CN107314161A - A kind of construction drainage pipeline - Google Patents

A kind of construction drainage pipeline Download PDF

Info

Publication number
CN107314161A
CN107314161A CN201710691524.3A CN201710691524A CN107314161A CN 107314161 A CN107314161 A CN 107314161A CN 201710691524 A CN201710691524 A CN 201710691524A CN 107314161 A CN107314161 A CN 107314161A
Authority
CN
China
Prior art keywords
parts
tube layer
layer
drainage pipeline
construction drainage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710691524.3A
Other languages
Chinese (zh)
Inventor
谭颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710691524.3A priority Critical patent/CN107314161A/en
Publication of CN107314161A publication Critical patent/CN107314161A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L9/00Rigid pipes
    • F16L9/08Rigid pipes of concrete, cement, or asbestos cement, with or without reinforcement
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L9/00Rigid pipes
    • F16L9/12Rigid pipes of plastics with or without reinforcement
    • F16L9/127Rigid pipes of plastics with or without reinforcement the walls consisting of a single layer

Abstract

The present invention discloses a kind of construction drainage pipeline, including interior tube layer, polyurethane foam, quartz sand layer and external tube layer, said inner tube layer, polyurethane foam, quartz sand layer and external tube layer are set from the inside to the outside successively, described is that external tube layer is stainless steel layer, said inner tube layer outside is provided with support bar, the support bar is fixedly connected with interior tube layer and external tube layer respectively, the support bar is provided with three, fixed cover is provided with the outside of the external tube layer, the fixed cover side sets baffle plate, the baffle plate is integrally formed setting with fixed cover, the construction drainage pipeline has the function of fireproof heat insulating, structural stability is high, the interior tube layer used is easy for installation, anticorrosion effect is good.

Description

A kind of construction drainage pipeline
Technical field
The present invention relates to a kind of construction drainage pipeline.
Background technology
Building is people's soil, brick, watt, stone material, timber;(Modern age reinforced concrete, section bar)Constituted Deng construction material Space that is a kind of for human habitation and using, such as house, bridge, factory building, gymnasium, cave dwelling, water tower, temple etc..Broadly come Say, landscape, gardens are also wing.Say in a broad sense, the nest that animal is built consciously can also can be regarded as building.Western wise man There is cloud:Building is the music of solidification, and building is a stone history records.The classical masterpiece of Roman architecture man's Vitruvius《Building Ten books》Propose three standards of building:It is firm, practical, attractive in appearance, the architectural development of later age is affected always.Building composition Three elements:Building function, Building technology and art of architecture image.
Pipeline be with pipe, pipe connector and valve etc. be connected into be used for convey gas, liquid or with solid particle Fluid device.Feedwater, draining, heat supply, the oil transportation of the trunk pipeline given gas and long range in city, feed channel are most Be laid in underground, and the process pipe in factory is laid on the ground more for ease of Operation and maintenance.The current of pipeline, supporting, slope Degree and discharge opeing exhaust, compensation, insulation and heating, anti-corrosion and cleaning, identification and japanning and safety etc., no matter for over ground installation also It is the problem of underground laying is all important.
Pipeline on ground, which should try one's best, to be avoided intersecting with road, railway and navigation channel.When not being avoided that intersection, infall across Height more should be able to also make pedestrian and car and boat safety.The pipeline of underground is typically laid along road, is kept between various pipelines Appropriately distance, to install and to repair;There is heat-insulation layer on the surface of heat supply pipeline, is laid in trench or protection pipe, should avoid Gone bad by soil pressure and move pipe expansion.
Pipeline may bear the effect of many kinds of external force, including thrust of the weight, fluid matasomatism of in pipe end itself, wind and snow Load, ground pressure, expand with heat and contract with cold caused thermal stress, oscillating load and earthquake disaster etc..In order to ensure pipeline intensity and Rigidity, it is necessary to set various branch (to hang) frame, such as travel(l)ing rest, fixed support, guiding trestle and spring support.The setting of support According to conditional decisions such as the diameter of pipeline, material, pipe wall thickness and load.The heat that fixed support is used for Discrete control pipeline is stretched It is long, make expansion joint uniform operational;Guiding trestle makes pipe only move axially.
The current existing function without fireproof heat insulating, structural stability is not high, and the interior tube layer of use installs inconvenient, Anticorrosion effect is bad.
The content of the invention
The technical problem to be solved in the present invention is to provide a kind of function with fireproof heat insulating, structural stability is high, uses Interior tube layer it is easy for installation, the good construction drainage pipeline of anticorrosion effect.
To solve the above problems, the present invention is adopted the following technical scheme that:
A kind of construction drainage pipeline, including interior tube layer, polyurethane foam, quartz sand layer and external tube layer, said inner tube Layer, polyurethane foam, quartz sand layer and external tube layer are set from the inside to the outside successively, and described is that external tube layer is stainless steel layer, described Support bar is provided with the outside of interior tube layer, the support bar is fixedly connected with interior tube layer and external tube layer respectively, and the support bar is provided with Three, be provided with fixed cover on the outside of the external tube layer, the fixed cover side sets baffle plate, the baffle plate and fixed cover one into Type is set.
Preferably, the polyurethane foam thickness is 8mm, heat insulation effect effect is kept.
Preferably, being provided with spring on the inside of the baffle plate so that baffle plate install compact.
Preferably, being provided with fixing bolt in the middle part of the baffle plate, good fixing effect can be kept, it is convenient to install.
Preferably, said inner tube thickness degree is 5mm, keep fluid conveying smooth reliable.
