CN107292585A - A kind of development project information management system based on PLM platforms - Google Patents

A kind of development project information management system based on PLM platforms Download PDF

Info

Publication number
CN107292585A
CN107292585A CN201710501038.0A CN201710501038A CN107292585A CN 107292585 A CN107292585 A CN 107292585A CN 201710501038 A CN201710501038 A CN 201710501038A CN 107292585 A CN107292585 A CN 107292585A
Authority
CN
China
Prior art keywords
project
submodule
management module
risk
plm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710501038.0A
Other languages
Chinese (zh)
Inventor
褚景春
吴兵
贾冰
宋鑫
宋一鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guodian United Power Technology Co Ltd
Original Assignee
Guodian United Power Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guodian United Power Technology Co Ltd filed Critical Guodian United Power Technology Co Ltd
Priority to CN201710501038.0A priority Critical patent/CN107292585A/en
Publication of CN107292585A publication Critical patent/CN107292585A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of development project information management system based on PLM platforms, including:Logging in management module is used to provide User logs in and quits a program;Project initiation management module is used to realize that item types definition, project examination and project status determine program;Project plan progress module is used to realize that project task planning, task scheduling create and safeguarded WBS tasks, starts Specialty Program task decomposition and distribution program;Project communication and risk management module are used to realize BBS function settings, problem and risk report, risk class, risk classifications and risk profile management program;Date selection that project resource management module is used to realizing technical ability role selecting, request starts and request terminates, the selection of resource department and monthly full-time employee's quantity of equal value and resources costs option program.The present invention integrate the project application, examination & verification, statistical summaries, report printing, examination & approval put on record, manage, monitor function, macroscopic view comprehensively, the efficiency of management is high, practical.

Description

A kind of development project information management system based on PLM platforms
Technical field
The invention belongs to research and develop management system, in particular to a kind of development project information management based on PLM platforms System.
Background technology
Variation and the scale of project of the Modern Enterprise Administration due to information become increasingly complex, the manager of project and execution The task that person is faced is also more and more.How these tasks reasonably to be planned, perform and monitoring has become project The major issue to be faced in management.
Traditional project management system is typically only capable to provide some simple plans and monitoring tools for project administrator, and It can do nothing to help them and these plans effectively conveyed into related people to monitoring information, in this case, people must consume The substantial amounts of time is used for meeting and other are linked up, and these meetings and communication consume plenty of time and resource, and are difficult to ensure that The accuracy and uniformity of information.Among project is carried out, project personnel have considerable task to need execution, and each task has not Same content, priority and time requirement, conventional items management system can do nothing to help each program member and accurately, easily searches These mission bit streams, can not also provide effective instrument and mission bit stream can be carried out more to project team at any time by program member Newly, when the scale of project is increasing, after task quantity and elapsed time are increasingly grown, chaotic task management may be to item Purpose success or failure produce detrimental effects.
Traditional project management system another question is to be difficult to project personnel in the project implementation process to provide accurate True project status monitoring information, such as project process, project status etc..Research and development of products depends on the experience of research staff, write from memory Contract and the responsible attitude to work.The responsibilities of project participant, forward-backward correlation relation, perform content, deliver part etc. still It is not clear defined, the Critical Success Factors of project stage property target and Technical Review point, lacks the rule that can clearly follow and fall The real method performed.
As can be seen here, above-mentioned existing traditional Project information management system has still suffered from inconvenience and defect, and urgently adds Further to improve.How a kind of new development project information management system based on PLM platform is founded, can be to project In each task carry out effectively, centralized management and monitoring, it is allowed to project related personnel is more accurate, fast by PLM platforms The acquisition item related information of speed and the various project managements of progress and execution activity, improved target is needed as current industry pole.
The content of the invention
, can be to each in project it is an object of the invention to provide a kind of project management system based on PLM platforms Item task carries out effective, centralized management and monitoring, it is allowed to which project related personnel more accurately and rapidly obtains by PLM platforms Take item related information and carry out various project managements and execution activity, each related personnel is cooperateed with the project life cycle Ground is managed to product development, manufacture, sale.
In order to solve the above technical problems, the present invention provides a kind of development project information management system based on PLM platforms, bag Include:Log in management module, project initiation management module, project plan progress module, project communication and risk management module and item Mesh resource management module,
The login management module, for providing User logs in and the step that quits a program;
The project initiation management module, for realizing that item types definition, project examination and project status determine program Step;
The project plan progress module, for realizing that project task planning, task scheduling create and safeguarded that WBS appoints Business, starts Specialty Program task decomposition and distribution program step;
The project communication and risk management module, for realizing BBS function settings, problem and risk report, risk etc. Level, risk classifications and risk profile management program step;
The project resource management module, the date for realizing technical ability role selecting, request starts and request terminates is selected Select, the selection of resource department and the monthly quantity and resources costs option program step of full-time employee of equal value.
As a modification of the present invention, the login management module includes User logs in submodule and user exits submodule Block, the login management module provides secure log using ssl protocol.
Further improve, the project initiation management module defines submodule, project examination submodule including item types And project status determination sub-module.
Further improve, the project plan progress module includes project task planning submodule, task scheduling and created WBS task submodules are built and safeguarded, start Specialty Program task decomposition and distribution submodule.
Further improve, the project communication and risk management module include BBS function settings submodule, problem and risk Report submodule, risk class submodule, risk classifications submodule, risk profile management submodule.
Further improve, the project resource management module includes technical ability role selecting submodule, request and starts and ask Close Date selection submodule, monthly resource department selection submodule, full-time employee's quantity and resources costs selection of equal value Submodule.
After adopting the above technical scheme, the present invention at least has advantages below:
Development project information management system of the invention based on PLM platforms, can make all personnel relevant with project exist The data related to project are shared in whole life cycle of information, the project application can be collected, examination & verification, statistical summaries, report printing, careful The function such as batch put, manage, supervising on record in one, data analysis is comprehensively macroscopical, and the efficiency of management is higher, practical, it is easy to promote.
Brief description of the drawings
Above-mentioned is only the general introduction of technical solution of the present invention, in order to better understand the technological means of the present invention, below With reference to accompanying drawing, the present invention is described in further detail with embodiment.
Fig. 1 is the structural representation of the development project information management system of the invention based on PLM platforms.
Embodiment
Referring to the drawings shown in 1, the development project information management system of the invention based on PLM platforms, including log in management mould Block, project initiation management module, project plan progress module, project communication and risk management module and project resource management mould Block.Wherein:
The login module includes User logs in submodule and user exits submodule.The login management module is assisted using SSL View provides secure log, and the certificate deployment on PLM server, client does not have certificate not log in.And in view of future The requirement of distributed collaborative, PLM use distributed system architecture scheme, various regions user using physics independence Oracle systems and File server.Backup can be using a backup server centralized backup.When application is larger, server set can be used Group's (cluster:) and load balancing improves systematic function cluster.
The project initiation management module defines submodule, project examination submodule and project status including item types and determined Submodule.Wherein:Item types define submodule include determine technical research type project templet, new product development type project templet, Product sustained improvement type project templet, project management climbing shuttering, science and technology item declare template, standardization project template and knowledge Property right project templet.
The project examination submodule is in following establishment project, and project sponsor unit acquiescence can create " copending an item Mesh ", " copending project " is a project without the name before formally setting up the project." copending project " is only by certain examination & approval stream Cheng Hou, can just be transformed into the formal project for starting to perform.Main approval process is as follows:Project initiation head of the unit logs in system System, into after the operating environment of project, by " create project conceive " in " action " menu, newly-built " copending of expression one Project ".It is ready for finishing in related literary document and task scheduling book, tissue related personnel can be started and prepare examination & approval, confirmation is It is no to be converted to actual project implementation.Once countersign passes through, copending project will change the project that can formally perform.Really simultaneously It is startup to determine project status.
The project plan progress module includes project task planning submodule, task scheduling and creates and safeguard that WBS appoints Business submodule, starts Specialty Program task decomposition and distribution submodule.When in use, with " project manager " role's login system, Into a certain purpose operating environment, click on " WBS ", show the work breakdown structure (WBS) of the project, click in menu and " enable volume Volume " order, the overall tasks of edit item plan to show in project task planning submodule, can carry out the increasing of task Plus, insertion, deletion, the operation such as attributes edit.When inserting new task, task attribute is filled in pop-up dialogue box, passes through this Business plan creates and safeguarded that WBS task submodules add/establishment task (stage, project important node, evaluation), and addition is replicated Dependence between WBS, addition modification task, by project role's assigned tasks.Project manager according to main delivered product and The first layer point that project stage (or key node) is planned by the startup Specialty Program task decomposition and distribution submodule Solution, and determine the department that planned start time, end time, the task leader of delivered product sum and task are distributed.May be used also To filter basic layer by " filter " order, can be carried out by the menu on " operation " menu attribute, the time and The selection of professional person liable.
The project communication and risk management module include BBS function settings submodule, problem and risk report submodule, wind Dangerous grade submodule, risk classifications submodule, risk profile management submodule.Lead to the built-in BBS function setting submodules, item Mesh member can in BBS the related technical problem of colloquy project, while program member can be checked with login system with from The content of the discussions of oneself correlation.For the discussion created, program member can reply or upload annex and be described in detail, and also may be used To change or delete the reply content of oneself.And the problem and risk report submodule, risk class submodule, wind can be passed through Dangerous type submodule, risk profile management submodule carry out risk profile.
The project resource management module includes technical ability role selecting submodule, request and started and request Close Date selection Module, monthly resource department selection submodule, full-time employee's quantity and resources costs selection submodule of equal value.Pass through this Mesh resource management module sets up program member's information, and packet contains Chinese and English name, department, position, employee number, is in charge of and is System, E-mail address, phone, technical ability and speciality, department resource manager etc., project manager can be according to these information searchings Mesh member and to the resource needed for resource manager's application project.Simultaneously establishing resource plan application can by two ways, Directly create or the WBS job orders based on current project.During establishing resource application, the technical ability of personnel needed for project manager need to provide Role, affiliated function, preferred personnel ask Start Date, ask the Close Date, resource department, and FTE is (monthly of equal value complete Office worker's work) information such as quantity and resources costs.
The above described is only a preferred embodiment of the present invention, any formal limitation not is made to the present invention, this Art personnel make a little simple modification, equivalent variations or modification using the technology contents of the disclosure above, all fall within this hair In bright protection domain.

Claims (8)

1. a kind of development project information management system based on PLM platforms, it is characterised in that including:Log in management module, project Start management module, project plan progress module, project communication and risk management module and project resource management module,
The login management module, for providing User logs in and the step that quits a program;
The project initiation management module, for realizing that item types definition, project examination and project status determine program step;
The project plan progress module, for realizing that project task planning, task scheduling create and safeguarded WBS tasks, Start Specialty Program task decomposition and distribution program step;
The project communication and risk management module, for realizing BBS function settings, problem and risk report, risk class, wind Dangerous type and risk profile management program step;
The project resource management module, the date selection terminated for realizing technical ability role selecting, request to start and ask, money The selection of source department and the monthly quantity and resources costs option program step of full-time employee of equal value.
2. the development project information management system according to claim 1 based on PLM platforms, it is characterised in that described to step on Record management module includes User logs in submodule and user exits submodule, and the login management module is provided using ssl protocol Secure log.
3. the development project information management system according to claim 2 based on PLM platforms, it is characterised in that described to step on Record PLM platforms in management module and use distributed system architecture scheme.
4. the development project information management system according to claim 1 based on PLM platforms, it is characterised in that the item Mesh starts management module and defines submodule, project examination submodule and project status determination sub-module including item types.
5. the development project information management system according to claim 4 based on PLM platforms, it is characterised in that the item Mesh type definition submodule includes determining technical research type project templet, new product development type project templet, product sustained improvement type Project templet, project management climbing shuttering, science and technology item declare template, standardization project template and intellectual property project template.
6. the development project information management system according to claim 1 based on PLM platforms, it is characterised in that the item Mesh target advance module includes project task planning submodule, task scheduling and creates and safeguard WBS task submodules, starts Specialty Program task decomposition and distribution submodule.
7. the development project information management system according to claim 1 based on PLM platforms, it is characterised in that the item Mesh is linked up and risk management module includes BBS function settings submodule, problem and risk report submodule, risk class submodule Block, risk classifications submodule, risk profile management submodule.
8. the development project information management system according to claim 1 based on PLM platforms, it is characterised in that the item Mesh resource management module includes technical ability role selecting submodule, request and started and request Close Date selection submodule, resource institute Submodule, monthly full-time employee's quantity and resources costs selection submodule of equal value are selected in department.
CN201710501038.0A 2017-06-27 2017-06-27 A kind of development project information management system based on PLM platforms Pending CN107292585A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710501038.0A CN107292585A (en) 2017-06-27 2017-06-27 A kind of development project information management system based on PLM platforms

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710501038.0A CN107292585A (en) 2017-06-27 2017-06-27 A kind of development project information management system based on PLM platforms

Publications (1)

Publication Number Publication Date
CN107292585A true CN107292585A (en) 2017-10-24

Family

ID=60098233

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710501038.0A Pending CN107292585A (en) 2017-06-27 2017-06-27 A kind of development project information management system based on PLM platforms

Country Status (1)

Country Link
CN (1) CN107292585A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109840686A (en) * 2018-12-24 2019-06-04 万翼科技有限公司 A kind of partner alliance platform and event creative management method and system
CN112101687A (en) * 2019-06-17 2020-12-18 北京一石科技有限责任公司 Project process management system and management method
CN112884455A (en) * 2021-03-26 2021-06-01 中车青岛四方机车车辆股份有限公司 Task plan processing system, method and device
CN113778032A (en) * 2021-09-03 2021-12-10 深圳市至诚峰汇科技有限公司 Production and processing industry standard system digital transformation management system platform
CN115600997A (en) * 2022-12-12 2023-01-13 厦门盈趣科技股份有限公司(Cn) Standardized content management digital research and development project management system and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102147897A (en) * 2011-05-05 2011-08-10 江苏欧索软件有限公司 Project management system
CN103177306A (en) * 2011-12-20 2013-06-26 中工国际工程股份有限公司 Workflow control system of project implementation
CN104408587A (en) * 2014-12-25 2015-03-11 浪潮电子信息产业股份有限公司 Government project management information system
CN105373896A (en) * 2015-11-24 2016-03-02 杭州构家网络科技有限公司 Project management system
CN106845923A (en) * 2016-12-20 2017-06-13 柳州顺联科技有限公司 A kind of project management system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102147897A (en) * 2011-05-05 2011-08-10 江苏欧索软件有限公司 Project management system
CN103177306A (en) * 2011-12-20 2013-06-26 中工国际工程股份有限公司 Workflow control system of project implementation
CN104408587A (en) * 2014-12-25 2015-03-11 浪潮电子信息产业股份有限公司 Government project management information system
CN105373896A (en) * 2015-11-24 2016-03-02 杭州构家网络科技有限公司 Project management system
CN106845923A (en) * 2016-12-20 2017-06-13 柳州顺联科技有限公司 A kind of project management system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109840686A (en) * 2018-12-24 2019-06-04 万翼科技有限公司 A kind of partner alliance platform and event creative management method and system
CN112101687A (en) * 2019-06-17 2020-12-18 北京一石科技有限责任公司 Project process management system and management method
CN112884455A (en) * 2021-03-26 2021-06-01 中车青岛四方机车车辆股份有限公司 Task plan processing system, method and device
CN113778032A (en) * 2021-09-03 2021-12-10 深圳市至诚峰汇科技有限公司 Production and processing industry standard system digital transformation management system platform
CN115600997A (en) * 2022-12-12 2023-01-13 厦门盈趣科技股份有限公司(Cn) Standardized content management digital research and development project management system and method

Similar Documents

Publication Publication Date Title
CN107292585A (en) A kind of development project information management system based on PLM platforms
US11307770B2 (en) Capacity forecasting based on capacity policies and transactions
US7168045B2 (en) Modeling business objects
US7644013B2 (en) System and method for resource optimization
CN104809597B (en) Data resource management platform based on data fusion
CN107909349A (en) A kind of project management Cloud Server and its method for realizing project management
US20110145284A1 (en) Presenting skills distribution data for a business enterprise
US20070299953A1 (en) Centralized work distribution management
US20160014139A1 (en) Automation tool for providing users with security access to an electronic system
CN105989443A (en) Intelligent-mobile-terminal-based communication line inspection system
CN105653442A (en) Method for satisfying evaluation target of DO-178C standard
CN105184438A (en) System for managing human resources based on capacities and method of system
CN109214784A (en) A kind of method, client, server and the system of fire-fighting inspection management
WO2019215703A1 (en) Method and system for defining roles in an identity and access management system
US20040024629A1 (en) Methods and apparatus for project management
CN113393060A (en) Task allocation method and device, electronic equipment and storage medium
US8805919B1 (en) Multi-hierarchical reporting methodology
Margatama Employee self service-based human resources information system development and implementation. Case study: BCP Indonesia
JP2008250558A (en) Workflow management system, workflow management method, retrieval system, retrieval method, and program
US10037352B1 (en) Methods for editing hierarchical data
CN111523810A (en) Enterprise-level model management method, system, device and storage medium
JP5812911B2 (en) Workflow management system, workflow management method, and workflow management program
US8069180B1 (en) Systems and methods for automated employee resource delivery
JP2008250556A (en) Workflow management system, workflow management method, and program
CN103942474A (en) Method for controlling permission three-dimensional model system in software project management process

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination