CN107313320B - The embedded reinforcement asphalt pavement structure of cement concrete pavement and construction method - Google Patents

The embedded reinforcement asphalt pavement structure of cement concrete pavement and construction method Download PDF

Info

Publication number
CN107313320B
CN107313320B CN201710551533.2A CN201710551533A CN107313320B CN 107313320 B CN107313320 B CN 107313320B CN 201710551533 A CN201710551533 A CN 201710551533A CN 107313320 B CN107313320 B CN 107313320B
Authority
CN
China
Prior art keywords
pavement
baffle
concrete panel
breaking
cement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710551533.2A
Other languages
Chinese (zh)
Other versions
CN107313320A (en
Inventor
姜允庆
侯睿妮
张晓龙
刘甫
赵新创
李超
尹飞
刘宏伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANHUI XINLU CONSTRUCTION ENGINEERING GROUP Co Ltd
Original Assignee
ANHUI XINLU CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI XINLU CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical ANHUI XINLU CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201710551533.2A priority Critical patent/CN107313320B/en
Publication of CN107313320A publication Critical patent/CN107313320A/en
Application granted granted Critical
Publication of CN107313320B publication Critical patent/CN107313320B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/18Coherent pavings made in situ made of road-metal and binders of road-metal and bituminous binders
    • E01C7/187Repairing bituminous covers, e.g. regeneration of the covering material in situ, application of a new bituminous topping
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/205Securing of slopes or inclines with modular blocks, e.g. pre-fabricated
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Abstract

The invention discloses the embedded reinforcement asphalt pavement structure of cement concrete pavement and construction methods, including roadbed, roadbed is equipped with water-stable gravel and side slope step, side slope step is equipped with baffle and mortar rubble masonry pavement, board bottom injecting cement paste is successively arranged on water-stable gravel, breaking concrete panel, the geotextiles that become mildewed and asphalt concrete pavement, baffle is equipped with through hole and preformed hole, baffle side is equipped with groove and is fixed with breaking concrete panel, inserted with the connecting screw for running through breaking concrete panel in through hole, baffle is fastened on breaking concrete panel, water-stable gravel, which corresponds to, is equipped with bolthole at the position of preformed hole, inserted with the reinforcing bar body of rod in bolthole, bolthole is formed with slurries reinforcing body to exosmosis, upgrading is carried out after cement concrete pavement serious damage capable of being directed to, it efficiently solves Later period pavement cracking and endurance issues significantly reduce the extension and roadbed subsidence deformation of reflection crack, there is good technical economic benefit.