A kind of construction drainage pipeline, said inner tube layer is made up by mass fraction proportioning of following material:Styrene - 23-28 parts of acrylonitrile copolymer, 5-8 parts of aluminium powder, 2-5 parts of silane coupler, 6-8 parts of castor bean wax, poly terephthalic acid fourth 7-10 parts of ester, 12-14 parts of mica powder, 6-8 parts of dimethicone, 7-10 parts of phthalic acid ester, 2-4 parts of phosphite, sulfydryl 5-10 parts of acid esters, 3-8 parts of triethoxysilane, 12-15 parts of rosin modified phenolic resin, 16-20 parts of polyvinyl acetate, carboxyl 2-5 parts of 7-8 parts of styrene-butadiene latex, 15-20 parts of styrene-acrylic emulsion, 3-9 parts of citric acid and activated carbon.
The preparation method of said inner tube layer comprises the following steps:
1)By styrene -23-28 parts of acrylonitrile copolymer, 5-8 parts of aluminium powder, 2-5 parts of silane coupler, 6-8 parts of castor bean wax, 7-10 parts of PA polybutyleneterephthalate, 12-14 parts of mica powder, 6-8 parts of dimethicone, 7-10 parts of phthalic acid ester, phosphorous 2-4 parts of hydrochlorate, 5-10 parts of sulfydryl acid esters, 3-8 parts of triethoxysilane, 12-15 parts of rosin modified phenolic resin, polyvinyl acetate 2-5 parts of 16-20 parts of ester, 7-8 parts of carboxylic styrene butadiene latex, 15-20 parts of styrene-acrylic emulsion, 3-9 parts of citric acid and activated carbon are put into and stirred Mix in machine, regulation rotating speed is 3600-3800r/min, is reacted 6-11 minutes, standby;
2)By step 1)Gained raw material is put into autoclave, and regulation temperature is 78 DEG C, and regulation air pressure is 12 times of atmospheric pressure, reaction It is 7-15 minutes, standby;
3)By step 2)Gained raw material is put into banbury, and regulation temperature is 220-245 DEG C, is in molten by raw material heating State, it is standby;
4)By step 3)Gained raw material is put into injection machine, and injection machine is fed injection into mould, after natural cooling shaping The interior tube layer of tubulose is obtained, it is standby.
5)By step 4)Tube layer is processed using lathe turning in gained so that spiral groove is formed on the outside of interior tube layer, i.e., Can.
Beneficial effects of the present invention are:The polyurethane foam of setting has heat insulation effect, and the quartz sand layer of setting has Good flameproof effect;The interior tube layer set keeps corrosion-resistant for polyethylene layer, and service life is long;The fixed cover of setting keeps peace Dress is convenient;There are spring and fixing bolt holding structure compact on the baffle plate of setting, stability is high, possess on the outside of the interior tube layer of use Spiral groove, so spreading glue can be arranged in pipeline on the outside of interior tube layer, and the material of use is corrosion-resistant, service life It is long.
Brief description of the drawings
Fig. 1 is a kind of structure chart of construction drainage pipeline of the invention.
Embodiment
Embodiment 1
As shown in figure 1, a kind of construction drainage pipeline, including interior tube layer 1, polyurethane foam 2, quartz sand layer 3 and outer Tube layer 4, said inner tube layer 1, polyurethane foam 2, quartz sand layer 3 and external tube layer 4 are set from the inside to the outside successively, and described is outer tube Layer 4 is stainless steel layer, and the outside of said inner tube layer 1 is provided with support bar 5, the support bar 5 respectively with interior tube layer 1 and external tube layer 4 It is fixedly connected, the support bar 5 is provided with three, and the outside of external tube layer 4 is provided with fixed cover 6, and the side of fixed cover 6 is set Baffle plate 7, the baffle plate 7 is integrally formed setting with fixed cover 6.
The thickness of polyurethane foam 2 is 8mm.
The inner side of baffle plate 7 is provided with spring 8.
The middle part of baffle plate 7 is provided with fixing bolt 9.
Said inner tube 1 thickness of layer is 5mm.
A kind of construction drainage pipeline, said inner tube layer is made up by mass fraction proportioning of following material:Styrene - 23 parts of acrylonitrile copolymer, 5 parts of aluminium powder, 2-5 parts of silane coupler, 6 parts of castor bean wax, 7 parts of PA polybutyleneterephthalate, cloud 12 parts of female powder, 6 parts of dimethicone, 7 parts of phthalic acid ester, 2 parts of phosphite, 5 parts of sulfydryl acid esters, triethoxysilane 3 Part, 12 parts of rosin modified phenolic resin, 16 parts of polyvinyl acetate, 7 parts of carboxylic styrene butadiene latex, 15 parts of styrene-acrylic emulsion, citric acid 3 2 parts of part and activated carbon.
The preparation method of said inner tube layer comprises the following steps:
