CN107313446A - A kind of city integrated piping lane construction vehicles combination formula internal model - Google Patents

A kind of city integrated piping lane construction vehicles combination formula internal model Download PDF

Info

Publication number
CN107313446A
CN107313446A CN201610266237.3A CN201610266237A CN107313446A CN 107313446 A CN107313446 A CN 107313446A CN 201610266237 A CN201610266237 A CN 201610266237A CN 107313446 A CN107313446 A CN 107313446A
Authority
CN
China
Prior art keywords
backform
side form
vehicle frame
piping lane
internal model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610266237.3A
Other languages
Chinese (zh)
Inventor
尤兆云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610266237.3A priority Critical patent/CN107313446A/en
Publication of CN107313446A publication Critical patent/CN107313446A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold

Abstract

The invention discloses a kind of city integrated piping lane construction vehicles combination formula internal model, including side form, backform, vehicle frame and telescopic component, the side form is arranged at the vehicle frame both sides, the backform is set up in above side form described in both sides, and the telescopic component is arranged on the vehicle frame and connects the side form and the backform.By the way that vehicle frame directly is fixed on into construction location, assembled side form and backform are carried out further according to the scale and size to be built pipe gallery, specifically supported by telescopic component, assembled outer mold outside it, concrete is directly injected between interior cavity mould and outside mould in space, pour and be shaped to pipe gallery, mould stretching operation, has the advantages that relatively easy, easy to operate structure, group mould precision height, steady quality, the construction period is short, operating expenses is low, the construction infection phase is short and production efficiency is high.

Description

A kind of city integrated piping lane construction vehicles combination formula internal model
Technical field
The present invention relates to pipe gallery technical field of construction, more particularly to a kind of city integrated piping lane construction Construction vehicles combination formula internal model.
Background technology
At present, the communal facility such as electric power, communication, water and heat provision, combustion gas, for a long time directly it is buried or Ditch poling is individually built, due to a lack of unified planning design, causes all kinds of pipelines to interlock layout, each supervisor is each For political affairs, meanwhile, made troubles to dilatation and maintenance.Frequently " road slide fastener " gives urban transportation every year Made troubles with people's lives, " sea is seen in city " is even more the safety that threaten people people and property.
City integrated piping lane construction is in the starting stage, and construction technology is conventional method, and formwork still uses pin Hand cradle and wood glue plate mode, formwork error are big, quality control difficulties, the material consumption such as wood glue plate scrapped Amount is big, and ambient influnence is big, long construction period, and cost of labor is high, and engineering cost is big, and traffic impact is big.
The content of the invention
The present invention is completed to solve of the prior art not enough, and it is an object of the invention to provide one kind City integrated piping lane construction vehicles combination formula internal model, passes through the inner chamber designed by interior cavity mould itself Telescopic component, realizes that mould stretches, with structure is relatively easy, easy to operate, group mould precision is high, matter Amount is stable, the construction period is short, operating expenses is low, short construction infection phase and the advantages of high production efficiency.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, including side form, top Mould, vehicle frame and telescopic component, the side form are respectively arranged at the vehicle frame both sides, and the backform is set up in Above side form described in both sides, the side of backform two is connected with the side form top movable, described flexible group Part is arranged on the vehicle frame and is all connected with the side form with the backform.
A kind of city integrated piping lane construction mould vehicles combination formula internal model of the present invention can also be:It is described to stretch Contracting component include side form telescopic component, the side form telescopic component include positive and negative silk leading screw, side form bracket and Leading screw location-plate, the side form is arranged on the side form bracket, the positive and negative silk leading screw end with it is described Side form bracket is hinged the flexible connection of nut position, and the positive and negative silk feed screw nut rotation is located at the side form bracket In, the positive and negative silk leading screw is movably set on the vehicle frame by the way that the leading screw location-plate is spacing.
The telescopic component, which includes vehicle frame lifting assembly, the vehicle frame lifting assembly, includes vehicle frame adjustment backing plate With axletree link, the axletree link is arranged at below the vehicle frame, and the axletree link is set At the two ends of wheel shaft, the vehicle frame adjustment backing plate is arranged under the axletree link and the vehicle frame Between surface.
Side form bracket adjustment backing plate is provided between the side form bracket and the vehicle frame.
The telescopic component also include backform telescopic component, the backform telescopic component include backform strut, Fore-set, lowering or hoisting gear and strut guide pin bushing are adjusted, described lowering or hoisting gear one end is fixed on the vehicle frame, institute State adjustment fore-set and be arranged at the lowering or hoisting gear upper end, the backform strut is set in the strut guide pin bushing Interior, the backform strut bottom is arranged at the adjustment fore-set top, and the strut guide pin bushing is fixed on described On vehicle frame.
The telescopic component also includes STATEMENT OF FEDERALLY SPONSORED, and the STATEMENT OF FEDERALLY SPONSORED includes backform pull bar, the backform pull bar Two ends are hinged with the backform and the corner template respectively.
The side form also includes being used for the second adjustment template for adjusting the side form specification, second adjustment Template-setup is between the Side shuttering and corner template.
The telescopic component is provided with slide rule and/or scale, the vehicle frame and is carved with scale.
The frame downward is provided with running gear.
The running gear includes wheel and wheel stand, and the wheel is arranged on described by wheel stand Frame downward.
The Auxiliary support leading screw is arranged on the frame downward, the Auxiliary support leading screw top and vehicle frame Connection, the Auxiliary support leading screw bottom can release formula with ground and offset.
Being provided with the middle part of the backform is used for the first adjustment template for adjusting backform specification.
On the inner surface of the side form and backform, vibrator is equipped with.