Description

The embedded reinforcement asphalt pavement structure of cement concrete pavement and construction method
Technical field
The invention belongs to field of road, and in particular to the embedded reinforcement asphalt pavement structure of cement concrete pavement and Construction method.
Background technique
Cement concrete pavement structure was open to traffic after many years, and supercrust, which gradually appears, gnaws the diseases such as side, disconnected plate, depression, was Improve driving condition, using the scheme of the repaving asphalt coat on old cement concrete road.The program to disease cement concrete slab and Plate stitch is punished, then the repaving asphalt coat on old pavement, is effectively utilized Old cement concrete, overhaul cost compared with It is low, it is easy for construction, it is an effective measures of Promotion Transformation section road-ability and bearing capacity.But due to old coagulating cement There is T-joining and disease cracks for soil surface, if incompletely processed with regard to carrying out cover construction, when vehicle passes through, old pavement is former It will change due to flexure between crack location adjacent plate and generate vertical displacement and shear stress occur, if stress is more than the anti-of finishing coat The curved drawing limit, the cracking that its bottom stress will be caused to concentrate position, crack slowly extend from the bottom to top, finally go out on finishing coat Existing reflection crack;In addition, since road surface is exposed in atmosphere, dual shadow of the reflection crack by rain erosion and temperature stress difference It rings, it will further expand, asphalt surface course is made reflection crack occur, eventually lead to bitumen layer and early stage Water Damage disease, shadow occur Overhaul engineering quality is rung.
Summary of the invention
The purpose of the present invention is to provide the embedded reinforcement asphalt pavement structure of cement concrete pavement and construction method, energy For the green upgrading of progress after cement concrete pavement serious damage, the pull-type baffle of anchor is set in both sides of the road and grouts piece Stone slope protection installs prefabricated board, and board bottom slip casting after the serious fracture area step excavation of concrete slab, and area of coming to nothing is reinforced in effectively filling And panel crack, it is laid with becomes mildewed geotextiles and asphalt concrete pavement thereon, efficiently solve later period pavement cracking and durable Property problem, the extension and roadbed subsidence deformation of reflection crack are significantly reduced, applied to achieving preferable Technological Economy in engineering Benefit.
In order to achieve the above object, major technique solution of the invention is to provide the embedded reinforcement drip of cement concrete pavement Green pavement structure, including roadbed, roadbed are equipped with water-stable gravel and side slope step, are provided with baffle and slurry on side slope step Build slabstone slope protection form firm protective slope structure, be successively arranged on water-stable gravel board bottom injecting cement paste, breaking concrete panel, The geotextiles that become mildewed and asphalt concrete pavement, baffle are equipped with through hole and preformed hole, and baffle side is equipped with groove and is crushed mixed Solidifying soil panel is fixed, and inserted with the connecting screw for running through breaking concrete panel in through hole, baffle is fastened on broken On concrete slab, water-stable gravel corresponds to and is equipped with bolthole at the position of preformed hole, inserted with the reinforcing bar body of rod in bolthole, Bolthole is formed with slurries reinforcing body to exosmosis.
Reinforcing bar body of rod free end in the preformed hole is locked equipped with anchor, is protected in preformed hole filled with anti-corrosion material Protect anchor.
The breaking concrete panel is equipped with serious fracture area step, and serious fracture area step is equipped with engaged therewith Prefabricated board, dowel and Grouting Pipe, there is the gap 10mm between prefabricated board and serious fracture area step, dowel and Grouting Pipe pass through Corresponding hole on prefabricated board, a terrace of serious fracture area step are set to the middle part of breaking concrete panel, and Grouting Pipe is set It is evenly distributed with slip casting aperture under prefabricated board, in Grouting Pipe, board bottom injecting cement paste is formed with around Grouting Pipe.
The present invention also provides the construction methods of the embedded reinforcement asphalt pavement structure of the cement concrete pavement, including The following steps:
1) side slope step is arranged: excavating in the side slope of cement concrete pavement two sides and forms side slope step;
2) baffle is installed: being made according to the breaking concrete plate thickness of cement concrete pavement with fluted and preformed hole Baffle, baffle is caught on breaking concrete panel by groove, baffle is fastened on broken mixed by drilling implantation connecting screw On solidifying soil panel;
