CN107298291A - Position transfer device on a kind of petroleum pipeline production line - Google Patents

Position transfer device on a kind of petroleum pipeline production line Download PDF

Info

Publication number
CN107298291A
CN107298291A CN201710733907.2A CN201710733907A CN107298291A CN 107298291 A CN107298291 A CN 107298291A CN 201710733907 A CN201710733907 A CN 201710733907A CN 107298291 A CN107298291 A CN 107298291A
Authority
CN
China
Prior art keywords
slide rail
baffle
petroleum pipeline
sliding block
connecting rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710733907.2A
Other languages
Chinese (zh)
Other versions
CN107298291B (en
Inventor
范郑卓
莫善仪
郭琦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinchang Qiyao Building Material Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710733907.2A priority Critical patent/CN107298291B/en
Publication of CN107298291A publication Critical patent/CN107298291A/en
Application granted granted Critical
Publication of CN107298291B publication Critical patent/CN107298291B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G35/00Mechanical conveyors not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Manipulator (AREA)

Abstract

The present invention relates to position transfer device on a kind of transfer device, more particularly to a kind of petroleum pipeline production line.The technical problem to be solved in the present invention is to provide it is a kind of transfer petroleum pipeline position during will not damage petroleum pipeline and can stablize constantly transfer petroleum pipeline petroleum pipeline production line on position transfer device.In order to solve the above-mentioned technical problem, the invention provides position transfer device on such a petroleum pipeline production line, bottom plate etc. is included;It is connected with the top of bottom plate at the top of drive mechanism, drive mechanism and is connected with placement mechanism.The present invention can transport the petroleum pipeline of different model size; it can prevent dust or other impurities from dropping to motor; petroleum pipeline that can be in transportation plays a part of protection, the illuminating lamp of setting cause the device night or light dark place need not also can transporting petroleum pipeline by extraneous light.

Description

Position transfer device on a kind of petroleum pipeline production line
Technical field
The present invention relates to position transfer device on a kind of transfer device, more particularly to a kind of petroleum pipeline production line.
Background technology
One of oil, the main object of geological prospecting, it is a kind of sticky, dark brown liquid, is referred to as " industrial blood Liquid ".There is petroleum storage upper crustal some areas.Main component is the mixture of various alkane, cycloalkane, aromatic hydrocarbon.
Pipeline be with pipe, pipe connector and valve etc. be connected into be used for convey gas, liquid or with solid particle Fluid device.Generally, after fluid is pressurized through air blower, compressor, pump and boiler etc., low pressure is flowed at the high pressure of pipeline Place, can also be used pressure or the gravity conveying of fluid itself.Having many uses for pipeline is general, be used primarily in feedwater, draining, heat supply, Give gas, long distance delivery oil and natural gas, agricultural irrigation, in hydraulic engineering and various commercial plants.
It is fast-developing in modern economy, under the ever-increasing background of yield of petroleum gas, for the position of oil-gas pipeline Put transfer techniques and it is also proposed higher requirement, but position transfer device is not also on petroleum pipeline production line on the market at present It is very perfect, that goes or compare on the transfer petroleum pipeline of rotary type to another position is rare, in transfer petroleum pipeline position When putting, because petroleum pipeline is circular, petroleum pipeline will be easily lead to and be easily placed when shifting and placing Shakiness, causes petroleum pipeline to slide, and existing most of transfer devices are transmitted by feed belt, and feed belt To transmit the surface that petroleum pipeline is just easy to damage petroleum pipeline.
Therefore need badly to research and develop and a kind of will not damage petroleum pipeline and can be steady during the position of transfer petroleum pipeline Position transfer device on the petroleum pipeline production line of fixed constantly transfer petroleum pipeline, to overcome in the prior art in transfer oil Petroleum pipeline is easily damaged during the position of pipeline and the shortcoming for constantly shifting petroleum pipeline cannot be stablized.
The content of the invention
(1) technical problem to be solved
The present invention is easily damaged petroleum pipeline simultaneously during the position of transfer petroleum pipeline in the prior art in order to overcome And the shortcoming for constantly shifting petroleum pipeline cannot be stablized, the technical problem to be solved in the present invention is to provide one kind in transfer stone Petroleum pipeline will not be damaged during the position of oil-piping and the petroleum pipeline life of constantly transfer petroleum pipeline can be stablized Position transfer device in producing line.
(2) technical scheme
In order to solve the above-mentioned technical problem, filled the invention provides position transfer on such a petroleum pipeline production line Put, include to be connected with to be connected with the top of drive mechanism, drive mechanism at the top of bottom plate, drive mechanism and placement mechanism, bottom plate and put Put mechanism.
Preferably, drive mechanism includes the first slide rail, head rod, the first sliding block, the second connecting rod, the second cunning The equal slidingtype in four sides all around is connected with the first slide rail, the first slide rail at the top of block, the second slide rail, motor and runner, bottom plate It is connected with the first sliding block, bottom plate and is connected with head rod, head rod crown center is provided with motor, the output of motor Runner is connected with axle, all around four sides are respectively connected with the second slide rail, the second slide rail equal slidingtype connection to the outer wall of runner There is rotary type on the second sliding block, the second sliding block to be connected with the second connecting rod, the second connecting rod is connected with the first sliding block rotary type.
Preferably, placement mechanism include placement plate, the 3rd slide rail, the 3rd sliding block, the first installing plate, the first block rubber, First baffle, second baffle, the second block rubber and the first spring, place front and rear sides at the top of plate and are respectively connected with the 3rd slide rail, the The equal slidingtype in the left and right sides is connected with the 3rd sliding block on three slide rails, and the 3rd slider top of the left and right sides is respectively connected with the first installation The left and right sides is respectively connected with the inside of first baffle, the first baffle of the left and right sides and is respectively connected with first at the top of plate, the first installing plate Block rubber, the 3rd slide rail crown center is connected with the left and right sides at the top of the second block rubber, the 3rd slide rail and is respectively connected with second baffle, Second block rubber is located between the second baffle of the left and right sides, with the second gear of the left and right sides on the inside of the 3rd sliding block of the left and right sides The first spring is connected between on the outside of plate.
Preferably, also include at the top of ring-like slide rail, Four-slider, inserted link, the 3rd connecting rod and drawstring, head rod Ring-like slide rail is connected with, before and after the equal slidingtype in four sides all around of ring-like slide rail is connected with the top of Four-slider, Four-slider Both sides, which are provided with through hole, through hole, is provided with inserted link, and inserted link passes through through hole, and the second slide rail passes through the inserted link of front and rear sides, front and rear two The 3rd connecting rod is connected between the inserted link of side, the 3rd connecting rod is located above the second slide rail, the 3rd connecting rod and Four-slider Between be connected with drawstring.
Preferably, the 4th connecting rod, the 5th connecting rod and third baffle are also included, the second slide rail left and right sides symmetrically connects The 4th connecting rod is connected to, the second slide rail front and rear sides are symmetrically connected with the top of the 5th connecting rod, the second slide rail and are connected with third gear Plate.
Preferably, first annular baffle plate, the second ring baffle, the second installing plate, second spring, the first pole are also included And steel wire rope, place plate outer wall and be connected with first annular baffle plate, first annular baffle plate top is connected with the second ring baffle, placed Uniform be connected with the top of second spring, second spring is connected with the second installing plate at the top of plate, is slided at the top of the second installing plate with the 3rd Rail is connected, and is connected with the top of the first baffle in left side at the top of the first pole, the first baffle on right side and is connected with steel wire rope, steel wire rope Left end be wound on the first pole.
Preferably, also include and be connected with second at the top of the second pole, the 3rd mounting blocks and illuminating lamp, third baffle The 3rd mounting blocks are connected with the top of bar, the second pole, the 3rd mounting blocks bottom left and right sides is provided with illuminating lamp.
Operation principle:When needing using the device to carry out position transfer on a production line to petroleum pipeline, user The petroleum pipeline for needing to shift is positioned in placement mechanism by member, afterwards by starting drive mechanism come to the oil for needing to shift Pipeline carries out position transfer.
Because drive mechanism includes the first slide rail, head rod, the first sliding block, the second connecting rod, the second sliding block, Two slide rails, motor and runner, are connected with the first slide rail, the first slide rail that all around the equal slidingtype in four sides is connected with the top of bottom plate Head rod is connected with first sliding block, bottom plate, head rod crown center, which is provided with motor, the output shaft of motor, to be connected It is connected to runner, all around four sides are respectively connected with the second slide rail, the second slide rail equal slidingtype and are connected with second for the outer wall of runner Rotary type is connected with the second connecting rod on sliding block, the second sliding block, and the second connecting rod is connected with the first sliding block rotary type, when needs make During with the device to carry out position transfer to petroleum pipeline, user of service enables motor rotation, and runner will be rotated, and runner is rotated The second sliding block will be driven to slide, so as to drive the first sliding block to be slided in the first slide rail, the first sliding block is sliding in the first slide rail It is dynamic just placement mechanism to be driven to rotate, it is achieved thereby that the position transfer of petroleum pipeline.
Because placement mechanism includes placement plate, the 3rd slide rail, the 3rd sliding block, the first installing plate, the first block rubber, first Baffle plate, second baffle, the second block rubber and the first spring, place front and rear sides at the top of plate and are respectively connected with the 3rd slide rail, the 3rd slides The equal slidingtype in the left and right sides is connected with the 3rd sliding block on rail, and the 3rd slider top of the left and right sides is respectively connected with the first installing plate, The left and right sides is respectively connected with the inside of first baffle, the first baffle of the left and right sides and is respectively connected with the first rubber at the top of first installing plate Block, the 3rd slide rail crown center is connected with the left and right sides at the top of the second block rubber, the 3rd slide rail and is respectively connected with second baffle, and second Block rubber is located between the second baffle of the left and right sides, on the inside of the 3rd sliding block of the left and right sides and outside the second baffle of the left and right sides The first spring is connected between side, when petroleum pipeline needs transferring position, user of service places petroleum pipeline to be transferred In on the second block rubber, when petroleum pipeline than it is larger when, oil-piping extrudes the first block rubber of the left and right sides, now the left and right sides The 3rd sliding block will move laterally so that the first spring elongation, afterwards in the presence of drive mechanism, petroleum pipeline will Destination can be transported to, when removing transported petroleum pipeline from the second block rubber, the first spring restores to the original state, so that So that side moves back to original position to the 3rd sliding block of the left and right sides inwards, side movement will inwards for the 3rd sliding block of the left and right sides The first block rubber of the left and right sides is driven to return to home position, the first block rubber and the second block rubber of setting can protect transport During petroleum pipeline surface be not damaged, the first spring of setting allows the device to transport the stone of different model size Oil-piping.
Because also including and also including ring-like slide rail, Four-slider, inserted link, the 3rd connecting rod and drawstring, the first connection Ring-like slide rail is connected with the top of bar, the equal slidingtype in four sides all around of ring-like slide rail is connected with Four-slider, Four-slider top Portion front and rear sides, which are provided with through hole, through hole, is provided with inserted link, and inserted link passes through through hole, and the second slide rail passes through the inserted link of front and rear sides, It is connected with the 3rd connecting rod between the inserted link of front and rear sides, the 3rd connecting rod is located above the second slide rail, the 3rd connecting rod and the Drawstring is connected between Four-slider, when the rotation for needing to make the second slide rail stable, user of service will be slotting in the 3rd connecting rod Bar is inserted into the through hole in Four-slider, and inserted link will followed by the rotation of the second slide rail and rotate, when not needing the second slide rail During stable rotation, user of service takes down the inserted link being inserted in through hole, the inserted link of the setting energy when the second slide rail is rotated Its is stabilized, prevent the second slide rail from bent in rotation process.
Because also including the 4th connecting rod, the 5th connecting rod and third baffle, the second slide rail left and right sides is symmetrically connected There is the 4th connecting rod, the second slide rail front and rear sides are symmetrically connected with the top of the 5th connection, the second slide rail and are connected with third baffle, if The 4th connecting rod put and the 5th connecting rod prevent petroleum pipeline from falling down so that the second slide rail keeps stable when rotating, The third baffle of setting can be protected to motor, can prevent dust or other impurities from dropping in motor.
Because also include first annular baffle plate, the second ring baffle, the second installing plate, second spring, the first pole and Steel wire rope, places plate outer wall and is connected with first annular baffle plate, first annular baffle plate top is connected with the second ring baffle, places plate Top, which is uniformly connected with the top of second spring, second spring, is connected with the second installing plate, with the 3rd slide rail at the top of the second installing plate It is connected with the top of connection, the first baffle in left side at the top of the first pole, the first baffle on right side and is connected with steel wire rope, steel wire rope Left end is wound on the first pole, and the second spring of setting can play shockproof during the device transporting petroleum pipeline to it The effect of decompression, petroleum pipeline that can be in transportation plays a part of protection.
Because also including the second pole, the 3rd mounting blocks and illuminating lamp, the second pole is connected with the top of third baffle, the The 3rd mounting blocks are connected with the top of two poles, the 3rd mounting blocks bottom left and right sides is provided with illuminating lamp, and the illuminating lamp of setting makes Obtain the device night or light dark place need not also can transporting petroleum pipeline by extraneous light.
(3) beneficial effect
Position transfer device on a kind of petroleum pipeline production line of the present invention, the first spring of setting allows the device to fortune The petroleum pipeline of defeated different model size, the inserted link of setting can be stabilized by its when the second slide rail is rotated, and prevents the second slide rail It bent in rotation process, the third baffle of setting can be protected to motor, can prevent dust or other impurities from dropping To motor, the second spring of setting can play a part of shockproof decompression, energy during the device transporting petroleum pipeline to it Petroleum pipeline in enough transportations plays a part of protection, and the illuminating lamp of setting causes the device dark at night or light Place need not also can transporting petroleum pipeline by extraneous light.
Brief description of the drawings
Fig. 1 is overlooking the structure diagram of the invention.
Fig. 2 is the overlooking the structure diagram of drive mechanism of the present invention.
Fig. 3 is the overlooking the structure diagram of placement mechanism of the present invention.
Fig. 4 is the first partial top structural representation of the invention.
Fig. 5 is second of partial top structural representation of the invention.
Fig. 6 is the first part main structure diagram of the invention.
Fig. 7 is second of part main structure diagram of the invention.
Mark in accompanying drawing for:1- bottom plates, 2- drive mechanisms, the slide rails of 201- first, 202- head rods, 203- first Sliding block, the connecting rods of 204- second, the sliding blocks of 205- second, the slide rails of 206- second, 207- motors, 208- runners, 3- placement mechanisms, 301- places plate, the slide rails of 302- the 3rd, the sliding blocks of 303- the 3rd, the installing plates of 304- first, the block rubbers of 305- first, 306- first gear Plate, 307- second baffles, the block rubbers of 308- second, the springs of 309- first, the ring-like slide rails of 4-, 5- Four-sliders, 6- through holes, 7- is inserted Bar, the connecting rods of 8- the 3rd, 9- drawstrings, the connecting rods of 10- the 4th, the connecting rods of 11- the 5th, 12- third baffles, the first annular gears of 13- Plate, the ring baffles of 14- second, the installing plates of 15- second, 16- second springs, the poles of 17- first, 18- steel wire ropes, 19- second Bar, the mounting blocks of 20- the 3rd, 21- illuminating lamps.
Embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment 1
Position transfer device on a kind of petroleum pipeline production line, as shown in figs. 1-7, includes bottom plate 1, the and of drive mechanism 2 Placement mechanism 3, the top of bottom plate 1 is connected with drive mechanism 2, and the top of drive mechanism 2 is connected with placement mechanism 3.
Embodiment 2
Position transfer device on a kind of petroleum pipeline production line, as shown in figs. 1-7, includes bottom plate 1, the and of drive mechanism 2 Placement mechanism 3, the top of bottom plate 1 is connected with drive mechanism 2, and the top of drive mechanism 2 is connected with placement mechanism 3.
Drive mechanism 2 includes the first slide rail 201, head rod 202, the first sliding block 203, the second connecting rod 204, Two sliding blocks 205, the second slide rail 206, motor 207 and runner 208, the top of bottom plate 1 are connected with the first slide rail 201, the first slide rail 201 On all around the equal slidingtype in four sides be connected with the first sliding block 203, bottom plate 1 and be connected with head rod 202, head rod 202 crown centers are provided with motor 207, the output shaft of motor 207 and are connected with runner 208, and the outer wall of runner 208 is all around Four sides are respectively connected with the second slide rail 206, the second slide rail 206 equal slidingtype and are connected with the second sliding block 205, the second sliding block 205 Rotary type is connected with the second connecting rod 204, and the second connecting rod 204 is connected with the rotary type of the first sliding block 203.
Embodiment 3
Position transfer device on a kind of petroleum pipeline production line, as shown in figs. 1-7, includes bottom plate 1, the and of drive mechanism 2 Placement mechanism 3, the top of bottom plate 1 is connected with drive mechanism 2, and the top of drive mechanism 2 is connected with placement mechanism 3.
Drive mechanism 2 includes the first slide rail 201, head rod 202, the first sliding block 203, the second connecting rod 204, Two sliding blocks 205, the second slide rail 206, motor 207 and runner 208, the top of bottom plate 1 are connected with the first slide rail 201, the first slide rail 201 On all around the equal slidingtype in four sides be connected with the first sliding block 203, bottom plate 1 and be connected with head rod 202, head rod 202 crown centers are provided with motor 207, the output shaft of motor 207 and are connected with runner 208, and the outer wall of runner 208 is all around Four sides are respectively connected with the second slide rail 206, the second slide rail 206 equal slidingtype and are connected with the second sliding block 205, the second sliding block 205 Rotary type is connected with the second connecting rod 204, and the second connecting rod 204 is connected with the rotary type of the first sliding block 203.
Placement mechanism 3 includes placement plate 301, the 3rd slide rail 302, the 3rd sliding block 303, the first installing plate 304, the first rubber Blob of viscose 305, first baffle 306, second baffle 307, the second block rubber 308 and the first spring 309, place the top of plate 301 front and rear Both sides are respectively connected with the equal slidingtype in the left and right sides on the 3rd slide rail 302, the 3rd slide rail 302 and are connected with the 3rd sliding block 303, left and right two The top of the 3rd sliding block 303 of side is respectively connected with the first installing plate 304, and the top left and right sides of the first installing plate 304 is respectively connected with the One baffle plate 306, the inner side of first baffle 306 of the left and right sides is respectively connected with the first block rubber 305, the crown center of the 3rd slide rail 302 The second block rubber 308 is connected with, the top left and right sides of the 3rd slide rail 302 is respectively connected with second baffle 307, the second block rubber 308 Between the second baffle 307 of the left and right sides, the second baffle of the inner side of the 3rd sliding block 303 and the left and right sides of the left and right sides The first spring 309 is connected between 307 outsides.
Embodiment 4
Position transfer device on a kind of petroleum pipeline production line, as shown in figs. 1-7, includes bottom plate 1, the and of drive mechanism 2 Placement mechanism 3, the top of bottom plate 1 is connected with drive mechanism 2, and the top of drive mechanism 2 is connected with placement mechanism 3.
Drive mechanism 2 includes the first slide rail 201, head rod 202, the first sliding block 203, the second connecting rod 204, Two sliding blocks 205, the second slide rail 206, motor 207 and runner 208, the top of bottom plate 1 are connected with the first slide rail 201, the first slide rail 201 On all around the equal slidingtype in four sides be connected with the first sliding block 203, bottom plate 1 and be connected with head rod 202, head rod 202 crown centers are provided with motor 207, the output shaft of motor 207 and are connected with runner 208, and the outer wall of runner 208 is all around Four sides are respectively connected with the second slide rail 206, the second slide rail 206 equal slidingtype and are connected with the second sliding block 205, the second sliding block 205 Rotary type is connected with the second connecting rod 204, and the second connecting rod 204 is connected with the rotary type of the first sliding block 203.
Placement mechanism 3 includes placement plate 301, the 3rd slide rail 302, the 3rd sliding block 303, the first installing plate 304, the first rubber Blob of viscose 305, first baffle 306, second baffle 307, the second block rubber 308 and the first spring 309, place the top of plate 301 front and rear Both sides are respectively connected with the equal slidingtype in the left and right sides on the 3rd slide rail 302, the 3rd slide rail 302 and are connected with the 3rd sliding block 303, left and right two The top of the 3rd sliding block 303 of side is respectively connected with the first installing plate 304, and the top left and right sides of the first installing plate 304 is respectively connected with the One baffle plate 306, the inner side of first baffle 306 of the left and right sides is respectively connected with the first block rubber 305, the crown center of the 3rd slide rail 302 The second block rubber 308 is connected with, the top left and right sides of the 3rd slide rail 302 is respectively connected with second baffle 307, the second block rubber 308 Between the second baffle 307 of the left and right sides, the second baffle of the inner side of the 3rd sliding block 303 and the left and right sides of the left and right sides The first spring 309 is connected between 307 outsides.
Also include ring-like slide rail 4, Four-slider 5, inserted link 7, the 3rd connecting rod 8 and drawstring 9, head rod 202 is pushed up Portion is connected with ring-like slide rail 4, and the equal slidingtype in four sides all around of ring-like slide rail 4 is connected with Four-slider 5, and Four-slider 5 is pushed up Portion front and rear sides, which are provided with through hole 6, through hole 6, is provided with inserted link 7, and inserted link 7 passes through through hole 6, and the second slide rail 206 passes through front and rear sides Inserted link 7, the 3rd connecting rod 8 is connected between the inserted link 7 of front and rear sides, the 3rd connecting rod 8 is located at the top of the second slide rail 206, Drawstring 9 is connected between 3rd connecting rod 8 and Four-slider 5.
Also include the 4th connecting rod 10, the 5th connecting rod 11 and third baffle 12, the left and right sides of the second slide rail 206 is symmetrical The 4th connecting rod 10 is connected with, the front and rear sides of the second slide rail 206 are symmetrically connected with the 5th connecting rod 11, the top of the second slide rail 206 It is connected with third baffle 12.
Also include first annular baffle plate 13, the second ring baffle 14, the second installing plate 15, second spring 16, first Bar 17 and steel wire rope 18, place the outer wall of plate 301 and are connected with first annular baffle plate 13, the first annular top of baffle plate 13 is connected with second Ring baffle 14, places uniform be connected with the top of second spring 16, second spring 16 in the top of plate 301 and is connected with the second installing plate 15, the top of the second installing plate 15 is connected with the 3rd slide rail 302, and the top of first baffle 306 in left side is connected with the first pole 17, right The top of first baffle 306 of side is connected with steel wire rope 18, and the left end of steel wire rope 18 is wound on the first pole 17.
Also include the second pole 19, the 3rd mounting blocks 20 and illuminating lamp 21, the top of third baffle 12 is connected with second Bar 19, the top of the second pole 19 is connected with the 3rd mounting blocks 20, and the bottom left and right sides of the 3rd mounting blocks 20 is provided with illuminating lamp 21.
Operation principle:When needing using the device to carry out position transfer on a production line to petroleum pipeline, user The petroleum pipeline for needing to shift is positioned in placement mechanism 3 by member, afterwards by starting drive mechanism 2 come to the stone for needing to shift Oil-piping carries out position transfer.
Because drive mechanism 2 includes the first slide rail 201, head rod 202, the first sliding block 203, the second connecting rod 204th, the second sliding block 205, the second slide rail 206, motor 207 and runner 208, the top of bottom plate 1 are connected with the first slide rail 201, first All around the equal slidingtype in four sides is connected with the first sliding block 203, bottom plate 1 and is connected with head rod 202 on slide rail 201, the The crown center of one connecting rod 202, which is provided with motor 207, the output shaft of motor 207, is connected with runner 208, the outer wall of runner 208 All around four sides are respectively connected with the second slide rail 206, the second slide rail 206 equal slidingtype and are connected with the second sliding block 205, and second slides Rotary type is connected with the second connecting rod 204 on block 205, and the second connecting rod 204 is connected with the rotary type of the first sliding block 203, works as needs During using the device to carry out position transfer to petroleum pipeline, user of service enables motor 207 and rotated, and runner 208 will be rotated, Runner 208, which is rotated, will drive the second sliding block 205 to slide, so that drive the first sliding block 203 to be slided in the first slide rail 201, the One sliding block 203 is slided in the first slide rail 201 just can drive placement mechanism 3 to rotate, it is achieved thereby that the position of petroleum pipeline turns Move.
Because placement mechanism 3 includes placement plate 301, the 3rd slide rail 302, the 3rd sliding block 303, the first installing plate 304, the One block rubber 305, first baffle 306, second baffle 307, the second block rubber 308 and the first spring 309, place the top of plate 301 Front and rear sides are respectively connected with the equal slidingtype in the left and right sides on the 3rd slide rail 302, the 3rd slide rail 302 and are connected with the 3rd sliding block 303, left The top of the 3rd sliding block 303 of right both sides is respectively connected with the first installing plate 304, and the top left and right sides of the first installing plate 304 is all connected with There is first baffle 306, the inner side of first baffle 306 of the left and right sides is respectively connected with the first block rubber 305, the top of the 3rd slide rail 302 Centre is connected with the second block rubber 308, and the top left and right sides of the 3rd slide rail 302 is respectively connected with second baffle 307, the second block rubber 308 are located between the second baffle 307 of the left and right sides, the second gear of the inner side of the 3rd sliding block 303 and the left and right sides of the left and right sides Plate 307 is connected with the first spring 309 between outside, when petroleum pipeline needs transferring position, and user of service is by stone to be transferred Oil-piping is positioned on the second block rubber 308, when petroleum pipeline than it is larger when, oil-piping extrude the left and right sides the first block rubber 305, now the 3rd sliding block 303 of the left and right sides will be moved laterally, so that the first spring 309 is stretched, afterwards in driving In the presence of mechanism 2, petroleum pipeline will be transported to destination, when removing transported oil from the second block rubber 308 During pipeline, the first spring 309 restores to the original state so that the 3rd sliding block 303 of the left and right sides inwards side move back to it is original Position, the first block rubber 305 for driving the left and right sides is returned to raw bits to the 3rd sliding block 303 of the left and right sides by side movement inwards Put, the first block rubber 305 and the second block rubber 308 of setting can protect the petroleum pipeline surface in transportation not damaged Wound, the first spring 309 of setting allows the device to transport the petroleum pipeline of different model size.
Also include ring-like slide rail 4, Four-slider 5, inserted link 7, the 3rd connecting rod 8 and drawstring 9, first because also including The top of connecting rod 202 is connected with ring-like slide rail 4, and the equal slidingtype in four sides all around of ring-like slide rail 4 is connected with Four-slider 5, The top front and rear sides of Four-slider 5, which are provided with through hole 6, through hole 6, is provided with inserted link 7, and inserted link 7 passes through through hole 6, the second slide rail 206 Through the inserted link 7 of front and rear sides, the 3rd connecting rod 8 is connected between the inserted link 7 of front and rear sides, the 3rd connecting rod 8 is located at second The top of slide rail 206, drawstring 9 is connected between the 3rd connecting rod 8 and Four-slider 5, when turn for needing to make the second slide rail 206 stable When dynamic, the inserted link 7 in the 3rd connecting rod 8 is inserted into the through hole 6 in Four-slider 5 by user of service, and inserted link 7 will followed by the The rotation of two slide rails 206 and rotate, when not needing the stable rotation of the second slide rail 206, user of service will be inserted in through hole 6 Inserted link 7 is taken down, and the inserted link 7 of setting can be stabilized by its when the second slide rail 206 is rotated, and prevents the second slide rail 206 from turning It bent during dynamic.
Because also including the 4th connecting rod 10, the 5th connecting rod 11 and third baffle 12, the left and right sides of the second slide rail 206 The 4th connecting rod 10 is symmetrically connected with, the front and rear sides of the second slide rail 206 are symmetrically connected with the 5th connection, the top of the second slide rail 206 Third baffle 12 is connected with, the 4th connecting rod 10 of setting and the 5th connecting rod 11 cause the second slide rail 206 to be kept when rotating It is stable, prevent petroleum pipeline from falling down, the third baffle 12 of setting can be protected to motor 207, can prevent dust or Person's other impurities are dropped in motor 207.
Because also including first annular baffle plate 13, the second ring baffle 14, the second installing plate 15, second spring 16, One pole 17 and steel wire rope 18, place the outer wall of plate 301 and are connected with first annular baffle plate 13, the first annular top of baffle plate 13 is connected with Second ring baffle 14, places uniform be connected with the top of second spring 16, second spring 16 in the top of plate 301 and is connected with the second installation Plate 15, the top of the second installing plate 15 is connected with the 3rd slide rail 302, and the top of first baffle 306 in left side is connected with the first pole 17, The top of first baffle 306 on right side is connected with steel wire rope 18, and the left end of steel wire rope 18 is wound on the first pole 17, and the of setting Two springs 16 can play a part of shockproof decompression during the device transporting petroleum pipeline to it, can be in transportation Petroleum pipeline plays a part of protection.
Because also including the second pole 19, the 3rd mounting blocks 20 and illuminating lamp 21, the top of third baffle 12 is connected with the Two poles 19, the top of the second pole 19 is connected with the 3rd mounting blocks 20, and the bottom left and right sides of the 3rd mounting blocks 20 is provided with illumination Lamp 21, the illuminating lamp 21 of setting cause the device night or light dark place need not also can by extraneous light Transporting petroleum pipeline.
Embodiment described above only expresses the preferred embodiment of the present invention, and it describes more specific and detailed, but simultaneously Therefore the limitation to the scope of the claims of the present invention can not be interpreted as.It should be pointed out that for one of ordinary skill in the art For, without departing from the inventive concept of the premise, some deformations can also be made, improves and substitutes, these belong to this hair Bright protection domain.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (7)

1. position transfer device on a kind of petroleum pipeline production line, it is characterised in that include bottom plate (1), drive mechanism (2) and It is connected with the top of placement mechanism (3), bottom plate (1) at the top of drive mechanism (2), drive mechanism (2) and is connected with placement mechanism (3).
2. position transfer device on a kind of petroleum pipeline production line according to claim 1, it is characterised in that drive mechanism (2) the first slide rail (201), head rod (202), the first sliding block (203), the second connecting rod (204), the second sliding block are included (205) the first slide rail (201), first are connected with the top of, the second slide rail (206), motor (207) and runner (208), bottom plate (1) All around the equal slidingtype in four sides is connected with the first sliding block (203), bottom plate (1) and is connected with head rod on slide rail (201) (202), head rod (202) crown center is provided with motor (207), the output shaft of motor (207) and is connected with runner (208), all around four sides are respectively connected with the second slide rail (206) to the outer wall of runner (208), and the second slide rail is slided on (206) Formula is connected with rotary type on the second sliding block (205), the second sliding block (205) and is connected with the second connecting rod (204), the second connecting rod (204) it is connected with the first sliding block (203) rotary type.
3. position transfer device on a kind of petroleum pipeline production line according to claim 2, it is characterised in that placement mechanism (3) placement plate (301), the 3rd slide rail (302), the 3rd sliding block (303), the first installing plate (304), the first block rubber are included (305), first baffle (306), second baffle (307), the second block rubber (308) and the first spring (309), place plate (301) Top front and rear sides are respectively connected with the equal slidingtype in the left and right sides on the 3rd slide rail (302), the 3rd slide rail (302) and are connected with the 3rd cunning The first installing plate (304), the first installing plate (304) top are respectively connected with the top of block (303), the 3rd sliding block (303) of the left and right sides The portion left and right sides is respectively connected with the inside of first baffle (306), the first baffle (306) of the left and right sides and is respectively connected with the first block rubber (305), the 3rd slide rail (302) crown center is connected with the second block rubber (308), and the 3rd slide rail (302) the top left and right sides is equal Second baffle (307) is connected with, the second block rubber (308) is located between the second baffle (307) of the left and right sides, the left and right sides The first spring (309) is connected between on the inside of 3rd sliding block (303) and on the outside of the second baffle (307) of the left and right sides.
4. position transfer device on a kind of petroleum pipeline production line according to claim 3, it is characterised in that also include Connect at the top of ring-like slide rail (4), Four-slider (5), inserted link (7), the 3rd connecting rod (8) and drawstring (9), head rod (202) Ring-like slide rail (4) is connected to, the equal slidingtype in four sides all around of ring-like slide rail (4) is connected with Four-slider (5), Four-slider (5) top front and rear sides, which are provided with through hole (6), through hole (6), is provided with inserted link (7), and inserted link (7) passes through through hole (6), the second slide rail (206) pass through and the 3rd connecting rod (8) is connected between the inserted link (7) of front and rear sides, the inserted link (7) of front and rear sides, the 3rd connection Bar (8) is located above the second slide rail (206), and drawstring (9) is connected between the 3rd connecting rod (8) and Four-slider (5).
5. position transfer device on a kind of petroleum pipeline production line according to claim 4, it is characterised in that also include 4th connecting rod (10), the 5th connecting rod (11) and third baffle (12), the second slide rail (206) left and right sides are symmetrically connected with Four connecting rods (10), the second slide rail (206) front and rear sides are symmetrically connected with the top of the 5th connecting rod (11), the second slide rail (206) It is connected with third baffle (12).
6. position transfer device on a kind of petroleum pipeline production line according to claim 5, it is characterised in that also include First annular baffle plate (13), the second ring baffle (14), the second installing plate (15), second spring (16), the first pole (17) and Steel wire rope (18), places plate (301) outer wall and is connected with first annular baffle plate (13), and the is connected with the top of first annular baffle plate (13) Second ring baffle plate (14), places uniform be connected with the top of second spring (16), second spring (16) at the top of plate (301) and is connected with the It is connected, connects at the top of the first baffle (306) in left side with the 3rd slide rail (302) at the top of two installing plates (15), the second installing plate (15) It is connected at the top of the first pole (17), the first baffle (306) on right side and is connected with steel wire rope (18), the left end winding of steel wire rope (18) In on the first pole (17).
7. position transfer device on a kind of petroleum pipeline production line according to claim 6, it is characterised in that also include The second pole (19) is connected with the top of second pole (19), the 3rd mounting blocks (20) and illuminating lamp (21), third baffle (12), the The 3rd mounting blocks (20) are connected with the top of two poles (19), the 3rd mounting blocks (20) bottom left and right sides is provided with illuminating lamp (21)。
CN201710733907.2A 2017-08-24 2017-08-24 Position transfer device on a kind of petroleum pipeline production line Active CN107298291B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710733907.2A CN107298291B (en) 2017-08-24 2017-08-24 Position transfer device on a kind of petroleum pipeline production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710733907.2A CN107298291B (en) 2017-08-24 2017-08-24 Position transfer device on a kind of petroleum pipeline production line

Publications (2)

Publication Number Publication Date
CN107298291A true CN107298291A (en) 2017-10-27
CN107298291B CN107298291B (en) 2019-04-16

Family

ID=60132564

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710733907.2A Active CN107298291B (en) 2017-08-24 2017-08-24 Position transfer device on a kind of petroleum pipeline production line

Country Status (1)

Country Link
CN (1) CN107298291B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202070847U (en) * 2011-05-20 2011-12-14 浙江正泰电器股份有限公司 Multiple-station turntable type automatic welding equipment
JP2012040961A (en) * 2010-08-19 2012-03-01 Daifuku Co Ltd Article carrying facility
CN203382052U (en) * 2013-07-30 2014-01-08 济南大学 Cylinder-like material conveying device
CN203921931U (en) * 2014-06-19 2014-11-05 诸暨市赵家华辉干燥设备厂 Slide plate travel line and turning platform thereof
CN104909104A (en) * 2015-06-24 2015-09-16 上海观谷科技有限公司 Rotary track and medicine storage system
CN205413520U (en) * 2015-12-21 2016-08-03 重庆飚风电镀有限公司 Rotation type application frock

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012040961A (en) * 2010-08-19 2012-03-01 Daifuku Co Ltd Article carrying facility
CN202070847U (en) * 2011-05-20 2011-12-14 浙江正泰电器股份有限公司 Multiple-station turntable type automatic welding equipment
CN203382052U (en) * 2013-07-30 2014-01-08 济南大学 Cylinder-like material conveying device
CN203921931U (en) * 2014-06-19 2014-11-05 诸暨市赵家华辉干燥设备厂 Slide plate travel line and turning platform thereof
CN104909104A (en) * 2015-06-24 2015-09-16 上海观谷科技有限公司 Rotary track and medicine storage system
CN205413520U (en) * 2015-12-21 2016-08-03 重庆飚风电镀有限公司 Rotation type application frock

Also Published As

Publication number Publication date
CN107298291B (en) 2019-04-16

Similar Documents

Publication Publication Date Title
CN106522356A (en) Special dredging vehicle for sewer man-hole
CN202249866U (en) Underground differential-speed cable traction device
CN108775656A (en) A kind of portable type air purifier
JP2021061816A (en) Flower pot adding water with intelligence sensing
CN106764767A (en) A kind of anti-lamp holder falls automatic lifting street lamp
CN108482661B (en) A kind of petroleum pipeline on-bne repair unmanned plane
CN101007618B (en) Swing winch rope-discharging method and device
CN107298291A (en) Position transfer device on a kind of petroleum pipeline production line
CN107487747B (en) A kind of petroleum pipeline transport device
CN206647790U (en) A kind of LED frame dispensing press fit device
CN107697431A (en) A kind of natural gas line design drawing storage box
CN203428911U (en) Feeding system for pyrite acid-making fluidized bed roasters
CN102840563B (en) Lifting device without motor
CN109607092A (en) A kind of stable gradual change type suspension pallet transfer
CN204492698U (en) Swing arm tubing string transmission system
CN204787680U (en) Chain drive baking house device
CN203963582U (en) Single-ended glass mould 360 degree light emitting LED lamp
CN210687918U (en) Practical LED wall lamp device
CN103714757A (en) Overturning type player with adjusting device
CN209582643U (en) A kind of novel hose storage automatic cycle shelf
CN207093938U (en) A kind of Novel cultivation industry water pipe hanger
CN110550554A (en) Glass's for building hoist and mount protection fixing device
CN204827659U (en) Engine drive mechanism
CN213422299U (en) Flowmeter for conveying natural gas
CN210558892U (en) Hoisting equipment for underground mining field

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20190320

Address after: 312500 No. 110, Qishicun, Nanxiang, Xinchang County, Shaoxing City, Zhejiang Province

Applicant after: XINCHANG QIYAO BUILDING MATERIAL Co.,Ltd.

Address before: 330046 No. 808 Shuanggang East Street, Qingshan Lake District, Nanchang City, Jiangxi Province

Applicant before: Fan Zhengzhuo

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20171027

Assignee: Hangzhou Zhike Technology Co.,Ltd.

Assignor: XINCHANG QIYAO BUILDING MATERIAL Co.,Ltd.

Contract record no.: X2021330000631

Denomination of invention: A position transfer device for oil pipeline production line

Granted publication date: 20190416

License type: Common License

Record date: 20211028

EE01 Entry into force of recordation of patent licensing contract
EC01 Cancellation of recordation of patent licensing contract

Assignee: Hangzhou Zhike Technology Co.,Ltd.

Assignor: XINCHANG QIYAO BUILDING MATERIAL Co.,Ltd.

Contract record no.: X2021330000631

Date of cancellation: 20230220

EC01 Cancellation of recordation of patent licensing contract