A kind of city integrated piping lane construction vehicles combination formula internal model of the offer of the present invention, including side Mould, backform, vehicle frame and telescopic component, the side form are arranged at the vehicle frame both sides, and the backform is set up Above side form described in both sides, the telescopic component is arranged on the vehicle frame and connects the side form and institute State backform.By the way that vehicle frame directly is fixed on into construction location, further according to the scale to be built pipe gallery Assembled side form and backform are carried out with size, is particularly fixed backform with side form, it is by flexible group Part is supported, and in its outer assembled outer mold, concrete is directly injected into inner chamber by direct pouring synthetic piping lane Between mould and outside mould in space, pipe gallery, mould stretching operation, with structure phase are shaped to To being simple and convenient to operate, organizing mould precision height, steady quality, the construction period is short, operating expenses is low, apply The advantages of work influences short phase and high production efficiency.
Brief description of the drawings
Fig. 1 is the entirety of the city integrated piping lane construction vehicles combination formula internal model of the embodiment of the present invention Structural representation;
Fig. 2 is the main view of the city integrated piping lane construction vehicles combination formula internal model of the embodiment of the present invention Figure;
Fig. 3 is the city integrated piping lane construction vehicles combination formula internal model vehicle frame knot of the embodiment of the present invention Structure is illustrated;
Fig. 4 is that the city integrated piping lane construction vehicles combination formula internal model of the embodiment of the present invention is locally thin Save schematic diagram;
Fig. 5 is the city integrated piping lane construction vehicles combination formula internal model sectional view of the embodiment of the present invention;
Fig. 6 is the vehicles combination formula inner membrance walking dress of the city integrated piping lane construction mould of the embodiment of the present invention Put structural representation;
In figure:1:Vehicle frame;2:Backform;3:Side form basic templates;4:Second adjustment template;5: Wheel;6:Backform pull bar;7:Backform strut;8:Adjust fore-set;9:Positive and negative silk leading screw;10:Rise Falling unit;11:Leading screw location-plate;12:Wheel stand;13:Strut guide pin bushing;14:Axletree link; 15:Auxiliary support leading screw;16:Vehicle frame adjusts backing plate;17:Side form bracket;18:Side form bracket is adjusted Backing plate;19:First adjustment template;20:Corner template;36:Side form.
Embodiment
With reference to the accompanying drawings and examples to a kind of city integrated piping lane construction vehicle group of the present invention The embodiment of box-like internal model is described in further detail.Following examples are used to illustrate the present invention, But it is not limited to the scope of the present invention.
As shown in figures 1 to 6, a kind of city integrated piping lane construction vehicles combination of offer of the invention Formula internal model, including side form 36, backform 2, vehicle frame 1 and telescopic component, the side form 36 are arranged at institute The both sides of vehicle frame 1 are stated, the backform 2 is set up in the top of side form 36 described in both sides, and the telescopic component is set It is placed on the vehicle frame 1 and connects the side form 36 and the backform 2.By the way that directly vehicle frame 1 is consolidated Due to construction location, assembled side form 36 and backform 2 are carried out further according to the scale to be built pipe gallery, When flexible, telescopic component drives side form 36 and backform 2 inwardly to bounce back, and makes itself and casting concrete point From completion telescopic process, matched moulds process is opposite with above-mentioned steps.By the way that vehicle frame directly is fixed on into construction Position, carries out assembled side form and backform, specifically further according to the scale and size to be built pipe gallery It is to fix backform with side form, it is supported by telescopic component, assembled outer mold outside it, directly Pouring synthetic piping lane, concrete is directly injected between interior cavity mould and outside mould in space, is shaped to Pipe gallery, mould stretching operation, with structure is relatively easy, easy to operate, group mould precision is high, matter Amount is stable, the construction period is short, operating expenses is low, short construction infection phase and the advantages of high production efficiency.