3) anchor pole is installed: passing through the preformed hole on baffle with drilling machine and sets bolthole in water-stable gravel, to bolthole Interior insertion reinforcement rod body, and the cement injection into bolthole, finally with the free end of the anchor locking reinforcing bar body of rod;
4) mortar rubble masonry pavement is constructed: being built slabstone on side slope step and is formed firm mortar rubble masonry pavement;
5) serious fracture area step setting: the seriously broken concrete topping on breaking concrete panel is cut, Serious fracture area step is set on the intact breaking concrete panel of surrounding, and the drilling implantation dowel on step;
6) it buries Grouting Pipe: burying Grouting Pipe along breaking concrete panel bottom surface;
7) install prefabricated board: prefabricated board is placed in serious fracture area by the prefabricated board of production and the cooperation of serious fracture area step On step, dowel and Grouting Pipe pass through corresponding hole on prefabricated board;
8) cement slurry: being injected the board bottom of breaking concrete panel by Grouting Pipe by board bottom slip casting, and solidification forms board bottom note Slurry;
9) geotextiles that become mildewed are laid with: being laid with the geotextiles that become mildewed on the breaking concrete panel being disposed;
10) it asphalt concrete pavement decking and rolling: is paved bituminous concrete in geotextiles with paver becoming mildewed, using pressure Road machine grinding compacting forms asphalt concrete pavement.
The cement slurry injected in the step 3) is full of bolthole, the reinforcing bar body of rod is fastened after grout cures and to extravasation Slurries reinforcing body is formed thoroughly, and anchor is placed in the preformed hole on baffle, filled with anti-corrosion material protection anchoring in preformed hole Device.
One terrace of the serious fracture area step is set in the middle part of the layer of breaking concrete panel, is drilled and is planted on terrace Enter dowel, dedicated adhesive glue is filled between dowel and drilling.
Slip casting aperture is evenly distributed in the Grouting Pipe, Grouting Pipe is diverted through vertical bipass and realizes.
The shape of the prefabricated board matches with serious fracture area step, after installation prefabricated board and serious fracture area step it Between there are the gaps 10mm.
The invention has the characteristics that and the utility model has the advantages that
(1) present invention is in the pull-type baffle of both sides of the road setting anchor and mortar rubble masonry pavement, cement injection, cement slurry infiltration Slurries reinforcing body is formed, the stability of roadbed side slope is effectively improved, the setting of baffle prevents spillage of the cement slurry in side slope, Improve slip casting efficiency;
(2) prefabricated board, and board bottom slip casting are installed after the serious fracture area step excavation of breaking concrete panel, effectively fill Reinforcing is come to nothing area and panel crack;
(3) become mildewed geotextiles and asphalt concrete pavement are successively laid on the breaking concrete panel after reinforcing, it is effectively anti- The only generation of reflection crack improves the durability of road.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of one embodiment of the invention,
Fig. 2 is schematic diagram at the side slope of inode both sides of the road in Fig. 1,
Fig. 3 is schematic diagram at II node serious damage area in Fig. 1,
In figure: 1- roadbed, 2- water-stable gravel, 3- side slope step, 4- mortar rubble masonry pavement, 5- baffle, 6- slurries add Solid, 7- board bottom injecting cement paste, 8- asphalt concrete pavement, the 9- reinforcing bar body of rod, 10- bolthole, 11- Grouting Pipe, 12- are crushed coagulation Native panel, 13- anchor, 14- become mildewed geotextiles, 15- connecting screw, 16- prefabricated board, 17- dowel, and 18- is seriously crushed Area's step, 19- preformed hole.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art's every other embodiment obtained belong to what the present invention protected Range.
As depicted in figs. 1 and 2, the embedded reinforcement asphalt pavement structure of cement concrete pavement described in the present embodiment, Including roadbed 1, roadbed 1 is equipped with water-stable gravel 2 and side slope step 3, and baffle 5 is provided on side slope step 3 and grouts piece Stone slope protection 4 forms firm protective slope structure, is successively arranged board bottom injecting cement paste 7, breaking concrete panel on water-stable gravel 2 12, the geotextiles that become mildewed 14 and asphalt concrete pavement 8, baffle 5 are equipped with through hole and preformed hole 19, and 5 side of baffle is equipped with recessed Slot is fixed with breaking concrete panel 12, the interior connecting screw 15 inserted with through breaking concrete panel 12 of through hole, Baffle 5 is fastened on breaking concrete panel 12, is equipped with bolthole at the position of the corresponding preformed hole 19 of water-stable gravel 2 10, inserted with the reinforcing bar body of rod 9, bolthole 10 and slurries reinforcing body 6 is formed with to exosmosis in bolthole 10.
