CN107315025A - The pressure compensation and bleeder of HTHP thermal insulation test process - Google Patents

The pressure compensation and bleeder of HTHP thermal insulation test process Download PDF

Info

Publication number
CN107315025A
CN107315025A CN201610408779.XA CN201610408779A CN107315025A CN 107315025 A CN107315025 A CN 107315025A CN 201610408779 A CN201610408779 A CN 201610408779A CN 107315025 A CN107315025 A CN 107315025A
Authority
CN
China
Prior art keywords
pressure
compensation
test process
releasing
control system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610408779.XA
Other languages
Chinese (zh)
Inventor
金满平
王婷
孙冰
朱红伟
姜杰
徐伟
石宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
Sinopec Qingdao Safety Engineering Institute
Original Assignee
China Petroleum and Chemical Corp
Sinopec Qingdao Safety Engineering Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Chemical Corp, Sinopec Qingdao Safety Engineering Institute filed Critical China Petroleum and Chemical Corp
Priority to CN201610408779.XA priority Critical patent/CN107315025A/en
Publication of CN107315025A publication Critical patent/CN107315025A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N25/00Investigating or analyzing materials by the use of thermal means
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01JCHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
    • B01J3/00Processes of utilising sub-atmospheric or super-atmospheric pressure to effect chemical or physical change of matter; Apparatus therefor
    • B01J3/04Pressure vessels, e.g. autoclaves

Abstract

The present invention relates to the pressure compensation and bleeder of a kind of adiabatic test process of HTHP, mainly solve in the prior art high temperature high voltage resistant ability, the problem of test result is inaccurate.Pressure compensation and bleeder of the invention by using a kind of adiabatic test process of HTHP, pressure-bearing kettle including can be resistant to 800 DEG C of high temperature and 30MPa high pressures, place inside pressure-bearing kettle container wall thickness be 0.2~0.3mm, stainless steel, the technical scheme that can be resistant to 800 DEG C of high temperature, volume and be the cylindrical calorimetric ponds of 100~110mL preferably solve above mentioned problem, available in the adiabatic test process of HTHP.