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The telescopic component is flexible including side form Component, the side form telescopic component includes positive and negative silk leading screw 9, side form bracket 17 and leading screw location-plate 11, The side form bracket 17 is arranged in the side form basic templates 3, the positive and negative end of silk leading screw 9 with The articulated section of side form bracket 17 is flexibly connected, and the positive and negative silk leading screw 9 is located at by being hinged nut rotation In the side form bracket 17, the positive and negative silk leading screw 9 is set by the spacing activity of the leading screw location-plate 11 It is placed on the vehicle frame 1.So, can be specifically that described one end of side form bracket 17 is vertically fixed on institute State in side form basic templates 3, the other end is connected with leading screw 9, and the end center at its articulated position Position, which is provided with, is hinged nut, and the nut that is hinged is set on the positive and negative silk leading screw 9, described positive and negative Silk leading screw 9 centre position is welded with nut, and when mould is flexible, rotation nut drives positive and negative silk leading screw 9 Rotation, due to being positive and negative silk leading screw 9, and rotation is located at the nut that is hinged at the positive and negative two ends of silk leading screw 9 and is Cooperate and set, when rotating positive and negative silk leading screw 9, being hinged nut can be while be inwardly indented or or outside Uphold, be hinged nut and drive the side form bracket 17 to move, complete flexible or de- matched moulds, so according to The connected mode of the telescopic component of side form 36, can make the side form 36 of both sides while being shunk to inner side, complete side The demoulding of mould 36;The matched moulds process and said procedure of side form 36 are opposite.
Positive and negative silk screw mandrel 9 can also be:Centre is radial more than one piece sleeve pipe middle node, and the left and right sides Left-handed leading screw and dextrorotation screw mandrel pin connection is worn by auricle.In the sleeve pipe that middle node is filled in by reinforcing bar, Prize positive and negative silk screw mandrel rotation.
Positive and negative silk screw mandrel 9 can also be:The left-handed leading screw and dextrorotation screw mandrel of the left and right sides are respectively welded method Orchid, left-handed screw mandrel and dextrorotation screw mandrel connect integral by flange.By prizing connecting bolt, make positive and negative Silk screw mandrel rotation.The present invention takes off for guarantee both sides side form 36, the synchronism of matched moulds distance, described positive and negative Silk leading screw 9 is positioned by positive and negative silk leading screw location-plate 11, and the positive and negative silk leading screw 9 passes through positive and negative silk silk Thick stick location-plate 11 is fixed on the vehicle frame 1.Can be specifically, it is front and rear on the sill of vehicle frame 1 Two pieces of positive and negative silk leading screw location-plates 11 are welded with, the positive and negative silk leading screw location-plate 11 is U-shape structure, The positive and negative silk leading screw 9 is fastened in the U-type groove of the positive and negative silk leading screw location-plate 11, to limit just The anti-position of silk leading screw 9, prevents the play of positive and negative silk leading screw 9 or so, so as to ensure that both sides side form 36 is received Contracting is consistent with matched moulds distance.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The side form bracket 17 and the branch Side form bracket adjustment backing plate 18 is provided between frame.The side form bracket adjustment backing plate 18 is staged knot Structure, and side form bracket adjustment backing plate 18 passes through roller slidable connection, the adjustment of side form bracket with vehicle frame 1 The ladder intersection of backing plate 18 is designed as overbank section, so that what side form bracket 17 can be stablized Mobile and reduction resistance, the minimum and highest stepped locations for adjusting backing plate 18 in side form side form bracket are set There is bulge-structure, carried out for the retracted position of offside die shoe frame 17 spacing, side form bracket 17 is to contract When, the location following side form bracket 17 1 of adjustment side form 36 changes, and when side form side form bracket is adjusted When whole backing plate 18 is moved to minimum stepped locations, side form 36 is inwardly retracted to maximum position and can be downward The segment distance of displacement one, more convenient for the contraction of backform 2.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The telescopic component is lifted including vehicle frame Telescopic component, the vehicle frame lifts retraction assemblies, including vehicle frame adjustment backing plate 16 and axletree link 14, The axletree link 14 is arranged at the lower section of vehicle frame 1, and the axletree link 14 is arranged on wheel The two ends of axletree, the vehicle frame adjustment backing plate 16 is arranged at the axletree link 14 and the vehicle frame 1 Between lower surface.So setting up axletree link 14 facilitates the position of vehicle frame adjustment backing plate 16 to fix, and leads to Cross and increase or decrease the quantity of vehicle frame adjustment backing plate 16 to adjust the overall high of this vehicle assembly type internal model Degree, makes its group of mould reduce error, and it is more accurate to position.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The telescopic component is adjusted including vehicle frame Backing plate 16 and wheel bearing 12 are connected, and the wheel bearing 12 is arranged at the lower section of vehicle frame 1, institute State vehicle frame adjustment backing plate 16 to be arranged between vehicle frame 12 and axletree 43, adjusted by increasing or decreasing vehicle frame The quantity and thickness of whole backing plate 16 adjusts the whole height of this vehicle assembly type internal model.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The telescopic component is also stretched including backform Contracting component, the telescopic component of backform 2 include backform strut 7, adjustment fore-set 8, lowering or hoisting gear 10 and Strut guide pin bushing 13, the lowering or hoisting gear 10 is fixedly installed on the vehicle frame 1, the adjustment fore-set 8 Installed in the upper end of lowering or hoisting gear 10, the backform strut 7 is set in the strut guide pin bushing 13, The bottom of backform strut 7 is arranged at adjustment fore-set 8 top, and the strut guide pin bushing 13 is fixed on On the vehicle frame 1.So, the liftout attachment of lowering or hoisting gear 10 is ramped up or to decline, drives adjustment Fore-set 8 rises or falls so that backform strut 7 rises or falls, it is final drive backform 2 rise or under Drop, and during backform strut 7 rises or falls, strut guide pin bushing 13 ensures that backform strut 7 is transported Row ensures that vertically it plays guide effect.When backform strut 7 rises or is reduced to certain altitude, Then backform is risen or fallen to precalculated position, completes backform matched moulds or the demoulding.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The retraction assemblies also include STATEMENT OF FEDERALLY SPONSORED, Affiliated STATEMENT OF FEDERALLY SPONSORED includes backform pull bar 6, the two ends of backform pull bar 6 respectively with the backform 2 and described Corner template 20 is hinged.The corner template 20 is arranged on the side form 36 and the transition of backform 2 Position, has linkage effect when the demoulding and matched moulds, when mold releasability, and the side form 36 is first inwardly received Contracting, when being retracted to certain position, the retracted downward of backform 2, when backform 2 is in contraction process, Because backform pull bar 6 is hinged the backform 2 and the corner template 20, the related angle of the athletic meeting of backform 2 Portion's template 20 is together inside contracted, and the top of side form 36 is shunk, and during 36 matched moulds of side form, motion process is opposite. By adding corner template 20 so that the structure of mould is more flexible, when the demoulding and matched moulds more Plus it is quick and easy.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The side form 36 also includes second and adjusted Mould preparation plate 4, the second adjustment template 4 be arranged on the side basic templates and corner template 20 it Between.Side form 36 is made up of side form basic templates and the second adjustment template 4, and three is by passing through adpting flange Face bolt connection, according to pipe gallery different height requirement, change adjustment different height second adjustment Template 4.Corner template 20 is provided with otic placode structure with backform 2 with the connecting portion of backform pull bar 6.In side On die shoe frame 17, the nut that is hinged that can be rotated freely, the positive and negative two ends of silk leading screw 9 point are each installed The nut that is hinged not with both sides is screwed, and passes through dextrorotation or left-handed positive and negative silk leading screw 9, you can change both sides side The distance of mould 36.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The telescopic component provided with slide rule and Scale is carved with/or scale, the vehicle frame.To ensure the operating accuracy of this mould, the telescopic component On be provided with slide rule, the support and be carved with scale.With keep each telescopic component adjustable height unification and Required precision.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1 to Fig. 6 It is described, it can also be on the basis of previously described technical scheme:The frame downward is filled provided with walking Put.So, lead to after the completion of current workshop section constructs, it is necessary to vehicle frame 1 is moved into next construction location The running gear is crossed, vehicle frame 1 directly can be moved to next station, operating efficiency is greatly improved, Also substantial amounts of man power and material is saved, it is cost-effective.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1 to Fig. 6 It is shown, it can also be on the basis of previously described technical scheme:The running gear include wheel 5, Wheel stand 12, the wheel 5 is arranged on the frame downward by wheel stand 12.
The wheel 5 can be steel wheel, and the wheel 5 is rotatably connected in the wheel stand On 12, and then wheel 5 is rotatably mounted to the bottom of vehicle frame 1, vehicle frame 1 relies on wheel 5 in steel The positioning of predetermined work position is moved and reached on rail track, after one section of construction section completion, is prolonged before spreading Assembly type rail, under drive device or external force traction, runs to next station.
The wheel 5 can also be plastic wheel or rubber wheel.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes State, can also be on the basis of previously described technical scheme:Side form 36 passes through support-side die shoe frame The nut that is hinged on 17 supports, positive and negative the silk leading screw 9 and side form bracket 17 is screwed, and rotates positive and negative silk During leading screw 9, the nut that is hinged that both sides are fixed in side form bracket 17 can be simultaneously to positive and negative silk leading screw 9 Centre position or both sides movement, are fixed on inside the side form bracket 17 due to being hinged nut, are hinged spiral shell When mother is mobile, side form bracket 17 is driven to move together, side form bracket 17 is connected with side form basic templates 3, Contraction and the matched moulds of side form 36 are realized, positive and negative silk leading screw location-plate 11 is to ensure positive and negative silk leading screw 9 Axially position, it is ensured that the positional symmetry of side form 36 of the left and right sides is consistent, while the deformation of side form 36 is avoided, Lowering or hoisting gear 10 realizes the raising and lowering of backform 2 by adjusting fore-set 8 and backform strut 7, relies on Horizontal direction position when the positioning backform 2 of strut guide pin bushing 13 is lifted in matched moulds and knockout course is kept not Become.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The Auxiliary support leading screw 15 is set In the frame downward, the top of Auxiliary support leading screw 15 is connected with vehicle frame 1, the Auxiliary support The bottom of leading screw 15 can release formula with ground and offset.Auxiliary support leading screw 15 is installed on the bottom girder of vehicle frame 1, So, after internal model matched moulds, rotation Auxiliary support leading screw 15 makes it painstaking, reduces crossbeam moment of flexure, After interior moulding/demoulding, Auxiliary support leading screw 15 is continued into rotation, made between wheel 5 and rail vacantly, Now unscrew the connecting bolt between vehicle frame 1 and axletree link 14, you can vehicle frame is adjusted into backing plate 16 Remove, tighten the connecting bolt between vehicle frame 1 and axletree link 14, unscrew Auxiliary support leading screw 15, Inner chamber mold weight is set to be undertaken completely by wheel 5, the height reduction of internal model, also easily to be led by outside Draw and internal model is moved to subsequent work stations.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The middle part of backform 2, which is provided with, to be used for Adjust the first adjustment template 19 of backform specification.Backform 2 is by form surfacing, backform strut gusset and adds Strengthening tendons plate is constituted, by cottered joint wherein between backform strut gusset and backform strut, in a group mould state, The side of backform 2 and the corner mould side of the side form of side form 36 are adjacent to, and connect integral outer surface, structure Into pipe gallery inner chamber, backform 2 is divided into left half backform, right half backform and the first adjustment mould on section The part of plate 19 3, is linked by bolt.By add and subtract in the middle of backform 2 first width for adjusting template 19 and Quantity, so as to change the overall width of backform 2, meets the requirement of different cities piping lane cross-sectional width, pushes up The pin-and-hole that same backform strut 7 on mould strut gusset coordinates is wide according to the whole moulding plate series of the middle tone of backform 2 That spends and be made is porous, and according to different city integrated piping lane cross-sectional widths, centre is with addition of different in width First adjustment template 19, meanwhile, and backform strut 7 coordinate diverse location pin-and-hole.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:The steel plate of the template of the upper surface of backform 2 Working face, backform strut gusset and stiffener plate composition.Backform strut on backform strut 7 and backform 2 Connected between gusset:Contiguous block, backform strut gusset are provided between backform strut gusset and backform strut There is bolt connection between contiguous block, there is bearing pin connection between contiguous block and backform strut 7.Backform strut The row equidistant holes consistent with pitch-row on contiguous block are provided with gusset.Cut according to different city integrated piping lanes Face width, it is middle first to adjust template 19 with addition of different in width, while by backform strut gusset and Contiguous block coordinates the connection in diverse location hole.Connected between contiguous block and backform strut 7.
A kind of city integrated piping lane construction vehicles combination formula internal model of the present invention, such as Fig. 1-6 institutes Show, can also be on the basis of previously described technical scheme:On the inner surface of the side form and backform, It is equipped with vibrator.In order to effectively be stripped, on the inner surface of the side form 36 and backform 2, install There is vibrator.Vibrator is preferably electric and pneumatic vibrator, facilitates this mold releasability, improves demoulding effect Rate, so as to lift operating efficiency.
Described above is only the preferred embodiment of the present invention, it is noted that for the general of the art For logical technical staff, without departing from the technical principles of the invention, some improvement can also be made And modification, these improvement and modification also should be regarded as protection scope of the present invention.

