CN107326887B - Offshore wind farm elder generation pile leader frame construction method of installation - Google Patents

Offshore wind farm elder generation pile leader frame construction method of installation Download PDF

Info

Publication number
CN107326887B
CN107326887B CN201710481362.0A CN201710481362A CN107326887B CN 107326887 B CN107326887 B CN 107326887B CN 201710481362 A CN201710481362 A CN 201710481362A CN 107326887 B CN107326887 B CN 107326887B
Authority
CN
China
Prior art keywords
jacket
supporting leg
wind power
piling bar
power foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710481362.0A
Other languages
Chinese (zh)
Other versions
CN107326887A (en
Inventor
黄锡柱
陈龙剑
张青海
朱代炼
李陕锋
王书稳
叶亮
朱晓超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG HUAERCHEN OFFSHORE WIND POWER ENGINEERING Co Ltd
Original Assignee
GUANGDONG HUAERCHEN OFFSHORE WIND POWER ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG HUAERCHEN OFFSHORE WIND POWER ENGINEERING Co Ltd filed Critical GUANGDONG HUAERCHEN OFFSHORE WIND POWER ENGINEERING Co Ltd
Priority to CN201710481362.0A priority Critical patent/CN107326887B/en
Publication of CN107326887A publication Critical patent/CN107326887A/en
Application granted granted Critical
Publication of CN107326887B publication Critical patent/CN107326887B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Wind Motors (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a kind of offshore wind farm elder generation pile leader frame construction methods of installation, confirmation that this method enters stake by preparation of construction, jacket lifting, jacket contraposition, jacket, measurement correct, is installed, diver takes pictures, which records, removes hook warns, site clearing, jacket safety and precise is installed on by above-mentioned main seven steps and is fixed on four on sea bed wind power foundation piling bars in advance, it can effectively solve the problem that the technical problem that first pile leader frame is installed under water, promotion China, sea area, the southeast and deep-sea sea area wind power plant issued with great impetus.

Description

Offshore wind farm elder generation pile leader frame construction method of installation
Technical field
The present invention relates to leading for a kind of installation method of offshore wind farm construction of pile groups, especially a kind of first pile leader frame basis Pipe support construction method of installation.
Background technique
Jacket foundation pattern is one of broad form of offshore wind power foundation, jacket basis have overall stiffness it is big, by Effect to the environmental loads such as wave and water flow is smaller, be widely used in China's Southeast China Sea area with sea turn establish by cable Hair, and can be applied to large fan and deep-sea sea area, conform to the trend that deep-sea is gradually moved towards in offshore wind farm development.
Currently, domestic offshore wind power development is still within the starting stage, offshore wind farm construction technology is still immature, has opened The marine wind electric field of hair mainly based on single-pile foundation and high-rise pile cap, has certain limitation, jacket basis sea turn Electric construction technology is still in the exploration starting stage.
Summary of the invention
For overcome the deficiencies in the prior art, the present invention provides a kind of offshore wind farm elder generation pile leader frame construction method of installation.
The technical solution adopted by the present invention to solve the technical problems is:
Offshore wind farm elder generation pile leader frame construction method of installation, it is characterised in that: the following steps are included:
1, preparation of construction, crane ship, transport catheter frame transport barge reach construction site seat in the plane near predetermined point, Interim measurement platform is set, and carries out lifting and measurement preparation,
2, jacket lifting slings jacket to predetermined position by crane ship, and to two of jacket before lifting Cable wind rope is fixed on supporting leg respectively, and cable wind rope is arranged in a crossed manner, includes the supporting leg two of longest supporting leg one and the second length in supporting leg,
3, jacket contraposition, survey crew from interim measurement platform measure respectively jacket supporting leg one and it is another convenient for see The supporting leg of survey makes the corresponding wind power foundation piling bar of one face of supporting leg by adjusting cable wind rope,
4, jacket enters stake, and jacket slowly declines, and supporting leg one is sunk to inside wind power foundation piling bar, wait enter wind-powered electricity generation base In plinth piling bar after certain distance, makes the corresponding wind power foundation piling bar of two face of supporting leg by adjusting cable wind rope, then slowly declines again, Supporting leg two is sunk to inside wind power foundation piling bar, is sunk to inside wind power foundation piling bar after certain distance after supporting leg two, declines lifting The suspension hook of ship enters other two jacket supporting leg also inside corresponding wind power foundation piling bar, until jacket integrally falls in four On a wind power foundation piling bar,
5, measurement correction measures jacket levelness by survey crew, notifies to dive under water if not meeting predeterminated level degree Member corrects and reaches requirement,
6, it is installed, diver, which takes pictures, confirms record,
7, it removes hook and warns, site clearing.
The detailed process of the step 2 is:
2.1, the positioning of lifting secure, and operation platform is transferred at the mark of wind power foundation piling bar, interim measurement is put down Platform is hung in measurement position,
2.2, the transport barge of transport catheter frame casts anchor in place,
2.3, operator climbs up jacket installation suspender belt,
2.4, operator places U-shaped parallels and protects suspender belt,
2.5, suspension hook rises, and operator unbinds jacket,
2.6, and give and fix cable wind rope respectively on two supporting legs of crane ship,
2.7, loop wheel machine, which rises suspension hook, to be sling jacket and is moved to scheduled installation site.
It is double hook because hanging ship's tackle, then by double if jacket occurs blocking the case where can not declining entering a process Hook or so electric hoisting, and hoist engine is adjusted, keep the supporting leg of jacket vertical, jacket is proposed wind power foundation piling bar mouth, weight New adjustment decentralization jacket.
It is fixed on sea bed in advance the beneficial effects of the present invention are: being installed on jacket safety and precise by this method Four wind power foundation piling bars on, can effectively solve the problem that the technical problem that first pile leader frame is installed under water, to promote China southeast Sea area and deep-sea sea area wind power plant are issued with great impetus.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is general flow chart of the invention;
Fig. 2 is lifting lifting rope position view;
Fig. 3 conduit rack position lifting connection and instrumentation plan.
Specific embodiment
Referring to figs. 1 to Fig. 3, the invention discloses a kind of offshore wind farm elder generation pile leader frame construction method of installation, including it is following Step:
1, preparation of construction, crane ship 1, transport catheter frame 2 transport barge reach it is predetermined near the seat in the plane of construction site Interim measurement platform 5 is arranged in point, and carries out lifting and measurement preparation,
2, jacket 2 lifts by crane, and slings jacket 2 to predetermined position by crane ship 1, and to jacket 2 before lifting Cable wind rope 3 is fixed on two supporting legs respectively, and cable wind rope 3 is arranged in a crossed manner, includes that longest supporting leg one and second is long in supporting leg Supporting leg two, specifically includes the following steps:
2.1, after crane ship 1 navigates near seat in the plane positioning of casting anchor, interim transport barge casts anchor in front of crane ship 1, rises Weight ship 1 lifts operation platform and transfers along the mark of wind power foundation piling bar, decoupling device after stablizing.Interim measurement platform 5 is hung in machine Near position.
2.2, the transport barge of transport catheter frame 2 casts anchor in place,
2.3, operator climbs up jacket 2 and installs suspender belt, is characterized in particular in: disposing under jacket 2 to be lifted interim On ladder to the berthing pile ladder of jacket 2, personnel are reached by ladder in the steel platform of jacket 2.Personnel are in steel platform handle Suspender belt bypasses the tower diagonal brace of jacket 2, and instrumentation pays attention to the protection to the component paint of jacket 2.
2.4, operator places U-shaped parallels 7 and protects suspender belt, and operator passes through the blower fan tower barrel lower part iron of jacket 2 Door reaches tower upper mounting plate and places the U-shaped protection of parallels 7 suspender belt, and U-shaped parallels 7 has to play a protective role, then operator Personnel remove afterwards
From tower,
2.5, suspension hook 6 rises, and slowly after raising, whether operator pays attention to suspension hook 6 suitable in the position of the sheath of suspender belt, It is adjusted again when needing, hook is completed, and the stress condition of 1, No. 2 main hook is adjusted, and large arm plays positive 2 geometric center of jacket Hook simultaneously controls stress, then carries out jacket 2 and finally unbinds, and unbinds work according to 2 fixed form of jacket and carries out cutting fastening Part removes fixing bolt etc..
2.6, during unbinding jacket 2, respectively close to crane ship 1 two supporting legs at bolt cable wind rope 3, heaving pile wind Rope 3 needs to prevent component paint from destroying.The intersection of cable wind rope 3 is placed on corresponding hoist engine 4,
2.7, loop wheel machine, which rises suspension hook 6, to be sling jacket 2 and is moved to scheduled installation site, and loop wheel machine slowly hooks up, and leads Pipe support 2 leaves about 2 meter Gao Hou of transport barge deck fixing seat, and transport barge leaves, and it is predetermined that crane ship 1 passes through mobile anchor cable arrival It installs above seat in the plane, according to lifting situation, 1, No. 2 main hook rope capacity of appropriate adjustment makes its basic horizontal, at this time cable wind rope 3 connections on preset hoist engine 4, are hung substantially to predetermined position on the quarter,
3, jacket 2 aligns, and survey crew measures supporting leg one and another branch convenient for observation from interim measurement platform 5 respectively Leg makes the corresponding wind power foundation piling bar of one face of supporting leg by adjusting cable wind rope 3,
4, jacket 2 enters stake, and jacket 2 slowly declines, and supporting leg one is sunk to inside wind power foundation piling bar, wait enter wind-powered electricity generation In foundation steel pile after about 400mm, supporting leg two is observed and measured, is made by adjusting cable wind rope 3 by the corresponding wind-powered electricity generation base of two face of supporting leg Plinth piling bar, then slowly declines again, and supporting leg two is sunk to inside wind power foundation piling bar, sinks in wind power foundation piling bar to supporting leg two After portion about 600mm, after being positioned by supporting leg one and supporting leg two, decline suspension hook 6 makes other two 2 supporting leg of jacket also enter correspondence Wind power foundation piling bar inside, fallen on four wind power foundation piling bars until jacket 2 is whole, and be substantially at jacket 2 Horizontality,
If jacket 2 occurs blocking the case where can not declining entering a process, it is double hook because hanging ship's tackle 6, then passes through Double hook or so electric hoisting, and hoist engine 4 is adjusted, keep the supporting leg of jacket 2 vertical, jacket 2 is proposed wind power foundation piling bar Mouthful, decentralization jacket 2 is readjusted,
5, measurement correction measures 2 levelness of jacket by survey crew, notifies to dive under water if not meeting predeterminated level degree Member corrects and reaches requirement, specifically:
Diver, which takes pictures, confirms situation: if piling bar has all been implemented, then starting to measure;If three piling bar stress are implemented, separately From stake mouth within 5cm, diver beat padding one piling bar with correcting wedge, and diver observes each supporting leg and piling bar At least there is the compacting of 3-4 point, when compacting point is insufficient, beat with correcting wedge and pad and then start to measure,
Survey crew enters tower inner platform, takes at 8 points to flange, reads high difference with level, if flange levelness is super Design value out allows diver to level jacket 2 by increase and decrease cushion block, and specifically exist: each supporting leg is set as needed ultra-thin very heavy Top jacks up, and then uses dimension steel plate pad, after being encased inside between wind power foundation piling bar and supporting leg, then unloads jack and makes cushion block Compacting, and proceeding measurement method orchid disk reaches prescribed requirement,
6, it is installed, after jacket 2 is installed, diver need to carry out note of taking pictures to supporting leg and piling bar installation situation Record, photographing device is underwater camera, since construction area seawater is more muddy, it is necessary to it is equipped with waterproof light and is shot, it must Add transparent clear water bag when wanting before camera.It allows water bag to push down area of taking pictures to take pictures.
7, it removes hook and warns, decoupling device installs warning lamp, pulls up operation platform, move to next seat in the plane,
It is provided for the embodiments of the invention a kind of 2 construction method of installation of jacket above, is described in detail, herein In apply that a specific example illustrates the principle and implementation of the invention, the explanation of above example is only intended to sides Assistant solves method and its core concept of the invention;At the same time, for those skilled in the art, think of according to the present invention Think, there will be changes in the specific implementation manner and application range, in conclusion the content of the present specification should not be construed as pair Limitation of the invention.

Claims (3)

1. offshore wind farm elder generation pile leader frame construction method of installation, it is characterised in that: the following steps are included:
1, preparation of construction, crane ship, transport catheter frame transport barge reach construction site seat in the plane near predetermined point, setting Interim measurement platform, and lifting and measurement preparation are carried out,
2, jacket lifting slings jacket to predetermined position by crane ship, and gives two supporting legs of jacket before lifting It is upper to fix cable wind rope respectively, and cable wind rope is arranged in a crossed manner, includes the supporting leg two of longest supporting leg one and the second length in supporting leg,
3, jacket contraposition, survey crew from interim measurement platform measure respectively jacket supporting leg one and it is another convenient for observation Supporting leg makes the corresponding wind power foundation piling bar of one face of supporting leg by adjusting cable wind rope,
4, jacket enters stake, and jacket slowly declines, and supporting leg one is sunk to inside wind power foundation piling bar, wait enter wind power foundation steel In stake after certain distance, makes the corresponding wind power foundation piling bar of two face of supporting leg by adjusting cable wind rope, then slowly decline again, will prop up Leg two is sunk to inside wind power foundation piling bar, after supporting leg two sinks to wind power foundation piling bar inside certain distance, declines crane ship Suspension hook enters other two jacket supporting leg also inside corresponding wind power foundation piling bar, until jacket integrally falls in four wind In electric foundation steel pile,
5, measurement correction measures jacket levelness by survey crew, notifies diver to entangle if not meeting predeterminated level degree Just and reach requirement,
6, it is installed, diver, which takes pictures, confirms record,
7, it removes hook and warns, site clearing.
2. jacket installation construction method according to claim 1, it is characterised in that:
The detailed process of the step 2 is:
2.1, the positioning of lifting secure, and operation platform is transferred at the mark of wind power foundation piling bar, interim measurement platform is hung Measurement position is put in,
2.2, the transport barge of transport catheter frame casts anchor in place,
2.3, operator climbs up jacket installation suspender belt,
2.4, operator places U-shaped parallels in tower upper mounting plate and protects suspender belt,
2.5, suspension hook rises, and operator unbinds jacket,
2.6, and give and fix cable wind rope respectively on two supporting legs of crane ship,
2.7, loop wheel machine, which rises suspension hook, to be sling jacket and is moved to scheduled installation site.
3. jacket installation construction method according to claim 1, it is characterised in that: in the step 4: if jacket Occur blocking the case where can not declining entering a process, is double hook because hanging ship's tackle, then by double hook or so electric hoisting, and adjusts Whole hoist engine keeps the supporting leg of jacket vertical, and jacket is proposed wind power foundation piling bar mouth, readjusts decentralization jacket.
CN201710481362.0A 2017-06-22 2017-06-22 Offshore wind farm elder generation pile leader frame construction method of installation Active CN107326887B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710481362.0A CN107326887B (en) 2017-06-22 2017-06-22 Offshore wind farm elder generation pile leader frame construction method of installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710481362.0A CN107326887B (en) 2017-06-22 2017-06-22 Offshore wind farm elder generation pile leader frame construction method of installation

Publications (2)

Publication Number Publication Date
CN107326887A CN107326887A (en) 2017-11-07
CN107326887B true CN107326887B (en) 2019-06-18

Family

ID=60196074

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710481362.0A Active CN107326887B (en) 2017-06-22 2017-06-22 Offshore wind farm elder generation pile leader frame construction method of installation

Country Status (1)

Country Link
CN (1) CN107326887B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108374428A (en) * 2018-02-22 2018-08-07 浙江华蕴海洋工程技术服务有限公司 Jacket foundation construction device and installation method
CN108532604A (en) * 2018-03-07 2018-09-14 江苏龙源振华海洋工程有限公司 A kind of steady stake platform construction technique
CN109629568A (en) * 2018-12-30 2019-04-16 中交第三航务工程局有限公司江苏分公司 The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating
CN110925146B (en) * 2019-10-22 2021-07-27 广州文船重工有限公司 Offshore wind power jacket supporting seat
CN110878560A (en) * 2019-10-22 2020-03-13 江苏华蕴海洋科技有限公司 Auxiliary positioning method for offshore wind power jacket foundation hoisting device
CN112112186B (en) * 2020-09-27 2022-02-22 上海振华重工(集团)股份有限公司 Installation method of split jacket foundation on offshore converter station
CN112982399A (en) * 2021-02-05 2021-06-18 保利长大工程有限公司 Pile sinking construction method for fixed-arm type frame crane ship
CN113463644B (en) * 2021-07-07 2023-04-18 中交第一航务工程局有限公司 Suspension mounting method for suction pile jacket
CN114542394A (en) * 2022-01-20 2022-05-27 保利长大工程有限公司港航分公司 Method for hoisting vertical jacket by fixed-arm frame crane ship
CN114856919A (en) * 2022-01-20 2022-08-05 保利长大工程有限公司港航分公司 Method for hoisting jacket by full-circle slewing crane ship
CN114542398A (en) * 2022-02-24 2022-05-27 保利长大工程有限公司港航分公司 Construction method for hoisting horizontal jacket by fixed-arm frame crane ship
CN117773440B (en) * 2024-02-26 2024-04-19 广州文船重工有限公司 Movable inner container tool for wind power jacket

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852147A (en) * 2012-10-09 2013-01-02 中国海洋石油总公司 Method for righting jacket by using single cantilever gin pole and double hooks
CN103215956A (en) * 2013-04-03 2013-07-24 江苏龙源振华海洋工程有限公司 Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm
CN105780802A (en) * 2014-12-23 2016-07-20 广州华申建设工程管理有限公司 Jacket offshore wind turbine foundation with brackets and construction method thereof
CN105804111A (en) * 2016-05-26 2016-07-27 福建省新能海上风电研发中心有限公司 Unequal-length-leg offshore wind power jacket foundation and construction method thereof
CN106638530A (en) * 2016-12-29 2017-05-10 江苏海上龙源风力发电有限公司 Process for lifting offshore booster station jacket in shallow water

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852147A (en) * 2012-10-09 2013-01-02 中国海洋石油总公司 Method for righting jacket by using single cantilever gin pole and double hooks
CN103215956A (en) * 2013-04-03 2013-07-24 江苏龙源振华海洋工程有限公司 Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm
CN105780802A (en) * 2014-12-23 2016-07-20 广州华申建设工程管理有限公司 Jacket offshore wind turbine foundation with brackets and construction method thereof
CN105804111A (en) * 2016-05-26 2016-07-27 福建省新能海上风电研发中心有限公司 Unequal-length-leg offshore wind power jacket foundation and construction method thereof
CN106638530A (en) * 2016-12-29 2017-05-10 江苏海上龙源风力发电有限公司 Process for lifting offshore booster station jacket in shallow water

Also Published As

Publication number Publication date
CN107326887A (en) 2017-11-07

Similar Documents

Publication Publication Date Title
CN107326887B (en) Offshore wind farm elder generation pile leader frame construction method of installation
CN206826891U (en) A kind of offshore wind turbine single pile pile sinking operation based on barge with deck transformation is refuted
EP1356205B1 (en) Method and apparatus for placing at least one wind turbine on open water
US4744697A (en) Installation and removal vessel
CN109629568A (en) The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating
CN104527937B (en) Marine wind turbine whole machine is transported with installing special purpose ship and method
JP6741346B2 (en) Pile appending system
CN107089584B (en) A kind of jacket lifting technology for binding
CN103939299B (en) The split type mounting process of a kind of offshore wind turbine
CN108532604A (en) A kind of steady stake platform construction technique
CN103215956B (en) Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm
AU771609B2 (en) Method for removing a jacket of a drilling or production rig and vessel provided with a device therefor
CN208563968U (en) A kind of rectangle chimney twin-well frame displacement type template integral lifting apparatus
CN110185057A (en) A kind of tooling and construction method for the lifting staking out of offshore wind farm single-pile foundation steel-pipe pile
CN204170002U (en) A kind of artificial digging pile safety apparatus
CN112299231A (en) Single-blade lightering-free mounting equipment and method thereof
CN113915073B (en) Quick impeller hoisting method for offshore wind power self-elevating platform ship
CN209757445U (en) Boat davit with recoverable function
CN109914411A (en) A kind of non-embedding lithotype construction technology of marine four pile leaders frame
JP2023552909A (en) How to assemble a floating offshore wind farm
CN209778056U (en) Hoisting lockset for hoisting electric power tower with small shaking amplitude
CN106335608A (en) Mounting method of seabed anchor
KR200357757Y1 (en) Ship Lifting system
CN106400765B (en) The installation method of assembly platform
CN220432025U (en) Large box culvert hoisting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant