3 at end and the second Larsen steel plate B4 in steel sheet pile supporting 6 hook of connecting hook 2 41 connects, and auxiliary shoring The vertical steel sheet pile supporting 6 of component 7;
5) above-mentioned leading truck is all removed;
6) soil layer inside steel sheet pile supporting 6 is successively excavated;Said process is repeated until forming foundation ditch 5;
7) one layer of colour bar cloth or geotextiles are laid at the adjacent position in the lower end of steel sheet pile supporting 6 and the bottom surface of foundation ditch 5, then in base Cheat the thick C30 concrete cushions of 5 bottom surface upper, one layer of 30cm;The effect of colour bar cloth or geotextiles be by steel sheet pile supporting 6 with Concrete isolation is sealed, so that future can successfully pull out steel sheet pile supporting 6;Promoted, but should ensure that from one side to another side during back cover Continuously, uninterruptedly, do not stay seam, and disposably complete;
8) template is built on above-mentioned concrete cushion, construction is then carried out and completes construction frame structure main body, afterwards form removal;
9) space constructed in foundation ditch 5 between frame structure main body and steel sheet pile supporting 6 is successively backfilled using graded broken stone or concrete;
The engineering is 34 days in the practice of construction time.Construction period cofferdam (structure of steel sheet pile supporting 6) is firm, through being built around observation The divine force that created the universe and it is both wired do not occur substantially settling, favorably accomplished construction task.
Described above is only the preferred embodiment of the present invention, and protection scope of the present invention is not limited merely to above-mentioned implementation Example, all technical schemes belonged under thinking of the present invention belong to protection scope of the present invention.It should be pointed out that for the art Those of ordinary skill for, some improvements and modifications without departing from the principles of the present invention, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (7)

1. a kind of steel sheet pile supporting construction of the lateral reinforcement strength of band, including for the steel sheet pile supporting installed in foundation ditch (5) outside (6), it is characterized in that:Multiple auxiliary shoring components (7) are provided with the outside of the steel sheet pile supporting (6), each auxiliary shoring Component (7) one end is connected with steel sheet pile supporting (6), and one end that auxiliary shoring component (7) is connected with steel sheet pile supporting (6) certainly Vertical steel sheet pile supporting (6) stretches out.
2. the steel sheet pile supporting construction of the lateral reinforcement strength of band according to claim 1, it is characterized in that:The steel sheet pile supporting (6) multiple first Larsen steel sheet piles are included, the first Larsen steel sheet pile includes main part one (11) and positioned at main part The hook part one (12) at point (11) both ends, the mouth of hook of the hook part one (12) is towards the center line of main part one (11), phase The first adjacent Larsen steel sheet pile is connected by hook part one (12) hook.
3. the steel sheet pile supporting construction of the lateral reinforcement strength of band according to claim 2, it is characterized in that:The main part one (11) connecting hook one (21) is fixed in side;The auxiliary shoring component (7) includes multiple first Larsen steel sheet piles, auxiliary branch The connection that first Larsen steel sheet pile of protecting assembly (7) passes through the first Larsen steel plate in hook part one (12) and steel sheet pile supporting (6) Hook one (21) hook connects, and the first adjacent Larsen steel sheet pile is connected by hook part one (12) hook.
4. the steel sheet pile supporting construction of the lateral reinforcement strength of band according to claim 1, it is characterized in that:The steel sheet pile supporting (6) multiple second Larsen steel sheet piles are included, the second steel sheet pile includes main part two (31) and positioned at main part two (31) The hook part two (32) at both ends, the mouth of hook of hook part two (32) is at least partly backwards to the center line of main part two (31), wherein one The hook part two (32) at end is fixedly connected with a rotating shaft (33), the hook part two (32) of the other end opens up one and rotating shaft (33) cooperation Axis hole (34), axis hole (34) side wall set opening (35) radian of an opening (35) and axis hole (34) to be less than π, and adjacent the Two Larsen steel sheet piles are connected by rotating shaft (33) and axis hole (34).
5. the steel sheet pile supporting construction of the lateral reinforcement strength of band according to claim 4, it is characterized in that:The main part two (31) connecting hook two (41) is fixed in side;The auxiliary shoring component (7) includes multiple second Larsen steel sheet piles, auxiliary branch The connection that second Larsen steel sheet pile of protecting assembly (7) passes through the second Larsen steel plate in hook part two (32) and steel sheet pile supporting (6) Hook two (41) hook connects, and the second adjacent Larsen steel sheet pile is connected by hook part two (32) hook.
6. a kind of construction method of steel sheet pile supporting construction as claimed in claim 3, it is characterized in that, comprise the following steps:
1) height of steel sheet pile supporting (6) is determined according to the depth for treating soil layer in excavation pit (5), steel sheet pile supporting (6) Minimum constructive height is that its lower end is inserted into soil layer 1~1.5m the distance between to ground;Cutting according to construction frame structure main body simultaneously Face size determines the size of steel sheet pile supporting (6), and the size of steel sheet pile supporting (6) is outside every side of construction frame structure main body Along to 1~1.5m of external expansion;
2) internal layer leading truck and outer layer leading truck are installed according to steel sheet pile supporting (6) size of above-mentioned determination, internal layer leading truck and Outer layer leading truck is at least combined by multiple guide piles, and internal layer leading truck is located at steel sheet pile supporting (6) inner ring, and outer layer is oriented to Frame is located at steel sheet pile supporting (6) outer ring;
3) a first Larsen steel sheet pile of circle is plugged between internal layer leading truck and outer layer leading truck and forms steel sheet pile supporting (6);
4)Multigroup locating rack is installed outside in steel sheet pile supporting (6), every group of locating rack is made up of two row's guide piles, in two row's guide piles Between plug one ranked first Larsen steel sheet pile form auxiliary shoring component (7), the first Larsen steel of auxiliary shoring component (7) one end Connecting hook one (21) hook of sheet pile and the first Larsen steel plate in steel sheet pile supporting (6) connects, and the vertical steel plate of auxiliary shoring component (7) Stake supporting (6);
5) above-mentioned leading truck and locating rack are all removed.
7. a kind of construction method of steel sheet pile supporting construction as claimed in claim 5, it is characterized in that, comprise the following steps:
1) height of steel sheet pile supporting (6) is determined according to the depth for treating soil layer in excavation pit (5), steel sheet pile supporting (6) Minimum constructive height is that its lower end is inserted into soil layer 0.5~1.5m the distance between to ground;Simultaneously according to construction frame structure main body Sectional dimension determines the size of steel sheet pile supporting (6), and the size of steel sheet pile supporting (6) is every side of construction frame structure main body Outer is to 1~1.5m of external expansion;
2) one group of leading truck is installed according to the steel sheet pile supporting (6) of above-mentioned determination, this group of leading truck is simply possible to use in one piece of second drawing The installation of gloomy steel sheet pile;
3) first piece of the second Larsen steel sheet pile is squeezed into soil layer to desired depth in leading truck, squeeze into successively afterwards remaining second Larsen steel sheet pile is extremely identical with the depth of first block of the second Larsen steel plate and is enclosed, afterwards first by first piece of the second Larsen steel sheet pile Squeeze into projected depth, then remaining second Larsen steel sheet pile is squeezed into projected depth form steel sheet pile supporting (6) successively, in advance Depthkeeping degree is away from soil layer surface 2-3m;
4)Multiple auxiliary shoring components (7) are installed in steel sheet pile supporting (6) outside:Polylith the second Larsen steel sheet pile is squeezed into successively connected Form auxiliary shoring component (7), the second Larsen steel sheet pile of auxiliary shoring component (7) one end and in steel sheet pile supporting (6) second Connecting hook two (41) hook of Larsen steel plate connects, and the vertical steel sheet pile supporting (6) of auxiliary shoring component (7);
5) above-mentioned leading truck is removed.
CN201710608468.2A 2017-07-24 2017-07-24 Steel sheet pile supporting construction and its construction method with lateral reinforcement strength Pending CN107338796A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710608468.2A CN107338796A (en) 2017-07-24 2017-07-24 Steel sheet pile supporting construction and its construction method with lateral reinforcement strength

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710608468.2A CN107338796A (en) 2017-07-24 2017-07-24 Steel sheet pile supporting construction and its construction method with lateral reinforcement strength

Publications (1)

Publication Number Publication Date
CN107338796A true CN107338796A (en) 2017-11-10

Family

ID=60217197

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710608468.2A Pending CN107338796A (en) 2017-07-24 2017-07-24 Steel sheet pile supporting construction and its construction method with lateral reinforcement strength

Country Status (1)

Country Link
CN (1) CN107338796A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102253815B1 (en) * 2020-12-02 2021-05-20 건창산업(주) 3-way thumb pile reinforcement type self-supporting earthen guard
KR102261191B1 (en) * 2020-12-03 2021-06-03 김규학 Earth retaining wall

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5333971A (en) * 1992-11-03 1994-08-02 Lewis John A Interlocking bulkhead
JP2010126991A (en) * 2008-11-27 2010-06-10 Hirose & Co Ltd Earth retaining wall and method of reinforcing the same
CN104196034A (en) * 2014-09-18 2014-12-10 中建交通建设集团有限公司 Foundation pit construction method employing steel sheet piles as support cofferdam

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5333971A (en) * 1992-11-03 1994-08-02 Lewis John A Interlocking bulkhead
JP2010126991A (en) * 2008-11-27 2010-06-10 Hirose & Co Ltd Earth retaining wall and method of reinforcing the same
CN104196034A (en) * 2014-09-18 2014-12-10 中建交通建设集团有限公司 Foundation pit construction method employing steel sheet piles as support cofferdam

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102253815B1 (en) * 2020-12-02 2021-05-20 건창산업(주) 3-way thumb pile reinforcement type self-supporting earthen guard
KR102261191B1 (en) * 2020-12-03 2021-06-03 김규학 Earth retaining wall

Similar Documents

Publication Publication Date Title
CN106522242B (en) For soft stratum close to underground structure foundation pit supporting system construction method
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN107268636A (en) The diaphragm wall foundation ditch that the steel cylinder or steel sheet pile of a kind of seal groove and occlusion structure are constituted is with going along with sb. to guard him and construction method
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN106522241A (en) Deep foundation pit supporting method of ultrahigh floor height type basement structure
CN102094425A (en) Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam
CN105756091B (en) A kind of Metro station excavation construction method of control adjacent building composition deformation
CN105220703B (en) Enclosing type deepwater platform construction method based on condition of sand backfilling balance method
CN209741877U (en) Cofferdam structure with concrete ring beam water stop additionally arranged at root of steel sheet pile
CN105625437A (en) Earth excavation method under annular support of deep foundation pit
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN110374112A (en) Weak soil site system of deep foundation pit support and its construction method
CN105113514B (en) Foundation pit enclosure system with underground continuous wall as vertical cantilever fulcrum and construction method
CN206554099U (en) A kind of bottomless single wall steel boxed cofferdam of piecemeal pin-connected panel
CN107338796A (en) Steel sheet pile supporting construction and its construction method with lateral reinforcement strength
CN106759378B (en) Level is to the construction method for drawing anchor cable
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
CN108978680A (en) A kind of muck soil elevator foundation pit supporting construction device and method
CN106498957B (en) Steel sheet pile cofferdam construction platform and integral construction method
CN112523236A (en) Combined cofferdam structure and construction method thereof
CN205276254U (en) Drainage is and add prefabricated skirt tubular pile of pile body bearing diagonal
CN105178356B (en) Setting-up construction method for vertical joint bars of columns in reverse building method
CN107740419A (en) Foundation pit supporting method and raked pile
CN111779022A (en) Novel structure of underground comprehensive pipe gallery in anti-settling and anti-inclining soft soil foundation and construction method thereof
CN208088281U (en) One kind being used for deep sandy soil deep pit digging structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171110

RJ01 Rejection of invention patent application after publication