9 free end of the reinforcing bar body of rod in the preformed hole 19 is locked equipped with anchor 13, filled with anti-in preformed hole 19 Rotten material protection anchor 13.
As shown in figure 3, the breaking concrete panel 12 is equipped with serious fracture area step 18, serious fracture area step 18 It is equipped with prefabricated board 16 engaged therewith, dowel 17 and Grouting Pipe 11, is had between prefabricated board 16 and serious fracture area step 18 The gap 10mm, dowel 17 and Grouting Pipe 11 pass through corresponding hole on prefabricated board 16, a rank of serious fracture area step 18 Face is set to the middle part of breaking concrete panel 12, and Grouting Pipe 11 is placed under prefabricated board 16, is evenly distributed with slip casting in Grouting Pipe 11 Aperture is formed with board bottom injecting cement paste 7 around Grouting Pipe 11.
The present invention also provides the construction methods of the embedded reinforcement asphalt pavement structure of the cement concrete pavement, including The following steps:
1) side slope step 3 is arranged: excavating in the side slope of cement concrete pavement two sides and forms side slope step 3;
2) baffle 5 is installed: being made according to 12 thickness of breaking concrete panel of cement concrete pavement with fluted and pre- Box out 19 baffle 5, baffle 5 is caught on breaking concrete panel 12 by groove, drilling implantation connecting screw 15 is by baffle 5 It is fastened on breaking concrete panel 12;
3) anchor pole is installed: passing through the preformed hole 19 on baffle 5 with drilling machine and sets bolthole 10 in water-stable gravel 2, to It is inserted into reinforcement rod body 9, and the cement injection into bolthole 10 in bolthole 10, finally locks the reinforcing bar body of rod 9 with anchor 13 Free end;
4) mortar rubble masonry pavement 4 is constructed: being built slabstone on side slope step 3 and is formed firm mortar rubble masonry pavement 4;
5) serious fracture area step 18 is arranged: the seriously broken concrete topping on breaking concrete panel 12 is dug It removes, serious fracture area step 18 is set on the intact breaking concrete panel 12 of surrounding, and the drilling implantation connection on step Muscle 17;
6) it buries Grouting Pipe 11: burying Grouting Pipe 11 along 12 bottom surface of breaking concrete panel;
7) install prefabricated board 16: prefabricated board 16 is placed in sternly by the prefabricated board 16 of production and the cooperation of serious fracture area step 18 On weight fracture area step 18, dowel 17 and Grouting Pipe 11 pass through corresponding hole on prefabricated board 16;
8) cement slurry: being injected the board bottom of breaking concrete panel 12 by Grouting Pipe 11 by board bottom slip casting, and solidification forms plate Rising pouring slurry 7;
9) geotextiles 14 that become mildewed are laid with: being laid with the geotextiles 14 that become mildewed on the breaking concrete panel 12 being disposed;
10) it 8 decking and rolling of asphalt concrete pavement: is paved bituminous concrete, is adopted with paver in geotextiles 14 becoming mildewed The closely knit formation asphalt concrete pavement 8 of steamroller.
The cement slurry injected in the step 3) is full of bolthole 10, fasten after grout cures the reinforcing bar body of rod 9 and to Exosmosis forms slurries reinforcing body 6, and anchor 13 is placed in the preformed hole 19 on baffle 5, and anti-corrosion is filled in preformed hole 19 Material protection anchor 13.
One terrace of the serious fracture area step 18 is set in the middle part of the layer of breaking concrete panel 12, is bored on terrace Hole is implanted into dowel 17, and dedicated adhesive glue is filled between dowel 17 and drilling.
Slip casting aperture is evenly distributed in the Grouting Pipe 11, Grouting Pipe 11 is diverted through vertical bipass and realizes.
The shape of the prefabricated board 16 matches with serious fracture area step 18, prefabricated board 16 and serious fracture area after installation There are the gaps 10mm between step.
The present invention is in the pull-type baffle 5 of both sides of the road setting anchor and mortar rubble masonry pavement 4, cement injection, cement slurry infiltration Slurries reinforcing body 6 is formed, effectively improves the stability of 1 side slope of roadbed, the setting of baffle 5 prevents leakage of the cement slurry in side slope Slurry, improves slip casting efficiency;Prefabricated board 16 is installed, and board bottom is infused after the serious fracture area step excavation of breaking concrete panel 12 Slurry, effectively filling reinforce come to nothing area and panel crack;The geotextiles that become mildewed successively are laid on breaking concrete panel 12 after reinforcing 14 and asphalt concrete pavement 8, it is effectively prevent the generation of reflection crack, improves the durability of road.
The present invention is not limited to above-mentioned preferred forms, anyone can show that other are various under the inspiration of the present invention The product of form, however, make any variation in its shape or structure, it is all that there is skill identical or similar to the present application Art scheme, is within the scope of the present invention.

Claims (6)

1. the embedded reinforcement asphalt pavement structure of cement concrete pavement, including roadbed (1), which is characterized in that roadbed is set on (1) There are water-stable gravel (2) and side slope step (3), baffle (5) and mortar rubble masonry pavement (4), water are provided on side slope step (3) Board bottom injecting cement paste (7), breaking concrete panel (12), the geotextiles that become mildewed (14) and pitch are successively arranged on steady crushed rock base course (2) Concrete topping (8), baffle (5) are equipped with through hole and preformed hole (19), and baffle (5) side is equipped with groove and breaking concrete Panel is fixed, and inserted with the connecting screw (15) for running through breaking concrete panel (12) in through hole, baffle (5) are fastened On breaking concrete panel (12), bolthole (10) are equipped at the position of water-stable gravel (2) corresponding preformed hole (19), anchor Inserted with the reinforcing bar body of rod (9) in rod aperture (10), bolthole (10) surrounding is equipped with slurries reinforcing body (6), in the preformed hole (19) The reinforcing bar body of rod (9) free end locked equipped with anchor (13), filled with anti-corrosion material protection anchoring dress in preformed hole (19) It sets (13), the breaking concrete panel (12) is equipped with serious fracture area step (18), sets on serious fracture area step (18) There are prefabricated board engaged therewith (16), dowel (17) and Grouting Pipe (11), prefabricated board (16) and serious fracture area step (18) Between have a gap 10mm, dowel (17) and Grouting Pipe (11) pass through corresponding hole on prefabricated board (16), serious fracture area platform One terrace of rank (18) is set to the middle part of breaking concrete panel (12), and Grouting Pipe (11) is placed under prefabricated board (16), slip casting It is evenly distributed with slip casting aperture on pipe (11), is formed with board bottom injecting cement paste (7) around Grouting Pipe (11).
2. the construction method of the embedded reinforcement asphalt pavement structure of cement concrete pavement, characterized in that it comprises the following steps:
1) side slope step (3) is arranged: excavating in the side slope of cement concrete pavement two sides and forms side slope step (3);
2) baffle (5) are installed: are made according to breaking concrete panel (12) thickness of cement concrete pavement with fluted and pre- It boxes out the baffle (5) of (19), baffle (5) is caught on breaking concrete panel (12) by groove, drilling implantation connecting screw (15) baffle (5) is fastened on breaking concrete panel (12);
3) anchor pole is installed: passing through the preformed hole (19) on baffle (5) with drilling machine and sets bolthole in water-stable gravel (2) (10), reinforcement rod body (9) are inserted into bolthole (10), and to bolthole (10) interior cement injection, finally use anchor (13) free end of the reinforcing bar body of rod (9) is locked;
4) mortar rubble masonry pavement (4) is constructed: being built slabstone on side slope step (3) and is formed firm mortar rubble masonry pavement (4);
5) serious fracture area step (18) setting: the seriously broken concrete topping on breaking concrete panel (12) is dug It removes, serious fracture area step (18) is set on the intact breaking concrete panel (12) of surrounding, and the implantation that drills on step Dowel (17);
6) Grouting Pipe (11) are buried: buries Grouting Pipe (11) along breaking concrete panel (12) bottom surface;
7) install prefabricated board (16): the prefabricated board (16) of production and the cooperation of serious fracture area step (18) sets prefabricated board (16) In on serious fracture area step (18), dowel (17) and Grouting Pipe (11) pass through corresponding hole on prefabricated board (16);
8) board bottom slip casting: by Grouting Pipe (11) by the board bottom of cement slurry injection breaking concrete panel (12), solidification forms plate Rising pouring slurry (7);
9) it is laid with and becomes mildewed geotextiles (14): being laid on the breaking concrete panel (12) being disposed and become mildewed geotextiles (14);
10) it asphalt concrete pavement (8) decking and rolling: is paved bituminous concrete, is adopted with paver on the geotextiles that become mildewed (14) The closely knit formation asphalt concrete pavement (8) of steamroller.
3. the construction method of the embedded reinforcement asphalt pavement structure of cement concrete pavement according to claim 2, special Sign is that the cement slurry injected in the step 3) is full of bolthole (10), fastens the reinforcing bar body of rod (9) simultaneously after grout cures Slurries reinforcing body (6) are formed to exosmosis, anchor (13) is placed in the preformed hole (19) on baffle (5) Nei, preformed hole (19) It is interior to protect anchor (13) filled with anti-corrosion material.
4. the construction method of the embedded reinforcement asphalt pavement structure of cement concrete pavement according to claim 2, special Sign is that a terrace of the serious fracture area step (18) is set in the middle part of the layer of breaking concrete panel (12), on terrace Drilling implantation dowel (17) is filled with dedicated adhesive glue between dowel (17) and drilling.
5. the construction method of the embedded reinforcement asphalt pavement structure of cement concrete pavement according to claim 2, special Sign is to be evenly distributed with slip casting aperture on the Grouting Pipe (11).
6. the construction method of the embedded reinforcement asphalt pavement structure of cement concrete pavement according to claim 2, special Sign is that the shape of the prefabricated board (16) matches with serious fracture area step (18), and prefabricated board (16) is broken with serious after installation There are the gaps 10mm between broken area's step.
CN201710551533.2A 2017-07-07 2017-07-07 The embedded reinforcement asphalt pavement structure of cement concrete pavement and construction method Active CN107313320B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710551533.2A CN107313320B (en) 2017-07-07 2017-07-07 The embedded reinforcement asphalt pavement structure of cement concrete pavement and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710551533.2A CN107313320B (en) 2017-07-07 2017-07-07 The embedded reinforcement asphalt pavement structure of cement concrete pavement and construction method

Publications (2)

Publication Number Publication Date
CN107313320A CN107313320A (en) 2017-11-03
CN107313320B true CN107313320B (en) 2019-02-22

Family

ID=60179076

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710551533.2A Active CN107313320B (en) 2017-07-07 2017-07-07 The embedded reinforcement asphalt pavement structure of cement concrete pavement and construction method

Country Status (1)

Country Link
CN (1) CN107313320B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108396605A (en) * 2018-02-12 2018-08-14 中交第二公路勘察设计研究院有限公司 Underlie buried cave dwelling road structure and construction method
CN108547195B (en) * 2018-04-28 2020-03-20 江西博慧工程技术服务有限公司 Drainage asphalt pavement structure and construction method
CN109024135B (en) * 2018-08-15 2020-07-24 江西博慧工程技术服务有限公司 Green upgrading structure and modification method for concrete pavement
CN112095375B (en) * 2020-08-07 2022-03-01 中电建路桥集团有限公司 Durable asphalt pavement and construction method thereof
CN112832080B (en) * 2021-01-12 2022-04-01 四川省交通建设集团股份有限公司 Construction method for enlarging and rebuilding embankment of highway to widen
CN115354548B (en) * 2022-08-10 2024-04-05 聊城市交通发展有限公司 New and old pavement splicing structure and construction method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5698604B2 (en) * 2011-05-30 2015-04-08 矢作建設工業株式会社 Installation method of precast plate at the first stage in slope reinforcement method
CN202787044U (en) * 2012-09-12 2013-03-13 浙江八咏公路工程有限公司 Longitudinal crack treatment structure for bituminous concrete pavement
CN205875176U (en) * 2016-04-25 2017-01-11 杭州江润科技有限公司 Ventilation embankment step grouts slabstone and completely spreads slope protection structure
CN206902487U (en) * 2017-07-07 2018-01-19 安徽省新路建设工程集团有限责任公司 The embedded reinforcement asphalt pavement structure of cement concrete pavement

Also Published As

Publication number Publication date
CN107313320A (en) 2017-11-03

Similar Documents

Publication Publication Date Title
CN107313320B (en) The embedded reinforcement asphalt pavement structure of cement concrete pavement and construction method
CN102767173B (en) High polymer material slurry filled discrete material pile composite foundation and construction method thereof
CN104278608B (en) The constructional method of a kind of highway embankment widened structure
CN109972659B (en) Novel municipal inspection well structure and construction method
CN203383119U (en) Novel widening structure of highway embankment
CN108642988B (en) Comprehensive treatment and repair structure for embankment base layer diseases and construction method
CN104131502A (en) Construction method for widening road in rapid erection manner
CN106320120A (en) Construction process for pile slab type non-soil roadbed highway
CN107938456A (en) Fill out river road construction method
CN107165022A (en) A kind of big thickness subbase construction method of High-cold regions highway widening reinforcement
CN109838240A (en) Cross the river tunnel ledge cover and cut construction method
CN107700299B (en) Overpass lower-layer ground road structure and construction method thereof
CN203334154U (en) Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN110144931A (en) A kind of construction method of the board-like Ecological Retaining Wall of novel pile
CN206902487U (en) The embedded reinforcement asphalt pavement structure of cement concrete pavement
CN108589747A (en) EPS light road banks are widened in conjunction with plant biological bag protective slope structure and construction method
CN105256683A (en) Permafrost region roadbed thermal insulation construction method
CN102644224A (en) Novel roadbed side slope building protecting method and precast concrete blocks therefor
CN111809470A (en) Structure and method for preventing cracks of road base layer and road subbase layer
CN106245546A (en) A kind of corrugated steel Pipe rack
CN110747733A (en) Construction method of ecological prefabricated anti-collision wall
CN108824460A (en) A kind of construction technology of cut subgrade banket
CN105155387A (en) Garden road structure
CN206127789U (en) Structure of making an uproar falls in highway tunnel driving damping
CN104894942B (en) The recyclable combination construction sidewalk of drainage type

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant