CN107288313A - Diamond dust abrasion-proof terrace construction method - Google Patents

Diamond dust abrasion-proof terrace construction method Download PDF

Info

Publication number
CN107288313A
CN107288313A CN201710514437.0A CN201710514437A CN107288313A CN 107288313 A CN107288313 A CN 107288313A CN 201710514437 A CN201710514437 A CN 201710514437A CN 107288313 A CN107288313 A CN 107288313A
Authority
CN
China
Prior art keywords
concrete
hours
finisher
diamond dust
initial set
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710514437.0A
Other languages
Chinese (zh)
Inventor
刘宝堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710514437.0A priority Critical patent/CN107288313A/en
Publication of CN107288313A publication Critical patent/CN107288313A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Building Environments (AREA)

Abstract

The invention discloses diamond dust abrasion-proof terrace construction method, it is characterised in that is carried out by following construction procedure:1st, substrate concrete has been poured in 34 hours tentatively to be struck off with long floating rule, has been rolled before initial set with iron roller 2 times, then has rubbed concora crush reality with the hands with wooden float, has then added disk further smooth with special finisher, it is ensured that surfacing, closely knit;2nd, start to broadcast sowing curing agent after concrete initial set, before final set, it is floating with finisher plus disk compacting;3rd, after 12 hours, repeat and once broadcast sowing and compacting operation;Finally it is polished sealing, manual operation corner parts;Finally spray sealing compound or cover film;4th, covering curing is leveled to from concrete, all operating process are maintained in 24 hours and completed;5th, construction can open walking after completing 23 days, and in finished surface slot.It is an advantage of the invention that improving the density of concrete, dirt has been reduced, the grease proofness on ground is added, the construction time is short, and efficiency high, cost is low, perception is good.

Description

Diamond dust abrasion-proof terrace construction method
Technical field
The present invention relates to diamond dust technical field of construction, more particularly to diamond dust abrasion-proof terrace construction method.
Background technology
Diamond dust abrasion-proof terrace is used for having very high abrasion requirement, the mattess of dust-proof requirement, for example:Parking lot, Lower garage, industrial premises, warehouse, harbour and unified color is needed to improve work hygiene environment and place attractive in appearance.But it is due to Crackle, decortication, pitted skin and dusting etc. often occurs in reason in terms of construction technology and material, large area diamond dust abrasion-proof terrace Defect, not only directly affects the use function on ground, and directly affects the overall perception of terrace.
The content of the invention
The problem of purpose of the present invention exists aiming at prior art has there is provided diamond dust abrasion-proof terrace construction method Effect ground solves the technical barrier of diamond dust terrace cracking cracking.
The object of the present invention is achieved like this:Diamond dust abrasion-proof terrace construction method, it is characterised in that by following construction Step is carried out:
1st, because pumped concrete surface cement is thicker, substrate concrete has been poured in 3-4 hours and has tentatively been scraped with long floating rule It is flat, rolled before initial set with iron roller 2 times, then rub concora crush reality with the hands with wooden float, it is cracked with control surface, and concrete surface can be reduced Moisture is distributed, and then adds disk further smooth concrete with special finisher, it is ensured that concrete surface is smooth, closely knit;
2nd, start to broadcast sowing curing agent after concrete initial set, before final set, while adding disk compacting floating using finisher;
3rd, after 1-2 hours, the operation once broadcasted sowing and be compacted is repeated;Finally blade is added to be polished with finisher close Envelope, while manual operation corner parts;Finally sprinkling sealing compound or cover film, prevent moisture quickly volatilizees from causing cracking;
4th, covering curing is leveled to from concrete, all operating process are maintained in 24 hours and completed;
5th, construction can open walking after completing 2-3 days, and in finished surface slot, prevent cold crack.
Compared with prior art, it is an advantage of the invention that:The density of concrete is greatly improved, dirt has been reduced, added The grease proofness on ground, and a high density, easy to clean, impermeabilisation ground are formd in terrace surface, with concrete base layer one Construction is played, the construction period is short, and efficiency high, cost is low, and perception is good.
Embodiment
To further describe the present invention, with reference to embodiment, the invention will be further described.
Substrate concrete has been poured in 3-4 hours tentatively to be struck off with long floating rule, it is pre-hardening before rolled with iron roller 2 times, then use Wooden float rubs concora crush reality with the hands, and being cracked with control surface, and can reduce concrete surface moisture distributes, and then adds circle with special finisher The further smooth concrete of disk, it is ensured that concrete surface is smooth, closely knit.Start to broadcast sowing hardening after concrete initial set, before final set Agent, while adding disk compacting floating using finisher.After 1-2 hours, the operation once broadcasted sowing and be compacted is repeated;Finally with smearing Ray machine adds blade to be polished sealing, while manual operation corner parts;Finally sprinkling sealing compound or cover film, prevent moisture Quick volatilization causes cracking.Covering curing is leveled to from concrete, all operating process are maintained in 24 hours and completed.Construct Walking can be opened after into 2-3 days, and in finished surface slot, prevents cold crack.

Claims (1)

1. diamond dust abrasion-proof terrace construction method, it is characterised in that carried out by following construction procedure:
1) due to pumped concrete surface cement it is thicker, poured substrate concrete in 3-4 hours and tentatively struck off with long floating rule, Rolled before initial set with iron roller 2 times, then concora crush reality is rubbed with the hands with wooden float, be cracked with control surface, and concrete surface water can be reduced Scattered hair, then adds disk further smooth concrete, it is ensured that concrete surface is smooth, closely knit with special finisher;
2) starts to broadcast sowing curing agent after concrete initial set, before final set, while adding disk compacting floating using finisher;
3) after .1-2 hours, the operation once broadcasted sowing and be compacted is repeated;Finally blade is added to be polished sealing with finisher, together When manual operation corner parts;Finally sprinkling sealing compound or cover film, prevent moisture quickly volatilizees from causing cracking;
4) levels to covering curing from concrete, and all operating process are maintained in 24 hours and completed;
5) constructions can open walking after completing 2-3 days, and in finished surface slot, prevent cold crack.
CN201710514437.0A 2017-06-29 2017-06-29 Diamond dust abrasion-proof terrace construction method Pending CN107288313A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710514437.0A CN107288313A (en) 2017-06-29 2017-06-29 Diamond dust abrasion-proof terrace construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710514437.0A CN107288313A (en) 2017-06-29 2017-06-29 Diamond dust abrasion-proof terrace construction method

Publications (1)

Publication Number Publication Date
CN107288313A true CN107288313A (en) 2017-10-24

Family

ID=60099151

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710514437.0A Pending CN107288313A (en) 2017-06-29 2017-06-29 Diamond dust abrasion-proof terrace construction method

Country Status (1)

Country Link
CN (1) CN107288313A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109057243A (en) * 2018-08-16 2018-12-21 徽都建设有限公司 A kind of abrasion-proof terrace construction method
CN109098467A (en) * 2018-09-11 2018-12-28 嘉善凯达水泥构件有限公司 A kind of crack repairing method of curved surface cement components
CN110029798A (en) * 2019-03-06 2019-07-19 中国五冶集团有限公司 A kind of construction method reducing abrasion-proof terrace cracking
CN110593523A (en) * 2019-08-27 2019-12-20 江苏南通三建集团股份有限公司 Construction method of anti-cracking and moisture-proof gold steel grit terrace
CN114319875A (en) * 2021-12-29 2022-04-12 中国机械工业第四建设工程有限公司 Seamless construction process for super-large-area concrete ground

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10309360A1 (en) * 2002-03-04 2003-09-18 Karl Hetzl Production of slip-resistant cast coatings on metal surfaces, e.g. industrial floors, involves application of a coating containing silicon carbide particles and synthetic resin
CN103790357A (en) * 2012-11-01 2014-05-14 西安联合交通设施工程有限公司 Manufacturing method of hardened and wear-resisting floor system
CN105350559A (en) * 2015-11-27 2016-02-24 中国一冶集团有限公司 Construction method suitable for emery structural ground of large factory building
CN106836815A (en) * 2017-03-08 2017-06-13 杭州二建建设有限公司 Large area diamond dust floor structure plate and surface layer one-off construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10309360A1 (en) * 2002-03-04 2003-09-18 Karl Hetzl Production of slip-resistant cast coatings on metal surfaces, e.g. industrial floors, involves application of a coating containing silicon carbide particles and synthetic resin
CN103790357A (en) * 2012-11-01 2014-05-14 西安联合交通设施工程有限公司 Manufacturing method of hardened and wear-resisting floor system
CN105350559A (en) * 2015-11-27 2016-02-24 中国一冶集团有限公司 Construction method suitable for emery structural ground of large factory building
CN106836815A (en) * 2017-03-08 2017-06-13 杭州二建建设有限公司 Large area diamond dust floor structure plate and surface layer one-off construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王卫宏: "浅谈大面积金刚砂耐磨地坪施工应用", 《安徽建筑》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109057243A (en) * 2018-08-16 2018-12-21 徽都建设有限公司 A kind of abrasion-proof terrace construction method
CN109098467A (en) * 2018-09-11 2018-12-28 嘉善凯达水泥构件有限公司 A kind of crack repairing method of curved surface cement components
CN110029798A (en) * 2019-03-06 2019-07-19 中国五冶集团有限公司 A kind of construction method reducing abrasion-proof terrace cracking
CN110593523A (en) * 2019-08-27 2019-12-20 江苏南通三建集团股份有限公司 Construction method of anti-cracking and moisture-proof gold steel grit terrace
CN114319875A (en) * 2021-12-29 2022-04-12 中国机械工业第四建设工程有限公司 Seamless construction process for super-large-area concrete ground

Similar Documents

Publication Publication Date Title
CN107288313A (en) Diamond dust abrasion-proof terrace construction method
CN108625618B (en) Quick repair method for water seepage caused by rupture of waterproof layer of bathroom without disassembling bricks
Young et al. Maintenance and repair issues for stone cleaned sandstone and granite building façades
CN103790357A (en) Manufacturing method of hardened and wear-resisting floor system
CN102061798A (en) Epoxy self-leveling floor with concrete sealing curing agent and construction method thereof
CN103147562B (en) Construction method of ground cement mortar leveling
CN107587398A (en) The construction method of diamond dust ground curing agent
CN104047410A (en) Stone paving construction method
CN105178562A (en) Inorganic crystal grindstone integrated terrace system and construction process thereof
CN107724642A (en) The construction method of color wearing proof terrace
CN101545269A (en) Method for rigid waterproof construction of beam and slab type basement
CN103979887B (en) The anti-face checking coating of clear-water concrete and using method thereof
CN112408851A (en) Anti-radiation semi-permanent nano-penetration crystallization sealing compacting agent and use method thereof
CN107540314A (en) A kind of post-cast strip basal plane inorganic agent and its construction method
CN102912969A (en) Construction process of corrosion-resistant dustproof solidification agent floor
CN103206093A (en) Leakage repairing and preventing method for roof settlement joint
US20170166001A1 (en) Decorative concrete simulating natural wood and method of forming the same
Ashurst Cleaning masonry buildings
CN108385999A (en) A kind of leakage of non-damage type is prevented and restorative procedure
EP3398999B1 (en) Additive for paints, putties, plasters and other materials intended to cover architectural surfaces
CN109057243A (en) A kind of abrasion-proof terrace construction method
CN208293792U (en) A kind of quick service waterproof construction for toilet warterproof rupture
Coppola Repair and conservation of reinforced concrete tent-church by Pino Pizzigoni at Longuelo–Bergamo (Italy)
CN114934651B (en) High-hardness abrasion-resistant quick-setting crack-free integrated terrazzo processing technology
CN107700883A (en) A kind of construction method of swimming pool coating waterproofing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171024