Claims (13)

1. a kind of city integrated piping lane construction vehicles combination formula internal model, it is characterised in that:Including side form, backform, vehicle frame and telescopic component, the side form is respectively arranged at the vehicle frame both sides, the backform is set up in above side form described in both sides, the side of backform two is connected with the side form top movable, and the telescopic component is arranged on the vehicle frame and is all connected with the side form with the backform.
2. a kind of city integrated piping lane construction vehicles combination formula internal model according to claim 1, it is characterised in that:The telescopic component includes side form telescopic component, the side form telescopic component includes positive and negative silk leading screw, side form bracket and leading screw location-plate, the side form is arranged on the side form bracket, the positive and negative silk leading screw end is hinged nut position with the side form bracket and is flexibly connected, the positive and negative silk feed screw nut rotation is located in the side form bracket, and the positive and negative silk leading screw is movably set on the vehicle frame by the way that the leading screw location-plate is spacing.
3. a kind of city integrated piping lane construction vehicles combination formula internal model according to claim 2, it is characterised in that:The telescopic component includes vehicle frame lift telescopic component, the vehicle frame lift telescopic component includes vehicle frame and adjusts backing plate and axletree link, the axletree link is arranged at below the vehicle frame, the axletree link is arranged on the two ends of wheel shaft, and the vehicle frame adjustment backing plate is arranged between the axletree link and the vehicle frame lower surface.
4. a kind of city integrated piping lane construction vehicles combination formula internal model according to claim 2, it is characterised in that:Side form bracket adjustment backing plate is provided between the side form bracket and the vehicle frame.
5. a kind of city integrated piping lane construction vehicles combination formula internal model according to any one of claim 1-4 claim, it is characterised in that:The telescopic component also includes backform telescopic component, the backform telescopic component includes backform strut, adjustment fore-set, lowering or hoisting gear and strut guide pin bushing, described lowering or hoisting gear one end is fixed on the vehicle frame, the adjustment fore-set is arranged at the lowering or hoisting gear upper end, the backform strut is set in the strut guide pin bushing, the backform strut bottom is arranged at the adjustment fore-set top, and the strut guide pin bushing is fixed on the vehicle frame.
6. a kind of described city integrated piping lane construction vehicles combination formula internal model is required according to claim 5, it is characterised in that:The telescopic component STATEMENT OF FEDERALLY SPONSORED, the STATEMENT OF FEDERALLY SPONSORED also includes backform pull bar, and the backform pull bar two ends are hinged with the backform and the corner template respectively.
7. a kind of city integrated piping lane construction vehicles combination formula internal model according to claim 6, it is characterised in that:The side form also includes side form basic templates, adjusts template and corner template for adjusting the side form second of specification, and the second adjustment template-setup is between the side basic templates and the corner template.
8. a kind of city integrated piping lane construction vehicles combination formula internal model according to any one of claim 1-4 right, it is characterised in that:The telescopic component is provided with slide rule and/or scale, the vehicle frame and is carved with scale.
9. according to a kind of city integrated piping lane construction vehicles combination formula internal model described in claim 1-4 any one claim, it is characterised in that:Running gear is provided with below the vehicle frame.
10. a kind of city integrated piping lane construction vehicles combination formula internal model according to claim 9, it is characterised in that:The running gear includes wheel and wheel stand, and the wheel is arranged on the frame downward by wheel stand.
11. a kind of city integrated piping lane construction vehicles combination formula internal model according to claim 1-4, it is characterised in that:The Auxiliary support leading screw is arranged on the frame downward, and the Auxiliary support leading screw top is connected with vehicle frame, and the Auxiliary support leading screw bottom can release formula with ground and offset.
12. a kind of city integrated piping lane construction vehicles combination formula internal model according to claim 1-4 any one claims, it is characterised in that:Being provided with the middle part of the backform is used for the first adjustment template for adjusting backform specification.
13. according to a kind of city integrated piping lane construction vehicles combination formula internal model described in claim 1-4 any one claim, it is characterised in that:On the inner surface of the side form and backform, vibrator is equipped with.
CN201610266237.3A 2016-04-26 2016-04-26 A kind of city integrated piping lane construction vehicles combination formula internal model Pending CN107313446A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610266237.3A CN107313446A (en) 2016-04-26 2016-04-26 A kind of city integrated piping lane construction vehicles combination formula internal model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610266237.3A CN107313446A (en) 2016-04-26 2016-04-26 A kind of city integrated piping lane construction vehicles combination formula internal model

Publications (1)

Publication Number Publication Date
CN107313446A true CN107313446A (en) 2017-11-03

Family

ID=60185281

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610266237.3A Pending CN107313446A (en) 2016-04-26 2016-04-26 A kind of city integrated piping lane construction vehicles combination formula internal model

Country Status (1)

Country Link
CN (1) CN107313446A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108343087A (en) * 2018-04-26 2018-07-31 北京建工土木工程有限公司 A kind of the transport assembly equipment system and its construction method of prefabricated components
CN112439840A (en) * 2020-10-31 2021-03-05 深圳市铸新科技有限公司 Install fast and clear hot work product forming die

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101082280A (en) * 2007-07-18 2007-12-05 湖南中铁五新钢模有限责任公司 Single-track railway tunnel lining trolley
CN201614939U (en) * 2010-03-15 2010-10-27 中国葛洲坝集团股份有限公司 Three-dimensional space curved surface steel mould trolley
CN203248170U (en) * 2013-04-28 2013-10-23 中铁十二局集团第二工程有限公司 Lining trolley for secondary lining construction of pedestrian crosswalk
CN105114102A (en) * 2015-09-01 2015-12-02 东莞市万桥钢模有限公司 Subway station formwork trolley
CN205822233U (en) * 2016-04-26 2016-12-21 尤兆云 A kind of city integrated piping lane construction vehicles combination Shi Neimo

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101082280A (en) * 2007-07-18 2007-12-05 湖南中铁五新钢模有限责任公司 Single-track railway tunnel lining trolley
CN201614939U (en) * 2010-03-15 2010-10-27 中国葛洲坝集团股份有限公司 Three-dimensional space curved surface steel mould trolley
CN203248170U (en) * 2013-04-28 2013-10-23 中铁十二局集团第二工程有限公司 Lining trolley for secondary lining construction of pedestrian crosswalk
CN105114102A (en) * 2015-09-01 2015-12-02 东莞市万桥钢模有限公司 Subway station formwork trolley
CN205822233U (en) * 2016-04-26 2016-12-21 尤兆云 A kind of city integrated piping lane construction vehicles combination Shi Neimo

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108343087A (en) * 2018-04-26 2018-07-31 北京建工土木工程有限公司 A kind of the transport assembly equipment system and its construction method of prefabricated components
CN108343087B (en) * 2018-04-26 2024-04-12 北京建工土木工程有限公司 Prefabricated part transportation and assembly equipment system and construction method thereof
CN112439840A (en) * 2020-10-31 2021-03-05 深圳市铸新科技有限公司 Install fast and clear hot work product forming die

Similar Documents

Publication Publication Date Title
CN205822233U (en) A kind of city integrated piping lane construction vehicles combination Shi Neimo
CN107313447A (en) A kind of city integrated piping lane construction mould and construction method
CN205370595U (en) Automatic hydraulic pressure inverted arch landing stage platform truck
CN107363988B (en) Hydraulic internal mold toothed rail traveling system and traveling method for prefabricated box girder
CN106593469A (en) Trolley for construction of inverted arch
CN104533460B (en) Support replacement formula formwork jumbo and the construction method of underpass concreting
CN201730627U (en) Tunnel adit curve section and straight section full-circle hydraulic steel-form trolley
CN206768610U (en) A kind of highway small box girder external mold self-propelling device
CN109304795A (en) The hydraulic gliding model of T beam and operating method
CN207944955U (en) Tunnel widened section two serves as a contrast trolley
CN110273695A (en) A kind of Tunnel Second Lining formwork jumbo and its stage molding pouring procedure
CN107313446A (en) A kind of city integrated piping lane construction vehicles combination formula internal model
CN207567810U (en) A kind of formwork jumbo for pipe gallery cast-in-place concrete slding form operation
CN110394885B (en) Be applied to prefabricated whole fluid pressure type template of box culvert
CN210712594U (en) Culvert platform truck
CN206109994U (en) Pier pier shaft prefabricated mould
CN203248170U (en) Lining trolley for secondary lining construction of pedestrian crosswalk
CN206538781U (en) A kind of city integrated piping lane construction mould
CN103114572A (en) Underground diaphragm wall guide wall movable mold frame
CN112942154B (en) Culvert cover plate movable type support-free cast-in-place device and construction method thereof
CN106854875B (en) Vehicle-type mold assembly for construction of comprehensive pipe rack
CN212177162U (en) Through type emergency parking trolley with two steel-lined moulds
CN112832203A (en) Angle-adjustable lining trolley suitable for multiple sections of water conservancy ditches
CN211230492U (en) Hydraulic self-propelled movable formwork support for tunnel center ditch
CN206220975U (en) A kind of chassis for inverted arch construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171103

RJ01 Rejection of invention patent application after publication