1)By styrene-it is 23 parts of acrylonitrile copolymer, 5 parts of aluminium powder, 2-5 parts of silane coupler, 6 parts of castor bean wax, poly- to benzene two 7 parts of butyl formate, 12 parts of mica powder, 6 parts of dimethicone, 7 parts of phthalic acid ester, 2 parts of phosphite, 5 parts of sulfydryl acid esters, 3 parts of triethoxysilane, 12 parts of rosin modified phenolic resin, 16 parts of polyvinyl acetate, 7 parts of carboxylic styrene butadiene latex, phenylpropyl alcohol breast 2 parts of 15 parts of liquid, 3 parts of citric acid and activated carbon are put into mixer, and regulation rotating speed is 3600-3800r/min, 6-11 points of reaction Clock, it is standby;
2)By step 1)Gained raw material is put into autoclave, and regulation temperature is 78 DEG C, and regulation air pressure is 12 times of atmospheric pressure, reaction It is 7-15 minutes, standby;
3)By step 2)Gained raw material is put into banbury, and regulation temperature is 220-245 DEG C, is in molten by raw material heating State, it is standby;
4)By step 3)Gained raw material is put into injection machine, and injection machine is fed injection into mould, after natural cooling shaping The interior tube layer of tubulose is obtained, it is standby.
5)By step 4)Tube layer is processed using lathe turning in gained so that spiral groove is formed on the outside of interior tube layer, i.e., Can.
Embodiment 2
As shown in figure 1, a kind of construction drainage pipeline, including interior tube layer 1, polyurethane foam 2, quartz sand layer 3 and outer Tube layer 4, said inner tube layer 1, polyurethane foam 2, quartz sand layer 3 and external tube layer 4 are set from the inside to the outside successively, and described is outer tube Layer 4 is stainless steel layer, and the outside of said inner tube layer 1 is provided with support bar 5, the support bar 5 respectively with interior tube layer 1 and external tube layer 4 It is fixedly connected, the support bar 5 is provided with three, and the outside of external tube layer 4 is provided with fixed cover 6, and the side of fixed cover 6 is set Baffle plate 7, the baffle plate 7 is integrally formed setting with fixed cover 6.
The thickness of polyurethane foam 2 is 8mm.
The inner side of baffle plate 7 is provided with spring 8.
The middle part of baffle plate 7 is provided with fixing bolt 9.
Said inner tube 1 thickness of layer is 5mm.
A kind of construction drainage pipeline, said inner tube layer is made up by mass fraction proportioning of following material:Styrene - 25.5 parts of acrylonitrile copolymer, 6.5 parts of aluminium powder, 3.5 parts of silane coupler, 7 parts of castor bean wax, PA polybutyleneterephthalate 8.5 parts, 13 parts of mica powder, 7 parts of dimethicone, 8.5 parts of phthalic acid ester, 3 parts of phosphite, 7.5 parts of sulfydryl acid esters, three 5.5 parts of Ethoxysilane, 13.5 parts of rosin modified phenolic resin, 18 parts of polyvinyl acetate, 7.5 parts of carboxylic styrene butadiene latex, benzene 2-5 parts of 17.5 parts of acrylic emulsion, 6 parts of citric acid and activated carbon.
The preparation method of said inner tube layer comprises the following steps:
1)By styrene -25.5 parts of acrylonitrile copolymer, 6.5 parts of aluminium powder, 3.5 parts of silane coupler, 7 parts of castor bean wax, poly- pair 8.5 parts of butyl phthalate, 13 parts of mica powder, 7 parts of dimethicone, 8.5 parts of phthalic acid ester, 3 parts of phosphite, sulfydryl 7.5 parts of acid esters, 5.5 parts of triethoxysilane, 13.5 parts of rosin modified phenolic resin, 18 parts of polyvinyl acetate, Carboxy 2-5 parts of 7.5 parts of latex, 17.5 parts of styrene-acrylic emulsion, 6 parts of citric acid and activated carbon are put into mixer, and regulation rotating speed is 3600- 3800r/min, reacts 6-11 minutes, standby;
2)By step 1)Gained raw material is put into autoclave, and regulation temperature is 78 DEG C, and regulation air pressure is 12 times of atmospheric pressure, reaction It is 7-15 minutes, standby;
3)By step 2)Gained raw material is put into banbury, and regulation temperature is 220-245 DEG C, is in molten by raw material heating State, it is standby;
4)By step 3)Gained raw material is put into injection machine, and injection machine is fed injection into mould, after natural cooling shaping The interior tube layer of tubulose is obtained, it is standby.
5)By step 4)Tube layer is processed using lathe turning in gained so that spiral groove is formed on the outside of interior tube layer, i.e., Can.
Embodiment 3
As shown in figure 1, a kind of construction drainage pipeline, including interior tube layer 1, polyurethane foam 2, quartz sand layer 3 and outer Tube layer 4, said inner tube layer 1, polyurethane foam 2, quartz sand layer 3 and external tube layer 4 are set from the inside to the outside successively, and described is outer tube Layer 4 is stainless steel layer, and the outside of said inner tube layer 1 is provided with support bar 5, the support bar 5 respectively with interior tube layer 1 and external tube layer 4 It is fixedly connected, the support bar 5 is provided with three, and the outside of external tube layer 4 is provided with fixed cover 6, and the side of fixed cover 6 is set Baffle plate 7, the baffle plate 7 is integrally formed setting with fixed cover 6.
The thickness of polyurethane foam 2 is 8mm.
The inner side of baffle plate 7 is provided with spring 8.
The middle part of baffle plate 7 is provided with fixing bolt 9.
Said inner tube 1 thickness of layer is 5mm.
A kind of construction drainage pipeline, said inner tube layer is made up by mass fraction proportioning of following material:Styrene - 28 parts of acrylonitrile copolymer, 8 parts of aluminium powder, silane coupled 5 parts, 8 parts of castor bean wax, 10 parts of PA polybutyleneterephthalate, mica 14 parts of powder, 8 parts of dimethicone, 10 parts of phthalic acid ester, 4 parts of phosphite, 10 parts of sulfydryl acid esters, triethoxysilane 8 Part, 15 parts of rosin modified phenolic resin, 20 parts of polyvinyl acetate, 8 parts of carboxylic styrene butadiene latex, 20 parts of styrene-acrylic emulsion, citric acid 9 5 parts of part and activated carbon.
The preparation method of said inner tube layer comprises the following steps:
1)By styrene -28 parts of acrylonitrile copolymer, 8 parts of aluminium powder, silane coupled 5 parts, 8 parts of castor bean wax, poly terephthalic acid 10 parts of butyl ester, 14 parts of mica powder, 8 parts of dimethicone, 10 parts of phthalic acid ester, 4 parts of phosphite, 10 parts of sulfydryl acid esters, 8 parts of triethoxysilane, 15 parts of rosin modified phenolic resin, 20 parts of polyvinyl acetate, 8 parts of carboxylic styrene butadiene latex, phenylpropyl alcohol breast 5 parts of 20 parts of liquid, 9 parts of citric acid and activated carbon are put into mixer, and regulation rotating speed is 3600-3800r/min, 6-11 points of reaction Clock, it is standby;
2)By step 1)Gained raw material is put into autoclave, and regulation temperature is 78 DEG C, and regulation air pressure is 12 times of atmospheric pressure, reaction It is 7-15 minutes, standby;
3)By step 2)Gained raw material is put into banbury, and regulation temperature is 220-245 DEG C, is in molten by raw material heating State, it is standby;
4)By step 3)Gained raw material is put into injection machine, and injection machine is fed injection into mould, after natural cooling shaping The interior tube layer of tubulose is obtained, it is standby.
5)By step 4)Tube layer is processed using lathe turning in gained so that spiral groove is formed on the outside of interior tube layer, i.e., Can.
Experimental example
Experimental subjects:The inner tube layer material for choosing common pipe material, special pipeline material and the present invention carries out test comparison.
Requirement of experiment:The inner tube layer material of common pipe material, special pipeline material and the present invention is used into identical faces Product and thickness are detected.
Standard is detected;Tensile strength is detected using GBT228-2002 methods.Experimental method:To pipeline material Anticorrosive detection is carried out, is detected by corrosion test chamber, and it is 120 DEG C to adjust test temperature temperature, and relative humidity is 85%, air pressure is 106kPa, and ozone concentration is 45%, and ultraviolet illumination intensity is 25uw/cm2, obtains etching time;Flame retardant effect Pass through GB/T 31420-2015
Detect data such as following table:
With reference to upper table, the data of different pipeline materials gained under identical experimental method, interior tube layer material of the invention are contrasted Expect that structural strength is higher, more preferably, anticorrosion effect is more preferable for flame retardant effect.
Beneficial effects of the present invention are:The polyurethane foam of setting has heat insulation effect, and the quartz sand layer of setting has Good flameproof effect;The interior tube layer set keeps corrosion-resistant for polyethylene layer, and service life is long;The fixed cover of setting keeps peace Dress is convenient;There are spring and fixing bolt holding structure compact on the baffle plate of setting, stability is high, possess on the outside of the interior tube layer of use Spiral groove, so spreading glue can be arranged in pipeline on the outside of interior tube layer, and the material of use is corrosion-resistant, service life It is long.
The foregoing is only a specific embodiment of the invention, but protection scope of the present invention is not limited thereto, any The change or replacement expected without creative work, should all be included within the scope of the present invention.

Claims (7)

1. a kind of construction drainage pipeline, it is characterised in that:Including interior tube layer, polyurethane foam, quartz sand layer and outer Tube layer, said inner tube layer, polyurethane foam, quartz sand layer and external tube layer are set from the inside to the outside successively, and described is that external tube layer is Stainless steel layer, said inner tube layer outside is provided with support bar, and the support bar is fixedly connected with interior tube layer and external tube layer respectively, institute Support bar is stated provided with three, fixed cover is provided with the outside of the external tube layer, the fixed cover side sets baffle plate, the baffle plate with Fixed cover is integrally formed setting.
2. construction drainage pipeline according to claim 1, it is characterised in that:The polyurethane foam thickness is 8mm。
3. construction drainage pipeline according to claim 1, it is characterised in that:Bullet is installed on the inside of the baffle plate Spring.
4. construction drainage pipeline according to claim 1, it is characterised in that:Fixation is installed in the middle part of the baffle plate Bolt.
5. construction drainage pipeline according to claim 1, it is characterised in that:Said inner tube thickness degree is 5mm.
6. a kind of construction drainage pipeline, it is characterised in that:Said inner tube layer is by mass fraction proportioning by following material system Into:It is 23-28 parts of styrene-acrylonitrile copolymer, 5-8 parts of aluminium powder, 2-5 parts of silane coupler, 6-8 parts of castor bean wax, poly- to benzene 7-10 parts of diformazan acid butyl ester, 12-14 parts of mica powder, 6-8 parts of dimethicone, 7-10 parts of phthalic acid ester, phosphite 2-4 Part, 5-10 parts of sulfydryl acid esters, 3-8 parts of triethoxysilane, 12-15 parts of rosin modified phenolic resin, polyvinyl acetate 16-20 Part, 7-8 parts of carboxylic styrene butadiene latex, 15-20 parts of styrene-acrylic emulsion, 3-9 parts of citric acid and 2-5 parts of activated carbon.
7. construction drainage pipeline according to claim 6, it is characterised in that:The preparation method bag of said inner tube layer Include following steps:
1)By styrene -23-28 parts of acrylonitrile copolymer, 5-8 parts of aluminium powder, 2-5 parts of silane coupler, 6-8 parts of castor bean wax, 7-10 parts of PA polybutyleneterephthalate, 12-14 parts of mica powder, 6-8 parts of dimethicone, 7-10 parts of phthalic acid ester, phosphorous 2-4 parts of hydrochlorate, 5-10 parts of sulfydryl acid esters, 3-8 parts of triethoxysilane, 12-15 parts of rosin modified phenolic resin, polyvinyl acetate 2-5 parts of 16-20 parts of ester, 7-8 parts of carboxylic styrene butadiene latex, 15-20 parts of styrene-acrylic emulsion, 3-9 parts of citric acid and activated carbon are put into and stirred Mix in machine, regulation rotating speed is 3600-3800r/min, is reacted 6-11 minutes, standby;
2)By step 1)Gained raw material is put into autoclave, and regulation temperature is 78 DEG C, and regulation air pressure is 12 times of atmospheric pressure, reaction It is 7-15 minutes, standby;
3)By step 2)Gained raw material is put into banbury, and regulation temperature is 220-245 DEG C, is in molten by raw material heating State, it is standby;
4)By step 3)Gained raw material is put into injection machine, and injection machine is fed injection into mould, after natural cooling shaping The interior tube layer of tubulose is obtained, it is standby;
5)By step 4)Tube layer is processed using lathe turning in gained so that spiral groove is formed on the outside of interior tube layer, you can.
CN201710691524.3A 2017-08-14 2017-08-14 A kind of construction drainage pipeline Pending CN107314161A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710691524.3A CN107314161A (en) 2017-08-14 2017-08-14 A kind of construction drainage pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710691524.3A CN107314161A (en) 2017-08-14 2017-08-14 A kind of construction drainage pipeline

Publications (1)

Publication Number Publication Date
CN107314161A true CN107314161A (en) 2017-11-03

Family

ID=60175582

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710691524.3A Pending CN107314161A (en) 2017-08-14 2017-08-14 A kind of construction drainage pipeline

Country Status (1)

Country Link
CN (1) CN107314161A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112851244A (en) * 2021-01-26 2021-05-28 江西龙正科技发展有限公司 Novel ultra-high performance concrete UHPC water pipe

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3711351A1 (en) * 1987-04-03 1988-10-20 Steinbeisser Ing Georg Ready-insulated long-distance pipeline
DE102006056645B4 (en) * 2006-11-30 2008-11-13 Ffa Automotive Ag Protective device for cables and the like
CN203248980U (en) * 2013-03-11 2013-10-23 河北宝硕管材有限公司 PVC pipe fitting
CN204756192U (en) * 2015-07-20 2015-11-11 临沂金豪管业科技有限公司 Compound steel pipes
CN204922247U (en) * 2015-07-31 2015-12-30 北京建筑大学 Municipal drain pipe of easily connecting
CN204986071U (en) * 2015-10-08 2016-01-20 新疆绿赛节水科技开发有限公司 High strength feedwater is with polyethylene PE tubular product
CN205118574U (en) * 2015-11-11 2016-03-30 吉林杰瑞石油装备科技有限公司 A insulating tube for geothermal well
CN106280080A (en) * 2016-08-08 2017-01-04 陶如意 A kind of fire-retardant low free chlorine PVC pipeline and preparation method thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3711351A1 (en) * 1987-04-03 1988-10-20 Steinbeisser Ing Georg Ready-insulated long-distance pipeline
DE102006056645B4 (en) * 2006-11-30 2008-11-13 Ffa Automotive Ag Protective device for cables and the like
CN203248980U (en) * 2013-03-11 2013-10-23 河北宝硕管材有限公司 PVC pipe fitting
CN204756192U (en) * 2015-07-20 2015-11-11 临沂金豪管业科技有限公司 Compound steel pipes
CN204922247U (en) * 2015-07-31 2015-12-30 北京建筑大学 Municipal drain pipe of easily connecting
CN204986071U (en) * 2015-10-08 2016-01-20 新疆绿赛节水科技开发有限公司 High strength feedwater is with polyethylene PE tubular product
CN205118574U (en) * 2015-11-11 2016-03-30 吉林杰瑞石油装备科技有限公司 A insulating tube for geothermal well
CN106280080A (en) * 2016-08-08 2017-01-04 陶如意 A kind of fire-retardant low free chlorine PVC pipeline and preparation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112851244A (en) * 2021-01-26 2021-05-28 江西龙正科技发展有限公司 Novel ultra-high performance concrete UHPC water pipe

Similar Documents

Publication Publication Date Title
CN106368312A (en) Modular house
CN107314161A (en) A kind of construction drainage pipeline
CN206189685U (en) Integrated floor of modularization and house
CN109404608A (en) Water supply thin-walled stainless steel tube cartridge connection construction
CN206514071U (en) A kind of pipeline
CN204282460U (en) A kind of socket H pipe
CN201681683U (en) Glass fiber reinforced plastic optical cable protection sleeve
CN201443800U (en) Gripped pipe type heating board
CN204282865U (en) A kind of multifunctional support overhead device
CN204691176U (en) A kind of kitchen and toilet bag standpipe access hole structure
CN102661075A (en) Sectional chimney with single-barrel concrete structure and method for manufacturing sectional chimney
CN102277938A (en) Culture stone plate and construction method for dry-hanging same
CN106247608A (en) A kind of anticorrosion air-conditioner mounting rack
CN202627626U (en) Sectional-type single-barrel chimney with concrete structure
CN206530771U (en) Detachable large-scale upstanding tube support meanss
WO2011096679A3 (en) Heating structure
CN101818558B (en) Industrial factory building pipe shaft and installing method thereof
CN204492107U (en) Prefabricated flue Connection Block
CN212801925U (en) Electromechanical device installation reverse construction method construction structure based on BIM pipeline comprehensive technology
CN205716078U (en) Special reducing pipe
CN201764194U (en) Multifunctional telescoping energy dissipating device
CN209169866U (en) Deep basal pit faces the interim pipeline layout arranging system in side
CN202734020U (en) Indoor comfortable floor heating radiator
CN207230021U (en) A kind of building pipe
CN207740610U (en) A kind of anticorrosion steam conveying pipe being easily installed

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171103