Description

The pressure compensation and bleeder of HTHP thermal insulation test process
Technical field
The present invention relates to the pressure compensation and bleeder of a kind of adiabatic test process of HTHP.
Background technology
For the calorimetric test for the purpose of process heat risk assessment, using thermal inertia factor is as low as possible, sample size is most Reaction calorimetric pond more than possible can effectively avoid calorimetric pond from absorbing heat in itself and influence reaction system own temperature to raise Process and reduce material proof load it is smaller and produce enlarge-effect, this has extremely important for process heat risk assessment Meaning.
Thermal inertia factor can effectively be reduced using wall thickness thin calorimetric pond as far as possibleValue, but calorimetric pond can be reduced Compressive resistance, during temperature rise, the pressure of reaction system is constantly raised, more than can be led after the cumulative maximum pressure in calorimetric pond Calorimetric pond is caused to produce deformation or rupture.Now, compensation is certain in the external environment condition of calorimetric pond connects with calorimetric pond internal pressure value Near inert gas, and lasting dynamic during calorimetric pond internal pressure is constantly elevated compensates certain pressure, then may be used It is prevented effectively from calorimetric pond to deform upon or rupture, and the pressure changing inside calorimetric pond can be continued to monitor, until reaction is lost Control.
At present, the adiabatic calorimetry test equipment of main flow is mainly the ARC adiabatic calorimetry instrument of THT companies of Britain production in the world The VSP2 produced with FAI companies of the U.S. is released size calorimeter, and some other adiabatic calorimetry equipment test philosophy is all based on State two kinds of adiabatic test equipments.ARC adiabatic calorimetries instrument in order to prevent calorimetric pond be unlikely to material decompose produce high pressure effect Lower explosion, employs wall thickness, small volume and pressure-resistant calorimetric pond, without pressure compensating system, result in the thermal inertia of system The factorValue is higher, it is impossible to provide the data of technique amplification.VSP2 employs temperature tracking and pressure compensated method is automatic The pressure, temperature variation in adiabatic reaction runaway event is followed the trail of, but VSP2 heating system temperatures only up to be reached 250 DEG C, bearing capacity is no more than 13MPa, it is impossible to which the adiabatic reaction process to temperature more than 250 DEG C is tracked test. Meanwhile, VSP2 pressure compensating system compensates in adiabatic runaway event to pressure-bearing kettle, the normal temperature that reacts outside calorimetric pond is lazy Property gas material in certain cooling effect, absorbing reaction calorimetric pond can be produced to reaction calorimetric pond occur runaway reaction and produce Heat, influence can be produced on test result.Drawn by German Nai Chi companies STA499C synchronous solvings and French C1-esteraseremmer-N The micro- calorimeter reaction heat test results of nurse company C80 calculate that obtained adiabatic temperature rise data test obtained thermal insulation temperature with VSP2 Rising data has the provable this point of larger deviation.Therefore, realize using low-heat inertia factor calorimetric pond, avoid compensation lazy Property gas to the cooling effect in calorimetric pond, while the thermal insulation that can also track the temperature and pressure situation of change of high-temperature and high-pressure conditions is anti- Calorimetry system is answered, is had very important significance for process heat hazard assessment.According to literature search result, the current country is still The pressure compensation and drainage method in high-temperature and high-pressure conditions adiabatic calorimetry test process are not set up and design.
The content of the invention
The technical problems to be solved by the invention, which are that high temperature high voltage resistant ability, test result are inaccurate in the prior art, asks There is provided the pressure compensation and bleeder of a kind of adiabatic test process of new HTHP for topic.The device has test result accurate True advantage.
To solve the above problems, the technical solution adopted by the present invention is as follows:A kind of pressure of the adiabatic test process of HTHP is mended Repay and bleeder, include the cylindrical calorimetric pond of pressure-bearing kettle and the placement of pressure-bearing kettle inside, pressure-bearing kettle is top-loaded with for pressure release The pressure sensor of rupture disk and high temperature high voltage resistant, side wall has the temperature sensor for testing pressure-bearing kettle internal temperature, amount Hot pond is connected with the temperature sensor on the wall of pressure-bearing kettle side, pressure sensor and the charging of calorimetric pond and emptying control valve, temperature Degree sensor is connected by data wire with computer control system;High-pressure compressor, gases at high pressure heating system, pressure The control system that compensates and release is sequentially connected, and wherein vacuum pressure pump in pressure compensation and control system of releasing with vacuumizing electricity Magnet valve connect, high-pressure compressor produce high-pressure inert gas by after gases at high pressure heating system heats with pressure compensation And the pressure compensation magnetic valve in control system of releasing is connected, the Pressure Relief Valve in pressure compensation and control system of releasing is with holding Kettle connection is pressed, gases at high pressure heating system and its temperature sensor, pressure compensation and control system of releasing pass through data wire and meter Calculation machine control system is connected.
In above-mentioned technical proposal, it is preferable that computer control system is by data acquisition card, digital analog converter and preprogramming Computer software is constituted.
In above-mentioned technical proposal, it is preferable that gases at high pressure heating system is by a set of high pressure resistant gas pressure vessel and heating system Composition, is connected with high pressure compressed gas system and pressure compensation magnetic valve, for heating the inertia produced by high-pressure compression system Gas.
In above-mentioned technical proposal, it is preferable that pressure compensation and control system of releasing are by control pressure compensation, pressure releasing respectively Constituted with the three sets of high temperature high voltage resistant magnetic valves and its control system vacuumized, for carrying out in HTHP calorimetric test process Inert gas pressure compensation, pressure releasing and test before pressure-bearing kettle and calorimetric pond in take out negative pressure.
In above-mentioned technical proposal, it is preferable that inert gas passes through pressure in filling insulation material, test process outside calorimetric pond The control system that compensates and release enters in pressure-bearing kettle, plays a part of protection calorimetric pond.
In above-mentioned technical proposal, it is preferable that pressure releasing electromagnetic valve outlet pipeline is provided with pressure releasing pipeline cooler.
In above-mentioned technical proposal, it is preferable that pressure compensation magnetic valve, pressure releasing magnetic valve, vacuumize electromagnetic valve outlet mix It is connected after conjunction with pressure compensation pipeline heater one end, the pressure compensation pipeline heater other end and pressure-bearing kettle, pressure compensation pipe The pipeline that road heater is connected with pressure-bearing kettle is provided with pressure-bearing kettle pressure sensor.
In above-mentioned technical proposal, it is preferable that pressure-bearing kettle can be resistant to and be placed inside 800 DEG C of high temperature and 30MPa high pressures, pressure-bearing kettle It is the cylindrical calorimetrics of 100~110mL that container wall thickness, which is 0.2~0.3mm, stainless steel, can be resistant to 800 DEG C of high temperature, volume Pond.
The present invention provides one kind pressure compensation and drainage method suitable for high temperature and high pressure condition adiabatic calorimetry test process, is adopting On the basis of low-heat inertia factor heat pond, realized by entering trip temperature Tracing Control to high pressure compressed gas to HTHP Pressure compensation in adiabatic calorimetry test process and release, it is to avoid compensation inert gas makes it to the cooling effect in heat pond Test result is more intended for the operating environment of industrialized unit closer to real working condition condition, its temperature control system, pressure The design of the elements such as Force control system, pressure-bearing kettle and related pipe valve adds its tolerance to HTHP extreme operating condition.It is real The pressure compensation of adiabatic calorimetry test process is carried out under present HTHP extreme condition and is released;Pressure compensation mistake can be eliminated The cooling effect that inert gas is produced to calorimetric pond in journey;The requirement close to 800 DEG C of high temperature and 30MPa maximum pressures is met, Achieve preferable technique effect.
Brief description of the drawings
Fig. 1 is the pressure compensation and bleeder schematic flow sheet of HTHP adiabatic calorimetry test process.
In Fig. 1,1- computer control systems, 2- vacuum pressure pumps, 3- high-pressure compressors, 4- one-way control valves, 5- are high Press compressed gas heating system temperature sensor, 6- high pressure compressed gas heating system, 7- pressure releasing pipelines cooler, 8- Pressure compensation and control system of releasing, 9- pressure compensations magnetic valve, 10- pressure releasings magnetic valve, 11- vacuumize magnetic valve, 12- pressure compensations pipeline heater, 13- pressure-bearing kettles pressure sensor, 14- pressure-bearings kettle are connected control valve, 15- amounts with calorimetric pond Hot pond pressure sensor, 16- pressure-bearings kettle, 17- pressure-bearing kettles rupture disk, 18- calorimetrics pond, 19- pressure-bearing kettles temperature sensor, 20- Calorimetric pond temperature sensor, the charging of 21- calorimetrics pond and emptying control valve.
Below by embodiment, the invention will be further elaborated, but is not limited only to the present embodiment.
Embodiment
【Embodiment 1】
The pressure compensation and bleeder of a kind of adiabatic test process of HTHP, as shown in figure 1, including can be resistant to 800 DEG C The pressure-bearing kettle of high temperature and 30MPa high pressures, place inside pressure-bearing kettle container wall thickness be 0.2~0.3mm, stainless steel, can Resistance to 800 DEG C of high temperature, volume are the cylindrical calorimetric ponds of 100~110mL, and pressure-bearing kettle is top-loaded with rupture disk and Nai Gao for pressure release The pressure sensor of warm high pressure, side wall has the temperature sensor for testing pressure-bearing kettle internal temperature, and calorimetric pond is held with being mounted in Press temperature sensor, pressure sensor and the charging of calorimetric pond and emptying control valve connection on the wall of kettle side, calorimetric pond TEMP Device and pressure-bearing kettle sensor are connected by data wire with computer control system;Vacuum pressure pump, high-pressure compressor, height Pressure gas heating system, pressure compensation and control system of releasing are sequentially connected, and wherein vacuum pressure pump and pressure compensation and are released Magnetic valve connection is vacuumized in control system, the high-pressure inert gas that high-pressure compressor is produced are heated by gases at high pressure It is connected after system heating with the pressure compensation magnetic valve in pressure compensation and control system of releasing, pressure compensation and the control system that releases Pressure Relief Valve in system is connected with pressure-bearing kettle, gases at high pressure heating system and its temperature sensor, pressure compensation and control of releasing System processed is connected by data wire with computer control system.
Pressure compensation and bleed-off system are mainly comprised the following steps:
1) computer control system:It is made up of the computer software of data acquisition card, digital analog converter and preprogramming.
2) vacuum pressure pump:It is connected with vacuumizing magnetic valve, pressure in calorimetric pond and pressure-bearing kettle is evacuated to negative by test before starting Pressure, for checking calorimetric pond air-tightness and toward liquid feeding state or Gaseous materials in calorimetric pond.
3) high-pressure compressor:It is connected with gases at high pressure heating system and pressure compensation magnetic valve, for producing high pressure pressure Contracting gas, inert gas is compensated in adiabatic calorimetry test process into pressure-bearing kettle.
4) gases at high pressure heating system:It is made up of a set of high pressure resistant gas pressure vessel and heating system, with high pressure compressed gas System is united and the connection of pressure compensation magnetic valve, for heating the inert gas produced by high-pressure compression system.
5) pressure compensation and control system of releasing:By the compensation of control pressure respectively, pressure releasing and the three sets of resistance to height vacuumized Warm high-pressure solenoid valve and its control system composition, is mended for carrying out the inert gas pressure in HTHP calorimetric test process Repay, pressure releasing and test before pressure-bearing kettle and calorimetric pond in take out negative pressure.
6) pressure-bearing kettle:800 DEG C of high temperature and 30MPa high pressures are can be resistant to, inside is placed filling outside calorimetric pond, calorimetric pond and protected Inert gas is entered in pressure-bearing kettle by pressure compensation and control system of releasing in adiabator, test process, plays protection calorimetric The effect in pond.
Wherein, vacuum pressure pump, high-pressure compressor are outsourcing, computer control system, high pressure compressed gas heating system Unite to customize, pressure compensation and control system of releasing, pressure-bearing kettle are designed, designed and manufacture.
Temperature sensor, pressure sensor should be calibrated first, it is ensured that device each several part stainless steel pipeline, data wire connect Connect normal, it is ensured that precision temperature and pressure testing system are normal, are then tested according to the following steps:
1) computer control system 1, Opening pressure compensation and Control System Software of releasing are opened;
2) calorimetric pond inlet valve 21 is closed, pressure-bearing kettle is opened and is connected control valve 14 with calorimetric pond, calorimetric pond is connected with pressure-bearing kettle Together;
3) vavuum pump 2 is opened by computer control system 1 and vacuumizes magnetic valve 11, by pressure-bearing kettle 16 and calorimetric pond Negative pressure is evacuated in 18, until take out it is motionless untill, closing vacuumizes magnetic valve 11, observation calorimetric pond 18 and pressure-bearing kettle Whether pressure changes in 16, to check the air-tightness of pressure-bearing kettle 16.Close pressure-bearing kettle 16 and pressure sensor 15 Control valve is connected, magnetic valve 10 of releasing is opened, the pressure of pressure-bearing kettle 16 is returned to normal pressure, observation calorimetric pond 18 Interior pressure change, to check calorimetric pond air-tightness;
4) liquid or Gaseous materials are added in calorimetric pond by calorimetric pond inlet control valve 21, closes the charging control of calorimetric pond Valve 21, opens the one-way control valve 4 between connection high-pressure compressor 3 and gases at high pressure heating system 6, opens Pressure compensation and the software of control system 8 of releasing;
5) in test process, computer control system 1 first sets temperature to heat in calorimetric pond 18 according to program, will be logical Environment temperature feedback is crossed in the pressure-bearing kettle that the temperature sensor 19 in pressure-bearing kettle 16 is collected to computer control system 1, output order is automatically controlled by it and opens the high pressure that gases at high pressure heating system 6 is produced to high-pressure compressor Inert gas is heated, and its temperature is not less than 10 DEG C of environment temperature in pressure-bearing kettle;
6) pressure following temperature is raised and gradually increased, pressure superpressure pressure-bearing kettle pressure in equivalent speed pond 18 in calorimetric pond 18 During 0.3MPa, computer control system automatically turns on pressure compensation magnetic valve 9, by the indifferent gas after heating Body is compensated into pressure-bearing kettle automatically, the pressure differential in calorimetric pond and pressure-bearing kettle is in the range of 0.1~0.3MPa;
7) in test process, if calorimetric pond is less than 0.1MPa with the pressure differential in pressure-bearing kettle, computer control system can be certainly Dynamic Opening pressure is released magnetic valve 10, and the inert gas in pressure-bearing kettle is expelled into air by pressure releasing magnetic valve In, prevent that hypertonia causes calorimetric pond to deform upon in pressure-bearing kettle;
8) after experiment terminates, experimental data is preserved, according to the orderly release each part opposite with installation, associated pipe is arranged And circuit, by calorimetric pond cleaning, drying, it is standby.

Claims (8)

1. the pressure compensation and bleeder of a kind of adiabatic test process of HTHP, including put inside pressure-bearing kettle and pressure-bearing kettle The cylindrical calorimetric pond put, pressure-bearing kettle is top-loaded with the pressure sensor of the rupture disk and high temperature high voltage resistant for pressure release, side wall There are the temperature sensor for testing pressure-bearing kettle internal temperature, calorimetric pond and the temperature sensor on the wall of pressure-bearing kettle side, pressure Force snesor and the charging of calorimetric pond and emptying control valve connection, temperature sensor are connected by data wire and computer control system Connect;High-pressure compressor, gases at high pressure heating system, pressure compensation and control system of releasing are sequentially connected, wherein vacuum Compression pump is connected with the magnetic valve that vacuumizes in pressure compensation and control system of releasing, and the high pressure that high-pressure compressor is produced is lazy Property gas by after gases at high pressure heating system heats with pressure compensation and control system of releasing pressure compensation magnetic valve connect Connect, the Pressure Relief Valve in pressure compensation and control system of releasing is connected with pressure-bearing kettle, gases at high pressure heating system and its temperature Sensor, pressure compensation and control system of releasing are connected by data wire with computer control system.
2. the pressure compensation and bleeder of the adiabatic test process of HTHP according to claim 1, it is characterised in that calculate Machine control system is made up of the computer software of data acquisition card, digital analog converter and preprogramming.
3. the pressure compensation and bleeder of the adiabatic test process of HTHP according to claim 1, it is characterised in that high pressure Gas heating system is made up of a set of high pressure resistant gas pressure vessel and heating system, is mended with high pressure compressed gas system and pressure Magnetic valve connection is repaid, for heating the inert gas produced by high-pressure compression system.
4. the pressure compensation and bleeder of the adiabatic test process of HTHP according to claim 1, it is characterised in that pressure Compensate and release control system by the compensation of control pressure respectively, pressure releasing and the three sets of high temperature high voltage resistant magnetic valves vacuumized and Its control system is constituted, for carrying out the compensation of the inert gas pressure in HTHP calorimetric test process, pressure releasing and survey Negative pressure is taken out in pressure-bearing kettle and calorimetric pond before examination.
5. the pressure compensation and bleeder of the adiabatic test process of HTHP according to claim 1, it is characterised in that calorimetric Inert gas is entered in pressure-bearing kettle by pressure compensation and control system of releasing in filling insulation material, test process outside pond, Play a part of protection calorimetric pond.
6. the pressure compensation and bleeder of the adiabatic test process of HTHP according to claim 1, it is characterised in that pressure Magnetic valve outlet line of releasing is provided with pressure releasing pipeline cooler.
7. the pressure compensation and bleeder of the adiabatic test process of HTHP according to claim 1, it is characterised in that pressure Compensation electromagnetic valve, pressure releasing magnetic valve, vacuumize electromagnetic valve outlet mixing after be connected with pressure compensation pipeline heater one end, The pressure compensation pipeline heater other end and pressure-bearing kettle, pressure compensation pipeline heater are provided with the pipeline being connected with pressure-bearing kettle Pressure-bearing kettle pressure sensor.
8. the pressure compensation and bleeder of the adiabatic test process of HTHP according to claim 1, it is characterised in that pressure-bearing Kettle can be resistant to 800 DEG C of high temperature and 30MPa high pressures, placed inside pressure-bearing kettle container wall thickness be 0.2~0.3mm, stainless steel, Can be resistant to 800 DEG C of high temperature, volume is the cylindrical calorimetric ponds of 100~110mL.
CN201610408779.XA 2016-06-12 2016-06-12 The pressure compensation and bleeder of HTHP thermal insulation test process Pending CN107315025A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610408779.XA CN107315025A (en) 2016-06-12 2016-06-12 The pressure compensation and bleeder of HTHP thermal insulation test process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610408779.XA CN107315025A (en) 2016-06-12 2016-06-12 The pressure compensation and bleeder of HTHP thermal insulation test process

Publications (1)

Publication Number Publication Date
CN107315025A true CN107315025A (en) 2017-11-03

Family

ID=60185066

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610408779.XA Pending CN107315025A (en) 2016-06-12 2016-06-12 The pressure compensation and bleeder of HTHP thermal insulation test process

Country Status (1)

Country Link
CN (1) CN107315025A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108490025A (en) * 2018-03-30 2018-09-04 沈阳化工研究院有限公司 A kind of the calorimetric test method and device of continuous flow gas phase reaction process
CN113740376A (en) * 2020-05-28 2021-12-03 应急管理部化学品登记中心 Quantitative sample introduction device and method for converting normal-temperature gaseous substances into low-temperature liquid

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0057596B1 (en) * 1981-01-30 1985-11-27 Hoxan Corporation Apparatus for measuring melting point and boiling point of a sample
US4670404A (en) * 1985-04-22 1987-06-02 Fike Corporation Micro-scale chemical process simulation methods and apparatus useful for design of full scale processes, emergency relief systems and associated equipment
CN1333083A (en) * 2000-07-12 2002-01-30 罗姆和哈斯公司 Laboratory scale reaction system
CN1849501A (en) * 2003-07-10 2006-10-18 蒂艾克思股份有限公司 Low thermal inerta scanning adiabatic calorimeter
CN102393313A (en) * 2011-10-18 2012-03-28 中国石油化工股份有限公司 Temperature pressure tracking method of simulation device in petrifaction device in emergency discharge process
CN102423675A (en) * 2011-10-18 2012-04-25 中国石油化工股份有限公司 Simulation experiment device in petrochemical apparatus during emergent relief process

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0057596B1 (en) * 1981-01-30 1985-11-27 Hoxan Corporation Apparatus for measuring melting point and boiling point of a sample
US4670404A (en) * 1985-04-22 1987-06-02 Fike Corporation Micro-scale chemical process simulation methods and apparatus useful for design of full scale processes, emergency relief systems and associated equipment
CN1333083A (en) * 2000-07-12 2002-01-30 罗姆和哈斯公司 Laboratory scale reaction system
CN1849501A (en) * 2003-07-10 2006-10-18 蒂艾克思股份有限公司 Low thermal inerta scanning adiabatic calorimeter
CN102393313A (en) * 2011-10-18 2012-03-28 中国石油化工股份有限公司 Temperature pressure tracking method of simulation device in petrifaction device in emergency discharge process
CN102423675A (en) * 2011-10-18 2012-04-25 中国石油化工股份有限公司 Simulation experiment device in petrochemical apparatus during emergent relief process

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘显凡: "化学反应放热失控安全泄放设计及评估技术研究", 《中国优秀硕士学位论文全文数据库 工程科技I辑》 *
高忠白 等: "《压力容器安全管理工程》", 31 March 1992, 中国石化出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108490025A (en) * 2018-03-30 2018-09-04 沈阳化工研究院有限公司 A kind of the calorimetric test method and device of continuous flow gas phase reaction process
CN108490025B (en) * 2018-03-30 2023-08-08 沈阳化工研究院有限公司 Calorimetric test method and device for continuous flow gas phase reaction process
CN113740376A (en) * 2020-05-28 2021-12-03 应急管理部化学品登记中心 Quantitative sample introduction device and method for converting normal-temperature gaseous substances into low-temperature liquid

Similar Documents

Publication Publication Date Title
CN103308293B (en) A kind of high temperature valve detection experiment system
CN102435632B (en) Testing system for researching flow boiling heat transfer character and pressure drop character of cryogenic fluid
CN102901803B (en) Water-gas different adsorption-desorption-seepage experimental method for loaded coal containing methane
CN101762435B (en) Wide temperature zone hydrogen storage material low temperature hydrogen storage performance testing device
CN108730760B (en) Hydrogen storage tank fills hydrogen filling performance detecting system
CN104297072A (en) Device and method applied to experiment of supercritical carbon dioxide closed cycle compression characteristic
CN102759231B (en) Normal-pressure/negative-pressure liquid nitrogen subcooler system
CN101858842A (en) Test method of metal hydride thermal adsorption and desorption of hydrogen cycle life and special device thereof
CN107884435B (en) Device for measuring heat conductivity coefficient of material under high-pressure gas environment
CN106918458B (en) A kind of Test System for Rocket Engine Test kerosene high/low temperature heat-exchange system and charging method
CN102928151B (en) Pressure measuring method and device for liquid metal
CN105606767A (en) High vacuum-high pressure combined hydrogen storage property testing device for low hydrogen absorption equilibrium pressure material
CN107315025A (en) The pressure compensation and bleeder of HTHP thermal insulation test process
CN103837567B (en) The liquid specific heat capacity measurement device of energy self-equilibrating pressurization and method
CN107315029A (en) The pressure compensation and drainage method of HTHP thermal insulation test process
CN108187773A (en) A kind of high-low-temperature cold test system
CN104155425B (en) A kind of method of high precision PCT tester and test alloy material storing hydrogen PCT
CN107300430B (en) Vacuum insulation low-temperature pipe heat leakage measurement device and measurement method thereof
CN110107806B (en) Low-temperature heat-insulation gas cylinder evaporation rate detection method based on different filling rates
CN208780644U (en) Lithium ion battery thermal runaway gas, solid resultant product collection and test macro
CN103115743B (en) Can test spring at the device of wide low-temperature space elastic performance
CN109655372A (en) A kind of PdO getter inspiratory capacity test device and method
CN205593952U (en) Backing material contact interface heat conduction test device in cryrogenic container of vacuum
CN104596786A (en) Compressed air circulation system for performance test of heat exchanger
CN209182170U (en) A kind of full-automatic high-pressure hydrogen cylinder hydrogen cyclic test system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171103